INSPECTION REQUEST FOR MASONRY WORKS

PROJECT : SIWR :

ADDRESS : Date Requested :

Work Item : Requested by :

Contractor : JQ INTERNATIONAL CONSTRUCTION INC.

Contractor's Representative Project Management Inspector/s


Item # Checklist REMARS
Name/Initial Signature Name/Initial Signature

1 Line & Grade

2 Forms

3 Rebars, Dowel

4 Electrical

5 Sanitary

6 Plumbing

7 Structural

8 Mechanical

9 Architectural

10 Waterproofing

11 Equipment, Tools

12 QA/QC

13 Materials Approval

Notes:

Noted by : Mr. Liu Aden 30-Dec-99


Project Manager-Chinese Date

Received by :
Management Date

Note: SIWR''s shall be supported by Key plans, approved shop drawings reflecting the coverage/s of the subject request. Accomplish in two (2) sets. All trades
tasked to review for possible conflicts, imbeds and other preparations prior to the start of this requested work/s. Approval of this work request does not relieve
the contractor of its obligations under contract.