Professional Documents
Culture Documents
SOP For Building Maintenance
SOP For Building Maintenance
ISSUE : 01
DOC # MIN/SOP/BUIL/19
REVISION : 00
DATE : 01/01/2019
DESIGNATION SIGNATURES
Factory Manager
REVIEWED BY:
APPROVED BY CEO
DISTRIBUTION LIST
Page 1 of 5
TITLE : SOP FOR BUILDING MAINTENANCE
ISSUE : 01
DOC # MIN/SOP/BUIL/19
REVISION : 00
DATE : 01/01/2019
AMENDMENT SHEET
INITIATED NATURE OF
REV# DATE PAGE SECTION DONE BY
BY AMENDMENT
Page 2 of 5
TITLE : SOP FOR BUILDING MAINTENANCE
ISSUE : 01
DOC # MIN/SOP/BUIL/19
REVISION : 00
DATE : 01/01/2019
This procedure covers general principles of factory maintenance to protect food from unsanitary
conditions. It covers all areas of the factory premises including non-production areas.
2. RESPONSIBILITY
QA/QC Executive
Factory Head
3. PROCEDURE
3.1 Exterior Building
3.1.1 Factory exterior shall be kept well be maintained by providing adequate drainage.
3.1.2 All exterior Factory perimeters shall be kept free from storage of equipment, pallets
and other hardware materials.
3.1.3 Building structure should be in good condition (No cracks, no paint removing, poor
plaster, and no seepage).
3.1.4 Roof area should be clean, properly managed and free of debris and waste material.
No unnecessary dumping of material there.
3.1.5 There should no entry point (pipe, ducting going into production) for rodents from
roof area.
3.3 Lighting
3.3.1 Adequate natural and artificial lighting should be provided to enable the undertaking
to operate in a hygienic manner
3.3.2 Necessary lighting should not be such that the resulting color is misleading.
Page 3 of 5
TITLE : SOP FOR BUILDING MAINTENANCE
ISSUE : 01
DOC # MIN/SOP/BUIL/19
REVISION : 00
DATE : 01/01/2019
3.3.4 All electrical cords, necessary for an operation shall be kept to a minimum in
number.
3.3.6 Electrical panels and switchboards should be sealed or tightly closed; otherwise
horizontal surfaces will provide places for dust accumulation and insect harborage.
3.3.7 Light fixtures should be protected (Where necessary) to ensure that food is not
contaminated by breakage. (All Lights covers shall be protected with suitable
thermal Plastic Sheets).
3.4.6 Ventilation systems are designed and constructed so that air does not flow from
contaminated area.
3.5 General
3.5.1 All doors must be in good condition that no gaps than ¼ inch exists in vertical or
horizontal joints. Where required, a buffer area is provided for man movement or
separate doors will be provided for man and material movement. Layout of building
is designed in such a manner to maintain logical flow of man & material.
3.5.2 Overhead fixtures, ductwork, piping & conducts to be free from dust spider
webs, grease & food residue. Ceilings and overhead fixtures shall be designed to
Page 4 of 5
TITLE : SOP FOR BUILDING MAINTENANCE
ISSUE : 01
DOC # MIN/SOP/BUIL/19
REVISION : 00
DATE : 01/01/2019
minimize build-up of dirt and condensation and shall be accessible for inspection
and cleaning.
3.5.6 All windows shall be intact and be equipped with screens where applicable.
3.5.7 Floors must be smooth, which can easily clean; fill up cracked or chipped wall-
digging holes at floor that can become source of dust accumulation.
3.5.8 All surface of the wall must be smooth, as it is practically possible to make them and
must be free from scaling or flaking paint.
3.5.9 Cracked or chipped walls should be poured with solid concrete or cement. Walls and
floors are washable or cleanable, as appropriate for the food safety hazards
associated with the food packaging production.
3.5.10 In case of any non-conformance related to layout and facilities and maintenance of
building requirement is raised through maintenance work order form by respective
department heads to HR & Admin department. HR & Admin officer made
arrangements for the closeout of non-conformance.
3.5.11 Factory Layout diagrams are reviewed by HR & Admin department head annually or
when required. Monthly Inspection of factory is conducted by Admin Officer and
records are updated.