Professional Documents
Culture Documents
Petroleum Pipeline Construction Planning: A Conceptual Framework
Petroleum Pipeline Construction Planning: A Conceptual Framework
Petroleum Pipeline Construction Planning: A Conceptual Framework
231-240, 1996
Pergamon Copyright © 1996 Elsevier ScienceLtd and IPMA.
Printed in Great Britain. All rights reserved
0263-7863/96 $15.00 + 0.00
0263-7863(95)00092-5
Stephen O. Ogunlana
School of Civil Engineering, Asian Institute of Technology, GPO Box 2754, Bangkok 10501, Thailand
A cross-country petroleum pipeline construction project is adequate relationship between the essential design parameters
characterized by the complexity in its execution with (technical requirements, construction schedules, investment
respect to a lack of experience in relation to certain design planning and related expenditures) and to create reference
conditions being exceeded (water depth, ground condition, documents (time schedules, cost estimation and specifica-
pipeline size etc.), the influence of external factors that are tions) at the early feasibility stages of the project. The
beyond human control, external causes which limit resource relationships and documents are needed to improve the
availability (of techniques and technology), various en- evaluation accuracy, formulate a monitoring scheme for
vironmental impacts, government laws and regulations and various phases of the project, provide rapid and easy refer-
changes in the economic and political environments. Cost ence to technical and economic information for the project
and time overrun and the unsatisfactory performance of a team and establish close cooperation between members of
project are the general sources of disappointment to the the project team.
management of a pipeline organization. The main objective of this paper is to set forth a sys-
In these circumstances, a conventional approach to tematic procedure of project control by forming project
project planning for execution is inadequate, as it does breakdown structure (PBS) through risk analysis and deriving
not enable the project management team to establish an logical contingency provision for the project. The paper
also attempts to establish an execution planning model for
controlling and managing changes that arise during project
*Author for correspondence. execution.
231
Petroleum pipeline construction planning: P K Dey et al.
232
Petroleum pipeline construction planning: P K Dey et al.
and contractor, respectively. The variability of base cost di- represent the under-achievement of goal i, di+ represent
estimate leads owner-management to estimate specific the over-achievement of goal i, P,i is the priority associ-
activity in ranges. The lower and upper bound limit depends ated with d,-, and Poi is the priority associated with d~÷. If
on the specification and scope definition of activities. The over-achievement is acceptable, d/÷ can be eliminated
statistical approach leads to determination of expected cost from the objective function; if under-achievement is satis-
and variance of cost activities with consideration of 'beta' factory, d7 should be left out of the objective function and
distribution of activity cost data. Accordingly, the applica- if the goal must be achieved exactly as defined, both d~÷
tion of the 'central limit theorem' leads to determination of and dZ must be in the objective function. The deviational
even-chance estimate of work packages. Therefore, even- variables must be ranked according to their priorities, from
chance estimate conforms to quantity and unit cost risk the most important to the least important. If goals are
of activities. The uncertain environment of the project classified in R ranks, the priority factor Pr (r = 1 . . . . . R)
imposes further risk, without consideration of which project should be assigned to the deviational variables. The priority
achievement remains uncertain. The effect of risk on estimate factors have the following relationships: P r > > >NPr+l
is taken care of by considering the overall percentage of (r = 1 . . . . R - 1 ) , which implies that the multiplication of
risk on a work package which corresponds to probability of N, however large it may be, cannot make Pr+l greater than
cost overrun when combined with even-chance success of or equal to P~. The algorithm procedure is carried out by
the project. The detailed procedure and application is a modified simplex method.
illustrated elsewhere 6. Hannan 7 demonstrated in his paper how goal program-
ming can be used to incorporate considerations other than
the project completion time and project cost into the typical
Project control through contingency appropriation CPM problem. Vrat et al. 8 developed a crashing model
If the changes remain within the contingency limit or it is through GP to ensure non-crashing of a certain activity for
decided to spend the amount from the total contingency quality reasons, to maintain specific budget targets and to
reserve, the corresponding contingency reserve fund has to minimize total direct costs of crashing.
be updated. In a case where the contingency allowance is The total project plan is made separately in three levels
not enough to cover an appropriation or a change request, - project, work package and activity level. The output of
the project manager then seeks an additional funds one level planning is utilized to plan another level and vice
appropriation documenting the causes or needs. Either the versa. The total integrated model is depicted in Figure 1.
project scope is reduced or the owner decides to arrange Planning starts at the project level with the consideration of
additional funds for the project. When the authorized different constraints associated with that level. The outcome
amount is not fully used on a contract, it is transferred back is fed for planning work packages under the project. The
into the contingency reserve. desired level of output from the project level acts as addi-
tional constraints to the work package planning model. The
nature of the constraints in the work package level may or
Execution planning model may not be the same as the project level. The planning
Cross-country pipeline construction demands an integrated variables in the work package are utilized to plan each
planning model with time, cost and performance optimiza- activity. Activities related to a specific work package are
tion. As a result of uncertainties in the project environment planned with the consideration of different constraints
several changes from initial project planning are to be related to specific activity execution. The output levels of
carried out for its achievement. Moreover, priority of a work package become additional constraints to activity
construction activities are also to be changed to cope with planning.
the changing environment. These necessitate the application The work precedence relations (WPR) of the whole project
of goal programming (GP), a multi-criteria decision-making
technique for project planning.
Report to Project plan
the owner from
Goal programming approach
oi the Contractor
GP is a method that requires ordinal and cardinal infor-
mation for multiple objective decision making. In GP, Q
233
Petroleum pipeline construction planning: P K Dey et al.
is prepared in line with WBS. Each level provides WPR as Decision variables
per the content of the level, i.e. for project level planning x~k.,~= percentage progress of work package k during time
WPR is prepared for all work packages under the project, period t.
and for work package level planning WPR is prepared for
all activities under the corresponding work package. Then Goal constraints
the overall project duration is determined from the total (i) Cost constraint
work content of each activity in a critical path. Accord-
~kc~l.k~X(k.,) + d - - d + = Cl
ingly, the owner makes a contract with the contractor to
complete the project within that duration. These provide the where, Cl = aspiration level of cost in specific period,
base for designing the whole project. The owner's next task and cl~.k~= unit percentage cost of work package.
is to classify the total project duration into some periods for (ii) Percentage progress of work package
planning as well as controlling the project achievement. Percentage progress of work packages during specific
The number of periods depend on the requirement of the planning horizon may be aspired to be achieved.
owner about the frequency of review of the achievement of Therefore,
project parameters. To keep track of the project achieve-
ment, project parameters are to be controlled over periods x¢k.t) + d - - d + = X 1
up the initial project duration breakdown period. However, where, X~ = aspiration level of percentage progress of
the number of periods may be varied according to require- work package k during specific time period t, and X2
ments during the changing project environment in line with = aspiration level of percentage progress of specific
project objectives. The number of planning periods also work package in different period.
varies across the levels according to the criticality of (iii) Percentage progress of project
activities. Aspiration level of achievement is possible through the
Aspiration levels of goal constraints are established from setting of goals of percentage execution in the project
available input data, project objectives and the planning level. Therefore,
environment. Goal programming models are priority
based. In this study, models are formulated in different Xk Wk "x~.,j + d- - d + = PI
levels with the consideration of different priorities according
where, Wk = weightage of work packages, and PI =
to the owner's requirements regarding the project achieve-
aspirated level percentage progress of project during
ment. Various techniques, ranging from simple interview
the specific planning horizon.
to the Delphi technique, may be used to establish initial
(iv) Cost of specific work package to be kept within aspira-
priorities for different levels.
tion limit and specific cost flow to be maintained for
The detailed project planning procedures are as follows:
specific time period. Therefore,
C~l.k>~,X~k,,~ + d - - d + = C2
M o d e l 1: p r o j e c t l e v e l p l a n n i n g
c~w,~ "xa,., ) + d - - d + = C3
The whole project is classified into some work packages,
the execution of which can be planned through goal pro- where, c(~,k)= unit percentage cost work package k,
gramming according to the aspiration level of the man- C2 = aspirated level of cost of work package k, and
agement in the environment of different constraints. C3 = aspirated level of cost flow for specific work
The input data to the project levels are work breakdown package during specific planning horizon.
structures of the project, precedence relations of the work
packages, estimates in work package level and corres- System constraints
ponding contingencies, as well as policies of the contractors (i) Percentage progress of specific work package during
and owner. Provision of necessary updating of input data whole planning periods should indicate its full achieve-
has been provided for coping with environmental fluc- ment. Therefore,
tuations. The aspiration levels for different goals are fixed
from available input data, project objectives and the plan- ~,x~k.t ) = 100
ning environment. The ultimate project plan is in the form (ii) 100% achievement is possible by multiplying achieve-
of the percentage progress of different work packages in ment of all work packages throughout the planning
the specific planning horizon, which are derived in the horizon with their corresponding weightage. Therefore,
environment of few system and goal constraints. The
decision variables of project level planning act as con- ~, Ek W<l.kl "xlk.,/= 100
straints to the next level of planning, i.e. work package
The merits of the model lies in its simplicity and ease
planning. Priorities of the goals vary with the situations.
Therefore, it is initially fixed through the perception of of understanding on one hand, and on the other the
the planner in line with his organizational and project possibility of integrating it with other models through
which planning of work packages as well as activity
objectives. The flexibility of the model has been provided
levels can be carried out.
through provisions for updating of input data with the
changing environment, consideration of the effect of plan-
ning on other levels, changes in priorities and changes in M o d e l 2: w o r k p a c k a g e p l a n n i n g
constraints. Activities of work packages can be planned over periods in
The mathematical model in project level planning is the environment of several constraints. The necessary input
shown in the following sections: data comes from specifications, precedence relations of
234
P e t r o l e u m p i p e l i n e construction p l a n n i n g : P K D e y et al.
activities under specific work packages, detailed estimates where, Coj ) = unit cost of activity j and C , ( T ) =
of work packages, corresponding contingency, productivity aspirated level of field cost.
of deployed labor and equipment, management decisions Material cost:
about planning horizons, etc. These input data may be
collected from tender documents, risk analysis reports, ~p C(2,p)"P + d- - d + = C2(T)
project networks etc. along with the necessary additional where, C(2.p)= unit cost o f p type materials, and C2(T)
documents. The system constraints for the model generally = aspirated level of materials cost.
derived from activity scope limitation, environmental (vi) Percentage progress of work package during specific
effect, economics etc. Goal constraints come from the time period.
aspiration level of management at the work package level.
These are the execution of specific activities, resource Ej wj . xj + d - - d + = w t
utilization, cost flow, percentage progress of work package
Where, w, = aspiration level of percentage progress.
etc. Additional constraints may arise from project level
planning, which are to be maintained for the proper in- wj = weightage of activity j.
tegration of the total model. The priorities vary from
System constraints
situation to situation. Initially it may be decided according
to management policy. The output of work package plan- (i) Achievement cannot be more than quantum of job
ning is the level of achievement of activities and the cor- related to certain activity. Therefore,
responding resources requirement. The output of work xj <- A 2
package level planning is input of activity level planning
during the initial planning as well as during the changing where, A2 = total execution involved with certain
environment. The output also acts as input to the planning activity.
project level in varied situations. (ii) Quantum of job related to certain activities taken all
The mathematical model has been derived and enumerated together
below in line with the above discussion.
~ j X j <__a 3
235
Petroleum pipeline construction planning: P K Dey et al.
horizon, deployment of men and equipment, achievement ~'n=l ~t=l Cmi M(ad,t) "~ ~n=| ~t=l Cei E(a.i,t) - L < K3
of specific man and equipment hours, expenditure on
where, Cm, = unit cost of a type labor-hour for activity
activity to match with the availability of cash. Additional
operation i at different period t (t = 1 , 2 , . . . ) , Ce, =
constraints should be considered and/or the existing con-
unit cost of b type equipment-hour for activity opera-
straints should be updated to match with the output of work
tion i at different period t, and K3 = labor-hour and
package level planning. The decision variables that are
equipment-hour cost for aspirated activity level.
derived from the activity level of planning are the period
2. Labor-hour limitation in specific operation
related achievement in execution, type and amount of man
and equipment hours, materials requirement, extra payments M(a,i,t) ~ m
that are related to an increase or decrease in scope. The
variables may be the input to other levels of planning in the m = a type labor-hour available for activity operation i
changing environment. during period t.
The mathematical model is derived from the above 3. Equipment-hour limitation for specific operation due to
situation and enumerated below in detail. non-availability
E(b,i,t) <~ e
Decision variable
x, = Production related to activity in different time period e = b type equipment hour available for activity operation
t (where t = 1 . . . . n ) , M~a.i.,)=a type labor-hour for i during period t.
operation i in period t. Etb.i., ) = b type equipment-hour for Note: All d + and d- are subscripted. But for ease of
operation i, in period t, L = amount of money that is to be presentation these are not indicated when presenting within
paid to the contractor for deploying extra man-hours for equations.
executing the activity in the stipulated time period, and The whole model is initially designed with an established
N = amount of money that is to be paid to the contractor for work precedence relationship (WPR) and desired project
limiting the scope of work compared to that envisaged in duration breakdown in line with project objectives, plan-
the tender document on the basis of which the contractor ning environment and planner's perception. Accordingly,
indicated the unit rate for some activities. planning variables are determined for controlling time, cost
and quality goals. However, changing the project environ-
Goal constraints
ment demands alteration of WPR to cope with changed
1. Aspiration level of output in specific time period is situations. The models can be adapted to new environments
x, + d - d + = A, by changing the aspiration level of goal constraints as the
situation demands and planning variables are established
A, = aspiration level of activity achievement in period t. along with requisite resource requirements accordingly.
2. Aspiration cost level of activity is
C| ~7= l x, + d - - d + = KI Application
The project is classified into a few work packages through
C~ = cost per unit field activity in period t, and K~ = hierarchy 6. Risk analysis is applied in work package level
total approved cost of the activity (aspiration level of and the results are tabulated in T a b l e 1 for three work
field cost) in period t. packages. Logical contingencies are derived for project
The formula has to be modified if the unit cost varies for control through the proposed methodology and shown in
different periods. The formula will be T a b l e 2 for the same three work packages.
~=1 Ctxt "~- d - d + = K,
The work package precedence relations are developed
through network ( F i g u r e 2 ) . The weights of the work
3. Materials cost level packages are derived as per the works involved within
these, along with the complexity of construction (ranking
C2~7=,x, + d - - d + = K2
method) 9. The project duration is considered to be 18
(?2 = cost of material for per unit activity during period months and planning is made for six distinct periods of
t, and K2 = total cost of materials (aspiration level). 3 months each. The output of the project level planning is
An alternative equation like the previous one can be the percentage progress of work packages in different
established if the unit cost of materials varies with the planning periods. These are derived by considering the
period. following priorities within the model:
4. Activity is to be fully loaded with men and equipment.
(a) Priority 1: Completion of project in the total planning
Therefore,
horizon.
Qx, - R M ~ . i ) + d - d+= 0 (b) Priority 2: Aspirated percentage completion of specific
work package during a specific planning period.
R = production per labor-hour and Q = job involved (c) Priority 3: Aspirated cash flow for the work package in
per unit execution. a specific period.
5. Quantum of job planned to be completed within stip- (d) Priority 4: Specific percentage progress of project in a
ulated time period. Therefore, different planning period.
ZT=t x, + d - - d + = B (e) Priority 5: Aspirated level of cost flow for the project
during a specific period of planning.
where, B = aspiration level of job.
The priorities are in line with the project objectives,
System constraints planning environment and planner's perception. In this
1. Extra payment for changes in scope of work: model, project achievement is considered to follow a typical
236
Petroleum pipeline construction planning: P K Dey et al.
SI. Work package Overall Prob. of Z value Base cost Expected Variance S.D. Contingency
no. risk cost more from estimate cost
than mean table Amount %
I. Pipelineconstruction (Spread I) 0.42 0.92 1.75 9 6 1 3 . 0 4 9986.35 431399.91 6 5 6 . 8 1 1522.73 15.84
2. Pipelineconstruction (Spread II) 0.39 0.89 1.17 1 1 0 3 . 4 4 1144.38 6962.77 83.44 138.56 12.56
3. Pipelineconstruction (Spread III) 0.34 0.84 1.14 521.80 543.00 1327.71 36.44 62.74 12.02
Pipeline Construction I
14 Pipeline Construction II
10
Pipeline Construction III
Pipelaying
Mobilisation Cathodic Construction System Construction= ("
4 x,. 1,
Station Constn. Buildinc~ and Colon}/Construction . .
Mobilisation
/ 15 E Pump Slation/~" / j
. . 5
"A" Pump Station ~/"'~ C Pum. Slalion ~~ ~ / /
, -',._> 5 "v.J //
"B" Delivery Station =.~ "D" Scraper Station(""~ "F" Delivery Station / /
s 3 "k_J 4 /
"G" Delivery Station ....("~ "M" Pump cum Delivery Station [t
5 ~ 5 "K" Terminal
"1" Delivery Station P,O "J" Terminal Stati°n OStat4n
5 4
' S ' curve i.e. one quarter o f the project's progress is . Percentage progress in pipeline construction spread II
planned to occur in the first third of the contract programme, during periods 2 and 3 : 5 0 and 50, respectively.
one half in the middle third and the remainder in the last 4. Percentage progress of ' A ' pump station construction
third o f the programme. The project expenditure pattern is during periods 1 and 2 : 7 0 and 30, respectively.
also planned to follow the same lines. Accordingly, the 5. Percentage progress of ' B ' delivery station construction
aspiration levels of the models are fixed. during periods 1 and 2 : 9 0 and 10, respectively.
The mathematical models are formed in each level through 6. Percentage progress o f ' C ' pump station construction
GP and processed through the M I C R O M A N A G E R com- during periods 2 and 3 : 8 0 and 20, respectively.
puter package. Detailed model formulations have been 7. Percentage progress of ' D ' scraper station construction
described elsewhere j. The results are as follows: during period 2: 100.
8. Percentage progress of ' E ' pump station construction
1. Percentage progress in pipeline construction spread I during period 3: 100.
during periods 1, 2 and 3: 41.88, 26.12 and 32, 9. Percentage progress of ' F ' delivery station construction
respectively. during period 3: 100.
2. Percentage progress in pipeline construction spread II 10. Percentage progress of ' G ' delivery station construction
during periods 2 and 3 : 2 0 and 80, respectively. during period 2: 100.
237
Petroleum pipeline construction planning: P K Dey et al.
11. Percentage progress of 'H' pump-cum-delivery station model. The planning variables of typical activity 'Laying
construction during period 3: 100. pipe in ' A ' - ' B ' at 1st 20 km stretch' are as follows:
12. Percentage progress of 'I' delivery station construction
during periods 1 and 2 : 8 0 and 20, respectively. 1. Progress in pipe laying in first month: 1852 m
13. Percentage progress o f ' J ' terminal station construction 2. Progress in pipe laying in second month: 15 280 m
during periods 2 and 3 : 2 0 and 30, respectively. 3. Progress in pipe laying in third month: 2778 m
14. Percentage progress of 'K' terminal station construction 4. Progress in pipe laying in fourth month: 4600 m
during period 3: 100. 5. Labor-hours for welding and backfilling in first month:
15. Percentage progress of telecommunication system 480 and 177, respectively.
construction during periods 2 and 3 : 3 0 and 70, 6. Labor-hours for welding and backfilling in second
respectively. month: 3961 and 1467, respectively.
16. Percentage progress of telesupervisory system con- 7. Labor-hours for welding and backfilling in third month:
struction during period 3: 100. 720 and 267, respectively.
17. Percentage progress of cathodic protection system 8. Labor-hours for welding and backfilling in fourth
construction during periods 1, 2 and 3: 49.92, 24.96 month: 1192 and 442, respectively.
and 25.12, respectively.
18. Percentage progress of building and colony construction Equipment-hours for welding, lowering and backfilling are
during periods 1, 2 and 3: 33.25, 33.51 and 33.25, same as labor-hours. Sensitivity analysis of the models is
respectively. carried out for project level planning for the following three
19. Percentage progress of mobilization for construction conditions:
during period 1: 100.
1. Environmental effect.
When percentage progress of all the work packages during 2. Resource balancing (labor-hours).
a specific time are combined with its corresponding weights, 3. Scope increase.
percentage project progress during that period can be
Table 3 shows the overall percentage progress of the
derived. The percentage progress of projects and work
project for referred varied conditions along with the
packages for a specific period gives the basis for more
aspirated progress. Sensitivity analysis results at work
detailed planning of work packages. The output of work
package level planning for the pipeline construction I for package level for welding man-hours and cost flow analysis
the first planning period are as follows: are shown in Figure 3. Table 4 shows sensitivity analysis
on activity level planning for varied situations as indicated.
1. Laying of pipe in ' A ' - ' B ' at first 20 km stretch: These validate the applicability of the model in the changing
5000 m project environment.
2. Laying of pipe at ' B ' - ' F ' in normal terrain: 10000 m The aspiration level, in line with project objectives,
3. Laying of pipe at ' F ' - ' H ' in normal terrain: 141 570 m gives the basis of initial planning. However, projects
4. Laying of pipe in submerged crossing: 2000 m seldom operate as per plan. The dynamic environment
5. Laying of pipe in uncased crossing at first 20 km demands changes in project plans for proper achievement
stretch: 50 m during different phases of construction. The proposed
6. Labor-hours required for welding in activity 1:1296 model can easily be updated by changing priorities
7. Labor-hours required for welding in activity 2 : 2 1 6 0 according to demand, changing co-efficient of variables and
8. Labor-hours required for welding in activity 3 : 3 0 579 aspiration levels. Thus, it provides a decision support
9. Labor-hours required for welding in activity 4 : 5 1 9 system for project control for time, cost and quality
10. Labor-hours required for welding in activity 5 : 1 3 achievement.
11. Labor-hours required for lowering and backfilling
trench in activity 1:481
Conclusions
12. Labor-hours required for lowering and backfilling
trench in activity 2 : 8 0 0 Projects exposed to uncertain environments must deal with
13. Labor-hours required for lowering and backfilling the effective integration of various planning elements,
trench in activity 3:11 325 optimization of project parameters and risk management
14. Labor-hours required for lowering and backfilling throughout their life. Risk analysis combined with logical
trench in activity 4 : 1 3 3 4 contingency provision provide effective tools for decision
15. Labor-hours required for lowering and backfilling making for project control of a pipeline laying project. The
trench in activity 5 : 1 5 changes that arise during implementation are controlled
16. Requirement of pipes 22" dia. and 0.281" wt. : 162 179 m through a hierarchical planning model which optimizes
17. Requirement of pipes 22" dia. and 0.325" wt. : 7490 m
18. Requirement of pipes 22" dia. and 0.312" wt. : 53.50 m Table 3 Schedule plan of project (percentage progress cumulative)
Similarly, detailed planning to the work package level is SI. Planning Aspiration Environmental Resource Scope
carried out for other work packages through the proposed no. horizon level effect balancing increase
model with the application of the same software program.
1. Period 1 12.50 12.32 20.00 21.00
Activity level planning is carried out on the basis of 2. Period 2 25.00 24.64 40.00 42.21
planning output work package level. Planning periods for 3. Period 3 50.00 38.44 64.00 55.21
each activity are determined as per the importance of the 4. Period 4 75.00 52.24 80.00 68.21
activity from the overall project perspective. However, the 5. Period 5 87.00 75.76 90.00 84.21
6. Period 6 100.00 I00.00 100.00 100.00
total duration of activities is derived from the work package
238
Petroleum pipeline construction planning: P K Dey et al.
Figure 3 Man-hours and cost flow analysis of work package The applicability of the model is limited to a petroleum
pipeline construction project. However, the model can
Table 4 Welding man-hour for the activity of laying pipe in normal easily be updated for use with other types of construction
terrain of first 20 k m stretch projects. The application of the model demands a consider-
able concept of mathematical programming for effective
Sl. Description Period Total
no.
utilization. However, a user-friendly package may be
1 2 3 4 5 developed by interfacing mathematical models with some
1192 1985 1985 1192 0 6354
application software. The present study is a theoretical
1. Aspiration level of activity
achievement framework of a decision model for optimizing project
2. Activity achievement normal 480 3961 720 1193 0 6354 parameters in dynamic project environment, for achieving
3. Scope increase by 2 km 480 3961 720 1193 518 6872 completion of a project on time, within a specified budget
(accommodate in next period) and conforming to requirements.
4. Scope increase by 6 km 480 3961 720 1452 1296 7909
(accommodate in next period)
5. Special condition 480 0 720 3169 1985 6354 References
(no work in 2nd period) 1 Dey, P K 'Project planning through risk analysis: the case of a
6. Scope decrease 480 3532 720 648 0 5380 petroleum pipeline laying project', Msc. Thesis, Asian Institute of
7. Scope increase 480 4220 720 1452 0 6872 Technology NO: IE-92-13 (1992)
(accommodate in same period) 2 Saaty, T L The Analytic Hierarchy Process McGraw-Hill, New York
8. Finishing the activity within 480 5154 720 0 0 6354 ( 1980)
3 months (crashing) 3 Ogunlana, S O, Tabucanon, M T and Dey, P K 'A methodology for
project control through risk analysis: the case of a pipeline project'
IEEE Conference Proceedings "Managing projects in a borderless
world' IEEE Catalog no. 93CH3382-9 (1993) 18-22
different conflicting objectives of management for successful
project achievement.
In a typical PERT and CPM network, activity precedence Prasanta K Dey is a senior project
engineer in the Pipeline Division of
relations along with corresponding durations are indicated the Indian Oil Corporation. He
which lead to the determination of a critical path for the obtained a bachelor's degree in mech-
project, thereby providing a basis for project planning and anical engineering from Jadavpur
control. Though the network model results in different University, India, and a master's
planning variables, nothing is mentioned regarding the degree in industrial engineering and
management from the Asian Institute
percentage or absolute progress in execution during specific o f Technology, Thailand. His current
time periods. For managing long duration activities, this is research interest is in the area of
absolutely necessary. The proposed planning model provides project planning and control.
the above facilities. Therefore its use, along with network
analysis, provides a very useful project planning and
control tool.
239
Petroleum pipeline construction planning: P K Dey et al.
4 Scasso, R de H and Larenas, G S 'Project breakdown structure: project' International Journal of Project Management (1) (1994) 23-33
the tool for representing the project system in project manage- 7 Hannan, E L 'The application of goal programming techniques to the
ment' International Journal of Project Management 9 (1991) CPM problem' Socio-economic Planning Sciences 12 (1978) 267-270
157-161 8 Vrat, P and Kriengkrairut, C 'A GP model for project crashing with
5 Yeo, K T 'Risk classification of estimates and contingency man- piecewise linear time-cost trade-off" Engineering Cost and Production
agement' Journal of Management in Engineering 6 (1990) 458-470 Economics 10 (1986) 161-172
6 Dey, P K, Tabucanon, M T and Ogunlana, S O "Planning for project 9 Tabucanon, M T Multiple Criteria Decision Making in Industry
control through risk analysis: a case of petroleum pipeline laying Elsevier, Amsterdam (1988)
240