MS 02a Remedial of Anchoring System
MS 02a Remedial of Anchoring System
Construction of Surface
Water Treatment Plant and CQCP-Method Statement
Impounding Reservoir 02a-Remedial Work for the
CONTRACT No. KWASA / KWSP / Anchoring System
ICB-02
Date:2017.06.12 Revision:00
CQCP-MS-02a
Remedial Work for the Anchoring System
CONTENTS
Scope
Materials
Machinery & Equipment
Manpower
Procedure of remedial work
Flow Chart
Appendix
1. Scope
The scope under this paper covers the procedure to be followed in course of the remedial work
of anchoring system between Deadman and steel sheet pile in IPR.
2. Materials
The major materials used for the construction of steel sheet pile installation, but are not limited
to the following.
1) Concrete anchor blocks
2) Steel strand
3) Anchor bearing plate
4) Head cap
5) Anchor & clip
6) Grease
7) PVC pipe
-1-
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 02a-Remedial Work for the Anchoring System
1) Tension machine
2) Jack
3) Digger
4) Welding Machine
5) Road roller
6) Crawler crane
4. Manpower
1) Site Engineer
2) Contractor’s Site supervisor
3) Steel strand foreman
4) Welder
5) Worker
5. Reason of Failure
The reasons for the failure of the anchoring system are as follow:
1) Site operation not follow the proper procedure that involved to anchoring system and
backfill between sheet pile and Deadman. For example, the backfill performed before
installing of the steel strand and tension.
¦ Õ
15.2 STEEL STRAND
ANCHOR YJM15-3
ANCHOR YJM15-3
ANCHOR BEARING PLATE
¦ Õ
15.2 STEEL STRAND
ANCHOR CLIP
ANCHOR YJM15-3
-2-
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 02a-Remedial Work for the Anchoring System
1) Step1-
2) Step 2-
-3-
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 02a-Remedial Work for the Anchoring System
3) Step 3-
i. Set up tension machine (pump, hydraulic jack) at sheet pile side to tensioning bottom
strand.
ii. Apply tension force 200 KN.
4) Step 4-
-4-
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 02a-Remedial Work for the Anchoring System
5) Step 5-
6) Step 6-
-5-
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 02a-Remedial Work for the Anchoring System
7) Step 7-
i. Set up tension machine (pump, hydraulic jack) at sheet pile side to tensioning top
strand.
ii. Apply tension force 200 KN or as necessary for correct alignment of sheet piles.
8) Step 8-
-6-
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 02a-Remedial Work for the Anchoring System
9) Step 9-
-7-
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 02a-Remedial Work for the Anchoring System
1) Step1-
i. Excavate to 2.0 m below penetration point of top strand through the sheet pile.
2) Step 2-
-8-
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 02a-Remedial Work for the Anchoring System
3) Step 3-
4) Step 4-
-9-
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 02a-Remedial Work for the Anchoring System
5) Step 5-
i. Set up tension machine (pump, hydraulic jack) at sheet pile side to tensioning bottom
strand.
ii. Apply tension force 200 KN.
6) Step 6-
- 10 -
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 02a-Remedial Work for the Anchoring System
7) Step 7-
8) Step 8-
- 11 -
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 02a-Remedial Work for the Anchoring System
9) Step 9-
i. Set up tension machine (pump, hydraulic jack) at sheet pile side to tensioning
top strand.
ii. Apply tension force 200 KN or as necessary for correct alignment of sheet
piles.
- 12 -
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 02a-Remedial Work for the Anchoring System
- 13 -
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 02a-Remedial Work for the Anchoring System
Flow Chart for remedial work of anchoring system north & west side:
- 14 -
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 02a-Remedial Work for the Anchoring System
Flow Chart for remedial work of anchoring system south & east side:
- 15 -
Khulna Surface Water Treatment Plant CQCP-Method Statement
&Impounding Reservoir Project 02a-Remedial Work for the Anchoring System
APPENDIX: Tracking sheet for Deadman and steel strand remedial work: