Professional Documents
Culture Documents
Specification PVDF High Purity CP
Specification PVDF High Purity CP
Product Specification
1.2 References
The following standards apply to products used within this 1.7 Quality Assurance
section. Obtain components from a single source having
responsibility and accountability to answer and resolve
ASTM D 1598 ASTM D 1599 problems regarding proper installation, compatibility,
ASTM D 2122 ASTM D 2657 performance, and acceptance.
ASTM D 2837-85 ASTM D 3222-81
DVS 2207-15 1.8 Delivery, Storage and Handling
A. Deliver all Purad PVDF pipe to arrive on-site inside
The system design shall meet the requirements of protected hard black PE tubes. Cardboard tubes are not
ASME/ANSI B31.3 for design criteria where temperature allowed.
and pressure fall within the limits of the code.
B. Deliver all Purad PVDF fittings to arrive on-site
1.3 Definitions double bagged in boxes layered with bubble packing to
Purad High Purity PVDF prevent damage.
Polyvinylidene Fluoride
C. Store products on elevated platforms in a dry location
1.4 System Description and Pressure Rating with protection from the environment.
System shall be a Purad PVDF system made of uniform
pipe and fitting resin. System pressure ratings shall be D. Lift, support and transport Purad PVDF piping per
based on continuous use of 50 years. Purad Pipe and manufacturers’ recommendations.
Fittings shall be based on a Standard Dimensional Ratio
(SDR) of 21, ½” through 9” (20-225mm) or 33, 3” through 1.9 Warranty
12” (90-315mm). Pressure rating for pipe and fittings, Warranty period is one year after date of substantial
unless otherwise noted, shall be 232 psi (16 bar) for
SDR21 material and 150 psi (10 bar) for SDR33 material at completion.
68ºF.
Page 1 of 7
HP-PVDF Piping Systems
Product Specification
Page 2 of 7
HP-PVDF Piping Systems
Product Specification
Check Valves:
All sizes class 150, ball type PVDF body with FPM seat
and seals. 230 PSI at 73.4ºF for sizes ½” through 2½”
nominal 150 PSI at 73.4ºF for sizes above 2½” nominal.
Pressure Rating--Valves
Pressure rating of valves shall be per manufacturer’s
recommendations based on materials, valve type and size.
A. Butt-Fusion
Proper equipment selection should be based on pipe size
and site conditions. Butt fusion equipment should be
designed and tested to provide reliable welds. All
equipment should utilize electronically controlled heating
elements for accurate welding temperatures. Tools should
also incorporate planing units to face ends prior to heating.
Butt-fusion equipment supplied shall weld joints based on
force or pressure and not mechanical stops.
B. Socket Fusion
Proper equipment selection should be based on pipe size
and site conditions. Socket fusion tools shall be available
in two styles; one portable style capable of welding 1/2”- 2”
(20mm – 63mm) and a bench style capable of welding
3/4”- 4” (25mm – 110mm). Heating elements are to be
Page 3 of 7
HP-PVDF Piping Systems
Product Specification
electronically controlled for accurate welding temperatures. 7. Magnetic clamps to reduce change out time from
Tools should also incorporate male and female heater one size to another.
inserts with Teflon coating. 8. Vertical and Horizontal Adjustment for pipe
C. Non-Contact Butt-Fusion alignment.
(SP series).
UF2000 Style:
Tool shall be made available in ½”- 2” (20mm – 63mm)
and 2 ½” – 10” (75mm – 250mm) size ranges. Tools
shall possess electronic planer and non-contact
heating element. To avoid improper welded joints, tools
will utilize and measure the welding pressures to join
material and not mechanical stops. All IR fusion
equipment shall possess a minimum of the following
capabilities:
SP Series:
Tool shall be made available in ½” – 4” (20mm –
110mm) and 2½” – 10” (75mm – 250mm) size ranges.
Tools shall possess electronic planar and infra heating
element. Tools will utilize and measure the welding
pressures to join material and not mechanical stops. To
avoid improper welded joints, tool shall automatically
operate clamps and control joining force. Tools shall
possess the following features:
Page 4 of 7
HP-PVDF Piping Systems
Product Specification
D. Beadless Fusion 4. Pipe flanges shall be properly aligned. All flange bolts
High Performance Fusion (HPF) equipment should be should be checked for correct torques.
designed to weld all PVDF pipe valves and fittings 1/2-2” 5. All diaphragm valve bonnet bolts shall be checked for
(20mm – 62mm). Equipment shall incorporate a bar code correct torques.
scanner to set all weld parameters. An internal balloon 6. All joints should be reviewed for appropriate welding
shall be used to eliminate a bead formation. Where usage technique:
of the balloon is not possible, weld will be conducted
without balloon. Each weld will be done utilizing a HPF Butt: To have two beads, 360° around the joint.
coupling.
Socket: To have two beads on the end of the fitting
and on the outside of the pipe in contact.
PART 3 EXECUTION
Non-Contact: Identity labels shall identify weld
certification by the print “welding parameters OK”.
3.1 Installation
Joints should have two beads 360° around the joint.
A. Facilities
Subassembly and fabrication work should be conducted in
Manufacturer to supply inspection procedures beyond the
a separate, temporary clean room located within the
above recommendations. If any deficiencies appear, the
building. Cleanroom should be equipped with the following
quality control manager shall provide directions for repair.
to provide a clean installation:
B. Pressure Test
1. Provide Laminar flow Hepa filters in room ceiling to
1. Test fluid should be deionized water, with quality level
reach a level of class 10,000.
set by Quality Control Engineer. In all cases test must be
2. The quantity of filters should be determined by providing
done hydrostatically. Air test is not allowed
a minimum of 60 room air changes per hour.
3. Ideal set up is to place welding equipment directly under
2. Filling the system--Open all valves and vents to purge
a filter. In addition nitrogen should be available for purging
the system of air. Slowly inject the water into the system,
the pipelines with a positive pressure if the assemblies
making sure that air does not become trapped in the
expand beyond the bounds of the room.
system.
B. Tools
3. Begin pressurizing the system in increments of 10 PSI.
All fusion tools utilized are to be dedicated for clean build
Bring the system up to 100 PSI and hold. Allow system to
only, and should be kept separate. Special attention
hold pressure for a minimum of two hours and up to a
should be given to the fusion tools to prevent the possibility
recommended 12 hours. Check pressure gauge after one
of contaminating a weld. The contractor shall lease or
hour. Due to natural creep effects on plastic piping the
purchase all necessary welding equipment from the
pressure will have decreased. If drop is less than 10%
manufacturer. At the end of the installation, any necessary
pump the pressure back up. At this time the system may
equipment needed on-site should be sold to the owner.
be fully pressurized to desired test pressure.
Contractor is responsible for proper maintenance and care
of the fusion tools during construction.
4. If after one hour the pressure has decreased more than
10%, test is consider a failure. Note the10% value may
C. Certification need to be greater for larger systems, or systems
Installers shall be pre-qualified as per section 2.6. experiencing significant thermal changes.
Manufacturer shall provide on-site training in the assembly
and installation of the Purad PVDF piping system as 5. Test is to be witnessed by Quality Control Engineer and
needed. certified by the contractor.
3.3 Cleaning of HP-PVDF Piping System
System shall be cleaned at completion of project according
3.2 Testing to requirements set by owner.
A. Inspection
Prior to pressure testing, the system shall be examined
for the following items:
Page 5 of 7
HP-PVDF Piping Systems
Product Specification
Test Procedure:
Page 6 of 7
PVDF HIGH PURITY SYSTEMS
PRODUCT SPECIFICATIONS
Lithium < 6.2 < 4.8 4.0 6.6 < 1.3 < 2.2 9.2 < 15.0 2
Sodium 78.0 36.0 13.0 30.0 < 1.1 31.0 < 3.1 37.0 15
Ammonium 82.0 223.0 1813 3213 119.0 102.0 < 4.1 < 14.0 1000
Potassium < 41.0 50.0 56.8 91.0 < 1.5 8.4 7.6 < 21.0 15
Magnesium 50.0 116.0 31.0 61.0 4.3 < 2.2 < 4.1 < 15.0 5
Calcium 1661.0 1452.0 22.0 64.0 11.0 19.0 12.0 < 14.0 30
Page 7 of 7