Base Line Program Schedule: Start END S.No Date Status Typ. of Work Activity
Base Line Program Schedule: Start END S.No Date Status Typ. of Work Activity
TYP. OF DATE
S.NO ACTIVITY STATUS
WORK START END
All sides
1 Internal paint work(undercoat + final coat) 6/1/2021 24-02-21 1st coat completed, Final coat pending
CIVIL All sides
2 Apply of Epoxy paint work 6/1/2021 24-02-21 1st coat mostly completed, Final coat pending
SWIMMING POOL
2 CIVIL Internal paint work(undercoat + final ocat) 18/03/21 3/5/2021 Around 40% completed
5 All Ducts works installation & supports insulation works 6/1/2021 11/3/2021 In progress
MEP
6 Installation of light fittings 15/02/21 31/03/21 In progress
ADMIN BUILDING
1 CIVIL
Initail inspection done , waiting for AHAR final
Snagging works & handing over 29/04/21 10/5/2021
call for inspection.
2 MEP
SPORTS HALL