Purpose of Project
Business Case
Expected Deliverables
Objective
Research Production
Extraction Testing Brochures
analysis Testing
Testing Commercial
Research
market
Standard
process
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
2019 2020
Start
Finish
Your Logo or Name Here 11
A: I – II
Gantt Chart – Critical Path 4 + 4 = 8 weeks
B: I – III – IV – VI – VIII - IX
4 + 4 + 1 + 12 + 2 + 4 = 27 weeks
C: I – III – IV – VI – VIII - X
Start 4 + 4 + 1 + 12 + 2 + 4 = 27 weeks
D: I – III – IV – VII – VIII - IX
4 + 4 + 1 + 12 + 2 + 4 = 27 weeks
E: I – III – IV – VII – VIII - X
4 + 4 + 1 + 12 + 2 + 4 = 27 weeks
F: I – III – V – VI – VIII - IX
4 + 4 + 1 + 12 + 2 + 4 = 27 weeks
Finish G: I – III – V – VI – VIII - X
4 + 4 + 1 + 12 + 2 + 4 = 27 weeks
I: I – III – IV – VII – VIII - IX H: I – III – V – VII – VIII - X
Your Logo or Name Here 12
4 + 4 + 1 + 12 + 2 + 4 = 27 weeks 4 + 4 + 1 + 12 + 2 + 4 = 27 weeks
Cost Estimation
Most of the cost resources are from 4 members
of the group project.
Total 55,000,000
Financial
Labor
11%
20% 44%
Advertising
25%
Research and Production
Research the
market to direct the
quality of product