JOB CARD

NO WO : DATE :
TYPE JOBCARD PLANNED EXTENSION REWORK ADDITIONAL

AREA : BOP COAL HANDLING COMMON

BIDANG : MEKANIK LISTRIK KONTROL & INSTRUMENT

SCHEDULE START :

SCHEDULE FINISH :

ACTUAL START :

ACTUAL FINISH :

PERALATAN : Chemical raw water pump A

JUDUL PEKERJAAN : Penggantian mechanical seal dan penggantian bearing

GEJALA :

PLANNING QTY EST TIME ACT TIME ACTUAL

10 Periksa kondisi bearing,Ganti bearing bila rusak 90

20 Inspeksi kondisi statik dan rotating mecanical seal 10

30 Cleaning dan inspeksi All part pompa 60

40 install lip seal 15

JOB TASK : 50 install mechanical seal 20

60 install impeller 20

70 install coupling sisi pompa 20

80 install pompa ke cassing impeler 20

255

PLANNING ACTUAL

1 Majun

2 Rust removal/WD40
MATERIAL :
3 oli Presilia pertamina iso vg 46 2 liter

4 Bearing Skf nu 312 ecp 1pcs

5 Bearing Skf 7312 becbp 2pcs

6 Gasket asbestos 0,5mm 1

7 red silicon 1

SPARE PART : 2

1 Tool set( Kunci pas ring 12,14,17,19,22,24)

2 Kunci inggris
TOOLS :
3 Obeng minus

4 palu 3kg dan palu rubber

5 Tracker bearing

1 TECH

2
MAN RESOURCE:
3

TEKNISI PENANGGUNG JAWAB : TTD :

SUPEVISOR : TTD :

IZIN KERJA : TTD :

QC : TTD :

KETERANGAN :

QC TTD :

OUTAGE KOORDINATOR (OWNER) : TTD :