Directional drilling with minimum 140 MM main HDPE (OD), PN16 or as per
requirement to accommodate 3X50MM-OD (including supply and installation of
OSP-BB001 M 753.110
3X50MM HDPE PE100,PN 16 (40.8MM/50 MM (ID/OD)) ducts with 6mm Nylon rope
and end caps.
OSP-BB010 Milling and paving as per Municipality / MOT requirement with 1 meter width Sq.M 29.000
OSP-BB011 Milling and paving as per Municipality / MOT requirement with 3 meter width Sq.M 87.000
OSP-BB012 Milling and paving as per Municipality / MOT requirement with 4 meter width Sq.M 116.000
Supply and install 3x50mm HDPE PE100,PN 16 (40.8mm/50 mm (ID/OD)) duct with
OSP-BB015 M 27.000
detectable warning tape, 6mm Nylon rope, end caps and spacers for 20cm trench
Supply and install Mini-manhole Type-1 with round cover heavy duty cover as per ITC
OSP-BB024 Each 6,159.000
approved design by approved supplier.
Supply and install Two cover Handhole with square heavy duty cover as per ITC
OSP-BB026 Each 3,659.000
approved design by approved supplier.
OSP-BB031 Extra depth excavation in SOIL. Cu.M 46.880
Breaking & reinstatement of asphalt road surface as per municipality requirements &
OSP-BB033 standards including transportation of excavated materials to a pre-approved dumping Sq.M 73.820
area.
OSP-BB034 Breaking and reinstatement of normal concrete tile. Sq.M 89.780
OSP-BB036 Removing and reinstatement of interlocking tiles Sq.M 105.740
Supply and installation of concrete marker post as per ITC design and approved
OSP-BB050 Each 139.650
supplier including paint
Supply and placement of lean mix concrete (with minimum strength of 150kg/sq.cm at
OSP-BB055 Cu.M 183.540
28 days) for backfilling.
OSP-BB059 Dewatering from existing Manhole Type-A Each 448.880
Installation of fiber optic cable in sub-duct or hdpe pipe ( either blowing or pulling)-Hight
OSP-BB073 Lm 4.000
count with orange pipe installtion in MH/HH
OSP-BB076 Splice individual fiber in splice tray. Each 15.000
OSP-BB077 Terminate Individual Fiber at ODF (Any type) Each 15.000
OSP-BB078 Setting up joint closure or operate joint closure in manhole or in direct buried cable. Each 379.050
Trench excavation 200MM X 650MM in ROCK/Asphalt including full concrete back
filling (without 1M2 milling and paving) compaction and complete reinstatement. (Lump 61.00
OSP-BB163 M
sum cost, inclusive of preparing all kinds of drawings, obtaining permits transporting
surplus excavated material to designated area etc.) without marker post.
SUPPLY & INST. 1 x 4 ways 25/20mm HDPE Bundled MICRO DUCT
OSP-BB170 [25mm(OD)/20mm(ID)] SDR 11 in open trench, warning tape, and end caps. (Sheath M 15.000
color for the bundles as per ITC Standard).
Obtaining Permits for any type of trenching for Municipality Normal roads (irrespective
OSP-BB177 Meter 3.750
of the permit duration)
Obtaining Permits for any type of trenching for Municipality Main roads (irrespective of
OSP-BB178 Meter 7.500
the permit duration)
Charges for Asphalting of renovated streets of equal to or more than three (3) meters
OSP-BB179 wide using a Municipality approved contractor(Marshel mixed) with Administration Sq. M 42.500
charges
Charges for Asphalting of renovated streets of equal to or more than three (3) meters
OSP-BB180 wide using a Municipality approved contractor(Super paver) with Administration Sq. M 52.500
charges
Supply and install Handhole with Round cover hingable (Ductile Iron) cover as per ITC
OSP-BB198 Each 4,000.000
approved design and from approved supplier.
Supply and Install of bridge attachment consists of bracket to be fixed with bridge
OSP-BB204 structure at one meter spacing, installation of galvanized cable tray of minimum width of Mtr 500.000
350mm, installation of 315mm OD HDPE pipe. (LUMP SUM Cost)
Trench excavation 400MM X 1300MM in SOIL including back filling, (without milling
and paving) compaction and complete reinstatement. (Lump sum cost, inclusive of
OSP-BB212 M 29.930
preparing all kinds of drawings, obtaining permits, transporting surplus excavated
material to designated area etc.) without marker post.
OSP-BB264 Raise/lower manhole neck in pavement area Each 947.625