Standard Operating Procedure: Title: Sop For Ejector System Section No.: 13
Standard Operating Procedure: Title: Sop For Ejector System Section No.: 13
Standard Operating Procedure: Title: Sop For Ejector System Section No.: 13
: 05
Issue date: 01.04.2020
Revi no. : 00
WCL/TPP/DPM-08 Revi. Date : --
Title: SOP FOR EJECTOR SYSTEM Section No.: 13
Sr.No. Description
1 Ensure that all the drains in the auxiliary steam line are in open condition.
3 Ensure air line valves are closed for service air ejectors.
5 Ensure that steam for ejector is available at it’s design pressure & temperature.
6 Open steam valve for hogger & wait for few minutes till it is ensured no water vapour is coming
out fro the exhaust line.
1 Ensure that CEP is in operation & CST level is being maintained on auto.
Page 1 of 2
Standard Operating Procedure Issue no. : 05
Issue date: 01.04.2020
Revi no. : 00
WCL/TPP/DPM-08 Revi. Date : --
3 Identify the ejector set & open the steam for second stage ejector of service ejector .
SAFTEY PPE’s : Ear Plugs, Safety Goggles, Hand Gloves, F-rod etc.