TO : ALB BUILDING : SALCEDO TOWERS

FROM : KRIZZA CORDERO DATE : July 13, 2020


SUBJECT : DAILY REPORT

A. MAINTENANCE ON DUTY:
R. PAGASPAS R. MIRAMONTE A.LOYOLA
R. BEROG W.OCTA

B. REGULAR ACTIVITIES DONE:

*CHECKED TRANSFER PUMPS AND MOTORS OPERATION AT TB & TA. CONDUCTED DAILY CHEC
*TURNED ON COOLING TOWER UNITS. PERFORMED DAILY CHECKLIST.
*TURNED ON PACUs FROM 27/F -6/F OF BOTH TOWERS
*DAILY INSPECTION OF ATS, ACQUIRED TEMP, VOLTAGE, AND AMPERAGE READING
*SWITCHED OFF PACUs AT ALL FLOORS AND COOLING TOWER UNITS
*DAILY READING OF ELECTRICITY AND WATER CONSUMPTION
C. SPECIAL ACTIVITIES
*CHANGED-ENGINE OIL OF 2 GENERATOR SETS (438 AND 469 KVA) AT TOWER A
*REPLACED BATTERIES, FUEL FILTER, RADIATOR COOLANT, COOLANT FILTERS, COMBINATION
*TEST RUN GENSETS NEWLY CHANGED-OIL GENERATING SETS
*STRIPPING OF GENSET ROOM FLOORING AT TA
*DISMANTLED UNUSED BRACKET AT BASKETBALL COURT 28/F
*REPAINTED STORAGE RACKS AT 3/F PAINT STORAGE
*REPAINTED PIPELINES OF SUMP PIT

KRIZZA
*PERFORMED DAILY INSPECTION CHECKLIST OF EQUIPMENT ROOMS
*CHECKED AND MONITORED MAINTENANCE ACTIVITIES
*ASSISTED CHANGE-OIL ACTIVITIES AND LOGGED IT ALL TO LOGBOOKS
*FOLLOWED UP P.O. STATUS WITH HANNA (ACCOUNTING)
*FOLLOWED UP GONDOLA PARTS DELIVERY STATUS AND MOTOR RENTAL INQUIRY
*CONTINUE AUDIT MATERIALS INVENTORY IN ALL STORAGES
D. EMERGENCY REPAIRS:
Trouble/Defect Course of Action Result
NONE

E. TENANT REQUEST/COMPLAINTS:
Trouble/Defect Course of Action Result
NONE

PREPARED BY: NOTED BY


K. CORDERO ROWLEY F. TABUT
BUILDING ENGINEER HEAD ENGINEER

file:///conversion/tmp/activity_task_scratch/534414432.xlsx
TO : ALB BUILDING : SALCEDO TOWERS
FROM : KRIZZA CORDERO DATE : July 18, 2020
SUBJECT : DAILY REPORT
A. MAINTENANCE ON DUTY:
R. PAGASPAS R. MIRAMONTE A.LOYOLA
R. BEROG I. NOVIO W.OCTA

B. REGULAR ACTIVITIES DONE:

*CHECKED TRANSFER PUMPS AND MOTORS OPERATION AT TB & TA. CONDUCTED DAILY CHEC
*DAILY INSPECTION OF ATS, ACQUIRED TEMP, VOLTAGE, AND AMPERAGE READING
*DAILY READING OF ELECTRICITY AND WATER CONSUMPTION
C. SPECIAL ACTIVITIES
*CONSTRUCTED DELIVERY RAMP AT 4/F PARKING - DONE
*REPAINTED STAIR RAILINGS AT 27/F STAIR 4
*INSTALLED FIRE EXTINGUISHERS FROM 14/F TO 20/F
*DISMANTLED CEILING VENT GRILLS AT B2 PARKING
*CONTINUE ORGANIZED PAINTING SUPPLIES AT 3/F STORAGE - DONE
*REPAINTED 3/F PAINTING EQUIPMENT RM
*WEEKLY TEST RUN OF GENSET - REFILL RADIATOR COOLANT

KRIZZA
*CHECKED AND MONITORED MAINTENANCE ACTIVITIES
*RECEIVED DELIVERY FROM MALAYA LUMBER
*ANSWERED EMAIL INQUIRIES OF TENANTS ABOUT BUILDING LOCKDOWN
*REPRINTED INDEX CARD INVENTORY FOR MATERIALS AT B2 AND B1 STORAGES
*SUPERVISED WEEKLY GENSET TEST RUN AT 2/F (TA AND TB SIDE)
*LISTED MATERIALS NEEDED IN OPERATIONS
*COLLATED AND FILED CHECKLISTS FOR ALL EQUIPMENT
D. EMERGENCY REPAIRS:
Trouble/Defect Course of Action Result

NONE

E. TENANT REQUEST/COMPLAINTS:
Trouble/Defect Course of Action Result

PREPARED BY: NOTED BY

K. CORDERO ROWLEY F. TABUT


BUILDING ENGINEER HEAD ENGINEER

file:///conversion/tmp/activity_task_scratch/534414432.xlsx
TO : ALB BUILDING : SALCEDO TOWERS
FROM : KRIZZA CORDERO DATE : July 20, 2020
SUBJECT : DAILY REPORT
A. MAINTENANCE ON DUTY:
R. PAGASPAS R. MIRAMONTE A.LOYOLA
R. BEROG I. NOVIO W.OCTA
B. REGULAR ACTIVITIES DONE:
*CHECKED TRANSFER PUMPS AND MOTORS OPERATION AT TB & TA. CONDUCTED DAILY CHEC
*TURNED ON COOLING TOWER UNITS. PERFORMED DAILY CHECKLIST.
*TURNED ON PACUs FROM 27/F -6/F OF BOTH TOWERS
*DAILY INSPECTION OF ATS, ACQUIRED TEMP, VOLTAGE, AND AMPERAGE READING
*SWITCHED OFF PACUs AT ALL FLOORS AND COOLING TOWER UNITS
*DAILY READING OF ELECTRICITY AND WATER CONSUMPTION
C. SPECIAL ACTIVITIES

*DISMANTLED OLD CORRUGATED ROOF AT 28/F


*LAID OUT SLANTED ROOF TRUSSES OF FILTRATION RM
*REPAINTED STAIR RAILINGS AT 28/F TB
*PICKED UP NEWLY REWINDED WATER PUMP MOTOR FROM ARANAS SHOP
*REPAIRED DAMAGED WALL AT 4/F HOUSEKEEPING STORAGE (APPLIED PUTTY & REPLACED 1'X
*REPAINTED DOOR AND DOOR JAMB OF F&B STORAGE AT 4/F
*ORGANIZED PAINTING SUPPLIES AT 3/F - DONE
*FOLLOWED UP CLEANING OF 5/F MAINTENANCE QUARTERS AND ITS TOILET
*CLEANED CEMENT STORAGE AT B2 STORAGE
*ARRANGED NEWLY DELIVERED PAINT MATERIALS AT 3/F
*HUNG AND INSTALLED NEW FIRE EX UNIT AT 3/F STORAGE

KRIZZA
*PERFORMED DAILY INSPECTION CHECKLIST OF EQUIPMENT ROOMS
*CHECKED AND MONITORED MAINTENANCE ACTIVITIES
*ASSISTED SCHINDLER IN TROUBLESHOOTING PE.8 - NOT ADDRESSED TO BE CONTINUED T
*ASSISTED BEROG AND MIRAMONTE IN LAYINGOUT ROOF TRUSSES
*RECEIVED CIRCUIT BREAKERS AND NEMA ENCLOSURE DELIVERY FROM SOUTH AVE.
*SENT QUOTATION OF ANGLE VALVE AND FLEXIBLE HOSES REPLACEMENT TO JAMI ADMIN AT
*CALLED MS.EVELYN, FOLLOWED UP MOBILIZATION DATE OF RENTED GONDOLA - TENTATIVE ON JU

D. EMERGENCY REPAIRS:
Trouble/Defect Course of Action Result

NONE

E. TENANT REQUEST/COMPLAINTS:
Trouble/Defect Course of Action Result
NONE

PREPARED BY: NOTED BY


K. CORDERO ROWLEY F. TABUT

file:///conversion/tmp/activity_task_scratch/534414432.xlsx
BUILDING ENGINEER HEAD ENGINEER

file:///conversion/tmp/activity_task_scratch/534414432.xlsx
TO : ALB BUILDING : SALCEDO TOWERS
FROM : KRIZZA CORDERO DATE : July 22, 2020
SUBJECT : DAILY REPORT
A. MAINTENANCE ON DUTY:
R. PAGASPAS R. MIRAMONTE A.LOYOLA
R. BEROG I. NOVIO- ON-LEAVE W.OCTA
B. REGULAR ACTIVITIES DONE:
*CHECKED TRANSFER PUMPS AND MOTORS OPERATION AT TB & TA. CONDUCTED DAILY CHEC
*TURNED ON COOLING TOWER UNITS. PERFORMED DAILY CHECKLIST.
*TURNED ON PACUs FROM 27/F -6/F OF BOTH TOWERS
*DAILY INSPECTION OF ATS, ACQUIRED TEMP, VOLTAGE, AND AMPERAGE READING
*SWITCHED OFF PACUs AT ALL FLOORS AND COOLING TOWER UNITS
*DAILY READING OF ELECTRICITY AND WATER CONSUMPTION
*FOLLOWED UP CLEANING OF 5/F MAINTENANCE QUARTERS AND TOILET
C. SPECIAL ACTIVITIES

*INSTALLED FLEXIBLE LIQUID TIGHT ELECTRICAL CONDUIT FOR FAN MOTORS OF COOLING TOWER
*REPLACED DAMAGED COVERS OF JUNCTION BOXES
*CONTINUE INSTALLATION OF CORRUGATED ROOF OF FILTRATION RM AT 28/F - DONE
*REPAINTING OF WALL AT 28/F STAIR 1
*DIAGNOSED WATER PUMP OF FILTRATION SYSTEM - UNIT HAD AN UNCESSARY NOISE (FOR F
*REPAINTED AIR-COMPRESSOR UNIT AT 3/F
*DISMOUNTED 6018CHAIN COUPLING OF TRANSFER PUMP AND MOTOR AT B3 PUMP ROOM - F
*RECEIVED MATERIALS DELIVERY (PLYWOOD AND WELDING ROD)
*REPAINTED STAIR STEEL RAILINGS OF STAIR 4 FROM 3F -5/F

KRIZZA
*PERFORMED DAILY INSPECTION CHECKLIST OF EQUIPMENT ROOMS AND PARKING FLOORS
*CHECKED AND MONITORED MAINTENANCE ACTIVITIES
*ASSISTED BEROG IN INSTALLATION OF FLEXIBLE CONDUITS OF COOLING TOWER B
*ASSISTED REPLACEMENT OF BUSTED STRIPLIGHTINGS AT TOWER B LOBBY
*CHECKED AND COLLATED COOLING TOWER CHECKLISTS FOR A AND B
*DIAGNOSED WATER PUMP OF FILTRATION SYSTEM
*ASSISTED BEROG IN DISMOUNTING OF CHAIN COUPLING OF TRANSFER PUMP AND MOTOR
*CALLED MR.DION OF CHEMSY ABOUT THE SCHEDULE OF THE DESCALING ACTIVITY
D. EMERGENCY REPAIRS:
Trouble/Defect Course of Action Result

NONE

E. TENANT REQUEST/COMPLAINTS:
Trouble/Defect Course of Action Result
NONE

PREPARED BY: NOTED BY


K. CORDERO ROWLEY F. TABUT
BUILDING ENGINEER HEAD ENGINEER
file:///conversion/tmp/activity_task_scratch/534414432.xlsx
TO : ALB BUILDING : SALCEDO TOWERS
FROM : KRIZZA CORDERO DATE : July 24, 2020
SUBJECT : DAILY REPORT
A. MAINTENANCE ON DUTY:
R. PAGASPAS R. MIRAMONTE A.LOYOLA
R. BEROG I. NOVIO W.OCTA
B. REGULAR ACTIVITIES DONE:
*CHECKED TRANSFER PUMPS AND MOTORS OPERATION AT TB & TA. CONDUCTED DAILY CHEC
*TURNED ON COOLING TOWER UNITS. PERFORMED DAILY CHECKLIST.
*TURNED ON PACUs FROM 27/F -6/F OF BOTH TOWERS
*DAILY INSPECTION OF ATS, ACQUIRED TEMP, VOLTAGE, AND AMPERAGE READING
*SWITCHED OFF PACUs AT ALL FLOORS AND COOLING TOWER UNITS
*DAILY READING OF ELECTRICITY AND WATER CONSUMPTION
*FOLLOWED UP CLEANING OF 5/F MAINTENANCE QUARTERS AND TOILET
C. SPECIAL ACTIVITIES

*ASSISTED DELIVERY OF ACQUA EPOXY GRAY PAINT FROM MALAYA LUMBER


*CONDUCTED INVENTORY COUNT AT 3/F MAINTENANCE CONSUMABLES STORAGE
*REPLACED 1-DEFECTIVE UNIT OF FLOOR HINGE OF TB GLASS DOOR ENTRANCE
*NEUTRILIZE DELIVERY RAMP AT 4/F AND B1 PARKING
*REPAINTED 5/F PARKING SLOTS - 6 SLOTS DONE
*REPAINTED B1 PARKING SLOTS - 2 SLOTS DONE
*ATTENDED MEETING W/ ALB AT MARAJO TOWER

KRIZZA
*PERFORMED DAILY INSPECTION CHECKLIST OF EQUIPMENT ROOMS
*CHECKED AND MONITORED MAINTENANCE ACTIVITIES
*ASSISTED BEROG AND MIRAMONTE IN INSTALLATION OF NEW FLOOR HINGE AT TB ENTRAN
*RECEIVED CALL FROM MS.EVELYN OF ACCESS SAFEWORKS - CONFIRMED MOBILIZATION OF RENTE
*CHECKED INVENTORY AT 3/F MAINTENANCE CONSUMABLE MATERIALS
*FOLLOWED UP DELIVERY OF DISINFECTION PPES FOR HOUSEKEEPING
*ATTENDED MEETING W/ ALB AT MARAJO TOWER

D. EMERGENCY REPAIRS:
Trouble/Defect Course of Action Result

NONE

E. TENANT REQUEST/COMPLAINTS:
Trouble/Defect Course of Action Result

NONE

PREPARED BY: NOTED BY


K. CORDERO ROWLEY F. TABUT
BUILDING ENGINEER HEAD ENGINEER

file:///conversion/tmp/activity_task_scratch/534414432.xlsx
TO : ALB BUILDING : SALCEDO TOWERS
FROM : KRIZZA CORDERO DATE : July 25, 2020
SUBJECT : DAILY REPORT
A. MAINTENANCE ON DUTY:
R. PAGASPAS R. MIRAMONTE A.LOYOLA
R. BEROG I. NOVIO W.OCTA
B. REGULAR ACTIVITIES DONE:
*CHECKED TRANSFER PUMPS AND MOTORS OPERATION AT TB & TA. CONDUCTED DAILY CHEC
*TURNED ON COOLING TOWER UNITS. PERFORMED DAILY CHECKLIST.
*TURNED ON PACUs AT SEVERAL UNITS IN BOTH TOWERS
*DAILY INSPECTION OF ATS, ACQUIRED TEMP, VOLTAGE, AND AMPERAGE READING
*SWITCHED OFF PACUs AT SEVERAL UNITS IN BOTH TOWERS
*DAILY READING OF ELECTRICITY AND WATER CONSUMPTION
*FOLLOWED UP CLEANING OF 5/F MAINTENANCE QUARTERS AND TOILET
C. SPECIAL ACTIVITIES
*REPLACED AND LUBRICATED 6018 NIPPON CHAIN COUPLING OF CT PUMP AND MOTOR OF COOLING
*ASSISTED MERALCO PERSONNEL IN CHECKING ELEC. METERS OF JAMI (22/F)
*HAULED GARBAGE MATERIALS AND DEBRIS FROM 2/F TO B1
*REPLACED DEFECTIVE ANGULAR BALL BEARING OF PACU AT 18/F TB
*CONTINUE REPAINTING AT 5/F PARKING SLOTS
*CONTINUE REPAINTING AT 5/F PARKING SLOTS
*REPAINTING OF SEWER PIPELINES AT B3 PUMP ROOM
*ASSISTED LORICO PERSONNEL IN HAULING OF DEBRIS AND GARBAGES
*PAINTED FIRST COATING OF DELIVERY RAMP AT 4/F AND B1 PARKING
*TEST RAN GENSET UNITS AT TA & TB

KRIZZA
*HAULED GALLONS OF ALCOHOL AND LYSOL SUPPLIES FROM MARAJO
*CHECKED AND ASSISTED BEROG IN REPLACING WORN OUT CHAIN COUPLING OF 400-TR CT
*ASSISTED ACCESS SAFEWORKS DELIVERY OF GONDOLA PARTS (RENTED)
*CHECKED AND DOCUMENTED STIR-UPS DISMOUNTING AND PULLED OUT BY ACCESS SAFEWORKS
*ASSISTED MIRAMONTE IN REPLACING OF PACU BEARING AT 18/F
*ASSISTED LORICO PERSONNEL AND PAID HAULING SERVICE
*TEST RAN GENSET UNITS AT TA & TB
D. EMERGENCY REPAIRS:
Trouble/Defect Course of Action Result
NONE

E. TENANT REQUEST/COMPLAINTS:
Trouble/Defect Course of Action Result
NOISY OPERATION OF
PACKAGED AIR-CONDITIONING REPLACED ANGULAR BALL
OPERATION OF UNIT IS BACK TO NORMAL
UNIT AT PEOPLE 4 U'S OFFICE BEARING OF PACU
(18/F TB)
PREPARED BY: NOTED BY
K. CORDERO ROWLEY F. TABUT
BUILDING ENGINEER HEAD ENGINEER
file:///conversion/tmp/activity_task_scratch/534414432.xlsx
TO : ALB BUILDING : SALCEDO TOWERS
FROM : KRIZZA CORDERO DATE : July 27, 2020
SUBJECT : DAILY REPORT
A. MAINTENANCE ON DUTY:
R. PAGASPAS R. MIRAMONTE A.LOYOLA
R. BEROG I. NOVIO W.OCTA
B. REGULAR ACTIVITIES DONE:
*CHECKED TRANSFER PUMPS AND MOTORS OPERATION AT TB & TA. CONDUCTED DAILY CHEC
*TURNED ON COOLING TOWER UNITS. PERFORMED DAILY CHECKLIST.
*TURNED ON PACUs FROM 27/F -6/F OF BOTH TOWERS
*DAILY INSPECTION OF ATS, ACQUIRED TEMP, VOLTAGE, AND AMPERAGE READING
*SWITCHED OFF PACUs AT ALL FLOORS AND COOLING TOWER UNITS
*DAILY READING OF ELECTRICITY AND WATER CONSUMPTION
*FOLLOWED UP CLEANING OF 5/F MAINTENANCE QUARTERS AND TOILET
C. SPECIAL ACTIVITIES

*REPLACED OLD LAVATORY BASIN WITH NEW SEMI PEDESTAL UNIT AT B1 TOILET
*REPLACED AND RE-ALIGNED 6018 CHAIN COUPLING OF TRANSFER PUMP AND MOTOR AT B3
*ARRANGED AND REPAIRED RACKS OF CONSUMABLE MATERIALS AT 3/F STORAGE
*RECEIVED DELIVERY FROM WILCON
*MOUNTED TOOL CABINET AT 3/F STORAGE
*RELOCATED AND HAULED SCAFFOLDINGS FROM B2 TO 4/F
*ACCESS SAFEWORKS PERSONNEL IN MOBILIZATION OF WIRE ROPES TO 28/F AND SETTING

KRIZZA
*PERFORMED DAILY INSPECTION CHECKLIST OF EQUIPMENT ROOMS
*CHECKED AND MONITORED MAINTENANCE ACTIVITIES
*CHECKED ACCESS SAFEWORKS PERSONNEL IN MOBILIZATION OF WIRE ROPES TO 28/F AND SET
*CHECKED NEWLY REPLACED CHAIN COUPLING OF PUMP AND MOTOR OF 400-TR COOLING TO
*ASSISTED BEROG IN REPLACING WORN OUT CHAIN COUPLING OF TRANSFER PUMP AND MOTO
*MEETING WITH HUAWEI/GLOBE PERSONNEL (DISCUSSED PROBABLE UPGRADE OF THEIR AN
*WENT BACK TO HEAD OFFICE
*GAVE LIQUIDATION REPORT WITH MA'AM CYNTHIA AND HANNA
*REQUESTED MATERIALS NEEDED AT SITE AND RECEIVED DISINFECTION PPES FOR STAFF
D. EMERGENCY REPAIRS:
Trouble/Defect Course of Action Result
NONE

E. TENANT REQUEST/COMPLAINTS:
Trouble/Defect Course of Action Result
NONE

PREPARED BY: NOTED BY


K. CORDERO ROWLEY F. TABUT
BUILDING ENGINEER HEAD ENGINEER

file:///conversion/tmp/activity_task_scratch/534414432.xlsx
TO : ALB BUILDING : SALCEDO TOWERS
FROM : KRIZZA CORDERO DATE : July 28, 2020
SUBJECT : DAILY REPORT
A. MAINTENANCE ON DUTY:
R. PAGASPAS R. MIRAMONTE A.LOYOLA
R. BEROG I. NOVIO W.OCTA - Absent
B. REGULAR ACTIVITIES DONE:
*CHECKED TRANSFER PUMPS AND MOTORS OPERATION AT TB & TA. CONDUCTED DAILY CHEC
*TURNED ON COOLING TOWER UNITS. PERFORMED DAILY CHECKLIST.
*TURNED ON PACUs FROM 27/F -6/F OF BOTH TOWERS
*DAILY INSPECTION OF ATS, ACQUIRED TEMP, VOLTAGE, AND AMPERAGE READING
*SWITCHED OFF PACUs AT ALL FLOORS AND COOLING TOWER UNITS
*DAILY READING OF ELECTRICITY AND WATER CONSUMPTION
*FOLLOWED UP CLEANING OF 5/F MAINTENANCE QUARTERS AND TOILET
C. SPECIAL ACTIVITIES

*REPLACED OLD LAVATORY BASIN WITH NEW SEMI PEDESTAL UNIT AT 5/F MAINTENANCE QUARTE
*REPLACED DEFECTIVE TANK FITTINGS OF TOILET AT 5/F MAINTENANCE QUARTERS
*REPAINTED SECOND COATING OF ACQUA EPOXY AND QDE YELLOW OF DELIVERY RAMP AT 4/
*REPAINTED RACKS AND CABINETS OF CONSUMABLE MATERIALS AT 3/F STORAGE
*ASSISTED ACCESS SAFEWORKS PERSONNEL IN SETTING UP OF GONDOLA PLATFORM
*POLISHED AND APPLIED PRIMER PAINT TO NEWLY FABRICATED GRILLS AT WORKSHOP

KRIZZA
*PERFORMED DAILY INSPECTION CHECKLIST OF EQUIPMENT ROOMS
*CHECKED AND MONITORED MAINTENANCE ACTIVITIES
*ASSISTED ACCESS SAFEWORKS PERSONNEL IN POWER TAPPING AND CABLING WORKS
*ASSISTED MIRAMONTE IN INSTALLATION OF LAVATORY BASIN AND AND P-TRAP REPLACEMENT
*COLLATED CHECKLISTS FOR COOLING TOWERS, PUMP ROOMS AND GENSETS AT BOTH TOWE
*CHECKED AND FOLLOWED UP PENDING DELIVERY OF MATERIALS
D. EMERGENCY REPAIRS:
Trouble/Defect Course of Action Result

NONE

E. TENANT REQUEST/COMPLAINTS:
Trouble/Defect Course of Action Result
NONE

PREPARED BY: NOTED BY


K. CORDERO ROWLEY F. TABUT
BUILDING ENGINEER HEAD ENGINEER

file:///conversion/tmp/activity_task_scratch/534414432.xlsx
TO : ALB BUILDING : SALCEDO TOWERS
FROM : DATE :
SUBJECT : DAILY REPORT
A. MAINTENANCE ON DUTY:
R. PAGASPAS R. MIRAMONTE A.LOYOLA M. MACARAEG
R. BEROG I. NOVIO W.OCTA
B. REGULAR ACTIVITIES DONE:
*CHECKED TRANSFER PUMPS AND MOTORS OPERATION AT TB & TA. CONDUCTED DAILY CHEC
*TURNED ON COOLING TOWER UNITS. PERFORMED DAILY CHECKLIST.
*TURNED ON PACUs FROM 27/F -6/F OF BOTH TOWERS
*DAILY INSPECTION OF ATS, ACQUIRED TEMP, VOLTAGE, AND AMPERAGE READING
*SWITCHED OFF PACUs AT ALL FLOORS AND COOLING TOWER UNITS
*DAILY READING OF ELECTRICITY AND WATER CONSUMPTION
*FOLLOWED UP CLEANING OF 5/F MAINTENANCE QUARTERS AND TOILET
C. SPECIAL ACTIVITIES

D. EMERGENCY REPAIRS:
Trouble/Defect Course of Action Result
NONE

E. TENANT REQUEST/COMPLAINTS:
Trouble/Defect Course of Action Result
NONE

PREPARED BY: NOTED BY


ROWLEY F. TABUT
BUILDING ENGINEER HEAD ENGINEER