INSPECTION TEST PLAN

CCTV INSPECTION SURVEY


Document No.: PMS-ITP-AJE-08-2201-2020 Project Title: HIAEPSC-0014 REMOTE TRANSFER BAGGAGE FACILITY BUILDING Contract No.:

ACTIVITY INSPECTION
ACTIVITY DESCRIPTION INSPECTION & TEST REQUIRED CONTROLLING DOCUMENT INSPECTION FREQUENCY ACCEPTANCE CRITERIA VERIFYING DOCUMENTS
NO.
PMS CONT Consultant

DOCUMENT SUBMITTAL

1
Material Submittal, Method Statement As per Project Specification & QCS 2014 Prior to Start Review & Approval by Consulting Document Submittal H H R

MATERIAL, HANDLING AND STORAGE using CCTV SURVEY EQUIPMENT


INSPECTION

Materials Submittal, As per Project Specification, Delivery Receipt, Material &


a. CCTV Scanner Equipment Every Delivery , Before Assembly Visual Inspection, Proper Storage H H H
QCS 2014 Section 8 part 10 Equipment Inspection Request
2
Materials Submittal, As per Project Specification, Delivery Receipt, Material &
b. CCTV Van Equipped Every Delivery , Before Assembly Visual Inspection, Proper Storage H H H
QCS 2014 Section 8 part 10 Equipment Inspection Request

Delivery Receipt, Material &


c. Generator Materials Submittal, Method Statement Every Delivery Visual Inspection, Proper Storage H H H
Equipment Inspection Request

EXECUTION WORK FOR CCTV SURVEY INSPECTION FOR PIPE LINES

3
High Pressure Jetting Cleaning/Pre Cleaning Method Statement, QCS 2014 section 8 part 10 Prior to Start All surface Clean, Visual Inspection Work Inspection Report H H W

As per Standard EN 13508-2014 Method


CCTV Survey Inspection Operation After Completion each area/location/work After Assembly, Visual Inspection Work Inspection Report H H H
Statement

As per QCS 2014 Section 8 part 10, Method


Laser Profile/ Ovality Test After Completion each area/location/work Visual Inspection Work Inspection Test Report H W R
Statement

FINAL INSPECTION AFTER COMPLETION

4
As per Standard EN 13508-2014 Method
CCTV SURVEY Final Inspection Reports After Completion each area/location/work Visual Inspection, Clean Inspection Report H H H
Statement

LEGEND:

S = Surveilance H: (S/C column) Hold Point shall be inspected and Tested then released to next Activity by Subcontractor

W = Witness Point
H: (Cont. column) Hold Point shall be inspected and Tested then released to next Activity by Contractor
H = Hold Point
R = Review
H: (Consultant column) Hold Point shall be inspected and Tested then released to next Activity by Consultant
N/A = Not Applicable