Kta Alliance Spray /touch Up Painting of Project Materials: Job Safety Analysis (JSA)

You might also like

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 3

KTA ALLIANCE

SPRAY /TOUCH UP PAINTING OF PROJECT MATERIALS


Job Safety Analysis (JSA)

JOB: DATE:

DEPARTMENT: JSA NO.: ANALYSIS BY:

Required Personal Protective Equipment (PPE) Other Safety Equipment/Requirements

Hard Hat [x ] Cotton Gloves [x ] Work vest [x ] Fire Extinguisher [ ] Barricades [ x]


Safety Shoes [x ] Rubber Gloves [ ] Safety Harness [x ] Gas Detector [ ] Tag Out/Lock Out [ ]
Safety Glasses [x ] Leather Gloves [ ] Face Mask [ ] B.A. Set [ ] Cold Work Permit [ ]
Face/Welding Shield [ ] Gauntlets [ ] Ear Protection [x ] Safety Signs [ x ] Hot Work Permit [ ]
Goggles [ ] Leather Apron [ ]

Sequence of Basic Job Steps Potential Accidents OR Hazards Recommended Safe Job Procedure

1] Set up equipment & 1.1 Tripping hazards on the walkway. 1.1.1 Clear obstructions on the walkway.
prepare work site. 1.2 Rough/sharp edges on project materials 1.2.1 Avoid sharp edges and flag off rough spots on
1.3 Uncertified equipment. project materials with caution tape
1.4 Poor materials handling 1.3.1 Use only certified equipment and carry out
1.5 Exposure to hazardous substances checks before commencing operations.
1.4.1 Transport paints to site in suitable containers to
1.6 Trailing hoses
prevent spill
1.4.2 Follow proper lifting techniques when carrying
out manual handling of materials.
1.5.1 Wear disposable hand gloves and half face
respirator while mixing substance/Follow
MSDS
1.6.1 Route air pressure hoses properly

2] Startup air compressor 2.1 Adverse weather condition 2.1.1 Operate under favorable weather condition.
and connect painting 2.2 Pressurized airlines 2.2.1 Use whip checks on couplings
equipment. 2.3 Congested worksite 2.2.3. Restrict access of unclassified personnel and
barricade area with caution tape/post warning
signs.
Sequence of Basic Job Steps Potential Accidents OR Hazards Recommended Safe Job Procedure

3) Work at height 3.1 Slips, trips and falls 3.1.1 Use standard and safe means of access such as
Ladders, Scaffolds or Mobile Elevated
Work Platforms.
3.1.2 Use fall prevention or fall arrest systems such
as safety belts or full body harness.
3.2 Contact with electricity 3.1.3 Ensure good housekeeping.
3.2.1 Use appropriate PPE to avoid contact with
3.3 Equipment or structural failure electricity.
3.3.1 Ensure regular inspection and maintenance of
Ladders, Scaffolds and Elevated Work
3.4 Persons moving under work area. Platforms.
3.4.1 Ensure work area is cordoned off to restrict
3.5 Incompetent or inexperienced operator. unauthorized access into work area.
3.5.1 Only qualified and experienced operators
should handle Mobile Elevated Work
Platforms. Fall arrest rescue plan should be
communicated to workers involved in working
at height.
3] Commence spray 3.1 Unlocked trigger on painting guns could spill 3.1.1 Ensure trigger on spraying gun is on lock
painting / touch up painting chemical substance position.
operations 3.2 Exposure to paint fume during painting 3.2.1 Wear respirators and wear appropriate clothing
3.3 Potential spill of paints 3.3.1 Follow MSDS when cleaning spill and have
absorbent pads in place.

4] Shut down equipment and 4.1 Trapped air on pressure hoses / trailing hoses 4.1.1 Bleed out trapped air and arrange hoses away
Clean-up work site on walkway from walkway
4.2 Excess paints from operation 4.2.1 Turn out excess paint into special containers and
take back to storage for proper disposal
according to MSDS
4.2.2 Carry out housekeeping and close out permit.

WORK TEAM DECLARATION:


I acknowledge that I have reviewed the above JSA; I understand my roles and responsibilities and will comply with instructions for the task.

DATE NAME SIGNATURE

PREPARED BY: REVIEW BY: APPROVED BY: