1 Scope............................................................. 2
2 Conflicts and Deviations................................. 2
3 References..................................................... 2
4 Definitions....................................................... 3
5 Qualification of Manufacturers........................ 3
6 Required Specification................................... 4
1 Scope
This specification together with the Purchase Order and the appropriate Saudi Aramco
Inspection Requirements Form 175 covers the minimum requirements for
manufacturing, inspection and testing of crossovers covered by API SPEC 5CT for
Saudi Aramco. The material covered by this SAMSS will be used with the casing and
tubing covered by 45-SAMSS-006.
2.1 Any conflicts between this specification and other applicable Saudi Aramco
Materials System Specifications (SAMSSs), Engineering Standards (SAESs),
Standard Drawings (SASDs), or industry standards, codes, and forms shall be
resolved in writing by the Company or Buyer Representative through the
Manager, Drilling and Workover Engineering Department of Saudi Aramco,
Dhahran.
2.2 Direct all requests to deviate from this specification in writing to the Company or
Buyer Representative, who shall follow internal company procedure SAEP-302
and forward such requests to the Manager, Drilling and Workover Engineering
Department of Saudi Aramco, Dhahran.
3 References
The selection of material and equipment, and the design, construction, maintenance, and
repair of equipment and facilities covered by this specification shall comply with the
latest edition of the references listed below, unless otherwise noted.
Page 2 of 7
Document Responsibility: Drilling & Workover Wellhead & Valves 45-SAMSS-008
Issue Date: 29 December 2004 Casing and Tubing - Crossovers Requirements
Next Planned Update: 1 January 2010 Per API SPEC 5CT and API SPEC 5B
4 Definitions
Vendor: The other party to the order who may or may not be the manufacturer of the
material.
Buyer's Representative: The person acting on behalf of the Buyer, who may be from
Vendor Inspection (or its agent), or Purchasing.
5 Qualification of Manufacturers
Page 3 of 7
Document Responsibility: Drilling & Workover Wellhead & Valves 45-SAMSS-008
Issue Date: 29 December 2004 Casing and Tubing - Crossovers Requirements
Next Planned Update: 1 January 2010 Per API SPEC 5CT and API SPEC 5B
B. The plants or facilities as well as the Quality Control and Quality Assurance
Programs of both the manufacturer and the sub-contractor shall be approved by
Saudi Aramco Inspection Department (SAID). However, the SAID Survey
Reports have to be approved by the RSA in order to include that manufacturer in
The Approved List of Manufacturers.
6 Required Specification
For API 8RD or Buttress connections, the threads of both pin and box shall have
either Zinc or Phosphate plating.
For Premium Connections, the anti-galling plating shall be applied on both pin
and box threads. However, the plating type shall be to the patent holder's
specification.
For API 8RD or Buttress threaded and coupled connections, the hydrostatic
pressure test shall be performed in accordance with API SPEC 5CT with the
couplings installed power tight with API Modified Thread Compound with
friction correction factor of 1.0 in accordance with API BULL 5A2.
For Premium Grades and Premium Connections, the hydrostatic pressure test shall
be conducted in accordance with the manufacturers pressure ratings specification
with the couplings installed power tight with API Modified Thread Compound
with Friction Correction Factor of 1.0 in accordance with API BULL 5A2.
Prior to shipping, both the pin and the box threads shall be covered with a Saudi
Aramco approved anti-corrosive storage compound such a Kendall Kendex,
Driltec Thred Protec, and Jet Marine Imperator 2571.
For 4-½ inch and smaller sizes with API Connections, and all sizes with
Premium Connections, anti-corrosive thread storage compound shall be applied
on the threads and thread protectors shall be installed immediately after final
inspection.
Page 4 of 7
Document Responsibility: Drilling & Workover Wellhead & Valves 45-SAMSS-008
Issue Date: 29 December 2004 Casing and Tubing - Crossovers Requirements
Next Planned Update: 1 January 2010 Per API SPEC 5CT and API SPEC 5B
Both box and pin protectors shall be heavy duty polyethylene elastomer Drilltec
type resistant to ultraviolet radiation and with the size and thread type
permanently marked either by die stamping or embossing. The box end shall be
closed ended non-liftable and the pin end shall be open ended.
For 7 inch and larger sizes with either API 8RD or Buttress Connections, anti-
corrosive thread storage compound shall be applied on the threads and thread
protectors shall be installed immediately after final inspection. Protectors shall
be heavy duty mill standard steel thread protectors, Drilltec steel encapsulated
polyethylene type or Drilltec composite type resistant to ultraviolet radiation and
with size and thread type permanently marked on the protector. The box end
shall be closed ended non-liftable and the pin end shall be open ended.
For API Grades and API Connections, all API markings shall be both paint
stenciled and low stress die stamped in accordance with API SPEC 5CT, Section
10.
For API Connections, the pins and couplings shall be threaded in accordance
with API SPEC 5B. The threader shall be licensed by API and its facilities
approved by Saudi Aramco Inspection Department.
Page 5 of 7
Document Responsibility: Drilling & Workover Wellhead & Valves 45-SAMSS-008
Issue Date: 29 December 2004 Casing and Tubing - Crossovers Requirements
Next Planned Update: 1 January 2010 Per API SPEC 5CT and API SPEC 5B
The coupling "J" dimension in API SPEC 5B shall be coated with the same
coating as the pipe body. The coating shall not exceed 2 threads beyond the "J"
area. Approved coatings are Tubescope TK-69, Baker PA-400 or Vetco CEV-
226.
6.9 Traceability
A. For normalized material (J-55 or K-55), the material shall be lot traceable.
B. For heat treated material, pipe body shall be tube traceable from heat
treatment to delivery.
C. Couplings shall be lot traceable.
A. For all crossovers bodies and couplings stocks with wall thickne smaller
than 0.50 inch, Ultrasonic or Electromagnetic Test shall be performed over
the full length in accordance with SR1 of API SPEC 5CT.
B. For all crossovers bodies and couplings stocks with wall thickne of 0.50
inch or bigger, Ultrasonic Test shall be performed over the full length in
accordance with SR1 of API SPEC 5CT. Electromagnetic Test is not
acceptable.
For all crossovers from 2-3/8 inch to 18-5/8 inch (inclusive), each crossover
shall be drifted using API drift in accordance with API SPEC 5CT.
The down graded N-80 material shall not be substituted for J-55 or K-55. The
use of any material as an equivalent to the material specified in the Purchase
Order shall be approved by the RSA.
For API Grades, the pipe and coupling stock shall be produced in accordance
with API SPEC 5CT and the manufacturer shall be licensed by API and their
facilities shall be approved by Saudi Aramco Inspection Department.
Page 6 of 7
Document Responsibility: Drilling & Workover Wellhead & Valves 45-SAMSS-008
Issue Date: 29 December 2004 Casing and Tubing - Crossovers Requirements
Next Planned Update: 1 January 2010 Per API SPEC 5CT and API SPEC 5B
For Premium Grades, the pipe and coupling stock shall be produced in
accordance with API SPEC 5CT in regards to dimensions and tolerances and in
accordance with the manufacturers specification in regards to chemical and
mechanical properties.
Saudi Aramco shall only accept the following sizes for Seamless, Electric
Resistance Welded (ERW), and Submerged arc Welded (SAW) pipes:
2-3/8" - 13-3/8" = Seamless
18-5/8" - 24" = Seamless or ERW
6.14 Anti-Rust Mill Coating and Varnish
Revision Summary
29 December 2004 Revised the "Next Planned Update". Reaffirmed the contents of the document, and
reissued with change of responsibility from Drilling and Workover Services Dept. to Drilling
and Workover Engineering Dept.