Base line program Schedule

TYP. OF DATE
S.NO ACTIVITY STATUS
WORK START END
All sides

1 Internal paint work(undercoat + final coat) 6/1/2021 24-02-21 1st coat completed, Final coat pending
CIVIL All sides
2 Apply of Epoxy paint work 6/1/2021 24-02-21 1st coat mostly completed, Final coat pending
SWIMMING POOL

1 Tile laying works 6/1/2021 16-03-21 Mostly completed

2 CIVIL Internal paint work(undercoat + final ocat) 18/03/21 3/5/2021 Around 40% completed

3 Swimming pool finishes with equipments 18/03/21 26/04/21 In progress

4 Installation of package units(Internal & External) 1/2/2021 11/4/2021 In progress

5 All Ducts works installation & supports insulation works 6/1/2021 11/3/2021 In progress
MEP
6 Installation of light fittings 15/02/21 31/03/21 In progress

7 Installation of PA system /CC TV 1/4/2021 15/03/21 In progress

ADMIN BUILDING

1 CIVIL
Initail inspection done , waiting for AHAR final
Snagging works & handing over 29/04/21 10/5/2021
call for inspection.
2 MEP

SPORTS HALL

1 CIVIL Installation of false ceiling 19/03/21 7/5/2021 45% completed

2 Installation of sanitary fittings 2/3/2021 5/4/2021 In progress

3 Installation of package units(Internal & External) 14/03/21 2/5/2021 In progress


MEP
4 Installation of light fittings 24/03/21 12/5/2021 Yet to started

5 Installation of PA system /CC TV 29/03/21 17/05/21 In progress


External works

1 Guard room - 4 No's 6/1/21 15/04/21 Around 40% completed

2 Electrical room - 4 No's 6/1/21 15/04/21 Around 40% completed

3 Service yard 6/1/21 15/04/21 Around 80% completed

4 Assembling & Erection of score board 6/1/21 15/04/21 Yet to start

Asphalt, syn. Turf, equipments & fencing work


5 Practice pitch 7/3/21 25/04/21
pending

Asphalt work just started, 90% -kerb stone work


6 CIVIL Road work, kerb stone work & parking interlock area works 6/1/21 17/05/21
completed.

7 Landscaping works 17/02/21 17/05/21 In progress


8 Parking area landscape works 7/3/21 5/5/2021 In progress
9 Testing & commissioning 18/04/21 17/05/21 Yet to start

Admin building snagging done, waiting for final


10 Snagging works & handing over 18/04/21 17/05/21
inspection of MS, sports hall & swimming pool.