Galang, Jhion Jerald M.

3-AHR

1. Using the following figure, perform resource leveling. Assume that each task can be
performed independently of the other tasks.

TASK 1
TASK 2
TASK 3
TASK 4
TASK 5
TASK 6

DAY 1 2 3 4 5 6 7 8 9 10 11 12 13 14
WORKER 3 3 3 3 3 3 2 2 3 3 3 3 3 3

completion time - 14 days

2.Using the figure in question 1, perform resource-limited scheduling. Assume that you have
only three workers available at any given time. What is the new completion date for the project?
Number workers x Number of days
Assuming task one to six has 3 workers.

Tasks # Worker
Days Days
1 4 12
2 1 3
3 1 3
4 4 12
5 1 3
6 3 9
Total: 42

Time taken for completion of the project= Total Worked Day of Workers /Number of Workers


*42/3 = 14*
The total number of days required to complete the project is 14

Day Tasks Resources


s Performed

1 1 3

2 1 3

3 1 3

4 1 3

5 2 3

6 3 3

7 4 3

8 4 3

9 4 3

10 4 3

11 5 3

12 6 3

13 6 3

14 6 3