Professional Documents
Culture Documents
Iet-Gtd 2015 0054
Iet-Gtd 2015 0054
Iet-Gtd 2015 0054
Research Article
Abstract: In this study, a new reactive power loss index (RPLI) is proposed for identification of weak buses in the system.
This index is further used for determining the optimal locations for placement of reactive compensation devices in the
power system for additional voltage support. The new index is computed from the reactive power support and loss
allocation algorithm using Y-bus method for the system under intact condition and as well as critical/severe network
contingencies cases. Fuzzy logic approach is used to select the important and critical/severe line contingencies from
the contingency list. The inherent characteristics of the reactive power in system operation is properly addressed while
determining the reactive power loss allocation to load buses. The proposed index is tested on sample 10-bus
equivalent system and 72-bus practical equivalent system of Indian southern region power grid. The validation of the
weak buses identification from the proposed index with that from other existing methods in the literature is carried out
to demonstrate the effectiveness of the proposed index. Simulation results show that the identification of weak buses
in the system from the new RPLI is completely non-iterative, thus requires minimal computational efforts as compared
with other existing methods in the literature.
IET Gener. Transm. Distrib., 2015, Vol. 9, Iss. 14, pp. 1826–1834
1826 & The Institution of Engineering and Technology 2015
it is necessary to trace the path of power supplied from the source bus Now these equivalences are added to the corresponding diagonal
to sink bus. Although, it is difficult, but power can be traced based on entries of Y-bus matrix. Then, from (1), one can solve for generator
power flow tracing techniques. Here, the main focus on the reactive voltage VG as a function of load voltage VL. This is given as
power support and loss allocation rather than tracing the reactive
power flow contribution from the sources. The main requirement ′
[V G ] = −[YGG ]−1 [Y GL ][V L ] (5)
for any tracing/allocation method is that before application of the
methodology, the sources and sinks in the system have to be ′
where [YGG ] is the modified sub-matrices of [YGG]. From (5), it is
identified. In case of real power, the source and sink are fixed in
assumed that
the system under consideration irrespective of system operating
point. The generators are the sources and loads are the sinks. ′
B
Whereas in case of reactive power, the sources are indefinite such [YGL ] = −[YGG ]−1 [Y GL ] (6)
as generators, line charging capacitances, synchronous condensers,
switchable and variable capacitors, flexible alternating current Then, (5) can be written as
transmission system devices and so on [17]. They keep changing
continuously depending on the system operating conditions. One B
[V G ] = [YGL ][V L ] (7)
more issue is that unlike active power, the reactive power flow
often involves bidirectional flow, that is, reactive power flows into The voltage contribution to generator bus from each load bus
a branch or out of a branch towards both end nodes. The indirect voltages is expanded as
nature of reactive power produced by the line charging
capacitances is considered separately by suitable steady state NL
model based on the power flow results. Further, the net reactive
B
VGj = YGL j,i ∗ VLi (8)
power support at each generator and load buses are calculated by i=1
taking into consideration the other reactive sources/sinks at the
respective buses with retaining the original generator and load It can be seen from (8) that the original generator voltage at bus j is
buses. These changes are only applicable to determine the RPLI the sum of individual voltage contribution from all load buses.
for identification of weak load buses in the system. The second By substituting (7) into (3), the generator current can be expressed
issue, that is, the reactive power bidirectional flow is inherently as
addressed in the methodology itself.
C
I G = [KGL ][I L ] + [YGL ][V L ] (9)
3 Proposed index for optimal placement of C
where [YGL e
] = [YGG B
][YGL ]
reactive compensation devices To determine the generators share/contribution to meet load
demand and losses at load bus, the vectors [IL] and [VL] should be
Consider a system comprising of n number of total buses with 1, 2… consider in diagonal matrix. Take a conjugate of (9) and
g;g be the number of generator buses and g+1, g+2…n;(n−g) be the pre-multiplying by [VG] the diagonal generator voltage matrix, the
remaining load buses. Under steady state operating condition, for a generators complex power can be expressed as
given system, the network steady state performance equation is
given by
[V G ]G∗G [IG∗ ]G∗L
[I G ] = [Y GG ][V G ] + [Y GL ][V L ] (1) = [Sgen−contrb ]G∗L (10)
∗ C∗
= [V G ]G∗G [KGL ]G∗L [IL∗ ]L∗L + [V G ]G∗G [YGL ]G∗L [VL∗ ]L∗L
[I L ] = [Y LG ][V G ] + [Y LL ][V L ] (2)
The reactive power contribution of all generators w.r.t. load buses
where [IG], [IL] are the complex bus current injection vectors, [VG], can be given as,
[VL] are the complex bus voltage vectors and [YGG], [YGL], [YLG],
[YLL] are the corresponding partitioned matrices of the bus [Qgen−contrb ]G∗L = Im([Sgen−contrb ]G∗L ) (11)
admittance matrix. Equation (1) is rewritten in terms of load bus
currents and generator bus voltages is given by
With further simplification of (11), the reactive power contribution
e from generator j to load bus i is as follows
[I G ] = [KGL ][I L ] + [YGG ][V G ] (3)
NL
e
where [KGL] = [YGL][ZLL], [YGG ] = [Y GG ] − [Y GL ][ZLL ][Y LG ] and Qgen−contrb (j) = Qgen−contrb (ji) (12)
[ZLL] = [YLL]−1 i=1
The main aim is to get the generators contribution to meet
individual load demand and losses in the system. To do so, from From (12), the reactive power loss allocated to each load bus i can be
circuit theory analysis, the generator voltage VG in (3) is being expressed as
replaced as a function of load bus voltages, that is, VG = f (VL). A
possible way to deduce generator voltage as a function of load NG
voltages, is to apply superposition theorem. However, it requires Qloss(i) = Qgen−contrb (ji) − QLi (13)
replacing all generators current injection into its equivalent j=1
admittances in the circuit. Using readily available load flow
results, the equivalent shunt admittance YGj of generator node j where QLi is the net reactive power load demand at bus i.
can be calculated using the following
∗ 3.1 Determining the RPLI for identification of weak
1 −SGj buses in the system
YGj = (4)
VGj VGj
At each load bus, the reactive power loss (Qloss) is determined as
explained in the preceding section. It is well known that the
where (*) means conjugate, SGj be the generator apparent power at reactive power losses in the system not only depend on reactive
node j and VGj be the generator voltage at node j. demand at load buses, but also depend on active power
IET Gener. Transm. Distrib., 2015, Vol. 9, Iss. 14, pp. 1826–1834
& The Institution of Engineering and Technology 2015 1827
flows/demand and the relative location of load buses with respect to
the sources buses in the network [18]. At high loadings, the reactive
power losses can increase significantly with the distance transported.
Consequently, the reactive power loss allocated to respective load
buses also increases [19]. Thus, the reactive power loss allocation
to load buses can act as an indicator to the reactive power
deficient/surplus at a bus. Therefore it can be considered as an
index for optimal placement of reactive compensation devices.
A weighted sum of normalised values of reactive power loss at
each load buses under system intact condition and different severe
contingencies is computed, and termed as ‘reactive power loss
index (RPLI).’ The normalised NCOSI as discussed in [16], is
taken as the relative weightage for different contingencies, as it
reflects relative severity of a particular line outage condition. The
RPLI at bus i can be expressed as
Nc
RPLIi = Qlossni,0 + (Qlossni,k ∗ NCOSIk ) (14)
k=1
Table 1 Load flow result of sample 10-bus system under intact condition with peak load
Bus no Voltage Generation Load Net reactive power (MVAr)
IET Gener. Transm. Distrib., 2015, Vol. 9, Iss. 14, pp. 1826–1834
1828 & The Institution of Engineering and Technology 2015
Table 2 Contribution of generator reactive sources to load buses and reactive loss allocation for 10-bus system under intact condition with peak load
Load bus Net demand, MW, MVAr Generator sources, MVAr Total, MVAr Qloss, MVAr Normalised Qloss
calculated at the generator bus and the total reactive power loss are not provided. Therefore the reactive power loss allocation at
calculated by power flow method, respectively. load buses give the clear indication about the system reactive
As we can see from Table 2, the reactive power loss allocated to power issues, which intern give an indication about the system
load bus 9 is maximum, that is, 90.717 MVAr and that for load bus 6 voltage instability/collapse problem. Thus, the amount of reactive
is minimum, that is, 8.1133 MVAr. To meet the power demand at power loss allocated to load buses can be considered as an
load bus 9, the partial reactive power contribution from the indicator to the reactive power deficit/surplus at the buses and
generators are G1 = 96.862 MVAr, G2 = 51.441 MVAr and hence, further it can be used for identification of weak buses in the
G3 = 68.652 MVAr. The total partial contribution from all system.
generator reactive sources in a system is 216.95 MVAr. The net As reported in the literature [2, 3], system may be voltage unstable
reactive power demand at load bus 9 is 126.24 MVAr and rest of if it includes at least one voltage collapse bus. For this reason,
the power lost in the transmission corridors while power is being identifying the weak buses in the system is very much important.
transferred from source to load because of inductive nature of the The identification of weak buses in the system for additional
transmission lines. In case of load bus 6, which is nearer to two voltage support is not only decided based on the system
generator buses G1 and G2 in comparison with other generator performance under heavy load condition. Under certain severe
bus G3 and get maximum share from these two nearest generator network contingencies the system may result in voltage instability.
sources. To meet the power demand at load bus 6, the partial The main factor causing voltage instability is the reactive power
reactive power contribution from the generators are G1 = 7.3908 reserve facilities are not sufficient/adequate to meet the reactive
MVAr, G2 = 6.1588 MVAr and G3 = −3.2018 MVAr. As reported power demand. The possibility of voltage instability is more in a
in [17], generators are sources for real power but may be sources system under severe network contingencies than in a system under
or sinks for reactive power. The partial reactive power support normal condition. Therefore it is important to consider the reactive
received at bus 6 from generator bus G3 is −3.2018 MVAr, hence power loss allocation to load buses under severe network
it can be interpreted as generator G3 acts as a sink instead of contingencies for identifying the weakest buses in the system.
source for bus 6 for that partial contribution/support. However, the The contingency analysis is carried out in the system and the line
total partial contribution from all the generator reactive source contingency/outage ranking is obtained from the fuzzy logic
buses to load/sink bus 6 is positive. The proposed approach is approach [16]. The overall severity index of each post-contingent
based on superposition theorem applied to linearised system quantities and NCOSI for the particular line outage are determined.
model, the partial contribution represents the impact of a particular The ranking of the outages are carried out based on the values of
generator reactive source to meet the load demand in accordance NCOSI, which reflects the impact/severity of particular line outage
with circuit characteristics. Since this work mainly focuses on in the system. Table 3 shows first five severe contingencies and
reactive power loss allocation to load buses and its application to arrange them in descending order of NCOSI. As we can see from
system voltage stability improvements, the discussion on Table 3, the line connected between bus 2 and 6 is of most severe
individual generator partial reactive power contributions to load contingency. This may lead to voltage instability/collapse, if proper
bus is not in the scope of this paper. However, the individual preventive steps are not incorporated to protect the system.
generator partial reactive power contributions to load bus is the The first five severe contingencies as listed in Table 3 along with
basic building block for allocating the reactive power losses to their respective normalised NCOSI values are considered in the
load buses. The detailed evaluation of reactive power support and identification process of weak buses in the system. The normalised
loss allocation under various system operating conditions, and its RPLI value at each load bus is calculated for the system intact
impact on system reactive power issues by the same authors is condition and five more severe contingencies cases under normal
presented in [19, 21]. From these discussions and case studies and peak load in the system is shown in Table 4, which arrange
[19, 21], it can be inferred that under heavy loading/stressed them in descending order of their severity. It can be seen from
condition, even though generator may have enough reactive power Table 4, the weak load buses identified based on the proposed
that cannot be efficiently used if the reactive power requirement in index under normal and peak loading conditions are in agreement
the network is far away from their location because of requirement with each other.
of reactive power loss in the transmission lines itself. Thus, the The bus with lowest value of RPLI is assumed to be more stable and
remote bus may be in reactive power deficient area, which may the bus with highest value of RPLI is considered to be the weakest bus
lead to voltage instability if proper reactive power compensation in the system. From Table 4, bus 9 is the weakest bus and then
Table 3 Fuzzy logic based line outage/contingency ranking of 10-bus equivalent system [16]
Sl no Outage line Overall severity index (OSI) NCOSI Normalised NCOSI
IET Gener. Transm. Distrib., 2015, Vol. 9, Iss. 14, pp. 1826–1834
& The Institution of Engineering and Technology 2015 1829
Table 4 Proposed RPLI for 10-bus equivalent system under different the power system [3]. Therefore RPLI at the load buses under peak
loading conditions with severe contingencies load condition is considered for identification of weak buses in the
Severity Load Normal load Load Peak load system. Since the system under consideration is small and for both
order bus RPLI bus RPLI load conditions with critical contingencies, the proposed index
identified the same severity order of the weak load buses in the
1 9 5.2781 9 5.2538 system. However, the severity order of weak load buses may differ
2 8 4.0879 8 4.172 in large interconnected system for different loading in the system,
3 4 3.2907 4 2.8588
4 10 2.8361 10 2.8143
which will be discussed in the Section 4.2.
5 5 2.6734 5 2.4187 The results from the proposed index is compared with that from
6 7 2.4944 7 2.415 other existing methods [5, 7] in the literature such as V-Q
7 6 0.54572 6 0.5416 sensitivity based modal analysis [7], CPF method [5], which have
been used for identification of weak buses in the system. The
results of the comparison is shown in Table 5. The V-Q sensitivity
Table 5 Identification of weak buses for 10-bus equivalent system: a modal analysis is based on system Jacobian matrix near the point
comparison of voltage collapse and determining the bus participation factor
(BPF) corresponding to the critical mode (least stable mode
Severity Proposed V-Q sensitivity CPF method [5]
order index modal analysis [7] corresponds to minimum eigenvalue of reduced Jacobian matrix)
of operation are used to determine the best site for placing the
Bus RPLI Bus BPF Bus Voltage reactive compensation devices. The weak buses from the method
(p.u.) [7] are buses 9, 8, 4, 10, 6, 5 and 7 as shown in Table 5. In the
method based on CPF, the real and reactive power at load buses
1 9 5.2538 9 0.3875 9 0.56425 are increased in proportion to their initial base case load levels,
2 8 4.172 8 0.2272 8 0.61605
3 4 2.8588 4 0.1273 4 0.6585 step by step up to the critical loading point with the help of
4 10 2.8143 10 0.0926 10 0.72015 continuation parameter (loading parameter). The generator output
5 5 2.4187 6 0.0772 5 0.72078 is also increased in proportion to their initial base case generations
6 7 2.415 5 0.0723 6 0.77201 to meet the increased load. The weak buses from the method [5]
7 6 0.5416 7 0.0159 7 0.81755
are buses 9, 8, 4, 10, 5, 6 and 7 as shown in Table 5.
From the results of the comparison, we can see that bus 9 is the
followed by bus 8, bus 4, bus 10, bus 5, bus 7 and bus 6 for both load weakest bus among the other load buses from the proposed index
conditions. The occurrence of severe contingencies under heavy load and as well as from other existing methods [5, 7]. The remaining
condition is the main cause for voltage instability/collapse problem in buses 9, 8, 4 and 10 are in the same severity order produced by
Table 6 Optimal settings of the reactive compensation devices and system performance parameters of 10-bus equivalent system under different
operating points
Case 1: No Comp. – – –
Case 2: Comp. at Bus 9 1.06 0.84 0.78
Case 1: No compensation
IET Gener. Transm. Distrib., 2015, Vol. 9, Iss. 14, pp. 1826–1834
1830 & The Institution of Engineering and Technology 2015
which is not the main scope of this paper. However, for system
performance studies/analysis, the short-term reactive power
procurement/optimal reactive power dispatch (ORPD) analysis is
carried out. As reported in the literature [22], the ORPD model
may consider different objective functions with different
constraints set depending on the system operator goal/objectives in
the system, which are discussed detail in [22]. However, for our
studies, minimising the sum of the squares of the voltage
deviations from desired voltages at all load buses, that is,
n d a 2
j=g+1 (Vj − Vj ) is considered as an objective function subject
to various system constraints. Where Vjd and Vja are the desired
and actual voltage at load bus j, respectively. Many algorithms can
be used to solve the optimization based ORPD model [22]. In this
paper, ORPD model is solved by linear programming technique
and the detailed mathematical formulation of the linear
programming for the specified objective function is discussed in [23].
Table 7 Fuzzy logic based line outage/contingency ranking of SR 72-bus system [16]
Sl no Outage line OSI NCOSI Normalised NCOSI
IET Gener. Transm. Distrib., 2015, Vol. 9, Iss. 14, pp. 1826–1834
& The Institution of Engineering and Technology 2015 1831
Table 8 Proposed RPLI for SR 72-bus equivalent system under different of four south Indian states. The system is considered on a 100
loading conditions with severe contingencies MVA base. The system data are taken from [20]. The system
Severity Load Zone Normal Load Zone Peak load comprising of 15 generators, which come under five generating
order bus load RPLI bus RPLI utilities namely, Karnataka generating companies (K-Genco),
Andhra Pradesh generating companies (AP-Genco), Tamil Nadu
1 38 3 20.5470 38 3 20.1250 generating companies (TN-Genco), National Thermal Power
2 53 3 8.1690 53 3 7.5836 Corporation (NTPC) and Nuclear Power Corporation (NPC) and
3 41 3 8.0509 41 3 7.1315
4 36 1 6.6928 36 1 6.7477
85 transmission lines including the transformers, which are of
5 35 1 6.4067 35 1 6.2390 400 kV and 200 kV lines in Karnataka, Andhra Pradesh and Tamil
6 40 3 5.7935 49 3 5.2699 Nadu. The real and reactive loads are connected at 38 locations.
7 31 1 5.7095 40 3 5.2035 Shunt reactors are connected at few buses for transient over
8 65 3 5.6385 31 1 4.9299
9 49 3 5.5742 65 3 4.3524
voltage protection. The system has an initial base case load of
10 39 3 5.0000 39 3 4.3428 7494 MW and 3756 MVAr.
11 37 3 3.8431 37 3 3.4203 Similar to the sample 10-bus equivalent system, first the
12 43 3 3.5370 43 3 2.8228 contingency analysis on the system is carried out from the fuzzy
13 54 1 2.4287 19 2 2.3788
14 19 2 2.2749 54 1 2.2585
logic approach [16] to find the severe network contingencies.
15 68 3 1.6268 33 1 1.4907 Table 7 shows first 20 severe contingencies, and their respective
overall severity index of each post contingent quantities and
NCOSI. These contingencies are arranged them in descending
order of their severity. From this table, we can see that the line
4.2 Practical 72-bus system of Indian southern region connected between bus 44 and 57 is of most severe contingency
power grid followed by the outage of line connected between bus 67 and 64.
These severe contingencies and their respective normalised NCOSI
A 72-bus, 400 kV/220 kV voltage level system of Indian southern values are considered in the identification of weak buses in the
region power grid is considered to demonstrate the effectiveness of system.
the proposed index. The geographical map of Indian southern As discussed in the Section 4.1, from the proposed approach, the
region power grid with zone-wise representation is shown in normalised RPLI value at each load bus is calculated for the system
Fig. 2. The southern region power grid covers electrical network intact condition and 20 more severe contingencies cases. Results
Table 9 System-wide identification of weak buses for SR 72-bus equivalent system (First 15 weak buses): a comparison
Severity order Proposed index V-Q sensitivity modal analysis [7] CPF method [5]
Bus Zone RPLI Bus Zone BPF Bus Zone Voltage (p.u.)
Table 10 Zone-wise identification of weak buses for SR 72-bus equivalent system (First five weak buses in each zones): a comparison
Proposed index V-Q sensitivity modal analysis [7] CPF method [5]
Severity Bus RPLI Severity Bus BPF Severity Bus Voltage (p.u.)
Zone-1
4 36 6.7477 2 36 0.081786 3 36 0.71526
5 35 6.2390 4 35 0.071826 4 35 0.72388
8 31 4.9299 5 45 0.067166 6 56 0.76361
14 54 2.2585 6 24 0.061764 8 45 0.77334
15 33 1.4907 7 56 0.05277 9 24 0.79338
Zone-2
13 19 2.3788 8 18 0.040064 10 21 0.79828
17 21 1.3379 11 46 0.035543 12 18 0.8134
18 69 1.2620 13 21 0.031066 13 46 0.81803
20 23 1.0641 15 60 0.023733 18 60 0.83799
21 61 1.0614 25 70 0.006197 21 19 0.85144
Zone-3
1 38 20.1250 1 38 0.14131 1 38 0.59731
2 53 7.5836 3 49 0.07263 2 49 0.69412
3 41 7.1315 9 51 0.039673 5 53 0.75538
6 49 5.2699 10 53 0.037752 7 51 0.76487
7 40 5.2035 16 64 0.021386 11 39 0.81312
IET Gener. Transm. Distrib., 2015, Vol. 9, Iss. 14, pp. 1826–1834
1832 & The Institution of Engineering and Technology 2015
Fig. 3 Real and reactive power loss for SR 72-bus system: System-wide compensation
a Real power loss for SR 72-bus system
b Reactive power loss for SR 72-bus system
obtained under normal and peak load conditions are summarised in Similarly, the severity order of other load buses is also shown in
Table 8, which shows top 15 weak load buses along with their Table 9.
respective zones. It can be observed from table, in such a large Owing to locational dependent nature of reactive power, system
interconnected network, the weak load buses identified based on reactive power needs should be addressed locally. Since the size of
the proposed index under normal and peak loading conditions are the system is very large, there should be a sufficient amount of
closely in agreement with each other. From the results we can see, reactive power reserve available in the system, and it should be
bus 38 is the weakest bus and then followed by buses 53, 41, 36, widely distributed across all three-Zones to protect the system
35 and so on. against the voltage collapse during unexpected severe disturbance
The bus with lowest value of RPLI is assumed to be more stable such as severe contingencies. Hence, the weak load buses
and the bus with highest value of RPLI is considered to be the most identification is made on zone-wise as per their severity in the
critical bus. Further, the system-wide top 15 weak load buses are respective zones. The comparative analysis of weak load buses
selected as per their severity in the system-wide (based on the identification in all three zones separately from the proposed index
values of RPLI) under peak load condition for validation studies and other existing methods [5, 7] is shown in Table 10 (first five
with the reason as mentioned in the Section 4.1. Out of 15 weak weak buses in each zone). It can be seen from Table 10, from the
load buses, we can see five buses are in Zone-1 (buses 36, 35, 31, proposed and other existing methods [5, 7] the buses 36 and 35,
54 and 33), one bus in Zone-2 (bus 19) and nine buses are in and bus 38 are the weakest buses in Zone-1 and Zone-3, respectively.
Zone-3 (buses 38, 53, 41, 49, 40, 65, 39, 37 and 43). Depending
on the system topology and reactive power requirements, the
system operator may select few weak load buses for placing the 4.2.1 Reactive compensation performance studies: Once
reactive compensation devices for additional voltage support to the identification of weak buses in the system under consideration
protect the system under severe disturbance. is completed, then depending on system size and reactive power
The comparative analysis is carried out with the results from other needs/requirements, few weak buses in the system are selected for
existing methods [5, 7] in the literature such as V-Q sensitivity based additional voltage support to prevent voltage collapse. These buses
modal analysis [7], CPF method [5], which have been used for are the optimal location of placement of reactive compensation
identification of weak buses in the system. The results of devices to support the voltage. Thereafter, the ORPD algorithm
system-wide comparison of weak load buses from the proposed may be executed to determine the optimum size of the reactive
index and other existing methods is shown in Table 9. From the compensation devices, which is not the main scope of this paper.
proposed and other two existing methods [5, 7], it can be seen that However, we consider the size of the reactive compensation device
bus 38 (Zone-3) is one of the weakest/critical bus in the system. is 50 MVAr for system performance analysis.
Fig. 4 Maximum loadability and system minimum load bus voltage for SR 72-bus system: System-wide compensation
a Real power maximum loadability (p.u.)
b System min. load bus voltage (p.u.)
IET Gener. Transm. Distrib., 2015, Vol. 9, Iss. 14, pp. 1826–1834
& The Institution of Engineering and Technology 2015 1833
To highlight the features and robustness of the proposed index in contingencies cases. Fuzzy logic approach is used to identify the most
comparison with other existing methods [5, 7], the compensation severe network line outages in the system. The proposed index is
performance analysis has been studied in two scenarios for different tested on the sample 10-bus equivalent system and 72-bus equivalent
operating conditions caused by either because of maximum/peak practical southern region power grid. The test results demonstrate the
loading or severe network contingencies (First three severe effectiveness of the proposed index in terms of reducing the real and
contingencies are consider as given in Table 7). Scenario-I focuses reactive power losses, improvement in system voltage profile and
on system-wide compensation selection and scenario-II discuss on enhance the real power maximum loadability in the power system
zone-wise compensation selection. In each scenarios, the system under different operating conditions. Comparative analysis of the
performance in terms of reduction in real and reactive power losses, proposed approach with the other existing methods such as Q-V
improvement in system voltage profile and increase in real power sensitivity modal analysis and CPF method is presented. The
loading capabilities have been studied. However, because of space advantage of the proposed index is that the weak load buses are
constraints, the results of the scenario-I is discussed in the paper. identified in the system under peak loading condition with
Scenario-I: Looking into the system size, five weakest load buses incorporating the severe network contingencies. However, the existing
are selected for placing the reactive compensation devices for methods need an iterative approach up to the critical loading point.
system-wide analysis (refer Table 9). The reactive compensation The whole procedure of identifying the weak buses from the proposed
performance analysis is carried out for the following cases: index is completely non-iterative, thus reducing the computational
efforts. Hence, this can find application in control centre where the
Case-1: No compensation placed in the system. control and monitoring of the system against voltage vulnerability/
Case-2: Reactive compensation devices placed at weak load buses instability in real time. With the information obtained from the
35, 36, 38, 41 and 53 from the proposed index (PI). proposed index, the system operator may execute some preventive
Case-3: Reactive compensation devices placed at weak load buses measures to ensure the reliable and secure operation of the power
35, 36, 38, 45 and 49 from Q-V sensitivity modal analysis (Q-V) [7]. system.
Case-4: Reactive compensation devices placed at weak load buses
35, 36, 38, 49 and 53 from CPF method [5].
6 References
The real and reactive power loss, system maximum real power
1 FERC: ‘Principles for efficient and reliable reactive power supply and
loadability and system minimum load bus voltage for different consumption’. Docket No. AD05-1-000, FERC Staff Reports, USA, 2005
cases under different operating conditions are presented in Figs. 3 2 Taylor, C.W.: ‘Power system voltage stability’ (McGraw-Hill Companies, 1994)
and 4. 3 Cañizares, C.A., De Souza, A.C., Quintana, V.H.: ‘Comparison of performance
It can be seen that with compensation in the system, the real power indices for detection of proximity to voltage collapse’, IEEE Trans. Power Syst.,
1996, 11, (3), pp. 1441–1450
and reactive power losses are decreased by around 6 to 10% from the 4 Ajjarapu, V., Lee, B.: ‘Bibliography on voltage stability’, IEEE Trans. Power Syst.,
peak load condition and real power maximum loadability increased 1998, 13, (1), pp. 115–125
by around 3 to 6% from the system without compensation under 5 Ajjarapu, V., Christy, C.: ‘The continuation power flow: a tool for steady state
different operating conditions. From the figures, we can also see voltage stability analysis’, IEEE Trans. Power Syst., 1992, 7, (1), pp. 416–423
6 Tamura, Y., Mori, H., Iwamoto, S.: ‘Relationship between voltage instability and
that the results from the proposed index are closely in agreement multiple load flow solutions in electric power systems’, IEEE Trans. Power
with that produced from other existing methods [5, 7]. Appar. Syst., 1983, (5), pp. 1115–1125
Inference: From the detailed system performance studies, it can be 7 Gao, B., Morison, G., Kundur, P.: ‘Voltage stability evaluation using modal
observed from the figures and tables, the system performance analysis’, IEEE Trans. Power Syst., 1992, 7, (4), pp. 1529–1542
8 W. CIGRE Task Force 38.02.11 Report: ‘Indices predicting voltage collapse
produced by the proposed index is closely in agreement with that including dynamic phenomena’ (CIGRE, 1994)
produced by other existing methods [5, 7] in the literature. One of 9 Lof, P.-A., Andersson, G., Hill, D.: ‘Voltage stability indices for stressed power
the main advantage of the proposed index is that the weak load systems’, IEEE Trans. Power Syst., 1993, 8, (1), pp. 326–335
buses are identified in the system under peak loading condition 10 Kessel, P., Glavitsch, H.: ‘Estimating the voltage stability of a power system’, IEEE
Trans. Power Deliv., 1986, 1, (3), pp. 346–354
with incorporating the severe network contingencies. There is no 11 Thukaram, D., Lomi, A.: ‘Selection of static var compensator location and size for
need to load the system up to its critical loading point as did in system voltage stability improvement’, Electr. Power Syst. Res., 2000, 54, (2),
other two existing methods [5, 7]. In the existing methods, the pp. 139–150
actual weak load buses can only be identified when the system is 12 Ajjarapu, V., Lau, P.L., Battula, S.: ‘An optimal reactive power planning strategy
against voltage collapse’, IEEE Trans. Power Syst., 1994, 9, (2), pp. 906–917
very close to diverging point. Hence, the system has to move from 13 Thukaram, D., Bansilal Parthasarathy, K.: ‘Optimal reactive power dispatch
an initial operating point up to the collapse point by changing the algorithm for voltage stability improvement’, Int. J. Electr. Power Energy Syst.,
loading factor. Thus, the whole process goes in an iterative 1996, 18, (7), pp. 461–468
manner and therefore it is seems to be computationally more 14 Thukaram, D., Parthasarathy, K., Khincha, H., Udupa, N., Bansilal: ‘Voltage
stability improvement: case studies of indian power networks’, Electr. Power
expensive. With the knowledge of system voltage profile by the Syst. Res., 1998, 44, (1), pp. 35–44
system operator, the peak loading can easily simulated by taking 15 Singh, J., Singh, S., Srivastava, S.: ‘An approach for optimal placement of static var
10–15% more load from the normal loading condition in the compensators based on reactive power spot price’, IEEE Trans. Power Syst., 2007,
system. The proposed index for identification of weak load buses 22, (4), pp. 2021–2029
16 Visakha, K., Thukaram, D., Jenkins, L.: ‘Application of upfc for system security
is completely non-iterative manner, thus involving minimal improvement under normal and network contingencies’, Electr. Power Syst. Res.,
computational efforts. The whole procedure will be completed by 2004, 70, (1), pp. 46–55
taking one set of results from the state estimator with simulating 17 Kirschen, D., Strbac, G.: ‘Tracing active and reactive power between generators
the peak load and readily available offline network contingency and loads using real and imaginary currents’, IEEE Trans. Power Syst., 1999,
14, (4), pp. 1312–1319
results. Hence, this may find application in control centre for the 18 Elgerd, O.l.: ‘Electic energy systems theory-an introduction’ (TMH, 1982)
control and monitoring of the system against voltage vulnerability/ 19 Moger, T., Dhadbanjan, T.: ‘Reactive power loss allocation to consumers in a
instability in real time. If necessary, the system operator may deregulated power system’. Fifth Int. Conf. on Power and Energy Systems
execute some preventive measures with the information obtained (ICPS), 2013, October 2013, pp. 1–7
20 Surendra, S.: ‘Development of algorithms for improved planning and operation of
from the proposed index to protect the system. deregulated power systems’. Ph.D. dissertation, Department of Electrical
Engineering, Indian Institute of Science, Bengaluru, 2012
21 Moger, T., Dhadbanjan, T.: ‘An improved approach for evaluation of reactive
power sources contribution to reactive load and loss’. 2013 Annual IEEE India
5 Conclusions Conf. (INDICON), December 2013, pp. 1–6
22 Zhang, W., Li, F., Tolbert, L.M.: ‘Review of reactive power planning: objectives,
In the paper, a new RPLI is proposed to identify the weak load buses in constraints, and algorithms’, IEEE Trans. Power Syst., 2007, 22, (4),
pp. 2177–2186
the power system. This index is obtained from the reactive power 23 Thukaram, D., Yesuratnam, G.: ‘Comparison of optimum reactive power schedule
support and loss allocation algorithm using Y-bus method for the with different objectives using lp technique’, Int. J. Emerging Electr. Power Syst.,
system under intact condition and as well as severe network 2006, 7, (3), pp. 1–31
IET Gener. Transm. Distrib., 2015, Vol. 9, Iss. 14, pp. 1826–1834
1834 & The Institution of Engineering and Technology 2015