Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

IEEE Transactions on Dielectrics and Electrical Insulation Vol. 15, No.

5; October 2008 1449

In-situ Insulation Test of 400 kV GIS


H. Mohseni, J. Jadidian, A. A. Shayegani-Akmal, E. Hashemi, A. Naieny and E. Agheb
School of Electrical and Computer Engineering,
University of Tehran, Campus #2, North Kargar Ave, P.O. Box 14395/515, IR-
14395 Tehran, Iran

ABSTRACT
To guarantee the insulation strength of gas insulated substations (GIS), a number of
different voltage waveforms, e.g., switching, lightning and ac have to be applied to the
GIS after installation. Because of very huge dimensions of GIS for nominal high
voltages, it is not possible to carry out these tests in the factory and parts of the whole
system have to be delivered and put together to build the complete GIS. As the result,
all insulation tests have to be performed on site. Even if different parts of the system
are tested in the factory, because some of the problems occur during the transportation
and installation, the insulation strength of the whole GIS can be degraded. In this
paper, a novel test set-up and the measurement results of a 400 kV GIS have been
installed for the Mobarakeh steel industries, Isfahan, Iran, are presented. This system
has a length of about 100 m, which corresponds to a total capacitance of about 10 nF
per phase. Because of this relatively large capacitance, the power ratings of the test
voltage sources have to be very high. For achieving such a high power, a two step
cascade voltage transformer (each 800 V/300 kV with a maximum output current of 2
A) fed through an autotransformer enhanced with a number of inductors to
compensate the capacitive current and to minimize the input current of the test
transformers have been used to apply the necessary 515 kV to perform the ac tests of
the whole GIS. The measurements carried out on the system showed that the first two
phases passed the test successfully; however the third phase could not withstand the
applied voltage because of the pollution near one of the spacers. After replacing the
faulty spacer, the insulation strength of the third phase has been recovered.
Index Terms — EHV Insulation, gas insulated substations, insulation test, GIS,
cascaded transformers, resonance.

1 INTRODUCTION electrostatic forces and create some serious problems such as


electrical breakdown [2-3].
NOWADAYS Gas Insulated Substations, because of
small dimensions and having no contaminations are widely Insulators are the most sensitive parts of GIS. They are
used in transmission and distribution of electrical power [1]. placed between the inner conductor and the outer pipe in the
In Iran, also many GISs have been installed successfully up to bus bars and bus ducts. Free moving particles are absorbed by
extra high levels of voltage such as 400 kV and they are in use stronger field and might settle on the conductor surface or
presently. One of the important aspects of GIS installation is insulator spacers [4]. As a result, the shape of the field would
how to perform the insulation tests on site [2]. Although all be disturbed; this can lead to an insulator defect and hence a
pieces of GIS have been tested in manufacturer factories, in breakdown. To be able to trap the free particles, before taking
transporting its different parts, joining them up and starting GIS into service, the whole system has to be stressed
the whole GIS, many faults might be come up. These types of electrically. For this purpose, an alternating high voltage wave
mistakes or faults would affect the functionality of GIS. For with frequency of 50 Hz, or more is required [4-6].
instance, some cracks could be created on insulators, also tiny It is recommended to apply voltages with amplitudes as
pieces of conductor or insulator would remain in bus ducts. It high as 80% of the nominal voltage for 15 minutes.
is possible to detect such particles using UHF partial (420/√3)×1.2=290 kV is the phase to earth voltage for a 400
discharge detection [3].These particles can be moved by kV system. The rated phase voltage has to be applied for 3
minutes, which is followed with an applied voltage of 120%
of the nominal voltage for one minute [7-10]. The first two
Manuscript received on 18 March 2008, in final form 22 June 2008. stages are the so-called forming or conditioning stages.

1070-9878/08/$25.00 © 2008 IEEE

Authorized licensed use limited to: Ehsan Hashemi. Downloaded on December 10, 2008 at 02:49 from IEEE Xplore. Restrictions apply.
1450 H. Mohseni et al.: In-situ Insulation Test of 400 kV GIS

After the conditioning stages, insulator tests can be started


by application of voltage waveforms such as impulse voltage,
switching surge or sinusoidal. In this paper, test set-up and
measurement results of a 400 kV GIS installed for the
Mobarakeh Steel Industries, Isfahan, Iran, are described.
Different possible solutions to generate the necessary voltage
waveforms as well as the measurement results are discussed in
detail.

2 POSSIBLE SOLUTIONS Figure 2. Variation of voltage ratio in terms of frequency for two different
values of R.

2.1 TEST REQUIREMENTS In series resonance, maximum voltage and current of


capacitor can be obtained when the values of L and C satisfy
To perform the test with alternating voltage, one high the resonance condition, ωC=1/ωL, therefore the maximum
voltage supply is needed. The capacitance of each bus bar current is equal to I=U0/R. As a result, the voltage of the
might be up to 10 nF or even 20 nF. For a typical value of this capacitor can be written as follows:
capacitance about 12 nF and voltage of 520 kV, the current
will be about 2A using 50 Hz. Therefore, for the whole three-
I U0 ωL
phase test in single essay, i.e., whole substation bus bar with a U0 = = = U0 (1)
power of about 1 MVA is required. It is obvious that ω C Rω C R
preparing such a power with an adjustable voltage source is
too complicated.
One solution which could be applied in such tests is This means that the voltage magnitude of the capacitor
resonant circuits; since, the load of the test circuit, can be which is the voltage across the bus bar is ωL/R times greater
stated as a pure capacitance. There are two different methods than the magnitude of the source voltage. This ratio is called
to achieve resonant circuits: series resonance and parallel as quality factor, Q.
resonance which is usually called compensation. In the next To attain the resonance, it is possible to adjust L or ω. In
sections, these types of the circuits are discussed briefly. this way, Q could be up to 40. It can be stated that the power
supply required for the test procedure, would be scaled down
with the factor of Q. To perform the test in this method, after
2.2 SERIES RESONANCE achieving resonance by varying L or ω or both of them, the
voltage of power supply should be increased up to the value in
which required current of the test is achieved.
In series resonant circuits, one reactor is applied in the
Figure 3 shows an instance reactor which is used as the
circuit in series as demonstrated in Figure 1.
series reactor transported to medium voltage side [8].

Figure 1. Series resonant circuit

In this circuit, C represents the capacitance between bus bar


and the earth; L is an adjustable high voltage reactor which is
placed in series with C to make the capacitor-inductor
resonance possible. This circuit is fed by transformer T. The
variable R is assumed to be the whole equivalent resistance of
the circuit. Variation of the ratio of voltage across the Figure 3. Series reactor which is used in medium voltage GIS.
capacitor terminals and the source voltage in terms of applied
frequency could be obtained from Figure 2. This figure has The dimensions of such a reactor for high levels of voltage
been plotted for constant L and two different resistances. As is are much greater than a medium voltage one, and
represented in this figure, the value of equivalent resistance consequently, transportation of such equipment into the site is
can change the amount of optimum frequency (fo) [11]. more complicated.

Authorized licensed use limited to: Ehsan Hashemi. Downloaded on December 10, 2008 at 02:49 from IEEE Xplore. Restrictions apply.
IEEE Transactions on Dielectrics and Electrical Insulation Vol. 15, No. 5; October 2008 1451

2.3 PARALLEL RESONANCE The complete circuit of the test set-up including the
low voltage autotransformer (T m ), step-up transformer,
In the parallel resonance, capacitive current of the bus (T 3) and cascaded transformers, (T 1 and T 2), is shown in
bar should be compensated with one or more parallel Figure 5. According to Figure 5, the test set-up has been
reactors [12-14]. It is not necessary for these reactors to fed by means of a low voltage phase to phase port, i.e.,
be joined with capacitive load directly. Since high voltage 400 V with relatively low output power (lower than 40
inductors are usually heavy and expensive, non-direct kVA).
inductors (reactors which are transmitted to the lower This method also needs a step-up transformer which has
levels of voltages) are recommended for in-situ a reactor in parallel at the second side to compensate a
applications. If high voltage reactors are available at the portion of capacitive current of the load. In this particular
substation site, there is no distinct need to have any high test, we used a high current dry transformer. This
voltage transformer which is capable of supporting the transformer is shown in Figure 8 and also at the left section
test current. In this paper, much smaller inductors have of Figure 9 in the GIS. As it can be seen in Figure 8, these
been used in low voltage side of the transformer. Figure 4 transformers have been specially designed to be able to
shows the suitable circuit for GIS insulation test by means provide a wide range of voltage/current gain ratios, and
of parallel resonance. In this kind of circuit, if L can even reactive compensation values via connecting the
compensate the capacitor current, no high power is input/output terminals in many ways. In this test procedure,
required to perform the test. This power is of the order of the connections of the dry transformer are performed in a
the circuit losses, but it is not possible to achieve manner to supply the maximum reactive compensation. In
complete compensation in practice, since L is usually not addition, some high current cable is twisted in a spool and
fully arbitrary adjustable. placed in the second side of the transformer as air-cored
reactor (L3 in Figure 5 and L0 in Figure 6) to compensate
the rest of the capacitive power and consequently minimize
the demanding apparent power of the test set-up. The role
of reactive compensation is also performed in the upper
levels of voltages, i.e., by means of interior reactors of each
stage of the cascaded transformers as illustrated in Figure 5.
This principle can be better figured out in the simplified
circuit which is shown in Figure 6. In the circuits of
Figures 5 and 6, T1 and T2 are the cascaded transformers,
Figure 4. Parallel resonant circuit using reactor in low voltage side of L11, L12, L21 and L22 are their internal inductors. The internal
transformer reactors of each transformer were arranged in series with
each other and then paralleled with the input of the
2.4 APPLIED SOLUTION: CASCADED VOLTAGE transformer. In this configuration, internal impedance of
TRANSFORMERS each transformer is about 3.5 Ω. The inner physical
construction of these transformers is shown in Figure 7.
In Figure 6, the currents which are flowing through each
Because of great weight and large dimensions of extra branch of the circuit are demonstrated. Some of these
high voltage transformers, these transformers are not values are measured at the test procedure, and the rest
suitable for portable test systems. Therefore, in such cases, which could not be directly measured are calculated
some less massive equipment should be applied. There are according to the measurements. As it can be seen, each
many experiences on in-situ measurements of GIS [1]. The reactor compensates a large amount of capacitive power.
different energy supply systems for on-site measurement of Without these reactors, the demanding power of the test
the high voltage components with high capacities are set-up and also the dimensions of the transformers would
already known [13-14]. In this paper a couple of cascaded be very huge.
transformers have been designed and fabricated to provide
the test. This two-stage cascaded voltage transformer set The voltage ratio of each stage of cascaded transformers
has provided two reactors to supply high levels of is 800/300000; therefore in two cascaded stages, the total
capacitive currents. The construction and the application ratio would be 800/600000 (see Figure 6). Consequently, to
method of these transformers are proposed in this paper. achieve the output voltage of 515 kV, a feeding voltage of
Each of these transformers has provided two reactors to
supply high levels of capacitive currents which could be 515kV
U = 800 × = 690 V (2)
connected in series or in parallel with the load. In this way, 600kV
it is possible to choose suitable configuration of reactors to
compensate the capacitive current. is required.

Authorized licensed use limited to: Ehsan Hashemi. Downloaded on December 10, 2008 at 02:49 from IEEE Xplore. Restrictions apply.
1452 H. Mohseni et al.: In-situ Insulation Test of 400 kV GIS

Figure 5. Complete circuit of the cascaded transformers

Figure 6. Simplified circuit of cascaded transformers and test objects

Authorized licensed use limited to: Ehsan Hashemi. Downloaded on December 10, 2008 at 02:49 from IEEE Xplore. Restrictions apply.
IEEE Transactions on Dielectrics and Electrical Insulation Vol. 15, No. 5; October 2008 1453

According to the magnitude of currents in each phase, it is


obvious that the capacitances of the three phases were not
equal. The capacitance of the center phase was greater than
the others, since it had an additional bus duct. The capacitance
of center phase was about 11.5 nF and the two other phases
were about 9 nF.
One of the significant points of this work is the use of air-
cored twisted cable which is used in the secondary side of the
step-up transformer. This reactor was capable to pass current
of 800 A. This reactor can be made promptly in a typical GIS
site, since such cables are easily available. Moreover, the
magnitude of such inductance, L0, could be adjusted by
increasing or subtracting turns of the bobbin. Using this
bobbin, the current of the variable transformer is compensated
to less than 100 A which was the critical value for our system.
This compensation is significant in practical experiences,
since many limitations arose in current supplying instruments.
For instance in this case, variable transformer can support 0 to
400 V with 150 A.
Figure 9 shows a comprehensive scheme of the test set-up
including step-up high current dry transformer, the cable
which is twisted around the spool as a shunt air-cored reactor,
the cascaded transformers, and the connection between the
secondary stage of the output transformers which are installed
on site, and the bushing of the GIS phase under test.
Figure 7. Inner construction of a cascaded transformer

Figure 8. High current dry transformer and its adjustable outputs can be
chosen in different connections via cables.
Figure 9. Comprehensive scheme of the test set-up and the 400
The current of C in this test was 1.9 A in one phase and in kV GIS.
the other two phases, this current was about 1.6 A. In the
optimum connection of the parts together, the current of
reactors in each stage would be about 200 A. Even with such 2.5 VOLTAGE DIAGNOSTICS
compensations which are performed in multiple levels of
voltage, the current of the primary low voltage supply is about To measure high voltages, one of the best methods which is
100 A. Total apparent power is required for this test is up to 1 recommended in this paper is using bushing tap. In other
MVA, and in the case that no inductive compensation has words, the measurement is performed by means of the
been applied, in the low voltage side, the power supply must capacitive divider situated in the high voltage bushing which
provide up to 2500 A instead of 100 A; In addition, the is accompanying the test procedure by entering the output
dimensions of the whole test setup will be one order of voltage of the cascaded transformers into the GIS bus bar.
magnitude larger. In these conditions, this test is inapplicable, These typical bushings are SF6 insulated with nominal voltage
since the test set-up should be portable and also such high of 400 kV and has been tested by a voltage up to 680 kV. This
power at low voltage grid is hardly available. capacitive type bushing is shown in Figure 10. By scaling

Authorized licensed use limited to: Ehsan Hashemi. Downloaded on December 10, 2008 at 02:49 from IEEE Xplore. Restrictions apply.
1454 H. Mohseni et al.: In-situ Insulation Test of 400 kV GIS

down the output voltage of the transformers, it can be


measured by means of a peak voltmeter. In cases where such
bushings are not available, providing a low capacitance high
voltage capacitive divider is unavoidable. The total
capacitance of such a divider should be lower than few nano
Farads.

(a)

(b)
Figure 10. Defected bus bars due to insulation weakness.

After removing these faults, the test procedure has been


repeated and the third phase could also withstand the applied
voltages.
It must be noted that in such failures during service, the
energy dissipated could be much higher and therefore the GIS
can be seriously damaged. In Figure 12, the bus bar after such
failures during normal operation is shown [13]. This shows
the importance of the insulation tests before starting the
operation of the gas insulated substations to prevent faults
resulting in disasters and waste of big investments.

Figure 9. Measuring circuit using bushing tap.

3 TEST RESULTS

In 400 kV GIS of Mobarakeh Steel Industries, Isfahan, Iran,


the final test was successfully made with 515 kV alternating
voltage by means of two cascaded transformers with a current
of about 1.9 A. This current led to a large apparent power of
up to 1 MVA.
After application of the test voltage as described above, no
phenomena corresponding to breakdown in GIS have been
detected. As a result, it has been concluded that the first tested
phases are without any problems. During the application of Figure 11. A defect caused by high short circuit capacity power grid.
the test voltage with amplitude of 80% of the rated phase
voltage for 15 minutes to the third phase, two breakdowns
have been detected in two separate test rounds. During the 4 CONCLUSION
third time, the first part of the test voltage (80% for 15 Insulation Tests of high voltage Gas Insulated Substations
minutes) has been successfully withstood, but during the (GIS) is a very important issue to be considered to guarantee
application of the second part of the test voltage (100% for 3 the appropriate functionality of such systems. Because of very
minutes), a breakdown occurred once more. large dimensions of the high voltage GIS, it is not possible to
After inspection, the fault has been located near one of the test the whole GIS before delivering to the installation site. On
spacers of the GIS. Figure 11 shows the breakdown traces on the other hand, because of relatively large capacitance of such
conductors and ducts of the GIS for the third phase. systems, especially in cases where the total length of the

Authorized licensed use limited to: Ehsan Hashemi. Downloaded on December 10, 2008 at 02:49 from IEEE Xplore. Restrictions apply.
IEEE Transactions on Dielectrics and Electrical Insulation Vol. 15, No. 5; October 2008 1455

installed GIS exceeds some tens of meters, the high voltage Hossein Mohseni (M'88) was born in Tehran on 7
February 1942. He studied electrical engineering at the
source has to be capable of delivering relatively high levels of
Technical University Graz, Austria and received the
current. degrees Dipl. Ing and Dr. techn in 1971 and 1975,
In this paper, a high power high voltage test setup is respectively. From 1971 to 1976 he was with ELIN
proposed to perform in-situ insulation tests on a 400 kV GIS UNION AG Austria, working as testing and research
installed for the Mobarakeh Steel Industries, Isfahan, Iran. engineer in the High Voltage Laboratory and the
Transformer R and D Department. In 1976 he joined the
Different possibilities to produce such high power high Faculty of Engineering, University of Tehran, Department
voltages have been discussed and the measurement results of Electrical Engineering. He is currently an associate professor and teaches
have been analyzed in detail. In the solution which is applied high voltage engineering, high voltage insulation technology, and transients in
in this paper, for achieving such a high power, a two step power System and Apparatus. During 1981/82 he was chairman, Department
of electrical engineering at the University of Tehran. Since 1980 he has been a
cascaded voltage transformer (each 800 V/300 kV with a technical consultant of the Iran Power Generation and Transmission Company
maximum output current of 2 A) fed through an (TAVANIR). Also since 1998 he is the dean of the High Voltage and Pulsed
autotransformer enhanced with a number of inductors to Power research center, at the University of Tehran
compensate the capacitive current and to minimize the input
Jouya Jadidian (S’06) was born in Kermanshah, Iran, on
current of the test transformers have been used to apply the 9 June 1984. He received the B.Sc. degree in electrical
necessary 515 kV to perform the ac tests of the whole GIS. engineering with "Exceptional Talent" honor from
The measurements carried out on the system showed that the University of Tehran, Tehran, Iran in 2006. He is
first two phases passed the test successfully; however the third currently working toward the M.Sc. degree at the
University of Tehran. Since 2004, he has been with the
phase could not withstand the applied voltage because of the High Voltage and Pulsed Power research center, at the
pollution near one of the spacers. After replacing the faulty University of Tehran. Also, since 2007 he has been
spacer, the insulation strength of the third phase has been working at the Iran Grid Management Company (IGMC) in the “High voltage
recovered. transmission system protection” office as a researcher. He has over 20
technical papers in journals and international conference proceedings. His
current research interests include pulsed power systems, high voltage, high
power technology, and plasma processing.
REFERENCES
Amir Abbas Shayegani Akmal was born in Tehran, Iran,
[1] M. S. Naidu, Gas Insulated Substations, McGraw-Hill, 1999. in 1974. He graduated with a B.Sc degree from the Sharif
[2] S. A. Boggs, R. Y. Chu, and N. Fujimoto, “Gas-Insulated Substations: University of Technology and from the University of
Technology and Practice”, Intern. Sympos. Gas-Insulated Substations, Tehran with a M.Sc. and Ph.D. with cooperation of the
pp. 650-661, 1996. University of Hanover (Schering-Institute) all in electrical
[3] J. D. McDonald, Electric Power Substations Engineering, Second engineering in 1996, 1998, and 2005, respectively. He has
Edition, CRC Press, 2007. been with the University of Tehran as an assistant professor
[4] IEEE Std C37.122: “Gas-Insulated Substations”, 2003. since 2006 and also has worked at the High Voltage
[5] IEC 60517: “Gas-insulated metal-enclosed switchgear for rated voltage Laboratory of the University of Tehran. His principal research interest is in
of 72, 5 kV and above”, 1997. high voltage power transformer insulation systems, testing and diagnostics.
[6] R. Bell, C. Charlson, S.P. Halliday, T. Irwin, J. Lopez-Roldan and J.
Nixon, “High-voltage onsite commissioning tests for gas-insulated Ehsan Hashemi (S’07) received the B.S. degree in
substations using UHF partial discharge detection”, IEEE Trans. Power electrical engineering from the University of Tehran in
Del., Vol. 18, pp. 1187-1191, 2003. 2006 and this year, started studying for the M.Sc. degree
[7] K. Feser, R. Sun, A Eriksson, K. Frohlich, “On-site dielectric testing of in the University of Tehran. He has jointed the Research
GIS: theoretical and practical considerations,” IEEE Trans. Power and Testing Division of High Voltage and Pulsed Power
Delivery, Vol.6, pp. 615 - 625, 1991. research center, at the University of Tehran in 2005.
[8] W. Hauschild and W. Mosch, “High-Voltage Field Testing of GIS Since 2007, he has been with Iranian Grid Management
from the Viewpoint of Failure Mechanism," Intern. Sympos. Gas- Company as a Power Engineer.
Insulated Substations, Toronto, Vol. 2, pp. 746-749, Canada, 1985.
[9] R. Haller, W. Hauschild and W. Mosch, “High-voltage field testing of
GIS from a physical view-point”, 2nd Intern. Conf. Properties and Alireza Naieny(S’07) received the B.Sc. degree in
Applications of Dielectric Materials, Vol. 2, pp. 746-749, 1988. electrical engineering from the University of Tehran in
[10] K. Azumi., H. Kuwahara, I. Sakon, T. Marutani and H. Niwa, “Design 2006 and this year, started studying for the M.S. degree in
Considerations on Three Phase Enclosure Type Gas Insulated the University of Tehran. He has jointed the Research and
Substation,” IEEE Trans. Power Apparatus Syst., Vol. 99, pp. 947– Testing Division of High Voltage and Pulsed Power
956, 1980. research center, at the University of Tehran in 2005.
[11] H. W. Anderl, C. L. Wagner and T. H. Dodds”, Insulation
Coordination for Gas Insulated Substations”, IEEE Trans. Power
Apparatus Syst., Vol. 92, pp. 1622 - 1630, 1973.
[12] W. W. Sparks and G. H. Hathaway, “Operation of detroit edison gas Edris Agheb (S’07) received the B.S. degree in electrical
insulated substations”, IEEE Trans. Power Apparatus Syst., Vol. 95, engineering from the University of Tehran in 2006 and this
pp. 344 - 351, 1976. year, started studying for the M.S. degree in the University
[13] J. P. Dupraz and G. F. Montillet, ”A new method for the measure of of Tehran. He has jointed the Research and Testing
current: applications up to 550 kV gas insulated substations”, Division of High Voltage and Pulsed Power research
Transmission and Distribution Conf. and Exposition, IEEE PES, Vol. center, at the University of Tehran in 2005. Since 2007, he
2, pp. 504 - 509, 2003. has been accepted as a Power Engineer in Iranian Grid
[14] G. Aldrovandi, I. Bonfanti, E. Figini, F. Giornelli, W.Koltunowicz and Management Company.
L. K. Shing, “Progress and experience on type and field testing
procedures of SF6 gas insulated substations”, Power System
Technology, Proc. POWERCON, Vol. 1, pp. 188–193, 1998.

Authorized licensed use limited to: Ehsan Hashemi. Downloaded on December 10, 2008 at 02:49 from IEEE Xplore. Restrictions apply.

You might also like