Doc. No.

Rev:
Weekly Progress Updates
(Mechanical) Date:

Page No.:

CLIENT Hi-Tech Lubricants Limited

PROJECT Nowshera Oil Depot


Report #
EPCC CONTRACTOR Haris & Co.

PROJECT #
SITE CONSTRUCTION MECHANICAL:- Weekly Progress Report/Next Plan
Currents Week's Progress (01-08-19 to 04-08-19) Next Week Plan (05-08-19 to 09-08-19)

FWT 1st and 2nd shell course LS welding (out side)


complete. FWT roof structure fabrication in progress. Erection & fitup of 4th shell. Welding of 3rd & 4th
FWT FWT CS-1 outside welding complete. FWT roof structure FWT shell course.
fabrication in progress. FWT 1st shell course LS back Back pass welding will be completed all courses.
pass welding complete.

Painting of underside of bottom plates.


HSD bottom plates fabrication complete. HSD bottom
HSD HSD Sand blasting and painting of upper side of bottom
plates sandblasting & painting internal side complete.
plates.

EXTRA/ ADDITIONAL WORKS DONE IN PREVIOUS WEEK

BOTTLENECKS:

COMMENTS:

Haris & Co. Hi-Tech Lubricants


Date
Name Name

Signature Signature
Doc. No.:

Rev:
Weekly Progress Updates
(Mechanical) Date:

Page No.:

CLIENT Hi-Tech Lubricants Limited

PROJECT Nowshera Oil Depot


Report #
EPCC CONTRACTOR Haris & Co.

PROJECT #
SITE CONSTRUCTION MECHANICAL:- Weekly Progress Report/Next Plan
Currents Week's Progress (05-08-19 to 09-08-19) Next Week Plan

Erection & fitup of 4th shell. Welding of 3rd & 4th


FWT roof structure fabrication inprogress. Curb angle
FWT FWT shell course.
rolling inprogress.
Back pass welding will be completed all courses.

HSD bottom plates sandblasting & painting upper side


HSD HSD Sand blasting and painting of upper side of bottom
inprogress.
plates.

No's 03 sumps sandblasting painting (Internal/External)


sides complete.

EXTRA/ ADDITIONAL WORKS DONE IN PREVIOUS WEEK

BOTTLENECKS:

Due to court order work is getting delayed.

COMMENTS:
Partial work is being done in workshop area.

Haris & Co. Hi-Tech Lubricants


Date
Name Name

Signature Signature
Doc. No.:

Rev:
Weekly Progress Updates
(Mechanical) Date:

Page No.:

CLIENT Hi-Tech Lubricants Limited

PROJECT Nowshera Oil Depot


Report #
EPCC CONTRACTOR Haris & Co.

PROJECT #
SITE CONSTRUCTION MECHANICAL:- Weekly Progress Report/Next Plan
Currents Week's Progress (14-10-19 to 20-10-19) Next Week Plan
1 1
FWT FWT
2 2
1 Shell#06 erection complete, fitup inprogress. 1 Shell#07 erection
2 Wind girder fabrication / rolling complete. 2 Shell #05 LS backpass
3 CS-3 backpass welding complete. 3 CS-4 backpass
HSD 4 Shell#05 LS outside welding complete. HSD 4
5 CS-4 outside welding complete. 5
6 6
7 7
1 Shell#03 LS outside welding complete. 1 Shell#06 erection
2 CS-2 outside welding complete. 2 Shell#04 LS outside welding
3 Shell#03 LS backpass complete. 3
PMG PMG
4 CS-2 backpass welding complete. 4
5 Curb angle fabrication / rolling complete. 5
6 Shell#05 erection complete, fitup in progress. 6
1 1
Gantry Gantry
2 2
EXTRA/ ADDITIONAL WORKS DONE IN PREVIOUS WEEK

BOTTLENECKS:

COMMENTS:

Haris & Co. Hi-Tech Lubricants


Date
Name Name
Muhammad Naeem Sarwar Muhammad Waris

Signature Signature