WBS ID Activity/Task Name Predecessor Task Dependency

1.1 Property Acquisition/Lease/Rental 1.1 LEGAL TEAM/ROW

1.2 Documentation 1.1 LEGAL TEAM/ROW

1.3 Permitting 1.1 LEGAL TEAM/ROW

2.1 Order & Received 2.1 Procurement

2.2 Materials Delivery 2.1 Procurement

3.1 Planning 3.1 Engineering Design

3.2 Pre-Plan Drawing / Layout 3.1 Engineering Design

3.3 Approved Final Drawing / Layout 4.1 Engineering Design

4.1 Site Survey 3.2 Engineering Design / Implementation

4.2 Assessment Validation 3.2 Engineering Design / Implementation

5.1 Construction 1.3 Implementation

5.2 Construction Team 5.1 Implementation

5.2 Kick off 5.1 Implementation

5.3 Construction Shelter 5.1 Implementation

5.4 Fiber Laying 5.1 Implementation

5.5 Installation of Rack Space & Power 5.1 Implementation


6.1 Pre-Testing 5.1 Implementation /QA

6.2 End to end connectivity testing 5.1 Implementation

6.3 Facilities turn up testing 5.1 Implementation /QA

6.4 Remediation /Finalizing/Validation 6.1 Implementation

7.1 Acceptance 6.1 Implementation

7.2 Closed out packages 7.1 Implementation


PROJECT TASK COST SCHEDULLING
Duration Start Finish Property Cost Travel Training Overhead Cost

4 MONTHS 5/1/2022 5/5/2022 500000 500 2000 4000

3 MONTHS 01/15/2022 04/30/2022 0 500 0 500

3 MONTHS 1/2/2022 05/30/2022 300000 500 0 500

4 MONTHS 5/1/2022 5/5/2022 0 0 0 3000

4 MONTHS 5/1/2022 5/5/2022 0 50000 0 5000

4 MONTHS 5/1/2022 5/5/2022 0 500 0 500

3 MONTHS 5/1/2022 5/4/2022 0 500 0 500

1 MONTH 5/4/2020 5/5/2022 0 500 0 500

2 MONTHS 5/2/2022 5/4/2022 0 500 0 500

2 MONTHS 5/2/2022 5/4/2022 0 500 0 500

12 MONTHS 5/3/2022 5/4/2023 0 20000 0 5000

2 MONTH 5/1/2022 4/3/2022 0 0 10000 0

4 DAYS 3/3/2022 8/3/2022 0 0 0 10000

7 MONTHS 4/3/2022 4/10/2022 0 500 0 5000

9 MONTHS 4/3/2022 5/12/2022 0 20000 0 10000

7 MONTHS 5/5/2022 5/12/2022 0 500 0 5000


2 MONTHS 5/12/2022 5/2/2023 0 500 0 5000

2 MONTHS 5/12/2022 5/2/2023 0 500 0 5000

2 MONTHS 5/12/2022 5/2/2023 0 500 0 5000

2 MONTHS 5/1/2023 5/3/2023 0 500 0 5000

1 MONTH 10/3/2023 10/4/2023 0 500 0 5000

1 MONTH 10/4/2023 10/5/2023 0 500 0 5000


CHEDULLING
Material Cost Engineering Cost Direct Labor Cost Resources Estimating Methodology

1000 500 7000 515000 PARAMETRIC

500 500 2000 4000 PARAMETRIC

300 0 2000 300000 PARAMETRIC

2,500,000 0 2000 2505000 ANALOGOUS

0 0 10000 65000 ANALOGOUS

1000 20000 10000 32000 BOTTOM-UP

1000 20000 10000 32000 BOTTOM-UP

1000 20000 10000 32000 BOTTOM-UP

1000 5000 5000 12000 BOTTOM-UP

1000 5000 5000 12000 BOTTOM-UP

0 0 100000 125000 BOTTOM-UP

0 0 100000 110000 BOTTOM-UP

0 0 100000 110000 BOTTOM-UP

0 0 100000 105500 BOTTOM-UP

0 0 100000 130000 BOTTOM-UP

0 0 100000 105500 BOTTOM-UP


0 0 100000 105500 BOTTOM-UP

0 0 100000 105500 BOTTOM-UP

0 0 100000 105500 BOTTOM-UP

0 0 100000 105500 BOTTOM-UP

5000 0 100000 110500 BOTTOM-UP

5000 0 100000 110500 BOTTOM-UP


TOTAL 4838000
REMARKS/REASON

I used Parametric Estimating as I refer to the historical data in the process.

I used Parametric Estimating as I refer to the historical data in the process.

I used Parametric Estimating as I refer to the historical data in the process.


I used Analogous Estimatingas I don’t have detailed information about the of
procurement
I used Analogous Estimatingas I don’t have detailed information about the of
procurement

I used Bottom-Up Estimating as I interpreted the the task in its maximum


amount of time to estimate. The cost or duration of individual work packages,
task or activities is estimated in detail.

I used Bottom-Up Estimating as I interpreted the the task in its maximum


amount of time to estimate. The cost or duration of individual work packages,
task or activities is estimated in detail.

I used Bottom-Up Estimating as I interpreted the the task in its maximum


amount of time to estimate. The cost or duration of individual work packages,
task or activities is estimated in detail.

I used Bottom-Up Estimating as I interpreted the the task in its maximum


amount of time to estimate. The cost or duration of individual work packages,
task or activities is estimated in detail.

I used Bottom-Up Estimating as I interpreted the the task in its maximum


amount of time to estimate. The cost or duration of individual work packages,
task or activities is estimated in detail.

I used Bottom-Up Estimating as I interpreted the the task in its maximum


amount of time to estimate. The cost or duration of individual work packages,
task or activities is estimated in detail.

I used Bottom-Up Estimating as I interpreted the the task in its maximum


amount of time to estimate. The cost or duration of individual work packages,
task or activities is estimated in detail.

I used Bottom-Up Estimating as I interpreted the the task in its maximum


amount of time to estimate. The cost or duration of individual work packages,
task or activities is estimated in detail.

I used Bottom-Up Estimating as I interpreted the the task in its maximum


amount of time to estimate. The cost or duration of individual work packages,
task or activities is estimated in detail.

I used Bottom-Up Estimating as I interpreted the the task in its maximum


amount of time to estimate. The cost or duration of individual work packages,
task or activities is estimated in detail.

I used Bottom-Up Estimating as I interpreted the the task in its maximum


amount of time to estimate. The cost or duration of individual work packages,
task or activities is estimated in detail.
I used Bottom-Up Estimating as I interpreted the the task in its maximum
amount of time to estimate. The cost or duration of individual work packages,
task or activities is estimated in detail.

I used Bottom-Up Estimating as I interpreted the the task in its maximum


amount of time to estimate. The cost or duration of individual work packages,
task or activities is estimated in detail.

I used Bottom-Up Estimating as I interpreted the the task in its maximum


amount of time to estimate. The cost or duration of individual work packages,
task or activities is estimated in detail.

I used Bottom-Up Estimating as I interpreted the the task in its maximum


amount of time to estimate. The cost or duration of individual work packages,
task or activities is estimated in detail. And also to provide enough time to
the team to validate the whole project key milestone completion

I used Bottom-Up Estimating as I interpreted the the task in its maximum


amount of time to estimate. The cost or duration of individual work packages,
task or activities is estimated in detail.

I used Bottom-Up Estimating as I interpreted the the task in its maximum


amount of time to estimate. The cost or duration of individual work packages,
task or activities is estimated in detail.