Professional Documents
Culture Documents
BSR Imperial - RA
BSR Imperial - RA
BSR Imperial - RA
CONTENTS
Introductory Notes
1 Excavation
2 Anti Termite Treatment
3 Earth work
4 Earth work Support
5 Concrete
6 Timber form work
7 Steel Reinforcement
8 Brick Work
9 Hollow Block Masonary
10 Random Rubble Masonary
11 Pressed Tilling
12 Wall Tiling & Terrazzo Tiles
13 Roofing
14 Roof Plumbing
15 Ceiling
16 Doors & Windows
17 Iron Mongery
18 Plastering
19 Painting & Decorating
20 Plumbing (PVC)
21 External Drainage (EW pipes)
22 Plumbing (CI Pipes)
23 Man holes & Gulleys
24 Sanitary fittings
25 Gutter & Down Pipes
Note:-
In carrying out a work, besides the Basic Cost, there are other costs that have to be incurred by the conntractor,
Which costs cannot be considered as direct protective work. These costs cannot be calculated in terms of materials
and labour cost and are termed as Overheads on a job and can be grouped under two main sub heads. Thus,
The common items that make up these overheads are listed in page (2) & (3) of th analysis. The Overhead item
involved in a job is assessed as a percentage of the basic cost of the job. These percentages have been arrived
at from records of expenditure incurred in such avtivities over a period of time.
From the details in page (2) & (3) it will be seen that the job overheads is about 25% of the basic cost of the work.
Profits
10% of the baisc cost is allowed as profits and that the total mark up of the basic cost is 35%
(25% for job Overhead + 10% for profits)
Thus it will be seen tht on the basic of a work, a contractor is allowed a mark up of 35% of which 25% is the cost
of servicing the contract and 10% as contractors profit.
It will be seen that the 25% of overheads is made up of 19% as job overheads and 6% as General Overheads.
The job overheads are overheads incurred at the site and are applicable to all classes of contractors.
The general O/H howevevr, will depend on the size of the contractors organization and the facilities maintained by
the oraganization.
Thus any reduction in the O/H allowance to a contractor could be only within this 6% as General O/H and that
any reduction will be marginal.
This committee is of the opinion that all contractors (irrespective of size of their organization) should be allowed a
mark up of 35% on the basic cost as O/H and profit allowance.
Originally this Ministry had said the mark up as 30% (in 1978) and on representation made, it was increased to
35% (In the years 1978-1980) and later it was reduced to 25% and again to 22% etc. we believe that this was one
of the ……… of the deterioration of the standard of building work
In order to measure quality and strict compliance with specifications, the committee recommends 35% mark up
on the basic rates.
The Material and Labour Component required fo rthe various item of work including the minimal plant required for same
is detailed in the analysis of the Basic rates which have been included in the following pages.
Basic Rate
(a) Material
The quantities of material required for the item are computed from known data and experience. Their total value
is calculated on the basis of current costs of purchase at sources of supply. Unless otherwise stated wastage is allowed
in the norms.
(b). Transport
This component provides for the cost of transport of material from sources of supply to the sites of work. This
component is usually added to the material cost.
( c ). Labour
The labour wages are as approved by the Government from time to time and the basis of an 8 hour working day.
( d). Plant
This component provides for the minimum plant required for the items of work. the cost of tools and implement is
provided for in the O/H allowances.
The common items that make up the overhead cpsts are listed below. The cost of the overhead items involved on a job is
assessed as a percentage of the Basic cost of the job. In the case of the construction agencies executing building construc
works the overheads component may be listed as below:
General O/H
13. Head office and rent, lights, telephone, Stationary supplies, furniture etc for same
14.
Salaries of
Head
15. Transportation and subsistance of head office staff
office
Manager,
16. Insurance, Interest and Taxes on business
Engineers
17.
, Legal expences and consultancy fees
Technical
18. Workshop & Yard rents, sheds, garages & supplies
Assistants
,19. Salaries of workshop & yard storekeepers, Drivers, Foremen, Mechanics & workmen
Draughts
men,
clerks,
Profits
stenos,
10% of the basic costs is allowed as profit to the Contractor.
Typists
minor staff
and
O/H and Profit Factor
Drivers
Combining the factors for O/H and the Profits factor we get 35% of the Basic rate as the O/H and profit factor which
also called the "Mark- Up" on the Basic Rate.
This Basic Rate Analysis does not include for the use of heavy plant and equipment. This analysis provides for a labour in
method of work with a minimal use of machinary. The machinery allowed in this analysis is the concrete mixer, the vibrator
hoist in the case of a multi - storeyed building for the lift of materials to the various floors.
This analysis is applicable for a building having a maximum of four storeys. i.e. ground & three floors.
If a building has more than four floors or when the contract period is compressed to a few months, then it will be necessary
for the use of heavy machinerysuch as tower cranes, mobile cranes, dumpers, loaders, batching plant for the mixing of con
bins for the storage of concrete material etc. and also for the employment of contract managers and additional staff.
The cost of such item of work will not be accommodated within the 35% "Mark - up" and will have to be provided for in sep
such as preliminaries to the Contract.
To
To Rate
Convert Multiply by
per
Rate per
Cube m3 0.353
Square m2 0.1075
ft2 m2 10.7584
Lft m 3.28
CWT kg 0.02
Allowances to be made in the rates for lift in respect of work on upper floors
In the analysis of the various items of work in the following pages the rates to work on the ground floor.
To these rtes the percentages ( of the ground floor rates) indicated in the table below should be added to obtain the rates
applicable to the 1st, 2nd and 3rd floors. This BSR is limited to work on the ground & 3 upper floors only.
Ground to
1st Fl
Concrete ( Cube) 3%
9" Thk. Brick work (sqr) 5%
9" thk. Brick work (Cube) 5%
4 1/2" thk. Brick work ( sqr) 5%
Steel Reinforcement (CWT) 2.5%
Plastering (Sqr) 5%
Painting (Sqr) 3%
Floor Tilling (Sqr) 2%
Wall Tilling (Sqr) 2%
Roof Calicut tiles (Sqr) 3%
Roof Asbestos ( Sqr) 3%
Ceiling Work 3%
Note:
2. The analysis has been prepared for each of the above categories as shown in item Nos 3-9
3. However, in the preparation of estimates for purposes of calling for Tenderers, on;y two BOQ item would be included in
BOQ as against the BSR item No 3,4,5,6,7,8,& 9. The description of these two BOQ items would be as follows;
(a). Excavation in any material met with except roc requiring blasting
(b). Excavation in rock requiring blasting
4. This classification has been adopted (where tenders are called) to avoid any dispute that may arise as to the exact natu
soil tht will be met with when the actual excavation is carried out. The tenderer is expected to examine the site and to form
opinion of the nature of the soil that is met with and rate his tender accordingly.
5. The classification of the soil in Note 1 above and the analysis provided for the different type of soil will help the estimato
at the actual cost of excavation, for which he will have to allow in his estimate.
6. Under Note 1 (6) b Hard rock, an analysis is provided for removing Hard rock met with in foundation excavations where
prohibited or cannot be done, like in built up areas where blasting can cause damage to adjoining buildings.
7. In the excavation items Nos 3 to 9 the labour norms allowed in the items is for an excavation up to a maximum depth of
additional unskilled labourer should be added for every additional depth of 5' 0" or part thereof for each cube of excavation
the original 5' 0" depth.
by the conntractor,
d in terms of materials
ub heads. Thus,
business whether
he Overhead item
have been arrived
neral Overheads.
ilities maintained by
ral O/H and that
hould be allowed a
was increased to
ve that this was one
% of Basic Cost
1.00
4.00
0.20
0.70
0.60
0.30
0.30
0.20
0.40
0.80
0.90
0.50
0.20
1.00
0.90
1.20
0.40
0.30
0.50
1.60
3.00
19.00
0.60
1.20
1.00
0.40
0.20
2.20
0.40
6.00
50
Ground to
2nd FL
Ground to
3rd FL
5% 7%
7% 9%
7% 10%
7% 10%
5% 7.5%
10% 15%
6% 9%
4% 6%
4% 6%
6% 9%
5% 7%
5% 7%
Ready Mix
Formwork
1-Apr-2006 01 Plywood - 9 mm thk. - MR Nr 1,608.70
1-Apr-2006 02 Plywood - 12 mm thk. - MR Nr 1,782.61
1-Apr-2006 03 Plywood - 15 mm thk. - MR Nr 1,869.57
1-Apr-2006 04 Plywood - 18 mm thk. - MR Nr 2,043.48
1-Apr-2006 05 Plywood - 21 mm thk. - MR Nr 2,391.30
1-Apr-2006 06 Plywood - 25 mm thk. - MR Nr 3,043.48
1-Apr-2006 07 Plywood - 29 mm thk. - MR Nr 4,304.35
Reinforcement
01 Mild Steel - 6 mm MT
02 Mild Steel - 8 mm MT
03 Tor Steel - 10 mm MT
04 Tor Steel - 12 mm MT
05 Tor Steel - 16 mm MT
06 Tor Steel - 20 mm MT
07 Tor Steel - 25 mm MT
08 Tor Steel - 30 mm MT
09 Binding Wire kg
10
11
12
13
14
Masonary/ Plastering/Rendering
01 Bricks Nr
02 Wire cut Bricks Nr
03 Rubble 6" x 9" cu
04 Cement Blocks
11-Oct-2006 Solid - 4" Nr
11-Oct-2006 Solid - 6" Nr 61.48
11-Oct-2006 Solid - 8' Nr 83.91
Hollow - 4" Nr 27.17
Hollow - 6" Nr 40.00
Hollow - 8" Nr 54.35
Tiliing
Painting
01 Weathersheild Ltr
02 Enemel Ltr
03 Aluminium Sealer Ltr
04 Filler Ltr
05 Pre - Coat Ltr
06 Joint Compound Ltr
07 Primer Ltr
Timber
Plywood Door
Labour
Per 10 Sqr
2). Excavation over site to reduce level, in any material except rock requiring blasting including depositing & levelling as
directed upto a distance not exceeding 30' 0"
Per Cube
3). Excavation in trenches for walls/ column pits in soft/ loose soil from 0'- 0" to 5'- 0" deep & depositing excavated
material to a distance not exceeding 30' 0" (Earth work support to be paid seperately where necessary
Per Cube
4). Excavation in trenches for walls/ column pits in Ordinary soil from 0'- 0" to 5'- 0" deep & depositing excavated material
not exceeding 30' 0"
Per Cube
5). Excavation in trenches for walls/ column pits in Hard/Dense soil upto depth of 5'- 0" deep & depositing excavated
material up to a distance not exceeding 30' 0"
Per Cube
6). Excavation in trenches for walls/ column pits in Mud/Wet soil upto depth of 5'- 0" & depositing excavated material to
distance not exceeding 30' 0"
(Earthwork & dewatering paid for seperately)
Per Cube
U/Sk Labour Day 3.00 800.00 2,400.00
7). Excavation in trenches for walls/ column pits in Soft distintegrated rock (not requiring) up to a depth of 5'- 0" &
depositing excavated material to a distance not exceeding 30' 0"
Per Cube
8). Excavation in trenches for walls/ column pits in Hard rock requiring blasting up to a depth of 5'- 0" & depositing
excavated material to a distance not exceeding 30' 0"
Per Cube
Material
Blasting powder Lbs 0.75 0.00
fuse Lft 10.00 0.00
Jumper Steel Lbs 1.00 0.00
Fuel & Forge (20% of Material cost) 20% 0.00 0.00
Labour
Sk. Labour Day 1.00 1,200.00 1,200.00
U/Sk Labour Day 2.00 800.00 1,600.00
2,800.00
Per 10 ft2
Drilling,Chipping & Welding -
Sk labour Day 1 1/2 1,200.00 1,800.00
Steel,Fuel & Forge - 25% of labour cos 25% 1,800.00 450.00
Collecting & Dipositing
U/Sk Labour Day 1 1/2 800.00 1,200.00
3,450.00
Ex-1 Excavation Column footing N.E. 1.5 m deep from exsisting Ground level Incl.
Per Cube
Excavator (120) hrs 1.25 0.00
(Incl. excavation, part
return fill loading tractor
tp dispose away from
site)
Ex-2 Excavation trench for wall column foundation n.e 1.0 m deep incl. back filling & well ramming, removing surplus
excavated materials & planking & strutting working space excavation.
Per Cube
Excavator hr 0.50 0.00
Back hoe hr 0.25 0.00
Removing excess earth in tractor 583.00 0.00
Allow fo rpump 250.00 0.00
Planking & Strutting
Class II timber ft3 14.00 0.00
Add For Wedges 5% 0.00
Add Transport & Wastages 10% 0.00
Labour ft2 70.00 0.00
0.00
Rate / m3 0.00
Ex-3 Site preparation incl. clearing site vegetation excavating top soil (Avg. depth 150 mm)
Per m3
Excavator hr 0.18 0.00
Back hoe hr 0.09 0.00
Removing excess earth in tractor (8 l 583.00 0.00 1 load = 0.75 Cu
Allow fo rpump 250.00 0.00
Labour Day 0.35 0.00
0.00
Ex-4 Excavating pits n.e.1.0 m deep pit of ( 1.0 x 1.0 x 1.0 m deep)
Per m3
Excavation incl. removing of excess earth
Ex-5 Bulk excavation exceeding 2.0m but n.e 3.0 m from existing ground level. Rate shall incl. for compacting & levelling
bottom of excavation & Sand filling…………………………
Per Cube
JCB hr 2.00 0.00
Back hoe hr 0.25 0.00
Tipper Cu 3.00 0.00
Sand filling Cu 0.66 0.00
Labour day 1.50 0.00
0.00
10). Anti termite treatment on excavated foundation and compacted soil under floors.
Per Sqr
Materials
D.D.T. Powder lbs 16.00 0.00 0.00
(8% in 20 gals of water)
Water gals 20.00 5.00 100.00
Labour
U/Sk Labour Days 1/2 800.00 400.00
500.00
Note: Alternative Mixes
10). DPC
Per Sqr
Materials
Labour
Sqr 6,136.30
m2 660.53
10). DPM
Per m2
Materials
Per Cube
Per Cube
1,000.00
13). Filling under floors including levelling,Watering & Compacting in 3" layers with available and Selected earth at
site
Per Cube
14). Filling under floors including levelling,Watering & Compacting in 3" layers with available and Imported Selected
earth at site
Per Cube
3,325.00
m3 1,174.91
15). Cutting turf sods, loading to hand carts and transporting upto 30 yards, laying and watering for 30 days.
(Royalty for turf, pegging & tranport beyond 30 yards paid seperately)
Per Sqr
3,900.00
NOTE:
d). Water
Consider trench 15' 0" long, 3' 0" wide & 5' 0" depth open planking to both faces.
Total area - 2/15' 0" x 5' 0" = 150 ft2
Materials
Labour
m2 546.56
Consider trench of length of 15' 0" 3'0" wide & 5' 0" height of planking to both faces
Then area suppotorted is 2/15' x 5'
ie 150 ft2
Labour
14,340.00
m2 1,028.66
18). Earthwork support (Close planking) in deep excavation in trenches up to 15' 0" depth
Consider trench of length of 15' 0" width 5' 6" at top 3' 6" bottom
Then area suppotorted is 2/15' x 15'
ie 450 ft2
Materials
Labour
0.00
BF-1 Filling to make up level with selected excavated earth under floors
Per m3
Compactor hr 0.53
0.00
Per Cube
0.00
1). Removing top soil to a depth not exceeding 6" & depositing as directed within site Sqr
2). Excavation over site to reduce level, in any material except rock requiring blasting including Cube
depositing & levelling as directed upto a distance not exceeding 30' 0"
3). Excavation in trenches for walls/ column pits in soft/ loose soil from 0'- 0" to 5'- 0" deep & Cube
depositing excavated material to a distance not exceeding 30' 0" (Earth work support to be paid
seperately where necessary
4). Excavation in trenches for walls/ column pits in Ordinary soil from 0'- 0" to 5'- 0" deep & Cube
depositing excavated material not exceeding 30' 0"
5). Excavation in trenches for walls/ column pits in Hard/Dense soil upto depth of 5'- 0" deep & Cube
depositing excavated material up to a distance not exceeding 30' 0"
6). Excavation in trenches for walls/ column pits in Mud/Wet soil upto depth of 5'- 0" & depositing Cube
excavated material to distance not exceeding 30' 0"
7). Excavation in trenches for walls/ column pits in Soft distintegrated rock (not requiring) up to a Cube
depth of 5'- 0" & depositing excavated material to a distance not exceeding 30' 0"
8). Excavation in trenches for walls/ column pits in Hard rock requiring blasting up to a depth of 5'- Cube
0" & depositing excavated material to a distance not exceeding 30' 0"
9). Benching rock in foundation in 3"- 6" steps. (Blasting prohobited) ft2
13). Filling under floors including levelling,Watering & Compacting in 3" layers with available and Cube
Selected earth at site
14). Filling under floors including levelling,Watering & Compacting in 3" layers with available and Cube
Imported Selected earth at site
15). Cutting turf sods, loading to hand carts and transporting upto 30 yards, laying and watering for 30 Sqr
days. (Royalty for turf, pegging & tranport beyond 30 yards paid seperately)
A4 - Planking & Strutting
16). Earthwork support (open Planking) in trenches up to a depth of 5' 0" Sqr
Consider trench 15' 0" long, 3' 0" wide & 5' 0" depth open planking to both faces.
17). Earthwork support (Close planking) in trenches up to 5' 0" depth Sqr
18). Earthwork support (Close planking) in deep excavation in trenches up to 15' 0" depth Sqr
B1 - Concreting
24). 2" thk cement concrete screed in foundation at depths n.e.5' 0" Sqr
25). 3" thk cement concrete screed in foundation at depths n.e.5' 0" Sqr
32). Cement concrete in 6" x 6" beam upto 1st floor level Cube
33). Cement concrete in 9" x 6" beam upto 1st floor level Cube
34). Cement concrete in 9" x 9" beam upto 1st floor level Cube
B2 - FormWork
41). Sawn Timber F/W to 9"x 9" Cement concrete column in G/FL ft2
B3 - Reinforcement
44). Tor steel R/F to lintels slab beams for columns bent to shape laid in position & tied with GI wire CWT
as directed
44a). Mild steel R/F to lintels slab beams for columns bent to shape laid in position & tied with GI wire CWT
as directed
C1 - Brick Work
47). Brick work in cement sand 1:5 in 4 1/2" thk walls in G/FL Sqr
48). Brick work in cement sand 1:5 in 9" thk walls in G/FL Sqr
49). Brick work 13 1/2" thk in cement sand 1:5 super structure in G/FL Sqr
50). Brick work 13 1/2" thk in cement sand 1:5 super structure in G/FL Sqr
51). 4 1/2" thk Brick wall (wire cut) in cement & sand 1:5 in G/FL Sqr
52). 9" thk in cement & sand 1:5 with wire cut bricks Sqr
53). 13 1/2" thk in cement & sand 1:5 with wire cut bricks Sqr
54). Extra over for facing including raised pointing 1/8" thk in cement & sand 1:1 mixture in G/FL Sqr
57). Brick drains in cement & sand 1:5, 9" wide & 6"-9" avg. depth incl. cement rendering 1/2" thk. 1:2 Lft
to exposed faces with 1' 6" ramp incl. necessary excavation.
58). Brick drains in cement & sand 1:5, 9" wide & 6"-9" avg. depth incl. cement rendering 1/2" thk. 1:2 Lft
to exposed faces without ramp incl. necessary excavation.
C2 - Block Work
59). 8" thk Hollow block work in cement and sand mortar 1:5 in G/FL (cavities unfilled) Sqr
60). 4" thk Hollow block masonary in cement and sand mortar 1:5 cavities unfilled Sqr
C3 - Rubble Work
62). Random rubble masonary in cement mortar 1:5 in Superstructure Cu
D1 - Tilling
63). Pressed floor tiles bedded in 1/2" cement mortar 1:2 and pointing in neat cement in around floor Sqr
64). Glazed tiles fixed to walls incl. bedding in cement mortar 1:2 and raking in ground floor. (specials Sqr
measured seperately)
65). Terrazzo floor tiles on 1/2" thk cement and sand 1:2 in G/FL Sqr
E1 - Roofing
66). Timber frame work for calicut pattern tile hip roof in single storey building consisting of wall plate, Sqr
beam, ridge plate, rafters etc. (preservative treatment to be measyred seperately)
67). Roof covering with calicut pattern clay tiles in single storyed building Sqr
68). Timber framework for corrugated asbestos sheet roof in single storyed building Sqr
69). Roof covering with corrugated asbestos sheets (timber framework and ridge covering measured Sqr
seperately)
70). One layer half round clay tiles over corrugated asbestos roof covering Sqr
71). Asbestos close fittings ridging fixed complete with roofing screws or bolts (hook) Lft
72). Ridging covering with calicut pattern ridge tiles bedded in cement lime mortar 1:1:4 Lft
73). 3/4"x 9" high valance board fixed with brass screws to ends of rafters (for tile roofing) Lft
74). 3/4"x 9" high barge board fixed with brass screws at 2' 0" centres to sides of refters. Lft
F1 - Roof Plumbing
75). 18 BWG (1.2 mm) galvanised iron sheet valley gutter 3' 0" girth overall once bent with end laps Lft
not less than 9" width including 3/4" tongued and grooved planks laid to slope and profile on
timber members.
76). 18 BWG (1.2 mm) galvanised iron sheet valley gutter 1' 6" girth overall 3 times bent with end laps Lft
not less than 6", lead soldered, turned and tucked up to not less than 6" into chase cut in wall and
pointed in cement mortar 1:2 lower end dressed over roof covering not less than 1' 0" wide.
G1 - Ceiling Work
77). Timber framework for 4' 0"x 4' 0" flat asbestos ceiling (sheet measured seperately) comprising of Sqr
4"x 2" joists and 2"x 2" bearers in class I timber
78). Horizontal ceiling lining using 4' 0"x 4' 0" flat asbetos cement sheets fixed with and including Sqr
beading and cove mouldings on timber framework. (Timber framework & painting measured
seperately)
79). 3/4" thk tongued and grooved Lunumidella ceiling boards fixed horizontal on 4"x 2" class I timber Sqr
joists at 2' 0" centres with 1 1/2" brass nails
80). 3/4"x 6" wide tongued and grooved Lunumidella ceiling boards fixed to underside of roof rafters, Sqr
(existing) with 11 1/2" brass nails including levelling with timber strips where necessary.
81). Door single hung 3' 3"x 7' 0" high overall with frame having 1 1/4" thk sash and 3 3/4"x 2 3/4" ft2
timber frame. (Glazing, ironmongery & painting measured seperately)
82). Door glazed and panelled double hung 4' 0"x 7' 0" high overall with frame having 1 1/4" thk sash ft2
and 3 3/4"x 2 3/4" timber frame. (Glazing, ironmongery & painting measured seperately)
83). Plywood Door single hung 3' 1 1/2"x 6' 1 1/2 overall with frame having 1 1/4" thk sash and 3 3/4"x ft2
2 3/4" timber frame. (Glazing, ironmongery & painting measured seperately)
84). Door ledged,braced and battened single hung 2' 6" x 6' 6" overall, with frame having 7/8" thk ft2
tongued & grooved planks and 3 3/4"x 2 3/4" frame.(Iron mongery and painting measured
seperately)
85). Window, glazed 7' 0"x4' 0" high overall with frame comprising 3 no openable sashes and 3 3/4"x ft2
2' 3/4" frame and mullions
86). 1/8" clear sheet glass panes exceeding 1' 0" but n.e. 4 ft2 cut and fixed with timber beadings to ft2
doors & windows
H2 - Iron Mongery
87). Butt Hinges 5"x 2 1/2" Pair
I1 - Plastering/ Rendering
98). 3/4" thk DPC, in cement sand 1:2 finished with 2 coats hot tar and blinded with sand Sqr
99). 5/8" thk plastering to wall in lime and sand 2:5 including floating with lime putty Sqr
100). 5/8" thk plastering to wall in cement sand 1:3 including cement floating Sqr
101). 3/8" thk plastering to Soffit slab in cement sand 1:3 including floating with lime putty Sqr
102). 3/8" thk plastering to sides & Soffit of beams in cement sand 1:3 including floating with lime putty Sqr
103). 5/8" thk to wall in lime cement and sand 1:1:5 semi - rough with wooden float. Sqr
104). 5/8" thk to wall in lime cement and sand 1:1:5 finished smooth with lime putty floating Sqr
105). 1/2" thk rendering in cement and sand 1:3 finished smooth Sqr
106). 1/2" thk rendering in cement and sand 1:2 in floors, finished smooth Sqr
107). 3/4" thk rendering in cement and sand 1:3 finished smooth Sqr
108). 3/4" thk rendering in cement and sand 1:2 in floors, finished smooth Sqr
109). 3/4" thk rendering in cement and sand 1:2 in coloured cement floors, finished smooth Sqr
110). 1/2"x 6" skirting in cement and sand 1:3 projected or flush to walls finished with floating including Lft
forming groove
J1 - Painting
111). Prepare and apply one coat of preservative (oil type) to structural timber including touching up cut Sqr
ends etc. after fixing
112). Prepare surface of steel truss and apply two coat of anti - corrosive primer. Sqr
113). Apply one coat of anti - corrosive primer and two coats of enamel paint on already shop primed Sqr
and erected steel roof truss.
114). Prepare and apply two coats primer and finishing coat of enamel paint to mild steel (angle/flat) Sqr
gate.
115). Painting steel on new work with two coats of anti - corrosive paint. Sqr
116). Painting steel on new timber work with two coats of wood preservative Sqr
117). Preparing & painting wood work with primer and two coats enamel paint Sqr
120). Prepare and apply one coat of Alkail resistant primer and two coats of emulsion paint to walls Sqr
121). Prepare and apply one coat of Alkail resistant primer and two coats of emulsion paint to walls Sqr
123). Prepare & apply one coat alkali resistant primer and two coats of emulsion paint to soffit of slabs Sqr
124). Varnishing two coats with copal varnish after sandpapering Sqr
125). Wax polishing to timber in panels & floors Sqr
K1 - Plumbing PVC
126). 1/2" diameter PVC pipes fixed to walls ( Specials paid seperately) Lft
127). 3/4" diameter PVC pipes fixed to walls ( Specials paid seperately) Lft
128). 1" diameter PVC pipes fixed to walls ( Specials paid seperately) Lft
129). 1 1/4" diameter PVC pipes fixed to walls ( Specials paid seperately) Lft
130). 1 1/2" diameter PVC pipes fixed to walls ( Specials paid seperately) Lft
131 2" diameter PVC pipes fixed to walls ( Specials paid seperately) Lft
132 3" diameter PVC pipes fixed to walls ( Specials paid seperately) Lft
133 Excavaion for laying 1/2" to 3" diameter PVC pipes in ground not less than 1' - 6" deep, back Lft
filling & compacting
134 Chasing brickwork for laying 1/2" to 1 1/2" dia. PVC pipes and making good average depth 2" Lft
(pipes and Specials paid seperately)
135 Chasing brickwork for laying 1 1/2" to 3" dia. PVC pipes in ground floor and making good average Lft
depth 3" (pipes and Specials paid seperately)
152 4" dia. Glazed earthware pipes laid on 6" thick bedding in cement concrete 1:3:6 (1 1/2) including Lft
excavation average 2' 0" depth, backfilling with selected excavated materials and concrete
haunching to joints
153 4" dia. C.I soil/ vent pipe fixed vertically to walls jointed with cement caulking. (Sepecials Lft
measured seperately)
154 4" dia. C.I soil/ vent pipe fixed to walls jointed with cement caulking. (Sepecials measured Lft
seperately)
K2 - Sanitary Ware
157 22"x 16" glazed fire clay wash basin with 1/2" dia. Chromium plated pillar tap, waste plug , Nr
Chromium plated waste chain and stay, including fixing wash basin on brackets (Water supply &
waste water connection measured seperately)
158 Sink 24"x 15"x 7" overall vitreous China with rubber plug and Chromium plated chain waste Nr
carried on iron brackets painted and fixed to walls. (Water supply and waste water connection
measured seperately)
159 Closet pedestal type with L/L flushing Cistern, flush pipe double plastic seat cover, 1/2" dia. Stop Nr
cock, trap supplied & fixed complete to working order
160 Closet squatting type with trap including high level Cistern fixed complete with flush pipe & 1/2" Nr
dia. Stop cock all complete to working order
162 4 Nos Bowl type Urinal with trap & 2 gals capacity automatic flushing cistern and spreaders Nr
complete to working orders
163 6" dia. Half round PVC eaves gutter fixed to timber valamce board including gutter joiner & Lft
brackets fixed at 18" centres. (Other specials paid seperately)
1,300.00
1,800.00
1,800.00
2,800.00
2,400.00
2,000.00
2,800.00
345.00
500.00
800.00
1,000.00
1,600.00
3,325.00
3,900.00
5,077.50 ft2 50.78
0 ft2 0.00
26,212.55
15,403.27
26,902.67
33,878.40
36,108.67
6,478.72
7,702.20
16,361.59
50,592.93
51,148.49
48,926.27
16,600.00
16,274.51
21,111.11
20,777.78
23,111.11
205.00
205.00
227.78
227.78
227.78
232.22
8,966.79 Ton kg
7,928.09 Ton kg
21,163.00 Sqr m2
20,901.33 Sqr m2
15,800.00 Cu 21,066.67
1Sqr - 0.75 Cu
16,759.00 Cu 22,345.33
25,060.00 Cu 33,413.33
15,988.50 Cu 21,318.00
5,098.40 Cu 6,797.87
9,336.00 Cu 12,448.00
14,497.00 Cu 19,329.33
9,261.00 Cu 12,348.00
6,705.17 Cu 8,940.23
248.60 m 815.41
433.56 m 1,422.08
369.24 m 1,211.11
11,901.50 m2 1,281.11
7,502.34 m2 807.57
19,510.00 m3 6,893.99
21,240.00 m3 7,505.30
9,810.29 m2 1,056.01
31,962.50 m2 3,440.53
9,225.96 m2 993.11
8,976.16
1,000.00
4,253.06
5,325.14
1,600.00
37.48 m 122.94
81.77 m 268.21
185.07 m 607.03
185.07 m 607.03
1,241.78 m 4,073.03
558.94 m 1,833.32
17,245.59 m2 1,856.36
2,981.79 m2 320.97
25,996.18 m2 2,798.30
4,806.67 m2 517.40
333.33
166.67
166.67
1,000.00
113.17
2,466.67
116.67
136.67
1,429.00
166.67
13.89
7,060.97
3,835.50
7,564.50
6,146.60
5,116.60
3,541.60
8,834.00
3,529.74
4,023.00
5,103.50
5,444.50
5,937.45
81.05
3,069.65
4,025.83
4,583.00
41.74
2,139.33
2,167.63
3,710.75
540.87
643.87
2,841.15
449.93
1,116.70
3,378.65
1,366.87
2,549.42
41.95
59.64
45.35
66.86
95.76
160.10
405.84
2.25
61.38
73.46
33.02
34.53
36.04
39.07
72.09
81.16
90.22
96.27
64.53
66.80
69.07
73.60
138.13
151.73
225.33
234.40
272.00
314.83
95.83
6,614.00
4,564.00
7,531.50
6,660.50
2,000.00
71.66
515.63
780.63
217.38
31.06
179.61
153.92
Description Unit Rate
Per ft2
Concrete column length of 5' 0"
Contact area - 15.0 ft2
a). MAKING MOULD
1). Material
1/2"thk. Plywood sheet ft2 18.15 67.94 1,233.07
2"x 2" class II timber in yorks (Rubber) Lft 17.10 15.00 256.50
2"x 1" class II timber battens (rubber) Lft 16.12 7.00 112.84
Wire Nails Lb 1.50 63.49 95.24
2). Fabricating
Carpenter day 0.50 1,200.00 600.00
U/Sk Labourer day 0.50 800.00 400.00
Total Cost 2,697.64
Allowing 3 uses cost of mould per 899.21
use
b).ASSEMBLING (Per Use)
1). Material
16 mm 18" long bolts (15 uses) Nos 12.00 25.00 20.00
Mould oil Ltr 0.50 450.60 225.30
4"x 2" Props(6 uses) Lft 35.00 25.00 145.83
Labour
Carpenter day 0.25 1,200.00 300.00
U/Sk Labour day 0.25 800.00 200.00
Cost of Assembling per use 891.13
c).DISMANTLING CLEANING & REPAIRING (Per Use)
Carpenter day 0.25 1,200.00 300.00
U/Sk Labour day 0.25 800.00 200.00
Cost of Dismantling per use 500.00
Total Cost per Use(a+b+c) - 15 ft2 2,290.35
Rate per ft2 152.69
m2 1,642.94
Per ft2
Concrete 9"x 12" beams of 20' 0" long.
Contact area - 55.0 ft2
A). MAKING MOULD
1). Material
1/2"thk. Plywood sheet ft2 60.00 67.94 4,076.25
2"x 2" ledgers Lft 45.00 15.00 675.00
2"x 1" battens Lft 24.00 7.00 168.00
4"x 2"bearers at bottom of mould Lft 30.00 25.00 750.00
Wire Nails Lb 2.00 63.49 126.98
2). Labour
Carpenter day 1.50 1,200.00 1,800.00
U/Sk Labourer day 2.00 800.00 1,600.00
Total Cost 9,196.23
Allowing 3 uses cost of mould per 3,065.41
use
Add 10% for repairs 306.54
Cost per use 3,371.95
B).ASSEMBLING (Per Use)
1). Material
Wedges Nos 22.00 8.00 176.00
4"x 2" Props(6 uses) Lft 110.00 25.00 275.00
2"x 2" bracing to mould & props Lft 80.00 15.00 120.00
2"x 2" bracing to a set of props Lft 50.00 15.00 75.00
1" timber base Plate to props ft2 6.00 30.00 18.00
Cost of Assembling per use 664.00
3 uses Cost of materials per use 221.33
Add 10% of cost of materials for repairs 66.40
Total cost of material per use 287.73
C).LABOUR & SUNDRIES
Labour
Carpenter day 1.00 1,200.00 1,200.00
U/Sk Labour day 2.00 800.00 1,600.00
Mould Oil gal 0.50 450.60 225.30
Nails lbs 0.50 63.49 31.75
Cost per use 3,057.05
D).DISMANTLING CLEANING & REPAIRING (Per Use)
Carpenter day 0.50 1,200.00 600.00
U/Sk Labour day 2.00 800.00 1,600.00
Cost of Dismantling per use 2,200.00
Total Cost per Use(a+b+c) - 55 ft2 8,916.73
Rate per ft2 162.12
m2 1,744.44
Per Sqr
Concrete a slab of dismensions 20"x 10"
Contact area - 2.0 Sqrs
A). MAKING PANELS
1). Material
1/2"thk. Plywood sheet ft2 220.00 67.94 14,946.25
4"x 2"runners at 2' 0" Ctrs Lft 121.00 25.00 3,025.00
Wire Nails Lbs 4.00 63.49 253.97
2). Labour
Carpenter day 3.00 1,200.00 3,600.00
U/Sk Labourer day 3.00 800.00 2,400.00
Total Cost for making p[anels 24,225.22
Allowing 3 uses cost of mould per use 8,075.07
Add 20% for repairs 1,615.01
Cost per use 9,690.09
B).ASSEMBLING (Per Use)
1). Material
Wedges Nos 122.00 8.00 976.00
4"x 2" Props(6 uses) (Rubber) Lft 690.00 25.00 2,875.00
2"x 2" bracing to props (Rubber) Lft 66.00 15.00 99.00
1" timber base Plate to props ft2 33.00 30.00 99.00
Cost of Assembling per use 4,049.00
3 uses Cost of materials per use 1,349.67
Add 20% of cost of materials for repairs 809.80
Total cost of material per use 2,159.47
C).LABOUR & SUNDRIES
Labour
Carpenter day 1.00 1,200.00 1,200.00
U/Sk Labour day 4.00 800.00 3,200.00
Mould Oil gal 1.00 450.60 450.60
Nails lbs 2.00 63.49 126.98
Cost per use 4,977.58
D).DISMANTLING CLEANING & REPAIRING (Per Use)
Carpenter day 0.50 1,200.00 600.00
U/Sk Labour day 2.00 800.00 1,600.00
Cost of Dismantling per use 2,200.00
Total Cost per Use(A+B+C+D) - 2.00 Sqr 19,027.14
Cost Per Sqr 9,513.57
m2 1,024.07
4,076.25
675.00
168.00
750.00
126.98
5,796.23
1,932.08
193.21
2,125.29
176.00
275.00
120.00
75.00
18.00
664.00
221.33
22.13
243.47
2,368.75
225.30
31.75
2,625.80
47.74
4,774.18
CONCRETE
Preambles
Assumptions:
1 Mixing concrete using a concrete mixer 14/10 ft3 capacity and manual loading are the basis on which the norms are
worked.
2 A gang of one skilled and six U/Sk labourers produce 3.00 Cubes of concrete per day using a 14/10 ft3 capacity
concrete mixer. This is as per accepted practice
3 The production of concrete is at the mixer site transporting mixed concrete and placing same in position is paid for seperately.
4 In concrete item 26 to 39 both inclusive, placing of concrete in columns, beams and floor slab on the ground floor the labour component allowed is for
of concrete between the ground floor and the top of the 1st floor slab which area is called the ground floor area. Similarly the area between the top of
slab and the top of 2nd floor slab is called the 1st floor area etc.
Per Cube
Material
b). If, water is not available allowances should be made fo transport of water
Per Cube
Material
Note:
b). If, water is not available allowances should be made fo transport of water
Per Cube
Material
Note:
b). If, water is not available allowances should be made fo transport of water
Per Cube
Material
b). If, water is not available allowances should be made fo transport of water
Note:
b). If, water is not available allowances should be made fo transport of water
Per Sqr
Material
Concrete Cube 0.17 33,878.40 5,646.40
Add wastage 5% 5,646.40 282.32
Labour
Note:
For laying concrete at depths more than 5' 0" add 1/6 day U/Sk labourer for each
additional 5'0" or part thereof per square.
Per Sqr
Material
m2 829.09
Note:
For laying concrete at depths more than 5' 0" add 1/4 day U/Sk labourer for each
additional 5'0" or part thereof per square.
Per Sqr
Material
m2 587.07
Note:
b). If water is not available allowance must be made for transport of water
27 Cement concrete in 4 1/2" x 6" columns in ground floor (Grade 25)
Materials
Per Cu 50,592.93
Note:
1). For column in 1st floor add 3% to ground floor rate
2). For column in 2nd floor add 5% to ground floor rate
3). For column in 3rd floor add 7% to ground floor rate
4). Water available at site.
5). If water is not available allowance must ne made for transport of water
Materials
Per Cu 51,148.49
Note:
1). For column in 1st floor add 3% to ground floor rate
2). For column in 2nd floor add 5% to ground floor rate
3). For column in 3rd floor add 7% to ground floor rate
4). Water available at site.
5). If water is not available allowance must ne made for transport of water
Materials
Note:
1). For column in 1st floor add 3% to ground floor rate
2). For column in 2nd floor add 5% to ground floor rate
3). For column in 3rd floor add 7% to ground floor rate
4). Water available at site.
5). If water is not available allowance must ne made for transport of water
Materials
Per Cu 16,600.00
Note:
1). For column in 1st floor add 3% to ground floor rate
2). For column in 2nd floor add 5% to ground floor rate
3). For column in 3rd floor add 7% to ground floor rate
4). Water available at site.
5). If water is not available allowance must ne made for transport of water
31 Cement concrete in 13 1/2" x 13 1/2" columns in ground floor
Per 0.51Cube
Materials
Per Cu 16,274.51
Note:
a). Water available at site
b). If water is not available allowances must be made for transport of water
Materials
Per Cu 21,111.11
Note:
a). Water available at site
b). If water is not available allowances must be made for transport of water
Materials
Per Cu 20,777.78
Note:
a). Water available at site
b). If water is not available allowances must be made for transport of water
34 Cement concrete in 9" x 9" beam upto 1st floor level
Consider 80 Lft,
Materials
Per Cu 23,111.11
Note:
a). Water available at site
b). If water is not available allowances must be made for transport of water
Per 50 Cu ft
Materials
Note:
a). Water available at site
b). If water is not available allowances must be made for transport of water
Per 50 Cu ft
Materials
Per 45 Cu ft
Materials
Note:
a). Water available at site
b). If water is not available allowances must be made for transport of water
Consider 80 Lft
Per 45 Cu ft
Materials
Concrete Cu 45.00 0.00
Add wastage 10% 0.00 0.00
Hire vibrator day 1.00 1,800.00 1,800.00
Labour
Note:
a). Water available at site
b). If water is not available allowances must be made for transport of water
Consider 60 Lft
Per 45 Cu ft
Materials
Note:
a). Water available at site
b). If water is not available allowances must be made for transport of water
Consider 36 Lft
Per 45 Cu ft
Materials
Note:
a). Water available at site
b). If water is not available allowances must be made for transport of water
Levelling screeed in 1:2 cement sand mortar laid to falls cross falls to required levels
Per Sqr
0.00
Rate / m2 0.00
perately.
694.68 75
9,100.00
450.00
450.00
10,000.00
38,960.16
40,128.96
8,400.00 1,400.00
140.00
900.00
2,440.00
7,450.53
8,400.00 2,100.00
210.00
900.00
3,210.00
552.72 2"thk
1,700.00 170.00
-
1,200.00 480.00
1,500.00 150.00
800.00
0.125
44 Tor steel R/F to lintels slab beams for columns bent to shape laid in position & tied with GI wire as directed
Material
Tor Steel rod Cwt 1 5,901.25 5,901.25 7375
(incl.transport to site) 1106.25
Allow for wastage 15% 15% 5,901.25 885.19 97 1/2
18 BWG binding wire Lbs 1 1/2 61.22 91.84 110.625
Add steel cost for spacers or chairs 1.5% 5,901.25 88.52 8689.375
Labour
Blacksmith day 1 1,200.00 1,200.00
U/Sk labour day 1 800.00 800.00
Rate per CWT 8,966.79
44a Mild stee R/F to lintels, slab, beams for columns bent to shape laid in position & tied with GI wire as directed
Material
MS Steel rod Cwt 1 5,000.00 5,000.00
(incl.transport to site)
Allow for wastage 15% 15% 5,000.00 750.00
18 BWG binding wire Lbs 1 1/2 61.22 91.84 65
Add steel cost for spacers or chairs 1.5% 5,000.00 86.25
Labour
Blacksmith day 1 1,200.00 1,200.00
U/Sk labour day 1 800.00 800.00
Rate per CWT 7,928.09
Per M.Ton
Material
Tor Steel rod M.ton 1 0.00 0.00
Transport to site 1,000.00
Add 10% for wastage 10% 0.00 0.00
18 BWG binding wire kg 14 0.00 0.00
Spacer 1.5% 0.00 0.00
Labour
Blacksmith day 1 0.00 0.00
U/Sk labour day 1 0.00 0.00
Add 3% for Tools 3% 0.00 0.00
Rate per M.ton 1,000.00
Rate per kg 1.00
44c Diameter 10-16/ > 16.00 mm
Per M.Ton
Material
Tor Steel rod M.ton 1 140,000.00 140,000.00
Transport to site 1,000.00
Add 10% for wastage 10% 140,000.00 14,000.00
18 BWG binding wire kg 14 130.00 1,820.00
Spacer 1.5% 140,000.00 2,100.00
Labour
Blacksmith day 1 1,200.00 1,200.00
U/Sk labour day 1 800.00 800.00
Add 3% for Tools 3% 2,000.00 60.00
Rate per M.ton 160,980.00
Rate per kg 160.98 185.127
9256.35
9500
179.34 kg 179,335.86 ton
6,025.00
903.75
97.50
103.93
7,130.18
217,323.00
45 Brick work in cement sand 1:5 in foundation upto D.P.C
Per Cu
Materials
Labour
Per Cu
Materials
Labour
Per Sqr
Materials
Labour
m2 1,700.75
Per Sqr
Materials
Labour
m2 1,803.98
49 Brick work 13 1/2" thk in cement sand 1:5 super structure in G/FL
Per Sqr
Materials
Labour
50 Brick work 13 1/2" thk in cement sand 1:5 super structure in G/FL
Per Sqr
Materials
Labour
51 4 1/2" thk Brick wall (wire cut) in cement & sand 1:5 in G/FL
Per Sqr
Materials
Labour
52 9" thk in cement & sand 1:5 with wire cut bricks
Materials
Labour
53 13 1/2" thk in cement & sand 1:5 with wire cut bricks
Per Sqr
Materials
Labour
54 Extra over for facing including raised pointing 1/8" thk in cement & sand 1:1 mixture in G/FL
Per Sqr
Materials
Labour
Per Sqr
Materials
Labour
105.00
56 Steps 1' - 1 1/2" x 0'6" in brick in cement and sand 1:5 with 1/2" thk cement and sand 1:2 rendering
including necessary excavation
Per 10 Lft
Materials
Labour
57 Brick drains in cement & sand 1:5, 9" wide & 6"-9" avg. depth incl. cement rendering 1/2" thk. 1:2 to
exposed faces with 1' 6" ramp incl. necessary excavation.
Per 10 Lft
Materials
Labour
58 Brick drains in cement & sand 1:5, 9" wide & 6"-9" avg. depth incl. cement rendering 1/2" thk. 1:2 to
exposed faces without ramp incl. necessary excavation.
Per 10 Lft
Materials
Labour
58a 75 mm thk. Brick on edge to sides of plinth beam in built 1:5 Cement Sand mortar
Per 10 Lft
Materials
Labour
Per Sqr
10' 0" x 10' 0" area (size of each block 16"x 8"x 8")
Materials
Labour
60 4" thk Hollow block masonary in cement and sand mortar 1:5 cavities unfilled
Per Sqr
10' 0" x 10' 0" area (size of each block 16"x 8"x 4")
Materials
Labour
140
270
225
3435
61 Random rubble masonary in cement mortar 1:5 in Foundation
Per Cu
Materials
6"x 9" Rubble Cu 1.30 3,000.00 3,900.00 3,000.00
Cement (50 kg) cwt 5.00 682.00 3,410.00 675.00
Sand cu 0.30 7,000.00 2,100.00 7,500.00
Water gals 100.00 5.00 500.00
Labour
Mason day 4.00 1,200.00 4,800.00
U/Sk Labour day 6.00 800.00 4,800.00
Rate per Cu 19,510.00
m3 6,893.99
Per Sqr
Materials
8"x 8" Pressed tiles Nos 225.00 0.00 0.00
Add 5% for wastage 5% 0.00 0.00
Cement (50 kg) cwt 1.25 682.00 852.50
Sand Cu 0.07 7,000.00 490.00
Wax Polish Lbs 0.25 172.56 43.14
Coloured pigment Lbs 0.25 98.59 24.65
cotton waste Lbs 2.00 0.00 0.00
Labour
Mason days 4.00 1,200.00 4,800.00
U/Sk Labour days 4.50 800.00 3,600.00
Rate per Sqr 9,810.29
64 Glazed tiles fixed to walls incl. bedding in cement mortar 1:2 and raking in ground floor. (specials measured
seperately)
Per Sqr
Materials
8"x 8" Glazed tiles Nos 225.00 85.00 19,125.00
Add 10% for wastage on cuting 10% 19,125.00 1,912.50
Cement (50 kg) cwt 2.50 682.00 1,705.00
Sand Cu 0.11 7,000.00 770.00
white cement lb 1.00 50.00 50.00
Labour
Mason days 4.00 1,200.00 4,800.00
U/Sk Labour days 4.50 800.00 3,600.00
Rate per Sqr 31,962.50
m2 3,440.53
65 Terrazzo floor tiles on 1/2" thk cement and sand 1:2 in G/FL
Per Sqr
Materials
Labour
63a 300x 300 Vinyl Tile of approved colour laid over 1:3 Cement Sand Smoothed bed
Per Sqr
Materials
300x 300 Vinyl tiles Nos 105.00 269.00 28,245.00
Add 2% for Breakage 2% 28,245.00 564.90
Cement (50 kg) cwt 2.00 120.00 240.00
Sand Cu 0.10 7,000.00 700.00
Add 3% for wastage 3% 940.00 28.20
Labour
Mason days 0.50 1,200.00 600.00
U/Sk Labour days 0.50 800.00 400.00
Add 3% for Tools 3% 1,000.00 30.00
Rate per Sqr 30,808.10
Rate per m2 3,316.26
64a 150 x 150 mm Ceramic floor tiles of approved colour over including 1:3 Cement Sand Smoothed
Per Sqr
Materials
200x 200 mm Glazed non slip Ceramic Floor tiles Nos 105.00 125.00 13,125.00
Add 2 % for wastage on cuting 2% 13,125.00 262.50
Cement (50 kg) cwt 2.00 682.00 1,364.00
Sand Cu 0.10 7,000.00 700.00
Add 2% for wastage on cuting 2% 2,064.00 41.28
Labour
Mason days 2.50 1,200.00 3,000.00
U/Sk Labour days 2.50 800.00 2,000.00
Add 3 % for Tools 3% 5,000.00 150.00
Rate per Sqr 20,642.78
m2 2,222.04
65a 300x 300 mm homogeneous semi gloss Ceramic floor tiles incl. 20 mm thk. 1:3 backing
Per Sqr
Materials
300x 300 mm Homogeneous Floor tiles Nos 100.00 60.00 6,000.00
Add 2 % for wastage on cuting 2% 6,000.00 120.00
Cement (50 kg) cwt 2.50 682.00 1,705.00
Sand Cu 0.10 7,000.00 700.00
Grout lbs 1.50 54.42 81.63
Add 2% for wastage 2% 2,486.63 49.73
Labour
Tiller days 3.00 1,200.00 3,600.00
U/Sk Labour days 3.00 800.00 2,400.00
Add 3 % for Tools 3% 6,000.00 180.00
Rate per Sqr 14,836.37
m2 1,597.03
63b 100 mm high Vinyl tile skirting of approved colour & quality laid on incl. smoothed cement sand backing
Per 10.00 Lft
Vinyl skirting Nos 3.34 60.00 200.40
Add 2% for Breakage 2% 200.40 4.01
Cement (50 kg) cwt 0.03 682.00 20.46
Sand Cu 0.004 7,000.00 28.00
Add 3% for wastage 2% 48.46 0.97
Mason hr 0.75 150.00 112.50
U/Sk Labour hr 0.75 100.00 75.00
Add 3% for Tools 3% 187.50 5.63
Rate per lft 44.70
m 146.60
63c 100 mm high Ceramic tile skirting of approved colour & quality laid on incl. smoothed cement sand backing
65x 300x 300 mm matt finished cement pressed floor tiles incl. 20 mm thk. 1:3 backing
Per Sqr
Materials
300x 300 mm Homogeneous Floor tiles Nos 100.00 160.00 20,000.00
Add 2 % for wastage on cuting 2% 20,000.00 400.00
Cement (50 kg) cwt 2.50 682.00 1,705.00
Sand Cu 0.10 7,000.00 700.00
Grout lbs 1.50 54.42 81.63
Add 2% for wastage 2% 2,486.63 49.73
Labour
Tiller days 3.00 1,200.00 3,600.00
U/Sk Labour days 3.00 800.00 2,400.00
Add 3 % for Tools 3% 6,000.00 180.00
Rate per Sqr 29,116.37
m2 3,134.16
150 140.00 21,000.00
14.00 2,100.00
675.00 1,687.50
7,500.00 825.00
50.00 50.00
25,662.50
sqr
275 27,500.00
550.00
675 1,687.50 2.5
7500 750.00 0.1
62 93.00 1.5
1.86
30,582.36
119.7768997
109.9527012
140 700.00
14.00
675 20.25
7500 22.50
0.86
757.61
9.75
767.36
76.74
66 Timber frame work for calicut pattern tile hip roof in single storey building consisting of wall
plate, beam, ridge plate, rafters etc. (preservative treatment to be measyred seperately)
67 Roof covering with calicut pattern clay tiles in single storyed building
Materials
Labour
68 Timber framework for corrugated asbestos sheet roof in single storyed building
69 Roof covering with corrugated asbestos sheets (timber framework and ridge covering measured
seperately)
70 One layer half round clay tiles over corrugated asbestos roof covering
Per Sqr
Materials
Half round clay tiles Nos 650.00 0.00 0.00
Labour
U/Sk labour days 2.00 800.00 1,600.00
Total per Sqr 1,600.00
71 Asbestos close fittings ridging fixed complete with roofing screws or bolts (hook)
72 Ridging covering with calicut pattern ridge tiles bedded in cement lime mortar 1:1:4
Per 12 Lft
Materials
Ridge tiles Nos 9.00 0.00 0.00
Cement cwt 1/3 682.00 227.33
Sand Cu 0.02 7,000.00 140.00
Slaked lime lbs 15.00 4.31 64.63
Coloured Powder lbs 0.50 98.59 49.29
Labour
Mason days 0.25 1,200.00 300.00
U/Sk labour days 0.25 800.00 200.00
Per 12 lft Ridging 981.25
Per Lft 81.77
73 3/4"x 9" high valance board fixed with brass screws to ends of rafters (for tile roofing)
74 3/4"x 9" high barge board fixed with brass screws at 2' 0" centres to sides of refters.
74a Supply & fix 25x 225 mm Timber valance & barge board
Per Lm
Materials
25x 225 mm Kempass Valance board m 1.00 0.00 0.00
Add 5% for wastage 5% 0.00 0.00
40 mm long Brass Screws Nos 3.00 0.00 0.00
Labour
Carpenter hrs 0.75 0.00 0.00
U/Sk labour hrs 0.75 0.00 0.00
Add Tools & Scaffolding - 5% 5% 0.00 0.00
Per 100 Lft 0.00
Per Lft 0.00
74b Calicut Pattern tile roof with kempass timber frame work
Per Sqr
4"x3" Wall plate Lft 20.00 0.00
6"x 3" Ridge Plate Lft 10.00 0.00
4"x2" Rafters (at 2' crs) Lft 120.00 0.00
2"x 1" Reepers (at 13" crs) Lft 200.00 0.00
Calicut tile Nos 260.00 0.00
Wood Preservative gal 1.25 0.00
wire Nails kg 1.00 0.00 0.00
Add 10% for Transport & wastage 10% 0.00 0.00
Carpenter Day 2.50 0.00 0.00
U/Sk labour Day 2.50 0.00 0.00
Add Tools & Scaffolding - 5% 6% 0.00 0.00
Per Sqr 0.00
Per m2 0.00
75 18 BWG (1.2 mm) galvanised iron sheet valley gutter 3' 0" girth overall once bent with end laps not less than 9" width
including 3/4" tongued and grooved planks laid to slope and profile on timber members.
76 18 BWG (1.2 mm) galvanised iron sheet valley gutter 1' 6" girth overall 3 times bent with end laps not less than 6", lead
soldered, turned and tucked up to not less than 6" into chase cut in wall and pointed in cement mortar 1:2 lower end
dressed over roof covering not less than 1' 0" wide.
Unit Price
S/N Material Type Unit Unit
14 DDT Powder kg
18 Bricks Nr 6.00
TILE/ TERAZZO
ROOFING
50 Grade 10 m3
51 Grade 15 m3 7,000.00
52 Grade 20 m3 7,600.00
53 Grade 25 m3 7,800.00
54 Grade 30 m3 8,200.00
55 Grade 35 m3 8,600.00
IRON MONGERIES
59
TIMBER
90
NAILS
PAINTING
BRUSHES
PLUMBING
SANITARY WARE
257 30" x 18" Single bowl Single drain Sink Nos 2,200.00
290 PVC Door - 2'-6" x 6' - 9" (with frame) Nos 1,540.00
291 PVC Door - 2'-6" x 6' - 9" (Sash only) Nos 2,830.00
292 Ordinary/MR - 2' 3" - 27" (Thk 1 1/4") Mackply Nos 3,100.00
293 Ordinary/MR - 2' 6" - 30" (Thk 1 1/4") Mackply Nos 3,150.00
294 Ordinary/MR - 2' 9" - 33" (Thk 1 1/4") Mackply Nos 3,300.00
295 Ordinary/MR - 3' 0" - 36" (Thk 1 1/4") Mackply Nos 3,850.00
296 Ordinary/MR - 3' 6" - 42" (Thk 1 1/4") Mackply Nos 4,100.00
MACHINES
6.19
5.03
45.00 m3 1,590.11
45.00 m3 1,590.11
23.00 m3 812.72
21.00 m3 742.05
70.00 m3 2,473.50
30.00 m3 1,060.07
5,000.00 kg 100.00
61.22
38.55
530.04
1,705.52
Local
Local
98.59
122.45 m2 72.63
1,201.41
0.00
54.42
1,600.00 m2 419.40
643.45
85,472.38
64,439.54
23,997.20
1,667.89
64.49
124.01
310.03
1,617.09
1,798.04
41.00
41.00
1,667.89
63.49
0.00
0.00
kg
172.56
804.31
917.86
629.26
1,625.66
664.27
657.64
1,405.18
1,548.07
2,335.16
2,269.11
1,954.01
921.65
0.00
0.00
0.00
2,668.43
3,330.80
2,235.04
12.70
24.65
Harris 271
Harris 271
Harris 271
Harris 271
Harris 271
Harris 271
Harris 271
Harris 271
Harris 271
12.80 PE
26.30 PE
39.33 PE
22.33 PE
58.08 PE
40.70 PE
83.77 PE
55.11 PE
47.87 PE
141.39 PE
89.94 PE
69.97 PE
292.30 PE
179.57 PE
113.57 PE
353.40 PE
226.83 PE
154.12 PE
528.20 PE
332.22 PE
157.98 PE
1.51
Flush door
Flush door
Flush door
Flush door
Flush door
77 Timber framework for 4' 0"x 4' 0" flat asbestos ceiling (sheet measured seperately)
comprising of 4"x 2" joists and 2"x 2" bearers in class I timber
78 Horizontal ceiling lining using 4' 0"x 4' 0" flat asbetos cement sheets fixed with and
including beading and cove mouldings on timber framework. (Timber framework & painting
measured seperately)
79 3/4" thk tongued and grooved Lunumidella ceiling boards fixed horizontal on 4"x 2" class I
timber joists at 2' 0" centres with 1 1/2" brass nails
80 3/4"x 6" wide tongued and grooved Lunumidella ceiling boards fixed to underside of roof
rafters, (existing) with 11 1/2" brass nails including levelling with timber strips where
necessary.
82 Door glazed and panelled double hung 4' 0"x 7' 0" high overall with frame having 1 1/4" thk sash and 3 3/4"x
2 3/4" timber frame. (Glazing, ironmongery & painting measured seperately)
Materials
a) Frame
4"x 3" timber ft3 1 2/3 0.00 0.00
Spur stones No 2.00 0.00 0.00
Fibre/ plastic plugs with 4" long Brass screws No 6.00 0.00 0.00
5/8" mild steel dowels 4" long No 2.00 0.00 0.00
b) Sash
1 1/2" Planks ft2 16.00 0.00 0.00
1" Planks ft2 7.00 155.01 1,085.06
Labour
Carpenter Day 6.00 1,200.00 7,200.00
U/Sk Labour Day 2.00 800.00 1,600.00
Total per 28.00 ft2 9,885.06
Total per ft2 353.04
83 Plywood Door single hung 3' 1 1/2"x 6' 1 1/2 overall with frame having 1 1/4" thk sash and 3 3/4"x 2 3/4"
timber frame. (Glazing, ironmongery & painting measured seperately)
Per 21.75 ft2 (3' 1 1/2"x 6' 1 1/2")
Materials
a) Frame
84 Door ledged,braced and battened single hung 2' 6" x 6' 6" overall, with frame having 7/8" thk tongued &
grooved planks and 3 3/4"x 2 3/4" frame.(Iron mongery and painting measured seperately)
85 Window, glazed 7' 0"x4' 0" high overall with frame comprising 3 no openable sashes and 3 3/4"x 2' 3/4"
frame and mullions
86 1/8" clear sheet glass panes exceeding 1' 0" but n.e. 4 ft2 cut and fixed with timber beadings to doors &
windows
Consider sash 3' 0"x 4' 0" high with 3"x 1 1/4" style and 4 Nos glass panes
Materials
Glass panes ft2 9.00 0.00 0.00
1/2"x 1/2" Beading Lft 30.00 0.00 0.00
Brass panel pins doz 4.00 0.00 0.00
Labour
Glazier Day 1/2 1,200.00 600.00
U/Sk Labour Day 1/2 800.00 400.00
Total per 9.00 ft2 1,000.00
Total per ft2 111.11
Panelled Door
(4' x 8'-9") 3.26 m2
D4 = 21,233.10
D5
2-6 x 6-9 Marine plywood sash no 1.00 2,800.00 2,800.00
4x3 timber lft 18.00 178.05 3,204.87
lock 1.00 2,350.00 2,350.00
hinges 3.00 110.00 330.00
rawl plug 6.00 15.00 90.00
Fixing lock 750.00
Fixing sash with fittings 750.00
250.00
10,524.87
F/W
8x 8-9
3x1 timber louver lft 48.00 25.00 1,200.00
4x3 timber lft 35.50 178.05 6,320.72
1 1/4" sash ft2 50.10 172.83 8,658.78
union Lock nr 1.00 2,350.00 2,350.00
4"x 3" hinges nr 12.00 110.00 1,320.00
Tower bolt nr 4.00 120.00 480.00
Rawl plug nr 6.00 15.00 90.00
Pull rings nr 2.00 20.00 40.00
Casement stays nr 2.00 75.00 150.00
casement fastners nr 2.00 75.00 150.00
Allow panel pins 75.00
6 mm Plain glass ft2 35.98 60.00 2,158.80
Fabricating & fixing door frame Lft 35.50 50.00 1,775.00
Fixing frame to wall 800.00
Fabricating sash ft2 50.10 250.00 12,525.00
Fixing sash with fittings 1.00 750.00 750.00
fixing glass ft2 35.98 55.00 1,978.90
40,822.20
W1
4x3 timber lft 41.00 178.05 7,299.99
3x1 timber louver lft 134.32 25.00 3,358.00
2"x 1" beading lft 14.84 23.00 341.32
1 1/4" sash ft2 8.06 172.83 1,393.53
6 mm Plain glass ft2 27.10 60.00 1,626.00
Casement stays nr 2.00 75.00 150.00
casement fastners nr 2.00 75.00 150.00
Pull rings nr 2.00 20.00 40.00
Barrel bolt nr 2.00 100.00 200.00
4"x 3" hinges nr 6.00 110.00 660.00
Fabricating & fixing door frame Lft 41.00 50.00 2,050.00
Fixing frame to wall 750.00
Fabricating sash ft2 8.06 250.00 2,015.75
Fixing sash with fittings 1.00 750.00 750.00
fixing glass ft2 27.10 55.00 1,490.50
Allow Panel Pins 100.00
22,375.09
W3
4x3 timber lft 39.68 178.05 7,064.96
3x1 timber louver lft 36.00 25.00 900.00
2"x 1" beading lft 13.53 23.00 311.19
1 1/4" sash ft2 7.53 172.83 1,301.41
6 mm Plain glass ft2 14.07 60.00 844.20
Casement stays nr 3.00 75.00 225.00
casement fastners nr 3.00 75.00 225.00
Pull rings nr 3.00 20.00 60.00
Barrel bolt nr 3.00 100.00 300.00
4"x 3" hinges nr 6.00 110.00 660.00
Fabricating & fixing window frame Lft 39.68 50.00 1,984.00
Fixing frame to wall 750.00
Fabricating sash ft2 7.53 250.00 1,882.50
Fixing sash with fittings 1.00 750.00 750.00
fixing glass ft2 14.07 55.00 773.85
Allow Panel Pins 75.00
18,107.11
F
4x3 timber lft 16.50 178.05 2,937.80
3x1 timber louver lft 12.00 25.00 300.00
1 1/4" sash ft2 1.25 172.83 216.04
6 mm Plain glass ft2 1.37 60.00 82.20
Casement stays nr 1.00 75.00 75.00
casement fastners nr 0.00
Pull rings nr 1.00 20.00 20.00
Barrel bolt nr 1.00 100.00 100.00
4"x 3" hinges nr 2.00 110.00 220.00
Fabricating & fixing door frame Lft 16.50 50.00 825.00
Fixing frame to wall 500.00
Fabricating sash ft2 1.25 250.00 312.50
Fixing sash with fittings 1.00 450.00 450.00
fixing glass 200.00
Allow Panel Pins 35.00
6,273.54
w6 3,903.17
Soakage Pit
Brick work m2 6.46 1,700.75 10,994.48
Cover slab Conc. m3 0.11 9,506.24 1,071.17
FW m2 0.21 1,642.94 343.65
RF kg 15.78 179.34 2,829.08
15,238.38
13,565.58
87 Butt Hinges 5"x 2 1/2"
Material
5"x 2 1/2" Butt hinges Pairs 1 1/2 0.00 0.00
Labour
Carpenter Day 1/4 1,200.00 300.00
U/Sk Labour Day 1/4 800.00 200.00
Per 1 1/2 pairs 500.00
Per pair 333.33
Material
6"x 12" Tee hinges Pairs 1.00 0.00 0.00
Labour
Carpenter hrs 2.00 50.00 100.00
U/Sk Labour hrs 2.00 33.33 66.67
Per pairs 166.67
89 Rim Lock
Material
Rim lock with screws Nos 1.00 0.00 0.00
Labour
Carpenter hrs 2.00 50.00 100.00
U/Sk Labour hrs 2.00 33.33 66.67
Per No 166.67
90 Mortice Lock
Material
Mortice lock with screws Nos 1.00 0.00 0.00
Labour
Carpenter Day 1/2 1,200.00 600.00
U/Sk Labour Day 1/2 800.00 400.00
Per No 1,000.00
91 Casement Stays
Material
Casement Stays Nos 4.00 71.50 286.00
1/2" Brass screws Nos 16.00 0.00 0.00
Labour
Carpenter hrs 2.00 50.00 100.00
U/Sk Labour hrs 2.00 33.33 66.67
Per 04 Nos 452.67
Per No 113.17
Material
Door closer Nos 1.00 2,300.00 2,300.00
3/4" Brass screws Nos 8.00 0.00 0.00
Labour
Carpenter hrs 2.00 50.00 100.00
U/Sk Labour hrs 2.00 33.33 66.67
Per Nos 2,466.67
Material
Tower/ Skelton brass bolt Nos 1.00 75.00 75.00
1/2" Brass screws Nos 10.00 0.00 0.00
Labour
Carpenter hrs 1/2 50.00 25.00
U/Sk Labour hrs 1/2 33.33 16.67
Per Nos 116.67
94 Barrel Bolt
Material
Barrel Bolt Nos 1.00 95.00 95.00
1/2" Brass screws Nos 8.00 0.00 0.00
Labour
Carpenter hrs 1/2 50.00 25.00
U/Sk Labour hrs 1/2 33.33 16.67
Per Nos 136.67
95 Casement fastners
Material
Casement fastners Nos 6.00 71.50 429.00
1/2" Brass screws Nos 24.00 0.00 0.00
Labour
Carpenter day 1/2 1,200.00 600.00
U/Sk Labour day 1/2 800.00 400.00
Per Nos 1,429.00
Material
Brass fanlight catches Nos 6.00 0.00 0.00
1/2" Brass screws Doz 2.00 0.00 0.00
Labour
Carpenter day 1/2 1,200.00 600.00
U/Sk Labour day 1/2 800.00 400.00
Per 06 Nos 1,000.00
Per No 166.67
97 Draw rings
Material
Draw rings Nos 6.00 0.00 0.00
1/2" Brass screws Doz 1.00 0.00 0.00
Labour
Carpenter hr 1.00 50.00 50.00
U/Sk Labour hr 1.00 33.33 33.33
Per 06 Nos 83.33
Per No 13.89
98 3/4" thk DPC, in cement sand 1:2 finished with 2 coats hot tar and blinded with sand
Per Sqr
Material
Cement cwt 2.25 682.00 1,534.50
Sand cu 0.11 7,000.00 770.00
Bitumen gals 1 1/2 804.31 1,206.47
Firewood lbs 10.00 0.00
Water gals 10.00 5.00 50.00
Labour
Mason Day 1 1/4 1,200.00 1,500.00
U/Sk Labour Day 2 1/2 800.00 2,000.00
Rate per Sqr 7,060.97
760.06
99 5/8" thk plastering to wall in lime and sand 2:5 including floating with lime putty
Per Sqr
Material
Slaked lime cwt 1.30 475.00 617.50
Sand cu 0.07 7,000.00 490.00
Water gals 10.00 5.00 50.00
Labour
Mason Day 1.00 1,200.00 1,200.00
U/Sk Labour Day 1 3/4 800.00 1,400.00
Add Scaffolding - 3% 3% 2,600.00 78.00
Rate per Sqr 3,835.50
100 5/8" thk plastering to wall in cement sand 1:3 including cement floating
Per Sqr
Material
Cement (50 kg) cwt 1.40 1,080.00 1,512.00
Sand cu 0.06 18,000.00 1,080.00
Water gals 10.00 8.00 80.00
Labour
Mason Day 1.00 2,500.00 2,500.00
U/Sk Labour Day 1 1/2 1,500.00 2,250.00
Add Scaffolding - 3% 3% 4,750.00 142.50
Rate per Sqr 7,564.50 75.645
101 3/8" thk plastering to Soffit slab in cement sand 1:3 including floating with lime putty
Per Sqr
Material
Cement (50 kg) cwt 0.80 682.00 545.60
Slaked lime cwt 0.16 475.00 76.00
Sand cu 0.05 7,000.00 350.00
Water gals 5.00 5.00 25.00
Labour
Mason Day 2 1/2 1,200.00 3,000.00
U/Sk Labour Day 2 1/2 800.00 2,000.00
Add Scaffolding - 3% 3% 5,000.00 150.00
Rate per Sqr 6,146.60
102 3/8" thk plastering to sides & Soffit of beams in cement sand 1:3 including floating with
lime putty
Per Sqr
Material
Cement (50 kg) cwt 0.80 682.00 545.60
Slaked lime cwt 0.16 475.00 76.00
Sand cu 0.05 7,000.00 350.00
Water gals 5.00 5.00 25.00
Labour
Mason Day 2.00 1,200.00 2,400.00
U/Sk Labour Day 2.00 800.00 1,600.00
Add Scaffolding - 3% 3% 4,000.00 120.00
Rate per Sqr 5,116.60
103 5/8" thk to wall in lime cement and sand 1:1:5 semi - rough with wooden float.
Per Sqr
Material
Cement (50 kg) cwt 0.80 682.00 545.60 675
Slaked lime cwt 0.40 475.00 190.00 475
Sand cu 0.07 7,000.00 490.00 7500
Water gals 10.00 5.00 50.00
Labour
Mason Day 1.00 1,200.00 1,200.00
U/Sk Labour Day 1 1/4 800.00 1,000.00
Add Scaffolding - 3% 3% 2,200.00 66.00
Rate per Sqr 3,541.60
m2 381.23
104 5/8" thk to wall in lime cement and sand 1:1:5 finished smooth with lime putty floating
Per Sqr
Material
Cement (50 kg) cwt 0.80 1,080.00 864.00 675
Slaked lime cwt 0.60 800.00 480.00 475.00
Sand cu 0.07 18,000.00 1,260.00 7500
Water gals 10.00 5.00 50.00
Labour
Mason Day 1 1/2 2,500.00 3,750.00
U/Sk Labour Day 1 1/2 1,500.00 2,250.00
Add Scaffolding - 3% 3% 6,000.00 180.00
Rate per Sqr 8,834.00
m2 950.91
105 1/2" thk rendering in cement and sand 1:3 finished smooth
Per Sqr
Material
Cement (50 kg) cwt 1.07 682.00 729.74
Sand cu 0.05 7,000.00 350.00
Water gals 10.00 5.00 50.00
Labour
Mason Day 1.00 1,200.00 1,200.00
U/Sk Labour (Curing) Day 1 1/2 800.00 1,200.00
Rate per Sqr 3,529.74
106 1/2" thk rendering in cement and sand 1:2 in floors, finished smooth
Per Sqr
Material
Cement (50 kg) cwt 1.50 682.00 1,023.00
Sand cu 0.05 7,000.00 350.00
Water gals 10.00 5.00 50.00
Labour
Mason Day 1.00 1,200.00 1,200.00
U/Sk Labour Day 1 1/2 800.00 1,200.00
U/Sk Labour (Curing) Day 1/4 800.00 200.00
Rate per Sqr 4,023.00
107 3/4" thk rendering in cement and sand 1:3 finished smooth
Per Sqr
Material
Cement (50 kg) cwt 1.75 682.00 1,193.50
Sand cu 0.08 7,000.00 560.00
Water gals 10.00 5.00 50.00
Labour
Mason Day 1 1/4 1,200.00 1,500.00
U/Sk Labour Day 2.00 800.00 1,600.00
U/Sk Labour (Curing) Day 1/4 800.00 200.00
Rate per Sqr 5,103.50
108 3/4" thk rendering in cement and sand 1:2 in floors, finished smooth
Per Sqr
Material
Cement (50 kg) cwt 2.25 682.00 1,534.50
Sand cu 0.08 7,000.00 560.00
Water gals 10.00 5.00 50.00
Labour
Mason Day 1 1/4 1,200.00 1,500.00
U/Sk Labour Day 2.00 800.00 1,600.00
U/Sk Labour (Curing) Day 1/4 800.00 200.00
Rate per Sqr 5,444.50
109 3/4" thk rendering in cement and sand 1:2 in coloured cement floors, finished smooth
Per Sqr
Material
Cement (50 kg) cwt 2.25 682.00 1,534.50
Sand cu 0.08 7,000.00 560.00
Powdered pigment lbs 5.00 98.59 492.95
Water gals 10.00 5.00 50.00
Labour
Mason Day 1 1/4 1,200.00 1,500.00
U/Sk Labour Day 2.00 800.00 1,600.00
U/Sk Labour (Curing) Day 1/4 800.00 200.00
Rate per Sqr 5,937.45
110 1/2"x 6" skirting in cement and sand 1:3 projected or flush to walls finished with floating
including forming groove
110a 20 mm thk. Cement Sand Plinth Plaster to smooth finish with Cement Slurry
Per Sqr
Material
Cement (50 kg) cwt 2.00 1,080.00 2,160.00 675
Sand cu 0.10 18,000.00 1,800.00 7500
Add For Wastage 2% 3,960.00 79.20
Labour
Mason Day 1.25 2,500.00 3,125.00
U/Sk Labour Day 1.25 1,500.00 1,875.00
Add ForTools 3% 5,000.00 150.00
Rate per Sqr 9,189.20
Per m2 989.15
101a 5/8" thk plastering to Soffit slab in cement sand 1:3 including floating with lime putty
Per Sqr
Material
Cement (50 kg) cwt 1.00 682.00 682.00
Slaked lime kg 40.00 9.50 380.00
Sand cu 0.10 242.50 24.25
Add Wastage 2% 1,086.25 21.73
Water gals 5.00 5.00 25.00
Labour
Mason Day 1.50 1,200.00 1,800.00
U/Sk Labour Day 1.75 800.00 1,400.00
Add Tols & Scaffolding - 3% 3% 3,200.00 96.00
Rate per Sqr 4,428.98
m2 476.75
8,320.95
15.63
50.00
540.00
190.00
525.00
1,305.00
540.00
285.00
525.00
1,350.00
Not Required:
Powdered pigment lbs 0.25 0.00
1,350.00
750.00
42.00
2,142.00
111 Prepare and apply one coat of preservative (oil type) to structural timber
including touching up cut ends etc. after fixing
Per Sqr
Material
Wood preservative (oil Type) Ltr 2.75 629.26 1,730.45
3" Brush (1/10 use) nos 1/10 392.00 39.20
Labour
Painter Day 3/4 1,200.00 900.00
U/Sk labour Day 1/2 800.00 400.00
Rate Per Sqr 3,069.65
112 Prepare surface of steel truss and apply two coat of anti - corrosive primer.
Per Sqr
Material
Anti - corrosive primer Ltr 2 1/4 429.50 966.38
Mineral turpentine or thinner Ltr 0.15 175.50 26.33
Wire Brush Nos 1.00 0.00 0.00
2" Brush (1/8 use) use 1/8 265.00 33.13
Labour
Painter Day 1 1/2 1,200.00 1,800.00
U/Sk labour Day 1 1/2 800.00 1,200.00
Rate Per Sqr 4,025.83
113 Apply one coat of anti - corrosive primer and two coats of enamel paint on already shop primed
and erected steel roof truss.
Per Sqr
Material
Anti - corrosive primer Ltr 0.20 429.50 85.90
Enamel Paint Ltr 1 1/3 371.25 495.00
Mineral turpentine or thinner Ltr 0.20 175.50 35.10
2" Brush (1/5 use) use 1/5 265.00 53.00
Labour
Painter Day 2 1/2 1,200.00 3,000.00
U/Sk labour Day 1.00 800.00 800.00
Add scaffolding - 3% 3% 3,800.00 114.00
Rate Per Sqr 4,583.00
114 Prepare and apply two coats primer and finishing coat of enamel paint to mild steel
(angle/flat) gate.
Per 50.00Sqr
Material
Anti - corrosive primer Ltr 1 1/5 429.50 515.40
Enamel Paint Ltr 2/3 371.25 247.50
Mineral turpentine or thinner Ltr 0.20 175.50 35.10
Wire Brush Nos 1/2 0.00 0.00
2" Brush use 1/5 265.00 53.00
Labour
Painter Day 1/2 1,200.00 600.00
U/Sk labour Day 3/4 800.00 600.00
Add scaffolding - 3% 3% 1,200.00 36.00
Rate Per 50 Sqr 2,087.00
115 Painting steel on new work with two coats of anti - corrosive paint.
Per Sqr
Material
Anti - corrosive primer Ltr 2/3 429.50 286.33
2" Brush use 1/5 265.00 53.00
Labour
Painter Day 1 1/2 1,200.00 1,800.00
Rate Per Sqr 2,139.33
116 Painting steel on new timber work with two coats of wood preservative
Per Sqr
Material
Wood preservative gal 1/2 629.26 314.63
2" Brush use 1/5 265.00 53.00
Labour
Painter Day 1 1/2 1,200.00 1,800.00
Rate Per Sqr 2,167.63
117 Preparing & painting wood work with primer and two coats enamel paint
Per Sqr
Material
Primer Ltr 3/4 599.50 449.63
Enamel Paint Ltr 2 1/2 371.25 928.13
2" Brush use 1/5 265.00 53.00
Sand Paper Nos 2.00 40.00 80.00
Labour
Painter Day 1 1/2 1,200.00 1,800.00
U/Sk Labour Day 1/2 800.00 400.00
Rate Per Sqr 3,710.75
Per 10 Sqr
Material
Boiled lime cwt 0.50 0.00 0.00
Salt lbs 2.00 0.00 0.00
Yellow Ocher lbs 0.50 0.00 0.00
oze blue 2.00 0.00 0.00
6" Brush use 1/3 626.00 208.67
water gals 10.00 5.00 50.00
Labour
Painter Day 2 1/2 1,200.00 3,000.00
U/Sk Labour Day 2 1/2 800.00 2,000.00
Scaffolding - 3% 3% 5,000.00 150.00
Rate Per 10.00 Sqr 5,408.67
Per 10 Sqr
Material
Boiled lime cwt 1/2 0.00 0.00
Salt lbs 2.00 0.00 0.00
Yellow Ocher lbs 1/2 0.00 0.00
oze blue 2.00 0.00 0.00
6" Brush use 1/3 626.00 208.67
water gals 10.00 5.00 50.00
Labour
Painter Day 3.00 1,200.00 3,600.00
U/Sk Labour Day 3.00 800.00 2,400.00
Scaffolding - 3% 3% 6,000.00 180.00
Rate Per 10.00 Sqr 6,438.67
120 Prepare and apply one coat of Alkail resistant primer and two coats of emulsion paint to
walls
Per Sqr
Material
Primer Ltr 0.90 599.50 539.55 700
Emulsion Paint Ltr 1.50 409.00 613.50 565
Water gals 0.10 5.00 0.50 800
6" Brush use 1/10 626.00 62.60
Sand Papers Nos 2.00 40.00 80.00
Labour
Painter Day 1 1/4 1,200.00 1,500.00
Scaffolding - 3% 3% 1,500.00 45.00
Rate Per Sqr 2,841.15
m2 305.83
121 Prepare and apply one coat of Alkail resistant primer and two coats of emulsion paint to
walls
Per 10 Sqr
Material
Cement cwt 5/8 682.00 426.25
6" brush use 0.13 0.00 0.00
Water gals 5.00 5.00 25.00
Labour
Painter Day 2.00 1,200.00 2,400.00
U/Sk labour Day 2.00 800.00 1,600.00
Scaffolding - 3% 3% 1,600.00 48.00
Rate Per 10.00Sqr 4,499.25
Per Sqr
Material
1st Coat - Emulsion p gals 1/6 409.00 68.17
2nd Coat - Emulsion p gals 1/7 409.00 58.43
6" brush use 1/10 626.00 62.60
Water gals 0.10 5.00 0.50
Labour
Painter Day 3/4 1,200.00 900.00
Scaffolding - 3% 3% 900.00 27.00
Rate Per Sqr 1,116.70
123 Prepare & apply one coat alkali resistant primer and two coats of emulsion paint to soffit of
slabs
Per Sqr
Material
Primer Ltr 0.90 599.50 539.55
Emulsion paint Ltr 1.50 409.00 613.50
6" Brush use 0.10 626.00 62.60
Labour
Painter Day 1 3/4 1,200.00 2,100.00
Scaffolding - 3% 3% 2,100.00 63.00
Rate Per Sqr 3,378.65
Per Sqr
Material
Varnish gal 0.40 590.50 236.20
3" Brush use 1/3 392.00 130.67
Labour
Painter Day 1/2 1,200.00 600.00
U/Sk Labour Day 1/2 800.00 400.00
Rate Per Sqr 1,366.87
Per Sqr
Material
wax polish lb 3/4 172.56 129.42
Sand paper sheets 1/2 40.00 20.00
floor brush use 1/10 0.00 0.00
Flannel cloth yards 1/2 0.00 0.00
Labour
U/Sk Labour hrs 3.00 800.00 2,400.00
Rate Per Sqr 2,549.42
126 Prepare & apply two coats of emulsion paint of approved colour & quality over two coats of
Acrylic to internal wall & columns.
Per Sqr
Material
Acrylic filler Ltr 1.43 73.25 104.75 700
Emulsion paint Ltr 1.50 86.25 129.38 565
6" Brush use 1/10 95.00 9.50 800
Add Transport & Wastage 5% 243.62 12.18
Labour
Painter Day 0.75 0.00 0.00
U/sk Labour Day 1.00 0.00 0.00
Scaffolding - 3% 3% 0.00 0.00
Rate Per Sqr 255.80
127 Prepare & apply one coat of 7 two coats of weathersheild paint of approved colour & quality
over External Walls & columns
Per Sqr
Material
Primer Ltr 1.50 744.00 1,116.00 700
Weathersheild paint Ltr 1.50 372.50 558.75 730
6" Brush use 1/8 800.00 100.00 1409.5
Add Transport & Wastage 5% 1,774.75 88.74
Labour
Painter Day 0.50 0.00 0.00
U/sk Labour Day 0.50 0.00 0.00
Scaffolding - 3% 3% 0.00 0.00
Rate Per Sqr 1,863.49
128 Prepare surface & apply two coats of emulsion paint of approved colour & quality over one
coats of Acrylic filler to slabs soffit
Per Sqr
Material
Acrylic filler Ltr 1.00 610.00 610.00
Emulsion paint Ltr 1.50 326.00 489.00
6" Brush use 1/10 48.00 4.80
Add Transport & Wastage 5% 1,103.80 55.19
Labour
Painter Day 0.75 0.00 0.00
U/sk Labour Day 1.00 0.00 0.00
Scaffolding - 3% 3% 0.00 0.00
Rate Per Sqr 1,158.99
129 Apply one coats of wood preservative one coat of primer & two coats of wood sheen
Per Sqr
Material
Wood preservative gal 0.50 62.00 31.00
Primer Ltr 0.75 29.00 21.75
Wood sheen Ltr 2.50 41.00 102.50
1/2" Brush use 1/5 1,125.00 225.00
Labour
Painter Day 0.00
U/sk Labour Day 0.00
Scaffolding - 3% 3% 0.00 0.00
Rate Per Sqr 380.25
130 Prepare & apply two coats of approved emulsion paint on a primer under coat & acrylic filler to
form uniform surface to receive paint including preparation of surface of internal walls.
Per Sqr
Material
Acrylic filler Ltr 1.43 731.00 1,045.33
Primer Ltr 0.90 0.00
Emulsion paint Ltr 1.50 300.50 450.75
6" Brush use 1/10 0.00 0.00
Add Transport & Wastage 5% 1,496.08 74.80
Labour
Painter Day 0.00
U/sk Labour Day 0.00
Scaffolding - 3% 3% 0.00 0.00
Rate Per Sqr 1,570.88
1,050.00
1,095.00
80.00
111.25
2,336.25
126 1/2" diameter PVC pipes fixed to walls ( Specials paid seperately)
Per 10 Lft
Material
1/2 " Pipes Lft 13.00 12.80 166.46
Clips & Nails Nos 3.00 0.00 0.00
Solvent Cement grms 2.00 1.51 3.02
Labour
Plumber hrs 1.00 150.00 150.00
U/Sk Labour hrs 1.00 100.00 100.00
Rate per 10.00L ft 419.49
Rate per L ft 41.95
127 3/4" diameter PVC pipes fixed to walls ( Specials paid seperately)
Per 10 Lft
Material
3/4 " Pipes Lft 13.00 26.30 341.84
Clips & Nails Nos 3.00 0.00 0.00
Solvent Cement grms 3.00 1.51 4.53
Labour
Plumber hrs 1.00 150.00 150.00
U/Sk Labour hrs 1.00 100.00 100.00
Rate per 10.00L ft 596.38
Rate per L ft 59.64
128 1" diameter PVC pipes fixed to walls ( Specials paid seperately)
Material
1 " Pipes Lft 100.00 39.33 3,932.93
Add 5% for wastage 5% 3,932.93 196.65
1" Dia. sockets Nos 8.00 29.00 232.00
Solvent Cement grms 32.00 1.51 48.36
Clips & Nails Nos 35.00 0.00 0.00
Labour
Plumber hrs 1/2 150.00 75.00
U/Sk Labour hrs 1/2 100.00 50.00
Rate per 100.00L ft 4,534.93
Rate per L ft 45.35
129 1 1/4" diameter PVC pipes fixed to walls ( Specials paid seperately)
Material
1 1/4 " Pipes Lft 100.00 58.08 5,807.93
Add 5% for wastage 5% 5,807.93 290.40
1 1/4" Dia. sockets Nos 8.00 41.00 328.00
Solvent Cement grms 48.00 1.51 72.53
Clips & Nails Nos 35.00 0.00 0.00
Labour
Plumber hrs 3/4 150.00 112.50
U/Sk Labour hrs 3/4 100.00 75.00
Rate per 100.00L ft 6,686.36
Rate per L ft 66.86
130 1 1/2" diameter PVC pipes fixed to walls ( Specials paid seperately)
Material
1 1/2 " Pipes Lft 100.00 83.77 8,376.52
Add 5% for wastage 5% 8,376.52 418.83
1 1/2" Dia. sockets Nos 8.00 62.00 496.00
Solvent Cement grms 64.00 1.51 96.71
Clips & Nails Nos 35.00 0.00 0.00
Labour
Plumber hrs 3/4 150.00 112.50
U/Sk Labour hrs 3/4 100.00 75.00
Rate per 100.00L ft 9,575.56
Rate per L ft 95.76
131 2" diameter PVC pipes fixed to walls ( Specials paid seperately)
Material
2 " Pipes Lft 100.00 141.39 14,138.72
Add 5% for wastage 5% 14,138.72 706.94
2" Dia. sockets Nos 8.00 101.00 808.00
Solvent Cement grms 112.00 1.51 169.24
Clips & Nails Nos 35.00 0.00 0.00
Labour
Plumber hrs 3/4 150.00 112.50
U/Sk Labour hrs 3/4 100.00 75.00
Rate per 100.00L ft 16,010.40
Rate per L ft 160.10
132 3" diameter PVC pipes fixed to walls ( Specials paid seperately)
Material
3 " Pipes Lft 100.00 353.40 35,340.45
Add 5% for wastage 5% 35,340.45 1,767.02
3" Dia. sockets Nos 8.00 365.50 2,924.00
Solvent Cement grms 200.00 1.51 302.22
Clips & Nails Nos 35.00 0.00 0.00
Labour
Plumber hrs 1.00 150.00 150.00
U/Sk Labour hrs 1.00 100.00 100.00
Rate per 100.00L ft 40,583.69
Rate per L ft 405.84
133 Excavaion for laying 1/2" to 3" diameter PVC pipes in ground not less than 1' - 6" deep, back filling &
compacting
Labour
U/Sk Labour hrs 2 1/4 100.00 225.00
Rate per 100.00L ft 225.00
Rate per L ft 2.25
134 Chasing brickwork for laying 1/2" to 1 1/2" dia. PVC pipes and making good average depth 2" (pipes and
Specials paid seperately)
Material
Cement cwt 0.10 682.00 68.20
Sand Cube 0.01 7,000.00 70.00
Labour
Mason day 3.00 1,200.00 3,600.00
U/Sk Labour day 3.00 800.00 2,400.00
Rate per 100.00L ft 6,138.20
Rate per L ft 61.38
135 Chasing brickwork for laying 1 1/2" to 3" dia. PVC pipes in ground floor and making good average depth 3"
(pipes and Specials paid seperately)
Material
Cement cwt 0.20 682.00 136.40
Sand Cube 0.03 7,000.00 210.00
Labour
Mason day 3 1/2 1,200.00 4,200.00
U/Sk Labour day 3 1/2 800.00 2,800.00
Rate per 100.00L ft 7,346.40
Rate per L ft 73.46
Per 10 Specials
Material
1/2" elbow/bends/socket Nos 10.00 0.00
Solvent Cement grms 20.00 1.51 30.22
Labour
Plumber hrs 2.00 150.00 300.00
Rate per 10 Specials 330.22
Rate per Special 33.02
Per 10 Specials
Material
3/4" elbow/bends/socket Nos 10.00 0.00
Solvent Cement grms 30.00 1.51 45.33
Labour
Plumber hrs 2.00 150.00 300.00
Rate per 10 Specials 345.33
Rate per Special 34.53
Per 10 Specials
Material
1" elbow/bends/socket Nos 10.00 0.00
Solvent Cement grms 40.00 1.51 60.44
Labour
Plumber hrs 2.00 150.00 300.00
Rate per 10 Specials 360.44
Rate per Special 36.04
Per 10 Specials
Material
1 1/4" elbow/bends/socket Nos 10.00 0.00
Solvent Cement grms 60.00 1.51 90.67
Labour
Plumber hrs 2.00 150.00 300.00
Rate per 10 Specials 390.67
Rate per Special 39.07
Per 10 Specials
Material
1 1/2" elbow/bends/socket Nos 10.00 0.00
Solvent Cement grms 80.00 1.51 120.89
Labour
Plumber day 1/2 1,200.00 600.00
Rate per 10 Specials 720.89
Rate per Special 72.09
Per 10 Specials
Material
2" elbow/bends/socket Nos 10.00 0.00
Solvent Cement grms 140.00 1.51 211.56
Labour
Plumber day 1/2 1,200.00 600.00
Rate per 10 Specials 811.56
Rate per Special 81.16
Per 10 Specials
Material
2 1/2" elbow/bends/socket Nos 10.00 0.00
Solvent Cement grms 200.00 1.51 302.22
Labour
Plumber day 1/2 1,200.00 600.00
Rate per 10 Specials 902.22
Rate per Special 90.22
143 3" dia. PVC specials viz-elbow/bends/sockets.
Per 10 Specials
Material
3" elbow/bends/socket Nos 10.00 0.00
Solvent Cement grms 240.00 1.51 362.67
Labour
Plumber day 1/2 1,200.00 600.00
Rate per 10 Specials 962.67
Rate per Special 96.27
Per 10 Nr
Material
1/2" Tees Nos 10.00 0.00
Solvent Cement grms 30.00 1.51 45.33
Labour
Plumber day 1/2 1,200.00 600.00
Rate per 10 Nr 645.33
Rate per Nr 64.53
Per 10 Nr
Material
3/4" Tees Nos 10.00 0.00
Solvent Cement grms 45.00 1.51 68.00
Labour
Plumber day 1/2 1,200.00 600.00
Rate per 10 Nr 668.00
Rate per Nr 66.80
Material
1" Tees Nos 10.00 0.00
Solvent Cement grms 60.00 1.51 90.67
Labour
Plumber day 1/2 1,200.00 600.00
Rate per 10 Nr 690.67
Rate per Nr 69.07
Per 10 Nr
Material
1 1/4" Tees Nos 10.00 0.00
Solvent Cement grms 90.00 1.51 136.00
Labour
Plumber day 1/2 1,200.00 600.00
Rate per 10 Nr 736.00
Rate per Nr 73.60
Per 10 Nr
Material
1 1/2" Tees Nos 10.00 0.00
Solvent Cement grms 120.00 1.51 181.33
Labour
Plumber day 1.00 1,200.00 1,200.00
Rate per 10 Nr 1,381.33
Rate per Nr 138.13
Per 10 Nr
Material
2" Tees Nos 10.00 0.00
Solvent Cement grms 210.00 1.51 317.33
Labour
Plumber day 1.00 1,200.00 1,200.00
Rate per 10 Nr 1,517.33
Rate per Nr 151.73
Per 10 Nr
Material
2 1/2" Tees Nos 10.00 0.00
Solvent Cement grms 300.00 1.51 453.33
Labour
Plumber day 1 1/2 1,200.00 1,800.00
Rate per 10 Nr 2,253.33
Rate per Nr 225.33
Per 10 Nr
Material
3" Tees Nos 10.00 0.00
Solvent Cement grms 360.00 1.51 544.00
Labour
Plumber day 1 1/2 1,200.00 1,800.00
Rate per 10 Nr 2,344.00
Rate per Nr 234.40
152 4" dia. Glazed earthware pipes laid on 6" thick bedding in cement concrete 1:3:6 (1 1/2) including excavation
average 2' 0" depth, backfilling with selected excavated materials and concrete haunching to joints
Material
4" dia. EW pipes Nos 50.00 0.00 0.00
Cement concrete 1:3:6 (1 1/2") cu 0.75 26,212.55 19,659.41
Yarn lbs 2.00 0.00 0.00
Cement (jointing) cwt 0.50 682.00 341.00
Excavation cu 4.00 0.00
Labour
Laying concrete bedding
U/Sk labourer day 1 1/2 800.00 1,200.00
laying and testing pipes
Plumber day 2.00 1,200.00 2,400.00
U/Sk labourer day 2.00 800.00 1,600.00
Backfilling
U/Sk labourer day 2 1/2 800.00 2,000.00
Rate 100 L ft 27,200.41
Rate per L ft 272.00
153 4" dia. C.I soil/ vent pipe fixed vertically to walls jointed with cement caulking. (Sepecials measured
seperately)
Material
4" dia. C.I. pipe Lft 6.00 0.00 0.00
Add 10% for wastage 10% 0.00 0.00
Yarn lbs 5/16 0.00 0.00
Timber plug 6"x6"x2" Nos 1.00 0.00 0.00
3" Iron screws Nos 2.00 0.00 0.00
cement lbs 2.00 682.00 1,364.00
Labour
Plumber day 1/4 1,200.00 300.00
U/Sk labourer day 1/4 800.00 200.00
Add Scaffolding 5% 500.00 25.00
Rate 6 L ft 1,889.00
Rate per L ft 314.83
154 4" dia. C.I soil/ vent pipe fixed to walls jointed with cement caulking. (Sepecials measured seperately)
Material
4" dia. C.I. pipe Lft 6.00 0.00 0.00
Add 10% for wastage 10% 0.00 0.00
lead lbs 6.00 0.00
yarn lbs 5/16 0.00 0.00
Timber plug 6"x6"x2" Nos 1.00 0.00 0.00
3" Iron screws Nos 2.00 0.00 0.00
Fire wood cwt 1/16 0.00
Labour
Plumber day 1/4 1,200.00 300.00
U/Sk labourer day 1/4 800.00 200.00
ADD Sundries in cement & sand 10% 500.00 50.00
Add Scaffolding 5% 500.00 25.00
Rate 6 L ft 575.00
Rate per L ft 95.83
155 4" dia. Stoneware gully with 6"x 6"x 6" gulley box including excavation, 4" cement concrete 1:2:4 (3/4")
base, surrounded by 4 1/2" thick cement & sand 1:5 extended 6" above top of gulley box including making
connection, 1/2" cement and sand 1:2 rendering internally and exposed faces finished smooth with neat
cement floating and providing G.I.grating on top of gulley
Per No
Material
4" dia. Stoneware gulley Nr 1.00 265.00 265.00
Excavation ft3 4.00 0.00 0.00
4 1/2" Brick work ft2 5.50 0.00
Cement Concrete 1:2:4 (3/4") ft3 0.80 0.00 0.00
1/2" Cemenr rendering 1:2 ft2 1.00 429.50 429.50
4" G.I. Grating Nos 1.00 166.25 166.25
Labour
Mason day 1/2 0.00 0.00
U/Sk labourer day 1/2 0.00 0.00
Rate per Nr 860.75
156 Manhole 2'0"x 2'0" internally with invert depth n.e. 2'0" including excavation, backfilling 6" cement concrete
1:2:4 (3/4") base with 3/8" dia. Mild steel rods at 4" centres bothways , forming channels and benching in
similarconcrete, 4 1/2" walls in brick in cement 1:5, 1/2" thick cement and sand 1:2 rendering internally and
exposed surfaces including channels , benching and 2" thick RCC removable cover slab 2'3"x 2'3" inlet &
outlet connection all complete to working order.
Per No
Material
Excavation ft3 35.00 0.00 0.00
4 1/2" Brick work in Cement 1:5 ft2 33.00 0.00
Cement Concrete 1:2:4 (3/4") in base & channels ft3 7.00 429.75 3,008.25
1/2" Cemenr rendering 1:2 ft2 28.00 0.00 0.00
RCC cover slab Nos 1.00 54.35 54.35
Labour
Mason day 1 1/2 0.00 0.00
U/Sk labourer day 2 1/2 0.00 0.00
Rate per Nr 3,062.60
157 22"x 16" glazed fire clay wash basin with 1/2" dia. Chromium plated pillar tap, waste plug
, Chromium plated waste chain and stay, including fixing wash basin on brackets (Water supply &
waste water connection measured seperately)
Per No
Material
Wash basin Complete with brackets Nos 1.00 0.00 0.00
1/2" tap Nos 1.00 3,850.00 3,850.00
Waste plug & chain Nos 1.00 0.00 0.00
Wooden plug Nos 4.00 0.00 0.00
1 1/2" Brass screws Nos 6.00 0.00 0.00
Cement lbs 2.00 682.00 1,364.00
Labour
Mason day 1/2 1,200.00 600.00
U/Sk Labour day 1.00 800.00 800.00
Rate per No 6,614.00
158 Sink 24"x 15"x 7" overall vitreous China with rubber plug and Chromium plated chain waste
carried on iron brackets painted and fixed to walls. (Water supply and waste water connection
measured seperately)
Per No
Material
24"x 15"x 7" Sink Nos 1.00 2,200.00 2,200.00
L Iron brackets Nos 2.00 0.00 0.00
Cement lbs 2.00 682.00 1,364.00
2" thk. Tapered wooden blocks Nos 2.00 0.00
1 1/2" brass screws Nos 8.00 0.00 0.00
Labour
Mason day 1/2 1,200.00 600.00
U/Sk Labour day 1/2 800.00 400.00
Rate per No 4,564.00
159 Closet pedestal type with L/L flushing Cistern, flush pipe double plastic seat cover, 1/2" dia.
Stop cock, trap supplied & fixed complete to working order
Per No
Material
L/L Suite Complete Nos 1.00 0.00 0.00
1/2" dia. Stop cock Nos 1.00 3,850.00 3,850.00
Cement lbs 2.00 682.00 1,364.00
Sand ft3 1/4 70.00 17.50
1 1/2" brass screws Nos 2.00 0.00 0.00
Labour
Mason day 1/4 1,200.00 300.00
Plumber day 1.00 1,200.00 1,200.00
U/Sk Labour day 1.00 800.00 800.00
Rate per No 7,531.50
160 Closet squatting type with trap including high level Cistern fixed complete with flush pipe &
1/2" dia. Stop cock all complete to working order
Per No
Material
Squatting pan with trap Nos 1.00 0.00 0.00
2 gals CI Cistern with 1 1/4" flush pipe, chain & Nos 1.00 0.00 0.00
overflow pipe Stop cock
Labour
Mason day 1/2 1,200.00 600.00
Plumber day 1.00 1,200.00 1,200.00
U/Sk Labour day 1.00 800.00 800.00
Rate per No 6,660.50
Per No
Material
Bidet Nos 1.00 0.00 0.00
Labour
Plumber day 1.00 1,200.00 1,200.00
U/Sk Labour day 1.00 800.00 800.00
Rate per No 2,000.00
162 4 Nos Bowl type Urinal with trap & 2 gals capacity automatic flushing cistern and spreaders
complete to working orders
Per 04 No
Material
Urinal Bowls Nos 4.00 0.00 0.00
2 gal Cistern Nos 1.00 0.00 0.00
Rawl plug Nos 8.00 2.50 20.00
Spreader Nos 1.00 3,590.00 3,590.00
Wooden Plugs (for Cistern) Nos 4.00 0.00 0.00
1 1/2" brass screws Nos 4.00 0.00 0.00
Cement lbs 4.00 682.00 2,728.00
Sand ft3 1/8 70.00 8.75
Labour
Mason day 1/4 1,200.00 300.00
Plumber day 1.00 1,200.00 1,200.00
U/Sk Labour day 1.00 800.00 800.00
Rate per 04 No 8,646.75
Rate per No 2,161.69
163 6" dia. Half round PVC eaves gutter fixed to timber valamce board including gutter
joiner & brackets fixed at 18" centres. (Other specials paid seperately)
Material
12'- 6" dia. Eaves gutter lengths 2.00 0.00 0.00
Joiner Nos 1.00 81.75 81.75
Gutter Brackets Nos 17.00 35.75 607.75
3/4" Brass Screws Nos 34.00 0.00 0.00
Solvent Cement gms 20.00 1.51 30.22
Labour
Plumber day 1/2 1,200.00 600.00
U/Sk Labour day 1/2 800.00 400.00
Rate per 24.00 Lft 1,719.72
Rate per Lft 71.66
Per 01 Nr
Material
PVC Gutter head Nos 1.00 0.00 0.00
Gutter Joiners Nos 2.00 81.75 163.50
Gutter Brackets Nos 2.00 35.75 71.50
3/4" Brass Screws Nos 4.00 0.00 0.00
Solvent Cement gms 12.00 1.51 18.13
Labour
Plumber day 1/8 1,200.00 150.00
U/Sk Labour day 1/8 800.00 100.00
Scaffolding 5% 250.00 12.50
Rate per Nr 515.63
Per 01 Nr
Material
Mitre bend Nos 1.00 265.00 265.00
Gutter Joiners Nos 2.00 81.75 163.50
Gutter Brackets Nos 2.00 35.75 71.50
3/4" Brass Screws Nos 4.00 0.00 0.00
Solvent Cement gms 12.00 1.51 18.13
Labour
Plumber day 1/8 1,200.00 150.00
U/Sk Labour day 1/8 800.00 100.00
Scaffolding 5% 250.00 12.50
Rate per Nr 780.63
Per 01 Nr
Material
End cap Nos 1.00 68.00 68.00
Solvent Cement gms 12.00 1.51 18.13
Labour
Plumber day 1/16 1,200.00 75.00
U/Sk Labour day 1/16 800.00 50.00
Scaffolding 5% 125.00 6.25
Rate per Nr 217.38
167 3 1/2" dia. PVC rain water down pipes fixed to brick wall with wooden plug buried in wall.
(specials measured seperately)
Material
3 1/2" dia. Pipe Length 2.00 0.00
3 1/2" Joiner Nos 1.00 0.00 0.00
PVC Straps Nos 4.00 0.00 0.00
Brass Screws 1" long Nos 8.00 0.00 0.00
Solvent Cement gms 30.00 1.51 45.33
Labour
Plumber day 1/3 1,200.00 400.00
U/Sk Labour day 1/3 800.00 266.67
Scaffolding 5% 666.67 33.33
Rate per 24.00 Lft 745.33
Rate per Lft 31.06
Per Nr
Material
600/800 Elbow Nos 2.00 0.00 0.00
Solvent Cement gms 32.00 1.51 48.36
Labour
Plumber day 1/16 1,200.00 75.00
U/Sk Labour day 1/16 800.00 50.00
Scaffolding 5% 125.00 6.25
Rate per Nr 179.61
Per Nr
Material
600/800 Shoe Nos 1.00 0.00 0.00
Solvent Cement gms 15.00 1.51 22.67
Labour
Plumber day 1/16 1,200.00 75.00
U/Sk Labour day 1/16 800.00 50.00
Scaffolding 5% 125.00 6.25
Rate per Nr 153.92
Description Unit Rate
MACHINES
Excavator Hrs
Dozer Day
3.28 Ft
1.00 m =
1.094 yard
1.00 Ft = 0.305 m
0.093 m2 25 mm 3.854
1.00 Ft2 =
0.01 Sqr
Volume
2.83 m3
1.00 Cu =
100 Ft3
0.353 Cu
35.288 Ft3
1000 Ltr
1.00 m3 =
61027 in3
1.308 yd3
264.186 gal
0.283 m3
1.00 Ft3 =
0.010 Cu
3.785 Ltr
1.00 gal =
0.003785 m3
Weight
0.02 CWT
1.00 Kg = 35.273 oz
2.205 pound
1.00 CWT = 50 Kg