Observation Report - U1 ESP by Venkatesan Sir
Observation Report - U1 ESP by Venkatesan Sir
Held on 28.07.2021 at BALCO - 1200MW Power plant, Korba during the overhauling work done
between 11.07.2021 to 28.07.2021
The following are the findings observed in UNIT 2 – ESP and work completed up to date:
1. Water washing work in ESP completed and inspected for cleanliness of the fields made ready for
the inspection and to improve the ionization of ESP
Field No 111:
GDRM system:
3 no’s 2 roller bearings and 1 no of bearing found damaged replaced with new found ok.
EERM motor driving mechanism & coupling to be cleaned for checking. Found ok.
Overhauling of gear box to be done.
Field No 112
Condition of collecting electrodes and alignment
Observations:
Except 3 no’s plates is having bend to be straightened all other CE plates are healthy and firm .
Alignment in rows is ok
GDRM system:
Field No 121:
Guide bar at striking and non striking and found damaged, removed the damage on and new
guide plate welded. Checked ok.
Shock bars are found ok
GDRM system:
Field No 122:
Guide bar at striking and non striking and found damaged, removed the damage on and new
guide plate welded. Checked ok.
Shock bars are found ok
GDRM system:
Shaft alignment done & lock provided
EERM system:
All the electrodes are ok.
GD screen:
In LHS:
In ESP inlet side, first layer out of 11, 9 rows are damaged in left side,13 plates replaced.
Work done:
In RHS:
In first layer it is observed 8 rows of plate got damaged,12 no’s new plates welded.
Work done:
Hoppers:
In hopper no’s 111,112, 121, 122welding work at top & full welding at the sides done.
In pass B:
Field No 221
Observations:
GDRM system:
EERM system:
Observations:
Support insulator found broken removed and fitted with new. Field lock removed and alignment
found ok. & shaft insulator ok
EERM motor drive mechanism to be checked. Ok.
Field No 212
Observations:
Guide bar at striking and non striking end repair work done. ok
GDRM system:
EERM system:
ok.
Observations:
Work done:
Field No 222
Hoppers:
ok.
GD screen in pass B:
Both in LHS & RHS at the outer layer about 10 plates and12plates found damaged and they were
changed with new plates. Bracing done and screen found ok. Work completed
ESP man hole doors, insulators are provided with new asbestos rope for airtight sealing.
Dy.manager/BALCO Service engineer/Sungentech.