JADWAL WAKTU PELAKSANAAN ( MASTER SCHEDULE)

WAKTU PELAKSANAAN :
1. KONTRAK AWAL = 210 HARI
2. KONTRAK MYC = 313 HARI
Nama Paket : Paket Pembangunan Rumah Susun Provinsi Sumatera Utara 3 TA. 2020 (RSNPP 20-03) 313
3. ADD WAKTU = 60 HARI
Type Prototype : Rumah Susun Type- 36 4. TOTAL = 583 HARI
Jumlah Lantai : 3 Lantai
Lokasi : Sumatera Utara, Kab Humbang Hasundutan
T.A. : 2020

W AKT U PELAKSANAAN 210 HARI KALENDER -> MENJADI MULT I YEAR 523 HARI KALENDER T AMBAHAN W AKT U 60 HARI KALENDER
MINGGU KE-

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83
BOBOT BOBOT
NO. URAIAN PEKERJAAN SESUAI SESUAI 9 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 KET
KONT RAK ADD
25-Feb-20 5-Mar-20 12-Mar-20 19-Mar-20 26-Mar-20 2-Apr-20 9-Apr-20 16-Apr-20 23-Apr-20 30-Apr-20 7-May-20 14-May-20 21-May-20 28-May-20 4-Jun-20 11-Jun-20 18-Jun-20 25-Jun-20 2-Jul-20 9-Jul-20 16-Jul-20 23-Jul-20 30-Jul-20 6-Aug-20 13-Aug-20 20-Aug-20 27-Aug-20 3-Sep-20 10-Sep-20 17-Sep-20 24-Sep-20 1-Oct-20 8-Oct-20 15-Oct-20 22-Oct-20 29-Oct-20 5-Nov-20 12-Nov-20 19-Nov-20 26-Nov-20 3-Dec-20 10-Dec-20 17-Dec-20 24-Dec-20 31-Dec-20 7-Jan-21 14-Jan-21 21-Jan-21 28-Jan-21 4-Feb-21 11-Feb-21 18-Feb-21 25-Feb-21 4-Mar-21 11-Mar-21 18-Mar-21 25-Mar-21 1-Apr-21 8-Apr-21 15-Apr-21 22-Apr-21 29-Apr-21 6-May-21 13-May-21 20-May-21 27-May-21 3-Jun-21 10-Jun-21 17-Jun-21 24-Jun-21 1-Jul-21 8-Jul-21 15-Jul-21 22-Jul-21 29-Jul-21 5-Aug-21 12-Aug-21 19-Aug-21 26-Aug-21 2-Sep-21 9-Sep-21 16-Sep-21 23-Sep-21

S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D

4-Mar-20 11-Mar-20 18-Mar-20 25-Mar-20 1-Apr-20 8-Apr-20 15-Apr-20 22-Apr-20 29-Apr-20 6-May-20 13-May-20 20-May-20 27-May-20 3-Jun-20 10-Jun-20 17-Jun-20 24-Jun-20 1-Jul-20 8-Jul-20 15-Jul-20 22-Jul-20 29-Jul-20 5-Aug-20 12-Aug-20 19-Aug-20 26-Aug-20 2-Sep-20 9-Sep-20 16-Sep-20 23-Sep-20 30-Sep-20 7-Oct-20 14-Oct-20 21-Oct-20 28-Oct-20 4-Nov-20 11-Nov-20 18-Nov-20 25-Nov-20 2-Dec-20 9-Dec-20 16-Dec-20 23-Dec-20 30-Dec-20 6-Jan-21 13-Jan-21 20-Jan-21 27-Jan-21 3-Feb-21 10-Feb-21 17-Feb-21 24-Feb-21 3-Mar-21 10-Mar-21 17-Mar-21 24-Mar-21 31-Mar-21 7-Apr-21 14-Apr-21 21-Apr-21 28-Apr-21 5-May-21 12-May-21 19-May-21 26-May-21 2-Jun-21 9-Jun-21 16-Jun-21 23-Jun-21 30-Jun-21 7-Jul-21 14-Jul-21 21-Jul-21 28-Jul-21 4-Aug-21 11-Aug-21 18-Aug-21 25-Aug-21 1-Sep-21 8-Sep-21 15-Sep-21 22-Sep-21 29-Sep-21

RENCANA
KONTRAK MYC
I. PEKERJAAN PERSIAPAN

I.A PEKERJAAN PERSIAPAN 0.809 0.818 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011

I.A' PEKERJAAN PERSIAPAN NON STANDARD 1.405 0.108 0.108 0.108 0.108 0.108 0.108 0.108 0.108 0.108 0.108 0.108 0.108 0.108

I.B. PEKERJAAN RK3K KONSTRUKSI 0.531 0.537 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007

RENCANA AWAL
II PEKERJAAN ST RUKT UR

II.A PEKERJAAN ST RUKT UR ST ANDART

A.1 Pekerjaan Struktur Lantai Dasar elv. -0.05 m 7.012 7.088 0.473 0.473 0.473 0.473 0.473 0.473 0.473 0.473 0.473 0.473 0.473 0.473 0.473 0.473 0.473

A.2 Pekerjaan Struktur Lantai 2 elv. +3.55 m 8.643 8.737 0.546 0.546 0.546 0.546 0.546 0.546 0.546 0.546 0.546 0.546 0.546 0.546 0.546 0.546 0.546 0.546

A.3 Pekerjaan Struktur Lantai 3 elv. +6.95 m 6.665 6.925 0.462 0.462 0.462 0.462 0.462 0.462 0.462 0.462 0.462 0.462 0.462 0.462 0.462 0.462 0.462

A.4 Pekerjaan Struktur Atap elv. +10.35 m 1.929 1.968 0.984 0.984
RENCANA ADD 1 DAN 2
PEKERJAAN LAND CLEARING DAN PENYIAPAN LEGALITAS LAHAN YANG DIPERUNTUKKAN YANG DI HANDLE LANGSUNG OLEH PEMERINTAH KABUPATEN HUMBANG HASUNDUTAN

A.5 Pekerjaan RingBalk elv. +11.450 m 3.680 3.741 1.871 1.871

II.B PEKERJAAN ST RUKT UR NON ST ANDART

B.1 PEKERJAAN STRUKTUR BAWAH (SUB STRUCTURE) 13.561 12.269 2.045 2.045 2.045 2.045 2.045 2.045
REALISASI ADD 1 DAN 2
HIMBAUAN DARI PEMERINTAH UNTUK PEMBATASAN SOSIAL SKALA BESAR (PSBB) DALAM PENCEGAHAN PENYEBARAN COVID-19

B.2 PEKERJAAN STRUKTUR GWT , RUANG POMPA DAN PONDASI STP - -

B.2.1 PEKERJAAN STRUKTUR GWT 1.697 0.948 0.316 0.316 0.316

B.2.2 PEKERJAAN STRUKTUR RUANG POMPA 0.675 0.454 0.151 0.151 0.151

B.2.3 PEKERJAAN STRUKTUR PONDASI STP 0.061 0.062 0.021 0.021 0.021

III. PEKERJAAN ARSIT EKT UR

III.A PEKERJAAN ARSIT EKT UR ST ANDAR


RENCANA SCM
I PEKERJAAN LANTAI SATU 12.071 12.183 0.102 0.102 0.102 0.102 0.102 0.102 0.102 0.122 0.122 0.381 0.381 0.381 0.381 0.381 0.381 0.381 0.381 0.812 0.937 0.812 0.937 0.937 0.937 0.937 0.937 0.936

II PEKERJAAN LANTAI DUA 12.214 12.297 0.102 0.102 0.102 0.102 0.102 0.102 0.102 0.123 0.123 0.351 0.351 0.351 0.351 0.351 0.351 0.351 0.351 0.946 0.946 0.946 0.946 0.946 0.946 0.946 0.946 0.956

III PEKERJAAN LANTAI TIGA 12.401 12.487 0.104 0.104 0.104 0.104 0.104 0.104 0.104 0.125 0.125 0.499 0.499 0.499 0.499 0.499 0.499 0.499 0.499 0.735 0.735 0.735 0.735 0.961 0.961 0.961 0.961 0.733

IV PEKERJAAN LANTAI DAK DAN ATAP 2.884 2.915 0.146 0.194 0.194 0.729 0.729 0.923

III.B PEKERJAAN ARSIT EKT UR NON ST ANDART

III.B.1 PEK. KELILING BAGIAN LUAR BANGUNAN 1.296 1.310 0.218 0.218 0.218 0.218 0.218 0.218
REALISASI
III.B.2 PEKERJAAN DRAINASE KELILING BAGIAN LUAR BANG. 0.640 0.647 SEBELUM ADD 0.108 0.108 0.108 0.108 0.108 0.108

III.B.3 PEKERJAAN GROUND TANK DAN R. POMPA DI LUAR BANGUNAN 0.482 0.375 0.062 0.062 0.062 0.062 0.062 0.062

III.B.4 PEKERJAAN LAIN-LAIN 0.066 0.067 0.017 0.017 0.017 0.017

IV. PEKERJAAN MEKANIKAL DAN ELEKT RIKAL

A. PEKERJAAN MEKANIKAL DAN ELEKT RIKAL ST ANDART

A.1 LANTAI 1 2.142 2.203 0.044 0.044 0.044 0.044 0.044 0.044 0.110 0.110 0.110 0.110 0.110 0.110 0.110 0.110 0.110 0.110 0.110 0.110 0.088 0.088 0.088 0.088 0.088 0.088 0.088

A.2 LANTAI 2 2.107 2.177 0.044 0.044 0.044 0.044 0.044 0.044 0.109 0.109 0.109 0.109 0.109 0.109 0.109 0.109 0.109 0.109 0.109 0.109 0.087 0.087 0.087 0.087 0.087 0.087 0.087

A.3 LANTAI 3 2.107 2.177 0.044 0.044 0.044 0.044 0.044 0.044 0.109 0.109 0.109 0.109 0.109 0.109 0.109 0.109 0.109 0.109 0.109 0.109 0.087 0.087 0.087 0.087 0.087 0.087 0.087

A.4 LANTAI ATAP 0.067 0.068 0.017 0.017 0.017 0.017

A.5 PEKERJAAN UTILITAS 1.040 0.991 0.099 0.099 0.099 0.099 0.099 0.099 0.099 0.099 0.099 0.099

A.6 PEKERJAAN SISTEM PENTANAHAN 0.109 0.110 0.022 0.022 0.022 0.022 0.022

A.7 PEKERJAAN PENANGKAL PETIR 0.226 0.228 0.057 0.057 0.057 0.057

B. PEKERJAAN MEKANIKAL DAN ELEKT RIKAL NON ST ANDART

B.1 PEKERJAAN PEMADAM KEBAKARAN 0.032 0.032 0.001 0.001 0.001 0.001 0.001 0.001 0.002 0.002 0.002 0.002 0.004 0.004 0.004 0.004 0.003

B.2 PEKERJAAN VENTILASI UDARA 0.416 0.420 0.014 0.014 0.014 0.014 0.014 0.014 0.026 0.026 0.026 0.026 0.026 0.026 0.047 0.047 0.047 0.039

B.3 PEKERJAAN INSTALASI ELEKTRONIK 0.596 0.603 0.020 0.020 0.020 0.020 0.020 0.020 0.040 0.040 0.040 0.040 0.067 0.067 0.067 0.067 0.054

B.4 PEKERJAAN SARANA DAN PRASARANA LINGKUNGAN (LUAR BANGUNAN) 3.841 3.758 0.626 0.626 0.626 0.626 0.626 0.626

RENCANA AW AL KONT RAK SY : 100.000 100.000 0.175 0.759 2.759 2.759 2.479 2.479 2.979 3.454 3.509 3.809 3.913 3.993 3.900 3.904 3.904 3.896 3.928 3.919 3.961 3.895 3.928 3.958 3.956 3.878 3.795 3.819 3.854 3.754 3.737 0.947

KOMULAT IF RENCANA AW AL KONT RAK SY : 0.175 0.934 3.693 6.452 8.931 11.411 14.390 17.844 21.353 25.162 29.074 33.067 36.967 40.871 44.775 48.671 52.599 56.518 60.478 64.373 68.301 72.259 76.215 80.093 83.888 87.707 91.561 95.316 99.052 100.000
- -

RENCANA PERUBAHAN KONT RAK SY : - - - - - - 2.318 2.318 2.487 3.298 4.739 4.739 4.788 4.788 4.599 4.651 4.902 4.781 4.405 4.600 4.340 4.330 4.352 4.369 4.461 5.975 5.775 5.187 3.798

KOMULAT IF RENCANA PERUBAHAN KONT RAK SY : - - - - - - 2.318 4.637 7.124 10.422 15.160 19.899 24.687 29.476 34.074 38.725 43.627 48.408 52.813 57.413 61.753 66.083 70.435 74.804 79.265 85.239 91.014 96.202 100.000
- -

RENCANA PERUBAHAN ADD MY : - - - - - - - 2.280 2.280 2.280 2.280 2.280 2.280 1.370 1.370 1.370 0.559 0.559 0.559 1.176 1.176 1.176 1.176 1.176 1.689 1.689 1.150 1.150 1.150 1.150 1.150 1.150 1.150 0.532 0.532 0.532 1.497 2.824 1.860 0.020 0.020 0.020 0.020 0.020 0.020 1.344 0.623 1.341 1.341 2.066 2.066 2.172 2.172 2.172 2.172 2.172 2.172 2.172 2.214 2.214 2.246 2.350 2.350 2.350 2.350 1.746 2.467 2.392 2.392 1.002 1.985 1.154 1.132 0.980 0.020

KOMULAT IF RENCANA PERUBAHAN ADD MY : - - - - - - - 2.280 4.560 6.840 9.119 11.399 13.679 15.049 16.419 17.789 18.348 18.907 19.466 20.643 21.819 22.996 24.172 25.349 27.038 28.727 29.877 31.027 32.176 33.326 34.476 35.626 36.775 37.308 37.840 38.372 39.869 42.694 44.553 44.573 44.593 44.613 44.632 44.652 44.672 46.016 46.639 47.980 49.321 51.388 53.454 55.626 57.798 59.970 62.141 64.313 66.485 68.657 70.871 73.084 75.330 77.680 80.029 82.379 84.729 86.475 88.942 91.334 93.727 94.729 96.714 97.868 99.000 99.980 100.000
- -

RENCANA PERUBAHAN ADD NILAI : - - - - - - - 2.065 2.065 2.065 2.173 2.173 2.173 1.089 1.089 1.089 0.601 0.601 0.601 0.601 0.601 0.601 1.147 1.039 1.039 1.039 1.039 1.039 1.028 1.028 1.028 1.028 1.028 1.028 1.028 1.028 1.028 1.028 0.482 0.482 0.482 1.466 3.336 1.891 0.020 1.358 0.739 1.354 1.463 2.087 2.196 2.196 2.196 2.196 2.196 2.196 2.196 2.196 2.238 2.238 2.370 2.370 2.370 2.370 2.370 1.761 2.418 2.386 2.277 0.981 1.718 1.113 1.113 0.960 0.020

KOMULAT IF RENCANA PERUBAHAN ADD NILAI : - - - - - - - 2.065 4.129 6.194 8.367 10.540 12.713 13.801 14.890 15.979 16.579 17.180 17.780 18.381 18.981 19.582 20.729 21.767 22.806 23.844 24.883 25.921 26.949 27.976 29.004 30.032 31.059 32.087 33.115 34.142 35.170 36.197 36.679 37.161 37.642 39.108 42.444 44.335 44.355 45.713 46.452 47.806 49.269 51.356 53.552 55.748 57.944 60.141 62.337 64.533 66.729 68.925 71.164 73.402 75.772 78.142 80.512 82.882 85.252 87.012 89.431 91.817 94.094 95.076 96.794 97.907 99.021 99.980 100.000
- -

RENCANA - SCM : - - - - - - - 2.065 2.065 2.065 2.173 2.173 2.173 1.089 1.089 1.089 0.601 0.601 0.601 0.601 0.601 0.601 0.601 1.039 1.039 1.039 1.039 1.039 0.566 0.566 0.566 0.566 1.028 1.028 1.028 1.028 1.028 1.028 1.028 0.482 0.482 0.482 0.482 0.482 0.482 0.482 1.466 1.004 0.020 0.020 0.020 2.001 2.690 1.405 1.514 2.138 2.138 2.138 2.138 2.138 2.180 2.180 2.312 2.312 2.312 2.312 2.312 2.312 2.351 3.662 4.602 4.549 4.346 2.432 0.798

KOMULAT IF- SCM : - - - - - - - 2.065 4.129 6.194 8.367 10.540 12.713 13.801 14.890 15.979 16.579 17.180 17.780 18.381 18.981 19.582 20.183 21.221 22.260 23.298 24.337 25.375 25.941 26.507 27.073 27.639 28.667 29.694 30.722 31.750 32.777 33.805 34.832 35.314 35.796 36.277 36.759 37.240 37.722 38.203 39.669 40.673 40.693 40.713 40.733 42.734 45.423 46.828 48.342 50.479 52.617 54.755 56.893 59.031 61.211 63.391 65.703 68.014 70.326 72.638 74.949 77.261 79.611 83.273 87.875 92.424 96.770 99.202 100.000
- -

RENCANA PERUBAHAN ADD W AKT U : - - - - - - - 2.063 2.063 2.063 2.171 2.171 2.171 1.087 1.087 1.087 0.598 0.598 0.598 0.598 0.598 0.598 0.598 1.036 1.036 1.036 1.036 1.036 0.564 0.564 0.564 0.564 1.026 1.026 1.026 1.026 1.026 1.026 1.026 0.479 0.479 0.479 0.479 0.479 0.479 0.479 1.463 1.002 0.018 0.018 0.018 1.889 1.889 0.018 0.062 0.207 0.353 0.457 0.457 0.457 0.523 0.588 0.674 0.695 0.974 1.203 1.577 1.591 1.612 1.758 1.807 1.807 2.751 3.560 3.864 3.065 3.392 4.102 4.374 4.380 4.291 3.278 1.707

KOMULAT IF RENCANA PERUBAHAN ADD W AKT U : - - - - - - - 2.063 4.125 6.188 8.359 10.529 12.700 13.787 14.873 15.960 16.558 17.157 17.755 18.354 18.952 19.551 20.149 21.185 22.222 23.258 24.295 25.331 25.895 26.459 27.023 27.587 28.612 29.638 30.663 31.689 32.714 33.740 34.765 35.245 35.724 36.204 36.683 37.163 37.642 38.122 39.585 40.587 40.605 40.623 40.641 42.529 44.418 44.435 44.497 44.704 45.057 45.514 45.971 46.428 46.951 47.540 48.214 48.908 49.883 51.085 52.663 54.254 55.866 57.624 59.431 61.238 63.988 67.548 71.412 74.477 77.869 81.971 86.345 90.724 95.015 98.293 100.000

REALISASI : - - - - 0.131 0.005 - - 1.191 5.455 1.296 3.067 - 0.992 0.825 0.930 1.110 0.389 0.440 1.385 0.707 2.600 0.112 0.922 0.999 1.275 2.101 0.757 1.709 1.448 0.818 1.982 1.321

KOMULAT IF REALISASI : - - - - 0.131 0.136 0.136 0.136 1.327 6.782 8.078 11.146 11.146 12.138 12.963 13.893 15.003 15.393 15.832 17.218 17.924 20.525 20.637 21.559 22.558 23.833 25.934 26.691 28.400 29.848 30.666 32.648 33.969
- -

REALISASI ADD : 33.273 1.736 0.895 0.621 0.625 0.675 0.510 0.270 0.098 0.276 0.134 - 0.325 0.223 0.712 0.795 0.304 0.092 1.175 0.905 0.294 0.381 0.041 0.704 2.296 1.195 1.058 0.350 0.562 0.652 0.202 2.601 4.533 0.986 1.452 1.717 0.873 1.246 1.807 5.456

KOMULAT IF REALISASI ADD : 33.273 35.009 35.903 36.524 37.149 37.825 38.334 38.604 38.702 38.978 39.112 39.112 39.437 39.660 40.372 41.167 41.471 41.563 42.738 43.643 43.937 44.318 44.359 45.063 47.359 48.554 49.612 49.962 50.524 51.176 51.378 53.979 58.512 59.498 60.950 62.667 63.540 64.786 66.593 72.049
- -

DEVIASI : ( 0.175) ( 0.934) ( 3.693) ( 6.452) ( 8.800) ( 11.275) ( 14.254) ( 17.708) ( 20.026) ( 0.342) ( 2.343) ( 4.015) ( 2.534) ( 2.911) ( 3.456) ( 3.896) ( 3.345) ( 3.515) ( 3.634) ( 3.425) ( 3.895) ( 2.471) ( 3.535) ( 3.790) ( 4.480) ( 4.894) ( 3.943) ( 4.335) ( 3.776) ( 3.478) ( 3.810) ( 2.978) ( 2.807) 1.186 1.894 1.761 1.354 0.952 1.146 1.174 0.962 ( 0.406) ( 3.466) ( 5.222) ( 5.242) ( 6.276) ( 6.792) ( 7.434) ( 8.102) ( 9.885) ( 11.989) ( 13.010) ( 14.302) ( 2.891) ( 4.024) ( 6.120) ( 7.554) ( 7.396) ( 8.339) ( 9.419) ( 11.249) ( 12.867) ( 14.527) ( 16.636) ( 16.347) ( 14.126) ( 15.451) ( 16.311) ( 16.944) ( 19.734) 5.355 5.355 8.060

UANG
TERMIN 1 TERMIN 2 TERMIN 3 TERMIN 4 TERMIN 5
MUKA

66.593% 72.049%

######
0.03%

Dolok Sanggul ; …........................


Diperiksa Oleh : Diperiksa Oleh : Diajukan Oleh :
KONSULTAN / MK KONSULTAN / MK PENYEDIA JASA
PT. MITRAPLAN KONS PT. MITRAPLAN KONS PT. ROBINSON MAJU BERSAMA

Sufrial Hendri, ST, MT Sufrial Hendri, ST, MT Sahabat Alfrido Fransisco, ST


Team Leader Team Leader Project Manager