Sample 2x50MW Coal Fired Thermal Power Plant Proposal and Quotation

Content

1. Quotation Remark and Specification

2. Power plant's Technical Specification on Main System

3. Main Schedule of the Implementation

4. Summary of Quotation

5. Main List of Power Plant Equipment

 /P>

1. Quotation Remark and Specification

a. Quotation validity December 2006

b. The quotation is a EPC quotation including power plant design, equipments and their auxiliaries,
materials, spare parts, installation and commissioning, training, not including maintenance and operation.
Civil engineering contract not included, and should be offered to local contractors and finished by locals.

c. Equipments should be packed to Chinese equipments export standard.

e. Power plant design, equipment manufacturing and materials should be to Chinese National Standards
for power plants.

f. This quotation is based on the limited information available from owner, and referred to our similar
power plants built in Indonesia. The quotation and specification should be revised to new data and
owners' detailed requirements through discussion.

g. Other issues should be referred to the forms of each equipments in the .xls file

2. Power plant's Technical Specification on Main System

a. Thermal System specification

Boiler YG-240/9.8 2 units of CFB boiler


Producer��?Jinan, with ISO9002,National First Class boiler producer

Rated Flow: 220t/h

Steam Pressure: 9.81Mpa

Steam Temp.: 540��?/P>

In feeding water temp.: 215��?

Fuel: Coal

Fuel Value��?SPAN style="mso-spacerun: yes">                    20934 kJ/kg

Design Efficiency: 90%

Steam Turbine:N50-8.82 1unit Qingdao Turbine

Producer��?Qingdao Turbine IS9002

In steam Flow��?SPAN style="mso-spacerun: yes">                186t/h

In steam Pressure��?SPAN style="mso-spacerun: yes">          8.82Mpa

In steam Temp.��?SPAN style="mso-spacerun: yes">              535��?

Rated Power��?SPAN style="mso-spacerun: yes">                 50MW

Rated Speed��?SPAN style="mso-spacerun: yes">                 3000r/min

Steam Turbine:C50-8.82/2.55 1 Unit

Producer��?Qingdao Turbine IS9002

In steam Flow��?SPAN style="mso-spacerun: yes">  Rated/Max. 458/480 t/h

Condensing 200 t/h

In steam Pressure��?SPAN style="mso-spacerun: yes">                           8.82Mpa


In steam Temp.��?SPAN style="mso-spacerun: yes">                               535��?

Extraction: Rated/Max. 72/95 t/h

Extraction Pressure: 2.55±0.30 Mpa (Abstract)

Extraction Temp.: 335 ��?/P>

Turbine Generator:QF-50 2 Units

Producer��?SPAN style="mso-spacerun: yes">   Jinan Generator IS9002

Rated Voltage��?SPAN style="mso-spacerun: yes">                                11KV

Rated Power��?SPAN style="mso-spacerun: yes">                                  30MW

Rated Speed��?SPAN style="mso-spacerun: yes">                                  3000r/min

Cooling��?SPAN style="mso-spacerun: yes">                                           Air Cooling

b. Coal and Ash handling system specification

Coal Supervison:coal be transported to plant by owner, and coal stockyard and dry coal booth be
installed with dry coal capacity of 15 days usage.

There are loaders and bridge Coal trucks for loading and loading coal, the 8MM pulverized coal convoyed
to two coal bunkers in from of the boiler, with each bunker' capacity for 12 hours coal supply.

Two streams of conveyor systems be installed, with detection and removal of ferrous tramp material,
screening, crushing, and metering equipments. Operation of two shifts, each shift for 5.5 hours.

Fuel handling system be equipped with limestone handling equipments if higher sulpher content in coal,
or ratioed limestone be added to coal stockyard and mixed for fuel supply to boiler.

Ash handling system: boiler flu gas handled by electro-precipitator with efficiency of 99.7%,precipitated
ash be transported to two ash bunkers by positive pneumatic ash removal ways with ask bunkers holding
capacity for 7 days. Bunker beneath ash be removed in dry or wet condition to outside plant by truck. In
the plant only transient ash sump constructed.
Cinder removal in dry condition, boiler beneath cinder or ash be cooler by cooler and convoyed to cinder
bunker and then trucked out. The bunker is of one day capacity.

Boiler cinder and ash can be reused, but not quoted in this quotation.

c.Electrical System Specification

This proposal is for that power supply is not connected with national grid��?1kv generator is connected
to transformer and step up to 22kv bus bar, Single bus bar is adopted, and 4 routers of feed out line to
ender users. High voltage for in plant usage be supplied directly from generator,single bus bar is used.
0.4kv in plant usage power is evacuated from 11kv in plant high voltage. The standby transformer
connected by power cables will automatically put into service when there are problems with certain prime
transformers. DC power supply system is installed too, Relay protection and control system are governed
by Micro computer. Steam turbo generator is of controllable silicon static excitation. Most of the electrical
system are made by Joint ventures with international quality.

Plant standby and starting power is offered by owner, and power transmission, illumination and
telecommunication is not inclued in the quotation.

D. Thermal control specification

Thermal control system covering boiler, steam, dearator and water supply, chemical water treatment, coal
feeding and ash handling and so on. Boiler and steam turbine control is of DCS. DCS covering mainly:
Data Collection and Process system (DAS). Analogue control System (MCS), Sequence control system
(SCS) and so on, with their main tasks as check. automatic governing (MCS). main auxiliary on-lock
protection (SCS. protection and alarming. All the equipments and systems are made by mature and high
standard quality.

Auxiliary systm such as boiler ash blow, ash removal, coal feeding, and chemical water treatment
systems are using independent PLC system.

Control methods: boiler, steam turbine, dearator and water supply are of centerilized control, chemical
water treatment, coal feeding and ash handling are of at site control.

e. chemical water treatment is adopted with process of anion-ion exchange desalt with capacity of 40t/h.

f. Water Suplly System��?BR>The quotation not including water source site supply and purification,
daily life water consumption.
Including water supply for equipment cooling, fire protection water and waste water treatment.

Steam turbine cooling usage of about 13500t/h, recycling method is used.

The total water supplement is about 400m3h��?SPAN style="mso-spacerun: yes"> 

g. Auxiliary operation systems: meeting the demand for equipment checking and repairement,
instrumentation, and laboratory, ventilation and fire protection. Some large sized components or parts can
be made assembled by local contractors. Office and dorm are not included in quotation.

3. Main Schedule of the Construction

Schedules in two stages:

Stage one of proposal: 60 days after complete data or documents available

Stage two of implementation: 660 days after signature.

To be continued.

4. Quotation (2x220+1xC50+1xN50) Thermal power plant, coal fired with bolier

Expenses Expenses
NO. 4
Item Name (RMB10 ) (USD)

1 Combustion system 8939.72 11,316,104


2 Thermodynamic system 6553.85 8,296,016
3 Fuel System 706.01 893,687
4 Ash remove System 506.04 640,562
5 Supply & Drainage water system 366.01 463,301
6 Demineralized water system 334.62 423,568
7 Electrical system 6568.54 8,314,613
8 The thermal control and instrumental system 1568.62 1,985,595
9 Subsidiary production equipment 331.14 419,170
10 Start-up power supply 1380.54 1,747,524

subtotal 27255.11 34,500,139


/FONT>
11 Main materials 2949.72 3,733,827
12 Expense for internal transportation and commodities 2270.18 2,873,639
inspect
13 Integration, management and tools 398.58 504,532
14 Design expenses 932.75 1,180,691
15 Civil work cost (Ex foundation treatment) 10865.00 13,753,165

Foundation treatment 901.00 1,140,506


/FONT>
Installation work cost (Ex large construction equipment
16 6909.08 8,745,671
cost)

Large construction equipment cost 424.00 536,709


/FONT>

Detail test & Running-in cost 212.00 268,354


/FONT>

Fuel cost 1653.60 2,093,165


/FONT>
17 Other one cost 3430.18 4,341,997

subtotal 30946.08 39,172,256


/FONT>

合计 Total expenses 58201.19 73,672,395


/FONT>
RMB change into Us dollar is 7.9��?/FONT>1 and quotation will be revised to exchange rate.