Exavation Works Pipercks
Exavation Works Pipercks
Part 3: Equipments / Tools to be used: Loader, Roller Compactor, Tractor, Plate compactor, Vibrator, wheel barrows & Hand Tools, Jack hammer
Part 4: Contingency Plans. Standard PPE’s: First aid kit must be present at work site and the HSE personnel will be the first response in case of
emergency, ERPs & Emergency contact numbers to be in placed at job location
Part 5:JSA Review Process. After the job has been completed, JSA leader should note: any hazards, which were identified in the original JSA? In
case of any new hazard indentified by any of the working team member during the job, JSA review process should be carried on.
JSA No: JOB TITLE: Manual Excavation Works for the Pipe racks (DHDS /Boiler House)
Step Describe Job Step Potential Hazards Hazard Controls
No
1 Mobilization of Worker & Tools Involvement of unskilled personnel Trained & skilled staff to be authorized
for working
Ensure JSA briefing to all workforce prior
to commence activity
Deliver daily TBT
Use of appropriate PPE’s
Unauthorised/ uninspected equipment/tools at Only inspected /Tools must be allowed at
site work site
All tools must be colour coded
Personnel injury / property damage Ensure use of proper PPE’s, avoid
throwing of materials
Close safety supervision
Dust Ensure use of Dust Mask
Water sprinkling to be carried out on
regular biases to avoid dust
Slip, Trip & fall Excavated area should be properly hard
barricaded
Keep access/walk ways always clear from
any obstruction
Inclement weather condition Stop work in case of any inclement
weather conditions (Rain, storm, fog etc.)
Restrict movement of heavy
vehicles/equipments in rain/fog
Fire & explosion Ensure availability of inspected fire
extinguishers at site
2 Manual Excavation & dismantling Personnel hit by hand tools due to SIMOPS Deliver tool box talk to all of workforce
JSA No: JOB TITLE: Manual Excavation Works for the Pipe racks (DHDS /Boiler House)
Step Describe Job Step Potential Hazards Hazard Controls
No
of concrete using jack hammer prior to commence the activity
(pneumatic) Ensure Hand tools are inspected & colour
coded
Workers should keep a reasonable
distance during manual excavation
Ensure Close HSE monitoring
/supervision
Working near live areas Working areas should be clearly marked
& hard barricaded
Restrict unauthorized personnel &
movement in live areas
Proper coordination with ARL/Hyundai
Team regarding all works
Stop work in case exposing of any
underground utilities & contact ARL
Dust Ensure use of appropriate PPE’s (dust
mask)
Ensure dust suppression on site
Slip, Trip & fall Excavated area should be properly hard
barricaded
Keep access/walk ways always clear from
any obstruction
Ensure proper housekeeping of workplace
all the time
Inclement weather condition Stop work in case of any inclement
weather conditions (Rain, storm, fog etc.)
Restrict movement of heavy
vehicles/equipments in rain/fog
3 Working at Night Shift Hours Poor visibility at night hours Ensure proper lighting arrangement for
JSA No: JOB TITLE: Manual Excavation Works for the Pipe racks (DHDS /Boiler House)
Step Describe Job Step Potential Hazards Hazard Controls
No
late night working hours
Vehicles/equipments hit with people, Careful movement of vehicles in night
equipment or structure hours
Place refection tapes at hard barriers,
structures
Banks men should worn high visibility
reflection vests
Slip , trip & fall No working should be allowed in poor
lighting conditions
Ensure proper housekeeping to avoid
tripping
4 Demobilization Same as item one Same as item one