07-10-2020

Types of Maintenance

Prepared By:
Aakash R. Suthar

What is Maintenance?
&
Why Maintenance?

1
07-10-2020

Maintenance
Maintenance is work that is carried out to
preserve an asset (such as a roof or a heating
boiler), in order to enable its continued use and
function, above a minimum acceptable level of
performance, over its design service life,
without unforeseen renewal or major repair
activities

Reasons for Maintenance


Maintenance serves to protect the owners’ real estate investment in
number of ways
• Physical Integrity
To keep the assets in good working order so as to minimize
disruptions and downtimes.
• Risk Management
To keep the assets in a state of good repair for the owners’ health and
safety.
• Aesthetic Preservation
To keep the assets from deteriorating in appearance and becoming
unsightly.
• Responsible Stewardship
To ensure that the assets achieve their full potential service life.

2
07-10-2020

• Duty of Care
To satisfy a legislated duty that is owed to owners, occupants and
guest on the property.

• Duty to Mitigate
To prevent unnecessary damage to assets that may result in their
premature failure.

Types Of Maintenance
• Breakdown maintenance
• Preventive maintenance
1. Periodic maintenance ( Time based
maintenance - TBM)
2. Predictive maintenance
I. Condition Monitoring
• Corrective maintenance

3
07-10-2020

• Break Down Maintenance

It means that people waits until equipment fails and repair it. Such a
thing could be used when the equipment failure does not significantly
affect the operation or production or generate any
significant loss other than repair cost.

• Preventive maintenance

It is a daily maintenance ( cleaning, inspection, oiling and re-tightening


), design to retain the healthy condition of equipment and prevent
failure through the prevention of deterioration, periodic inspection or
equipment condition diagnosis, to measure deterioration. It is further
divided into periodic maintenance and predictive maintenance. Just like
human life is extended by preventive medicine, the equipment service
life can be prolonged by doing preventive maintenance.

• Periodic maintenance

Time based maintenance consists of periodically inspecting,


servicing and cleaning equipment and replacing parts to prevent
sudden failure and process problems

• Predictive maintenance

This is a method in which the service life of important part is


predicted based on inspection or diagnosis, in order to use the
parts to the limit of their service life. Compared to periodic
maintenance, predictive maintenance is condition based
maintenance. It manages trend values, by measuring and
analysing data about deterioration.

4
07-10-2020

• Condition Monitoring
Condition monitoring is the process of determining the condition of
machinery while in operation.

• The key to a successful condition monitoring programme includes:


1. Knowing what to listen for
2. How to interpret it
3. When to put this knowledge to use

• Successfully using this programme enables the repair of problem


components prior to failure.

• Condition monitoring not only helps plant personnel reduce the


possibility of catastrophic failure, but also allows them to order parts
in advance, schedule manpower, and plan other repairs during the
downtime.

• Corrective maintenance
It improves equipment and its components so that preventive
maintenance can be carried out reliably. Equipment with design
weakness must be redesigned to improve reliability or
improving maintainability

5
07-10-2020

What is Maintenance?
&
Why Maintenance?

PG Department
Mr. Aakash Rajeshkumar Suthar

Maintenance

PG Department
Mr. Aakash Rajeshkumar Suthar

6
07-10-2020

Maintenance

PG Department
Mr. Aakash Rajeshkumar Suthar

Maintenance
Maintenance is work that is carried
out to preserve an asset (such as a
roof or a heating boiler), in order to
enable its continued use and
function, above a minimum
acceptable level of performance,
over its design service life, without
unforeseen renewal or major repair
activities

PG Department
Mr. Aakash Rajeshkumar Suthar

7
07-10-2020

Reasons for Maintenance


Physical Integrity
To keep the assets in good working
order so as to minimize disruptions
and downtimes.
Risk Management
To keep the assets in a state of good
repair for the owners’ health and
safety.

PG Department
Mr. Aakash Rajeshkumar Suthar

Reasons for Maintenance


Risk Management

PG Department
Mr. Aakash Rajeshkumar Suthar

8
07-10-2020

Reasons for Maintenance


Aesthetic Preservation
To keep the assets
from deteriorating
in appearance
and becoming unsightly.
Responsible Stewardship
To ensure that the assets achieve
their full potential service life.

PG Department
Mr. Aakash Rajeshkumar Suthar

Reasons for Maintenance


Duty of Care
To satisfy a legislated duty that is
owed to owners, occupants and
guest on the property.

Duty to Mitigate
To prevent unnecessary damage to
assets that may result in their
premature failure.

PG Department
Mr. Aakash Rajeshkumar Suthar

9
07-10-2020

Types Of Maintenance
• Breakdown maintenance
• Preventive maintenance
1. Periodic maintenance ( Time
based maintenance - TBM)
2. Predictive maintenance
• Condition Monitoring
• Corrective maintenance

PG Department
Mr. Aakash Rajeshkumar Suthar

Break Down Maintenance


• It means that people waits until
equipment fails and repair it.
• Such a thing could be used when
the equipment failure does not
significantly affect the operation
or production or generate any
significant loss other than repair
cost.

PG Department
Mr. Aakash Rajeshkumar Suthar

10
07-10-2020

Preventive maintenance
• It is a daily maintenance (
cleaning, inspection, oiling and
re-tightening ),
• Design to retain the healthy
condition of equipment and
prevent failure through the
prevention of deterioration,
periodic inspection or equipment
condition diagnosis, to measure
deterioration

PG Department
Mr. Aakash Rajeshkumar Suthar

Periodic maintenance
• It is a time based maintenance
• Consists of periodically
inspecting, servicing and cleaning
equipment and replacing parts to
prevent sudden failure and
process problems

PG Department
Mr. Aakash Rajeshkumar Suthar

11
07-10-2020

Predictive maintenance
• This is a method in which the
service life of important part is
predicted based on inspection or
diagnosis, in order to use the
parts to the limit of their service
life
• Compared to periodic
maintenance, predictive
maintenance is condition based
maintenance.

PG Department
Mr. Aakash Rajeshkumar Suthar

Corrective maintenance
• It improves equipment and its
components so that preventive
maintenance can be carried out
reliably.
• Equipment with design weakness
must be redesigned to improve
reliability or improving
maintainability

PG Department
Mr. Aakash Rajeshkumar Suthar

12
07-10-2020

Content
• Definition of periodic inspection
• Factors to be considered in periodic
inspection
• Procedure for periodic inspection
• Sample periodic chart general
purpose of machine

PG Department
Mr. Aakash Rajeshkumar Suthar

Definition of periodic inspection

PG Department
Mr. Aakash Rajeshkumar Suthar

13
07-10-2020

Definition of periodic inspection


• Work done in maintenance are
1. Lubrication
2. Cleaning of filters
3. Chips removals
4. Tightening of the loose bolts
5. Oil change

PG Department
Mr. Aakash Rajeshkumar Suthar

Definition of periodic inspection

PG Department
Mr. Aakash Rajeshkumar Suthar

14
07-10-2020

Definition of periodic inspection

PG Department
Mr. Aakash Rajeshkumar Suthar

Definition of periodic inspection


• It is helpful maintaining good and
efficient condition of the machine
• If the such work is done repeatedly
at a regular interval then this
process is termed as the periodic
inspection

PG Department
Mr. Aakash Rajeshkumar Suthar

15
07-10-2020

Definition of periodic inspection


• The maintenance work is required to
be done at an interval of weather in
1. Days
2. Weeks,
3. Quarterly or
4. Half yearly
• Maintenance work is decided on the
basis of the advice given by the
manufacturer the past experience to
industry

PG Department
Mr. Aakash Rajeshkumar Suthar

Factors to be considered in periodic


inspection
1. Age of the machine tools
2. Nature of production
3. Skill of operator
4. Seniority of operation
5. Type of machine tool
6. Repair complexity of machine
tool

PG Department
Mr. Aakash Rajeshkumar Suthar

16
07-10-2020

Factors to be considered in periodic


inspection
7. Repair scheme applicable
8. Total time duration repair
cycle
9. Different stages in adopted
repair cycle
10. Work involved in each stages
11. Criticality of the operation

PG Department
Mr. Aakash Rajeshkumar Suthar

Procedure for periodic inspection


• Section is carried out at various stages of the
work

• Proper charts are utilized to find the faults


and for the inspection

• In this chart the work to be done for the


inspection, lubrication, adjustment and
repairing are clearly mentioned

• By using all this the work will be done


completely

PG Department
Mr. Aakash Rajeshkumar Suthar

17
07-10-2020

Sample periodic chart general purpose of machine


include the following information and details
• Observe machine tool externally and
note down the faults in different units
• Check the condition of machine in
each units by opening the cover
• Clearness of lead screw and split nut,
saddle, carriage
• Interplay of the spindle bearing and
bearing lubrication
• Check the gear engagement and
position of the levers

PG Department
Mr. Aakash Rajeshkumar Suthar

Sample periodic chart general purpose of


machine include the following information and
details
• Check belt tension and adjust it if
found necessary
• Checking and adjust the spring
tension
• To adjust the all machine alignment

PG Department
Mr. Aakash Rajeshkumar Suthar

18
07-10-2020

Content
• Definition of Degreasing
• Different methods for the cleaning
and degreasing
• Requirement of cleaning

PG Department
Mr. Aakash Rajeshkumar Suthar

Definition of Degreasing
• It is the process of removal of
1. Dirt
2. Dust
3. Rust
4. Oil
5. Grease
• From the parts to make them ready
for inspection and measurement of
dimension

PG Department
Mr. Aakash Rajeshkumar Suthar

19
07-10-2020

Definition of Degreasing

PG Department
Mr. Aakash Rajeshkumar Suthar

Different methods for the degreasing and


cleansing
1. Cleaning using petrol, kerosene,
diesel and petrol
2. Thermal cleaning method
3. Cleaning of parts by machine
method
4. Chemical cleaning
5. Abrasive cleaning

PG Department
Mr. Aakash Rajeshkumar Suthar

20
07-10-2020

Cleaning using kerosene, diesel


and petrol
• The machine parts are washed
using
1. Petrol
2. Kerosene
3. Diesel
• Machine parts are dried using cloth
• Universally used method

PG Department
Mr. Aakash Rajeshkumar Suthar

Thermal cleaning method


• The removal of dust, dirt, rust, oil
and grease is done using burning
method
• The dust, dirt , rust , oil and grease
are burnt using the oxy acetylene
flame gas

PG Department
Mr. Aakash Rajeshkumar Suthar

21
07-10-2020

Thermal cleaning method

PG Department
Mr. Aakash Rajeshkumar Suthar

Cleaning of parts by machine method


• The cleaning of dust, dirt, rust, oil
and grease is done using
mechanical equipments like
1. Wire brush
2. Milling cutter
3. Rotary

PG Department
Mr. Aakash Rajeshkumar Suthar

22
07-10-2020

Chemical cleaning
• The grease and oil layer on the parts
of machine is in the form of sticked
layer
• It can be removed using chemical
• The chemical bath machine parts are
done and chemical used are listed
1. Lime
2. Caustic soda
3. Residual oil

PG Department
Mr. Aakash Rajeshkumar Suthar

Abrasive method
• The cleaning is done using hydraulic
sand blaster
• The sand particles are thrown on
the machine parts for the purpose
of cleaning of the surface

PG Department
Mr. Aakash Rajeshkumar Suthar

23
07-10-2020

Abrasive method

PG Department
Mr. Aakash Rajeshkumar Suthar

Requirement of cleaning
• For the inspection of the wornout
parts
• To increase the quality of the repairing
• To obtain the accurate and correct
dimension of the machine parts
• To provide a quality layer of paint so
as to increase the adhesion on the
surface3.
• For better handling of the machine
parts for during their repairs
• Improve the appearance of the parts

PG Department
Mr. Aakash Rajeshkumar Suthar

24
07-10-2020

Content
• Repair scheme
• Overhauling of the mechanical
ocmponents

PG Department
Mr. Aakash Rajeshkumar Suthar

Repair scheme
• The activities involved in the repair
scheme are
1. Inspection [I]
2. Small repair [S]
3. Medium repair [M]
4. Complete overhaul [C]

PG Department
Mr. Aakash Rajeshkumar Suthar

25
07-10-2020

Repair scheme
• The time interval between the two
complete overhaul is termed as total
cycle time
• The time interval between any two
nearby stages is termed as the
inspection time
• The time interval between small
repair and medium repair and
complete overhaul to small repair is
termed as repair time

PG Department
Mr. Aakash Rajeshkumar Suthar

Repair scheme (i)


• This repair cycle consists of many
activities like
• Drilling
• Lathe machine
• Shaping machine
• Cutting machine
• Slotting machine
• Work is done in one shift
• It will take 10 years to complete it
work at an interval of 6 months

PG Department
Mr. Aakash Rajeshkumar Suthar

26
07-10-2020

Repair scheme (i)


• When the repair complexity is upto
30 then such scheme is utilized
• It has 2- medium repairs, 6- small
repairs and 9- inspection

PG Department
Mr. Aakash Rajeshkumar Suthar

Repair scheme (ii)


• The repair cycle time is 6 years
• The interval between the two stages
is 4 months

PG Department
Mr. Aakash Rajeshkumar Suthar

27
07-10-2020

Repair scheme (ii)


• When the repair complexity is more
then such scheme is utilized
• It has 2- medium repairs 6- small
repairs and 27- inspection

PG Department
Mr. Aakash Rajeshkumar Suthar

Repair scheme
• The machine working in two shifts
then repair scheme shift should be
doubled
• For example in repair scheme (i)
work is done is one shift
• If the shift is double then the repair
shift should also be double and the
repairing work will double and
repairing work will also complete in
5 years

PG Department
Mr. Aakash Rajeshkumar Suthar

28
07-10-2020

Mechanical overhauling
• Mechanical components consists of
1. Head stock
2. Tail stock
3. Cross slide
4. Transmission mechanism
5. Gear box
• The assemblies need to dismantle
for their repairing

PG Department
Mr. Aakash Rajeshkumar Suthar

Mechanical overhauling
• Factors considered in dismantling the
sub parts of the machine are
1. Disconnect the electric connection of
the machine
2. Drain out all the residual oil form the
unit
3. Don’t apply the hammer stress on the
parts. Provide the wooden block
between the parts
4. Use tools and fixers that do not
damage

PG Department
Mr. Aakash Rajeshkumar Suthar

29
07-10-2020

Mechanical overhauling
5. Try not to damage the parts
6. Use only the specified force for
dismantling
7. Always used the necessary supports
8. Decide various groups of different
parts and place them group wise
9. Heavy parts should be placed in
stands
10.Very heavy parts should be placed in
the nearby place of assembly

PG Department
Mr. Aakash Rajeshkumar Suthar

Mechanical overhauling
11.Keep the nut and bolts in their
original pair by applying bolts on
their corresponding nuts by
developing the contacts of 2 to 3
threads

PG Department
Mr. Aakash Rajeshkumar Suthar

30
07-10-2020

Electric motor overhauling


• Electric motor are important and
efficient machine
• It requires less maintenance
• At regular time the overhauling is
required to be done otherwise
following can taker place
1. Breakdown
2. Stopping in the production
3. More repairing cost can take place
4. Early replacement of motor can occur

PG Department
Mr. Aakash Rajeshkumar Suthar

Outline
• Definition, need, steps and
advantages of preventive
maintenance.
• Steps / procedure for the periodic
and preventive maintenance of
machine tools

PG Department
Mr. Aakash Rajeshkumar Suthar

31
07-10-2020

Definition of preventive
maintenance
• It is the maintenance which stops
the wear and changes taking
place in the condition of machine
• It is the act of keeping the
machine in good condition and in
the efficient condition for the
longer period of time

PG Department
Mr. Aakash Rajeshkumar Suthar

Need of preventive
maintenance
• To increase the productivity of
the machine
• To reduce the cost of production
• To prevent the occurrence of the
fault
• To repair the fault at the early age
of the fault
• For the quality production

PG Department
Mr. Aakash Rajeshkumar Suthar

32
07-10-2020

Need of preventive
maintenance
• To avoid the obstruction of
working of machine
• To the keep the machine in good
condition

PG Department
Mr. Aakash Rajeshkumar Suthar

Steps involved in preventive


maintenance
• Training of preventive
maintenance to the operator,
fitters
• To prepare the list of item to be
checked
• To form the group of machine and
equipment
• To analyze the breakdown

PG Department
Mr. Aakash Rajeshkumar Suthar

33
07-10-2020

Steps involved in preventive


maintenance
• To get the support from the
management for preventive
maintenance
• To understand the basic idea of
preventive maintenance
• Preparation of maintenance
planning based on the past
records
• To keep the stock of spare parts

PG Department
Mr. Aakash Rajeshkumar Suthar

Advantages of preventive
maintenance
• Reduction in the stoppage time
due to reduced down time of
machine
• Number of costly repairs are
reduced
• Many repairing work will be
carried out at the same time
• The rejection of the output will be
reduced

PG Department
Mr. Aakash Rajeshkumar Suthar

34
07-10-2020

Advantages of preventive
maintenance
• More safety of machine parts and
of workers are found
• Cost of production will be
reduced
• Service life of the machine will be
increased
• The breakdown will also get
reduced
• Wear and tear of the machine will
be reduced

PG Department
Mr. Aakash Rajeshkumar Suthar

Steps / procedure for the periodic and


preventive maintenance of machine tools
• Remove the electrical connection
• Empty the oil from the sump
• Use the tools and fixtures that do
not damage the machine
• Do not damage the part directly
during the machine
• Provide the support if wood
before hammering

PG Department
Mr. Aakash Rajeshkumar Suthar

35
07-10-2020

Steps / procedure for the periodic and


preventive maintenance of machine tools
• Nut and bolts should be kept in
the special tray
• Do not heap up the spare parts
• Place them in the groups
• Heavy parts should be place in
the stand
• Very heavy pats should be placed
in the

PG Department
Mr. Aakash Rajeshkumar Suthar

Steps / procedure for the periodic and


preventive maintenance of machine tools
• Nut and bolts ahould be kept in
the pairs by applying the nuts to
their corresponding bolts
• Inspection
• Give speed and feed to the
mechanism
• Adjust the clearance
• Clear the oil filter and coolant
filter
• Provide oil and grease
PG Department
Mr. Aakash Rajeshkumar Suthar

36
07-10-2020

Steps / procedure for the periodic and


preventive maintenance of machine tools
• Inspection
• Tighten the bolts
• Change the worn-out bolts
• Change the lubrication oil as per
the schedule

PG Department
Mr. Aakash Rajeshkumar Suthar

Steps / procedure for the periodic and


preventive maintenance of machine tools
• Repairing
• Clear the parts which has more
wear
• Keep the predecided clearance
• Repair the oil pockets
• Remove the wear on the guide
surface by guiding
• Paint the machine surface
• Check and repair the machine
foundation

PG Department
Mr. Aakash Rajeshkumar Suthar

37
07-10-2020

Steps / procedure for the periodic and


preventive maintenance of machine tools
• Repairing
• Test the machine completely after
fitting
• Test the machine after every 6
months or after complete
overhauling

PG Department
Mr. Aakash Rajeshkumar Suthar

Outline
• Steps / procedure for the periodic
and preventive maintenance of
pumps
• Steps / procedure for the periodic
and preventive maintenance of
compressor
• Steps / procedure for the periodic
and preventive maintenance of
diesel generator set

PG Department
Mr. Aakash Rajeshkumar Suthar

38
07-10-2020

Steps / procedure for the periodic and


preventive maintenance of pumps
• Check whether the working of the
pump is as per the need
• Stop the leakage
• Clean the filter
• Regulate the discharge meter
using the manometer
• Tighten the bolts wherever
needed
• Provide the packing required

PG Department
Mr. Aakash Rajeshkumar Suthar

Steps / procedure for the periodic and


preventive maintenance of pumps
• Repairing
• Replace the worn out teeth and
bearing
• Replace the damage seals
• Finishing work if the gear should
be done
• Scratches on the face of the pump
should be removed
• Replace the worn-out piston

PG Department
Mr. Aakash Rajeshkumar Suthar

39
07-10-2020

Steps / procedure for the periodic and


preventive maintenance of pumps
• Repairing
• Replace the worn out pipes
• Test the pump and know the
pressure

PG Department
Mr. Aakash Rajeshkumar Suthar

Steps / procedure for the periodic and


preventive maintenance of compressor
• The air in compressor should be
clean and free form the dust
particles
• Provide the new filter
• Lubricate the compressor as per
the requirement
• Checking of the nut and bolt
should be done
• Adjust the clearance as per the
requirement

PG Department
Mr. Aakash Rajeshkumar Suthar

40
07-10-2020

Steps / procedure for the periodic and


preventive maintenance of compressor
• Check the defective switch and do
replace it if found
• Check the solenoid and replace it
if found defective
• Checking the water cooling
system

PG Department
Mr. Aakash Rajeshkumar Suthar

Steps / procedure for the periodic and


preventive maintenance of generator set
• Check the lubrication oil level
• Check the fuel level
• Check the leakage in the fuel tank
• Clean the engine and tighten the
nuts and bolts if required
• Clean all electrical connection
• Lubricate the fuel pump by oiling

PG Department
Mr. Aakash Rajeshkumar Suthar

41
07-10-2020

Outline
• Factors involved in the
formulating the program and
schedule
• Definition of maintenance
scheduling
• Procedure for maintenance
scheduling
• Schedule based on the
maintenance work
• VEIN analysis

PG Department
Mr. Aakash Rajeshkumar Suthar

Factors involved in the


formulating the program and schedule

PG Department
Mr. Aakash Rajeshkumar Suthar

42
07-10-2020

Factors involved in the


formulating the program and schedule
• Importance of the machine
• Availability of the spare parts of
the machine
• Availability of machine
• Availability of the skilled labors
• The number of hours during
which the machine is working the
during the whole day

PG Department
Mr. Aakash Rajeshkumar Suthar

Factors involved in the


formulating the program and schedule
• The stock of the spare parts
• Need of inspection frequency
• The age, condition and working of
the machine
• Repair complexity of the machine
• Policy of the management

PG Department
Mr. Aakash Rajeshkumar Suthar

43
07-10-2020

Definition of maintenance
scheduling
• The scheduling is the procedure
of preparing the time table to
carry out different maintenance
work based upon
1. Production target
2. Receipt of the material
3. Need of manpower
4. Availability of the tool
5. Requirement of service

PG Department
Mr. Aakash Rajeshkumar Suthar

Procedure for maintenance


scheduling
• Decide the standard time
requirement for the maintenance
work
• Only those machine should be
involved in the machine which
can be spared out
• Keep equal work load for the
maintenance work

PG Department
Mr. Aakash Rajeshkumar Suthar

44
07-10-2020

Procedure for maintenance


scheduling
• The maintenance work should be
carried out in the recess or in the
holiday
• A flexible time table should be
prepared
• Select the machine for the
repairing and overhauling in
number equal to square capacity
of the machine

PG Department
Mr. Aakash Rajeshkumar Suthar

Procedure for maintenance


scheduling
• The schedule should be prepared
in such a way that there should
not be any kind of loss to the
production

PG Department
Mr. Aakash Rajeshkumar Suthar

45
07-10-2020

Schedule based on the


maintenance work
The schedule of the maintenance
work is mention below

1. Emergency work
2. Non emergency work
3. New work
4. Preventive work

PG Department
Mr. Aakash Rajeshkumar Suthar

VEIN analysis
• Here the grouping of the activities
is done according to the utility
and importance
• The machine are divided in the
groups
V Vital machine
E Essential machine
I Important machine
N Normal machine

PG Department
Mr. Aakash Rajeshkumar Suthar

46
07-10-2020

Outline
• Advantages of preventive
maintenance
• Repair cycle concept

PG Department
Mr. Aakash Rajeshkumar Suthar

PG Department
Mr. Aakash Rajeshkumar Suthar

47
07-10-2020

Advantages of preventive maintenance

• Reduction in the production


stoppage
• Reduction in costly repairs
• All the repairing can be done at
the same time
• Rejection of manufactured
product will be less
• Less spare capacity of the
machine is required

PG Department
Mr. Aakash Rajeshkumar Suthar

Advantages of preventive maintenance

• Good industrial relation will be


formed
• Unit cost of production will be
reduced
• Machine will not require the
replacement before the intended
time
• Increase in the service life of the
equipment

PG Department
Mr. Aakash Rajeshkumar Suthar

48
07-10-2020

Advantages of preventive maintenance

• Increase in the productivity


• Maintenance work will became
effective and result oriented
• Modernization of the machine is
obtained
• Safe atmosphere will be found

PG Department
Mr. Aakash Rajeshkumar Suthar

Repair cycle concept

• For maintaining the good


condition following aims are
required to be achieved
1. Increase the life of the machine
2. Reduce the breakdown
3. Obtain the accuracy
4. Quality product

PG Department
Mr. Aakash Rajeshkumar Suthar

49
07-10-2020

Repair cycle concept

For maintaining good condition and


to achieve the required goals
following stages of work is required
to be done
• Inspection
• Small repair
• Medium repair
• Complete overhaul

PG Department
Mr. Aakash Rajeshkumar Suthar

Inspection

PG Department
Mr. Aakash Rajeshkumar Suthar

50
07-10-2020

Inspection
• It is not just merely checking
• Keeping the observation on
machine
• All activities are performing and
per the description given by the
manufacturer

PG Department
Mr. Aakash Rajeshkumar Suthar

Inspection
Observing the machine by running it at all speed

Adjusting the clearance of coupling, clutch, breaks

Cleaning of oil and coolant

Tightening all bolts

Replacing the worn-out bolts

Replacing the lubrication oil

PG Department
Mr. Aakash Rajeshkumar Suthar

51
07-10-2020

Small repairs

PG Department
Mr. Aakash Rajeshkumar Suthar

Small repairs
• Here each and every maintenance
activities of inspection will be
done
• The repairing work will be
distributed
• The condition of the machine will
be improved

PG Department
Mr. Aakash Rajeshkumar Suthar

52
07-10-2020

Small repairs
All the repairing work should be
carried out as per the schedule
Dismantle two to three units and
clean them
The parts that require repairing
should be repaired
Other parts beyond repairing
should be replaced
Assemble the dismantle repair
pats and run the machine

PG Department
Mr. Aakash Rajeshkumar Suthar

Medium repairs

PG Department
Mr. Aakash Rajeshkumar Suthar

53
07-10-2020

Medium repairs
Maintenance work as per the
inspection and small repairs
should be of
Repairing done first
some additional units
are carried out first
The wear of the guided surface is
improved
Layer of paint should be applied
on
Runthe outer
the surface
machine and testing
should be done as per the
accuracy required

PG Department
Mr. Aakash Rajeshkumar Suthar

Complete Overhaul

PG Department
Mr. Aakash Rajeshkumar Suthar

54
07-10-2020

Complete Overhaul
• It is the last stage of the repair
• The machine is bring back to the
original condition
• It will become capable for
working for the long time

PG Department
Mr. Aakash Rajeshkumar Suthar

Complete Overhaul
All the units are removed

Complete dismantling is done

Each part is completely checked


Repairing and replacement is done
accordingly
The wear on each part is decided on
measuring their dimension & based on
that repairing and replacement is done

PG Department
Mr. Aakash Rajeshkumar Suthar

55
07-10-2020

Complete Overhaul
The assembling of the dismantle parts is done

The clearance distance should be as per the


guidance of manufacturer

The foundation of the machine should


checked and repaired

The scrapping and grinding of the machine


should be done

PG Department
Mr. Aakash Rajeshkumar Suthar

Complete Overhaul
The testing of machine should be done by
running it in all speed

It should be checked in all accuracy

It the job is found as per the quality norms


then it is said to be as OK

If noy then corrective measures are required


to be taken

PG Department
Mr. Aakash Rajeshkumar Suthar

56
07-10-2020

PG Department
Mr. Aakash Rajeshkumar Suthar

57