SCOPE OF WORK : Same scope of work is done for both roads. First, they will be
done sub base construction for the roads and then implement
ABC layer. Then they will be applied prime coat to the road and
after applying track coat, finally apply asphalt layer. There will
be no sub base construction for existing macadam road section.
They will apply 10 Tons vibration roller for main road
construction such as sub-base, ABC layer and 1 Tons for the
shoulders. After the applying prime coat, finally, they construct
the road with asphalt layering. They did not decide to construct
culverts in this project for now. At this stage, they decided to
construct earth drains for this roads.
The proposer decided to carry out the work during day time.
They will use construction machines and equipment such as,
Excavator, Motor grader, Bulldozer, Backhoe Loader, Dump
Truck, Water Bowser, Rammer, Poker Vibrator, etc.
RISK TO PRINCIPAL PROPERTY : There are no predictable risk for the principal properties
RISK TO THIRD PARTY : In this road, there can be observed paddy fields, houses,
archaeology reservation forest and bare lands etc. Third party
structures section of the road is very long while other types of
surrounding environment having small length of sections. There
can be observed, block walls and sign boards of the road. Third
party houses are made with concrete structure and some of those
can be observed withing 30 ft distance. They will use 10 Tons
vibration roller for the compaction and 1 tons vibration will
implement for construction of shoulders. Therefore, there is a
high third-party risk due to vibration.
PROJECT PROGRESS : There can be observed the embankment and shouldering stages
are completing at the time of inspection. Some of the sections are
still completing at this stage. Therefore, 15% of the project can
be noted as project progress at the time of inspection.
Figure 1: Satellite view of the road
SCOPE OF WORK : Same scope of work is done for both roads. First, they will be
done sub base construction for the roads and then implement
ABC layer. Then they will be applied prime coat to the road and
after applying track coat, finally apply asphalt layer. There will
be no scope of work for the construction of interlock section
section.
They will apply 10 Tons vibration roller for main road
construction such as sub-base, ABC layer and 1 Tons for the
shoulders. After the applying prime coat, finally, they construct
the road with asphalt layering. There are 9 nos. culverts in this
project and 2 are new constructions while others are repairing the
existing damages. At this stage, they decided to construct earth
drains for this roads.
The proposer decided to carry out the work during day time.
They will use construction machines and equipment such as,
Excavator, Motor grader, Bulldozer, Backhoe Loader, Dump
Truck, Water Bowser, Rammer, Poker Vibrator, etc.
RISK TO PRINCIPAL PROPERTY : There are no predictable risk for the principal properties
RISK TO THIRD PARTY : In this road, there can be observed paddy fields, houses and
bare lands etc. Third party structures section of the road is very
long while other types of surrounding environment having small
length of sections. There can be observed, block walls and sign
boards of the road. Third party houses are made with concrete
structure and some of those can be observed withing 30 ft
distance. They will use 10 Tons vibration roller for the
compaction and 1 tons vibration will implement for construction
of shoulders. Therefore, there is a high third-party risk due to
vibration.
PROJECT PROGRESS : There can be observed the embankment and shouldering stages
are completing at the time of inspection. Some of the sections are
still completing at this stage. Therefore, 15% of the project can
be noted as project progress at the time of inspection.
Distance to third party properties from trench of excavation must be twice depth of
excavation. All foreseen damages should be excluded from the policy.
Excess of Rs.150,000.00 Should be added to for third party property damages during
construction.
According to the conferred person, they did not conduct a crack survey at the sites. It is
advisable to conduct a survey/pre-crack survey for third party properties around the
construction site
Standard traffic control system should be carried out and bi-road should be arranged to for
the third parties to mitigate the interruption due to construction.
According to the conferred person, they occupy the site for 24 hrs. throughout the day.
Excavation and construction areas should be barricaded with relevant sign board and other
protection method.
Should collect and refer project area existing communication cables as-build drawings,
Existing water lines as-build drawings and other underground utility as-build drawing before
excavation by the contractor.
It is advisable to take necessary safety precautions in order to protect the construction
materials and equipment.
Impose higher policy excess towards the flood peril.
Collect a Detailed inventory of the machinery and the equipment covered.
Approved BOQ is to be obtained.
Akila Wickramanayake
Risk Management Department
18th July 2021