RC9RC5-10.01-150677-MTCO-A0001-0001-Rev.0-Vendor Data Master List
RC9RC5-10.01-150677-MTCO-A0001-0001-Rev.0-Vendor Data Master List
RC9RC5-10.01-150677-MTCO-A0001-0001-Rev.0-Vendor Data Master List
VENDOR'S APPROVAL
VENDOR'S OWN DOCUMENT NO REV. NO DATE
(NAME AND SIGNATURE)
150677-MTCO-A0001-0001 A 21.12.2015 CHAU HUU TIN
B 04.03.2016 CHAU HUU TIN
C 13.05.2016 CHAU HUU TIN
0 03.06.2016 CHAU HUU TIN
Submitted For :
1. ACCEPTED
3. NOT ACCEPTED.
REVISE AND RE-SUBMIT.
PURCHASE ORDER NO: VT-261/15-XL - MTCORP
A0001
4. FOR INFORMATION ONLY. VDRL PRIME CODE :
NO SIGNATURE REQUIRED.
NAME : SEQUENCE
REQUISITION NO. VDRLCAT. Rev.
…………………………………… NO.:
DATE :
………………………….…………
RC9RC5-10.01 A0001 0001 0
SIGNATURE :
……………………………………
VENDOR DATA SCHEDULE
VENDOR: MT CORP
PROJECT TITLE: UPS SYSTEM FOR RC9RC5 PLATFORM
PO NO./CONTRACT NO.: VT-261/15-XL/N3-WD
PACKAGE DESCRIPTION: UPS SYSTEM
PACKAGE NO.: 150677-MTCO
Item Sequence
Document Code Number Drawing / Document Description REV. Plan to issue
No. No.
D- DRAWINGS D
2 RC9RC5-150677-MTCO-A2001-0002 General Arrangement Drawing for Distribution Board. A2001 0002 A 22/12/2015
3 RC9RC5-150677-MTCO-A1109-0001 Single Line Diagram, Schematic Diagram for UPS. A1109 0001 A 22/12/2015
4 RC9RC5-150677-MTCO-A1109-0002 Single Line Diagram, Schematic Diagram for Distribution Board. A1109 0002 A 22/12/2015
G- GENERAL G
1 week before
4 RC9RC5-150677-MTCO-C1011-0001 Packing List. C1011 0001 A
delivery
1 RC9RC5-150677-MTCO-A5016-0001 Installation, Operation , Maintenance & Commissioning Manuals A5016 0001 B 4 weeks before delivery
3 RC9RC5-150677-MTCO-A5021-0001 List Of Spare Parts for 2 Years Operation A5021 0001 A 11/01/2016
P- PROCEDURES P
2 weeks before
1 RC9RC5-150677-MTCO-A1104-0001 Factory Acceptance Test Procedure A1104 0001 A
FAT
2 weeks before
2 RC9RC5-150677-MTCO-A5027-0001 Inspection & Test Plan A5027 0001 A
FAT
1 RC9RC5-150677-MTCO-B1002-0001 Factory Acceptance Test Report B1002 0001 A 1 week after FAT