Professional Documents
Culture Documents
SPE 93866 Deepwater Subsea Well Intervention - The Future Solution
SPE 93866 Deepwater Subsea Well Intervention - The Future Solution
production. The wellbore is isolated from the existing vessels would result in significantly decreased
environment using one or two plugs set (usually with costs due to lower vessel day-rates. The trade-off
wireline) in the tubing hanger and/or in the tree cap. The against these savings is the limited heavy-duty
horizontal tree system is more compact than the dual functionality of such an intervention system.
bore version, allows for larger completion sizes (the
completion is run through the drilling BOP and hung-off Developing the Technology – JIP Scope
in the tree), and does not require dedicated running or
intervention equipment. Since the drilling BOP can be The JIP was set up in early 2004 to investigate the
installed on top of the horizontal X-mas tree, all feasibility of developing a lightweight (wireline) subsea
completion installation and intervention work can be well intervention system, suitable for deployment from a
conducted using this BOP as the primary pressure wide range of (low cost) surface vessels, of the type
control and containment system. shown in Figure 1. The intention is that the combined
intervention and deployment system will provide a new
Subsea Intervention Economics standard in the provision of cost-effective well monitoring
and remedial services. The system will also serve as a
The economics of subsea development have been, and platform for the deployment of new, high value well
remain, compelling. Lower capital costs and shorter intervention services.
development times to first oil have provided significant
benefits to the net present value (NPV) of deepwater The development programme has been organised into a
and small to medium sized offshore reserves. In series of projects, each forming part of the phased
addition, larger bore completions made possible by development / engineering of the system. These are
recent advances in subsea tree technology have being run as individual projects, with Expro managing
enabled operators to optimise the location, numbers and and engineering each phase. The basis of the overall
configuration of development wells drilled in these JIP was an initial concept developed by Expro based
reservoirs. Operating expenditure for such wells, if around the perceived technical requirements for a
intervention operations are required, is very high and deepwater intervention system.
risk-prone (both technically and commercially).
Operators, wisely, attempt to limit the number of Phase I (Project 1)
interventions in subsea wells to an absolute minimum. Technical feasibility
Initial commercial viability
However, current evidence demonstrates that subsea Scope and operational envelope
developments will be abandoned with significantly lower Operator functionality
recovery factors than those offshore assets developed Functional and technical specification
using fixed structures with surface or 'dry' trees. This Initial HAZOP/ HAZID and reliability analysis
may partly be due to the less attractive properties of the Concept Refinement
reservoirs and fluids developed using subsea Intellectual property aspects
technology, as well as to additional back pressures
introduced into the system by the subsea architecture. Phase II (Project 2)
There is a strong argument that there is an additional Detail design and engineering
reduction in recovery factors caused by the inability to Detail HAZOP/HAZID and reliability analysis
intervene in the wells on a regular basis, as one can Subcontractor identification and scope
when dry tree developments are undertaken.
Intervention covers a wide range of well operations from Phase III (Project 3.0)
tubing recovery and renewal requiring a rig, right through Construction and testing
to simple mechanical reconfigurations of the well using
slick wireline (plugs, sliding sleeves etc.). Phase III+ (Project 3.1)
Operations
Most well operations involve the use of wireline of some
type, or possibly the use of coiled tubing. Such Phase I (Project 1) was undertaken with three major
operations include well surveying (pressure/temperature, operators of subsea assets. At time of writing, this
production logging, thermal neutron) and mechanical phase is now complete and a detailed workscope has
well reconfigurations or repairs (plugs, sliding side doors, been identified, together with costings and timings, to be
reperforating, zone isolations) performed on either slick- undertaken during Phase II. It is likely that Phase I
or electric-line. partners will participate in the next phase, but there is
also the possibility of other operators joining at this
The key issue in the development of such intervention stage. It is expected that the second phase will take
technology is to remove the necessity to use a high cost approximately 14 months to complete, so consequently it
semi-submersible or drillship type rig, and to remove the is likely that the first system will be available in the first
need to new-build a boat type vessel to deploy the half of 2007.
technology. The ability to use a wider spectrum of
SPE 93866 3
The results of the first phase have been extremely minimises geometry problems that may occur during
encouraging and the JIP participants are confident that spooling and keeps the system’s centre of gravity
the proposed system will deliver a significant positive close to the centre-line of the well. The well tractor
change to current subsea well intervention practices. is attached to the wireline and is used to push (or
With this in mind, let us now look in more detail at the pull) the wireline tools in the more highly deviated
system being proposed. sections of the well. On the lower end of the tractor
is a quick-connect – release system for connecting
System Description to the wireline tools held in the tool carrier package.
The subsea intervention system has been designed to 4. Subsea Power Pack
meet the intervention requirements of the large number
of existing (or legacy) wells, as well as meeting the This is a stand-alone power pack to provide
intervention needs of the operator community. Figure 2 hydraulic and electrical power to the intervention
shows the intervention system installed on a horizontal system via a single electrical umbilical from surface.
subsea X-mas tree. In general the system can be
divided into 4 sub-systems or packages:– The intervention system is targeted at applications in
water depths of up to 10,000 feet (3,000 metres), with a
1. Well Control Package pressure rating of 10,000 psi, which will enable
interventions on large bore subsea wells. The combined
This package provides the ability to close the well so stack of packages will be in the region of 45 feet high
that the upper package can be removed from the and approximately 60 tonnes in weight, so will be both
well in the event of a system malfunction or compact and relatively lightweight. The whole system
emergency. It provides two testable barriers, and can be deployed from readily available platform supply
2
can (through the use of the appropriate cross–over) or anchor handling vessels with more than 500m of
be used on any make or type of X-mas tree. The top deck space and dynamically positioned (DP) class 2
of this package has a standard connector allowing a capability, using a heave compensated A-frame (as
BOP, lower marine riser package or high pressure shown in Figure 3) or a high capacity heave
riser to be connected to the X-mas tree from a compensated crane. Such vessels are available in all
surface vessel. major offshore producing regions of the world. In
addition, a work-class ROV is required for system hook-
2. Tool Carrier Package up.
The system will have the potential to deliver a full The Commercial Case
suite of well intervention tools in one run, without
recovery to surface of the intervention package Subsea wells represent a considerable investment, both
during the operations. The tool carrier package in terms of the wells themselves and the infrastructure
contains up to eight wireline tools for use during the associated with each well. The ability to manage these
well intervention. The tools are held around the wells, and so optimise the economics and recoverable
periphery of the carrier on hydraulically activated reserves, is a fundamental requirement of any asset
clamps. When a tool is selected, the hydraulic ram development plan. New technologies are under
presents the tool onto the well centre-line where it is development that could assist this, the so-called 'smart'
made up onto the running tool / well conveyance completion technology that can be activated remotely
tractor in the above package. The hydraulic clamp is from surface. This technology is commercially unproven,
then released and the tool can be run into the well. and does not address the problem of the current,
The different wireline tools can be multiply installed subsea wells. The management of these
interchanged onto the downhole conveyancing tool subsea wells provides a real and immediate challenge to
during a single run of the intervention system. The the industry - a challenge which requires a realignment
package will include well maintenance and of thinking on subsea well intervention.
reconfiguration tools plus well / reservoir
measurement and monitoring tools. The projected financial benefits include:-
Conclusion
Fig 1. Monohull Vessels enabling Subsea Well Fig 3. A-frame launched Subsea Well Intervention
Interventions System
Tool storage
package
Work-class ROV
Hydraulic/electric
jumper to upper
k
Well control
package
Hydraulic jumper to
lower package