Professional Documents
Culture Documents
MS 01steel Sheet Pile Method Statement
MS 01steel Sheet Pile Method Statement
MS 01steel Sheet Pile Method Statement
Date:2016.01.24 Revision:01
CQCP-MS-01
Steel Sheet Pile Construction Method Statement
CONTENTS
Materials
Machinery & Equipment
Manpower
Procedure
Safety Management and Control
Quality control
Measurement control
1. Materials
The major materials used for the construction of steel sheet pile installation, but are not limited
to the following.
1) Steel sheet piles
2) Coatings
3) Grease
3. Manpower
4. Procedure
-1-
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 01-Steel Sheet Pile construction method statement
4) positioning of crawler crane and hammer:the crawler crane and hammer shall be positioned,
and the hammer shall seize the steel sheet pile, and then the crawler crane shall be adjusted
to align with the design position of steel sheet pile
5) positioning of steel sheet piles:The position of first steel sheet pile to be driven shall be
selected according to the setting out and before the driving we will first install the steel
guide frame(see in picture) to make sure the direction of the sheet pile is right and to
control the in plan and vertical tolerance.
6) starting hammer: the hammer shall be started to slowly drive the steel sheet pile into
ground, and the position and elevation steel sheet pile shall be inspected to ensure meeting
the design, after which the driving of the next steel sheet pile can be started
7) driving steel sheet pile:Prior to the driving of the rest steel sheet piles, the steel sheet pile
driven shall be manually supported to interlock with the former steel sheet piles, and the
inserted and driven steel sheet piles shall be fixed and connected together by spot welding.
8) inspection on steel sheet pile position:Throughout the insertion of the first steel sheet pile,
contractor’s survey team shall continually monitor and control the vertical position of the
steel sheet pile by Total Station Instrument so that keep to the specified verticality.
9) qualified
10) entering into the next cycle
Safety precaution during the piling operations should comply with the contractor’s project
safety plan.
NOTE: Contractor shall provide and maintain on the Site sufficient proper and efficient
lifesaving appliances. The appliances must be conspicuous and available for use at all times. Site
operators shall be conversant with the use of safety equipment and drills shall be carried out
sufficiently frequently to ensure that all necessary procedures can be correctly observed
6. Quality control
-2-
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 01-Steel Sheet Pile construction method statement
Contractor. Prior to installation of the sheet pile wall, the element positions shall be checked
by the Contractor and confirmed by Consultant.
4) Positional and alignment tolerance (as per specification 02457-3.02):
Unless deflected by obstructions, sheet piles shall be installed within the following
tolerances:
In plan tolerance 75mm of the given sheet pile line at commencing surface
Vertical tolerance 1 in 75(within 0.77 angle degrees)
Level tolerance ±50mm of required top level
(tolerances of steel sheet pile see as following draft)
1) Numbering
As below picture, we start from corner 1 to corner 2, then corner 1 to corner 4,then corner
4 to corner 3, and finish from corner 2 to corner 3. And we numbering the steel sheet pile
of 4 direction of North, South, East and West. If there are any changes in this order, we
will first inform the Engineer for approval.
-3-
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 01-Steel Sheet Pile construction method statement
A:setting out and survey for in-plan tolerance in every 10 pieces(within +/-75mm)
Designed coordinate Actual coordinate as build Tolerance
No.
x y x y N-S W-E
-4-
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 01-Steel Sheet Pile construction method statement
-5-
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 01-Steel Sheet Pile construction method statement
4) Check List
No.
Employer Engineer Contractor
KWASA AECOM/SMEC CHEC
CHECK LIST FOR STEEL SHEET PILE INSTALLATION
( Notice to proceed)
This form must be completed and passed to the RE together with supporting documents. Work must not start until
approval is given by the RE's staff.
Approved by:
Resident Engineer: _________________ Date: _________________
-6-