Man Hour Estimation For SRU
Man Hour Estimation For SRU
1. Datasheet ( 3 A4)
SWS Gas KO Datasheet considered as Revised Document
1 2006-02 V / AG Relocated Vessel Acid Water N/A N/A 2. General Arrangement 10.00 2 12
Drum GA considered as New Document
Drawing (1 A3)
1. Datasheet ( 3 A4)
Fuel Gas KO Datasheet considered as Revised Document
1 2006-08 V / AG Relocated Vessel Hydrocarbons 4959-02-0058-D N/A 2. General Arrangement 10.00 2 12
Drum GA considered as New Document
Drawing (1 A3)
1. Datasheet ( 3 A4)
Datasheet considered as Revised Document
1 2005-04 H / AG Acid Gas Burner Relocated Heater Acid Gas N/A N/A 2. General Arrangement 10.00 4 14
GA considered as New Document
Drawing (1 A3)
1. Datasheet ( 3 A4)
Reaction Datasheet considered as Revised Document
1 2005-01 H / AG Relocated Furnace Claus Gas N/A N/A 2. General Arrangement 14.00 5 19
Furnace GA considered as New Document
Drawing (1 A3)
1. Datasheet (3 A4)
Shell Steam Datasheet & GA considered as New Document
1 2007-01 H / AG Condenser 1 Relocated Condenser - N/A 2. General Arrangement 10+12 0 22
Tube Claus Gas
Drawing (1 A3)
1. Datasheet (3 A4)
Shell Steam Datasheet & GA considered as New Document
1 2007-02 H / AG Condenser 2 Relocated Condenser - N/A 2. General Arrangement 10+12 0 22
Tube Claus Gas
Drawing (1 A3)
1. Datasheet (3 A4)
Datasheet considered as Revised Document
1 2006-05 H / AG Converter 1 Relocated Reactor Claus Gas N/A N/A 2. General Arrangement 12.00 5 17
GA considered as New Document
Drawing (1 A3)
1. Datasheet (3 A4)
Datasheet considered as Revised Document
1 2006-06 H / AG Converter 2 Relocated Reactor Claus Gas N/A N/A 2. General Arrangement 12.00 5 17
GA considered as New Document
Drawing (1 A3)
1. Datasheet (3 A4)
Shell Steam Datasheet & GA considered as New Document
1 2007-03 H / AG Condenser 3 Relocated Condenser - N/A 2. General Arrangement 10+12 0 22
Tube Claus Gas
Drawing (1 A3)
1. Datasheet (3 A4)
Shell Steam Datasheet & GA considered as New Document
1 2007-04 H / AG Last Condenser Relocated Condenser - N/A 2. General Arrangement 10+12 0 22
Tube Claus Gas
Drawing (1 A3)
1. Datasheet (3 A4)
Datasheet considered as Revised Document
1 2006-07 H / AG 3rd Converter Relocated Reactor Claus Gas N/A N/A 2. General Arrangement 12.00 5 17
GA considered as New Document
Drawing (1 A3)
1. Datasheet (3 A4)
Steam Datasheet & GA considered as New Document
1 2007-10X H / AG New Condenser LP Steam N/A N/A 2. General Arrangement 10+12 0 22
Condenser
Drawing (1 A3)
1. Datasheet (3 A4)
Vacuum Pump Datasheet considered as Revised Document
1 2006-10 V / AG Relocated Vessel Process Water 4959-02-0060-C Datasheet 2. General Arrangement 10.00 3 13
Drum GA considered as New Document
Drawing (1 A3)
Incinerator
2 2009-03/04 H / AG Relocated Blower Acid SWS Gas N/A N/A 1. Datasheet (2 A4) 5.00 0 5 Datasheet considered as New Document
Blower
Incinerator
1 2005-05 H / AG Relocated Burner Flue Gas - N/A 0.00 0 0 No Effect
Burner
1 2005-03 AG Incinerator Relocated Burner Flue Gas - Duty Spec Datasheet 20.00 20 Datasheet considered as Revised Document
Storage Pit
1 2028-01 AG Relocated Misc. Air + H2S Traces 4959-011/5026 Datasheet (1 A4) 2.00 0 2 Datasheet considered as New Document
Ejector
1. Datasheet (2 A4)
Datasheet & GA considered as New Document
1 2027-01 V / AG Catalyst Tank Relocated Tank Catalyst N/A N/A 2. General Arrangement 5+8 0 13
Drawing (1 A3)
1. Datasheet (3 A4)
Datasheet considered as Revised Document
1 2006-03 H / AG Steam Drum Relocated Vessel Water Steam 4959-02-0053-D Datasheet 2. General Arrangement 10.00 2 12
GA considered as New Document
Drawing (1 A3)
1. Datasheet (3 A4)
HP Condensate Datasheet considered as Revised Document
1 2006-04 H / AG Relocated Vessel Condensate 4959-02-0054-C Datasheet 2. General Arrangement 10.00 2 12
Drum GA considered as New Document
Drawing (1 A3)
1. Datasheet (1 A4)
Datasheet considered as Revised Document
1 2006-09 V / AG DeSuper Heater Relocated Vessel Steam N/A N/A 2. General Arrangement 10.00 1 11
GA considered as New Document
Drawing (1 A3)
Process Air
2 2009-01/02 H / AG Relocated Blower Air N/A N/A 1. datasheet (2 A4) 5.00 0 5 Datasheet considered as New Document
Blower
1. Datasheet ( 3 A4) Datasheet & GA considered as Revised
Shell Side Air
1 2007-05 H / AG Air Preheat Relocated S&T 4959-01-0015 Datasheet & GA 2. General Arrangement 0.00 2+3 5 Document
Tube side HP Steam
Drawing (1 A3)
1. Datasheet (2 A4)
Datasheet & GA considered as New Document
1 4804-04X V / AG SRU Stack New Stack Flue gas PP-PE-DS-4804-002 N/A 2. General Arrangement 8+12 0 20
Drawing (1 A3)
6- Equipment list, developed at Phase-1 FEED stage for SRU has been used for Man hours estimation. Total Project Hours (A+B+C)