Professional Documents
Culture Documents
Yellow Book 4ed 2013
Yellow Book 4ed 2013
Yellow Book 4ed 2013
Subcontract
The Yellow Book
IChemE
Fourth edition
2013
ADVANCING
CHEMICAL
ENGINEERING
WORLDWIDE
Historical note
In October 1968, IChemE published the original edition of the Model The increasing use of the Forms of Contract by industry led to
Form of Conditions of Contract for Process Plants suitable for Lump the publication of the ‘Orange Book’, a minor works contract, the
Sum Contracts in the United Kingdom - the ‘Red Book’ as it came to ‘Brown Book’, a subcontract for civil engineering works, and the
be known. ‘Burgundy Book’, a stand-alone target cost contract.
This publication proved highly successful and IChemE then In response to the growing use of the series on projects outside
undertook the preparation of a companion form suitable for reim- the UK, an international version of the Forms of Contract series was
bursable contracts, which was published in June 1976 as the ‘Green published in 2007, written specifically for those contracts where at
Book'. The next in the series was the ‘Yellow Book’, published in least one of the parties is contracting outside their home country.
1992, which was produced in response to requests from industry for The latest UK editions of the Red, Green, Burgundy, Yellow and
a subcontract that could be used as a ‘back to back’ subcontract Brown Books, all published in 2013, have been fully updated to
with the Red and Green Books. reflect current best practice in project delivery and recent
These Forms of Contract broke new ground in attempting to deal developments in both law and project implementation.
with the complex way in which purchaser, contractor and As with previous editions, the Guide Notes contained within the
subcontractor divide the responsibility for creating a new process publication provide a valuable resource for the user of the Forms of
plant, providing a fair and balanced framework where each party to Contract and have been fully updated to reflect the content of the
the contract could understand its responsibilities and achieve its General Conditions
objectives without confrontation. As process plants are judged by IChemE runs training courses examining in detail the Forms of
their performance in operation, process industry contracts must, Contract series - see www.icheme.org/courses.
therefore, also be performance based. This is the underlying
philosophy of the IChemE Forms of Contract suite and is a January 2013
fundamental difference from many of the other contract series used
in the wider construction industry.
Form of
Contract
Subcontracts
Published by
Institution of Chemical Engineers (IChemE)
Davis Building 165-189 Railway Terrace Rugby
Warwickshire CV21 3HQ, UK
IChemE is a Registered Charity in England and Wales and a charity
registered in Scotland (SC039661)
Copyright © 2013
Institution of Chemical Engineers
Agreement on Website
ISBN: 978-0-85295-545-1
To facilitate use of the Form of Contract the text of the Agreement is
freely available on the IChemE website at www.icheme.org
Fourth edition 2013
Page
Introductory notes 56
1. Use of the Conditions 1 57
2. Procurement policy in the process industry 1 58
3. ‘Back-to-back’ Subcontracts 2 58
4. Contract Procedure 3 59
5. Disputes 3 60
Subcontract Agreement 4
I
V
Introductory notes
1. Use of the Conditions Subcontractors, so far as they are applicable. Therefore most, if not
all, Subcontracts under a Reimbursable Main Contract would be
These conditions, referred to as the Institution of Chemical Engi- expected to be placed upon the basis of conditions which would be
neers’ (IChemE) ‘Yellow Book’, contain a form of back-to-back either back-to-back with those of the Main Contract or would
subcontract, for use with the: incorporate a significant proportion of them.
• Red Book (lump sum); Where a Lump Sum Main Contract is involved, however, the
• Green Book (cost reimbursable); or Contractor has substantial freedom to decide his own procurement
• Burgundy Book (target cost); policy, subject to any limits or requirements set out in the Main
Contract.
published by IChemE.
The Conditions of Subcontract have been drafted so as to allow
As with the main contract forms, these conditions have been
maximum freedom to the user as to the method of payment to be
developed by the IChemE Contracts Committee. The General
adopted, although there is an assumption that the subcontract will
Conditions have been formulated to reflect best practice and
be a priced-based contract and not a cost reimbursable contract.
relationships within the process plant sector, which are generally far
If the latter approach is to be adopted a number of changes
less adversarial in nature than in other parts of the construction
would be necessary to the Conditions of Subcontract. Anyone
industry. IChemE has always adopted the basic philosophy that the
contemplating such an approach is cautioned that without such
parties should co-operate to achieve the mutual objective of a
changes being undertaken by someone who knows and under-
successful project, rather than regarding the Contract as simply the
stands the required differences between price and cost-based
basis for an adversarial relationship. IChemE believes that it is in
contracts there is a strong likelihood of creating major difficulties in
the best interests of the parties to deal fairly with each other and
the application and management of the ensuing contract.
with their Subcontractors, specialists and suppliers in an
Comparison with the Green Book would be of value to anyone
atmosphere of co-operation in order to achieve ‘win-win’ solutions
experienced in undertaking such a task.
to the problems that will inevitably arise during the course of a
project.
These conditions are primarily intended for subcontracts that
include the design, supply, site construction/erection/ installation 2. Procurement policy in the process
and testing of equipment and for when the Subcontractor is to
supply plant and equipment that will be significant in terms of the industry
Main Contract Plant. Typically this might be because the
It is normal practice in the process industries for the Contractor to
Subcontractor is to supply a significant process package or system
adopt a wide range of procurement techniques, dependent for
that might be of some size or complexity.
example upon:
The aim has been to create a form of subcontract complete
within itself, without the need for frequent references to the main • market conditions;
contract. This means that the subcontract is more lengthy than it • subcontract size;
otherwise might be, but it should be easier to use. • type of equipment,sub-system or services to be procured;
The form is designed to be used in its entirety together with the • importance to the process of the equipment or services
Schedules and a Subcontract Specification. concerned;
Anyone contemplating modifications to the General Conditions • the price/risk implications of using different procurement
should take care not to introduce provisions which may conflict with strategies and conditions.
these well-established practices and relationships. They should In general terms, the Contractor will seek to purchase the
particularly be aware of the risk of introducing inconsistencies within various items of equipment and work that he needs to carry out his
the Conditions, or provisions that may be unenforceable. project on whatever conditions he considers will give him a
Users are cautioned that IChemE has not authorised or reasonable cost for the items concerned, together with a reason-
approved any amendments unless they are published by IChemE. able level of support for the project, and with the Subcontractor
Guide Notes are given at the end of this handbook to help the accepting an appropriate level of liability in the event that something
user in preparing the Subcontract Specification and Schedules. The goes wrong.
Guide Notes given in this Yellow Book have been kept brief. For The Contractor will achieve this by using different procurement
more extensive discussion and guidance users should refer to the conditions as appropriate. Specialist skills may be brought in on an
more detailed Guide Notes in the Red Book. appropriate commercial basis. Some items will be purchased using
The approach that the Contractor should take in subcontracting standard purchase orders of the ‘small print on the reverse’ type.
parts of the Main Contract Works will be different when working Some will be brought in under existing term supply or call-off
under a main contract incorporating either the Reimbursable and/or arrangements. Some will be brought in on the basis of one-off
Target Cost Conditions of Contract compared with working under a negotiated contracts. In every case the Contractor will balance the
main contract incorporating the Lump Sum Conditions. risks that he seeks to pass on to the Subcontractors against the
Under the terms of Clause 9 of the Forms of Contract for prices which those Subcontractors demand in return.
Reimbursable and Target Cost Contracts, the Contractor is required The ability to adopt a wide variety of procurement strategies,
to purchase equipment on either a basis agreed with the Project dependent upon circumstances, is one of the essential skills of the
Manager or on the basis of fixed-price competitive tenders from Contractor.
qualified suppliers. In either case the Contractor is then required to This handbook is not intended to call into question in anyway a
pass terms corresponding to those of the Main Contract on to the Contractor’s freedom to adopt whatever procurement strategy he
4. Contract Procedure
IChemE strongly recommends that a formal Subcontract Agree-
ment, in the form of wording provided in this publication, be used.
The Subcontract Agreement is to contain information which is
essential for the proper working of the Subcontract and, in
particular, defines the various documents which together form the
Subcontract and establishes an order of precedence to be used in
the event of conflict.
5. Disputes
It is hoped that those who use this form of contract will follow the
process plant industry’s tradition of cooperative and non-adver-
sarial relationships. However, should difficulties arise, in addition to
IChemE’s traditional combination of expert determination and
arbitration, this form continues the approach of reference in the first
instance of any problem to the Contract Manager (the Contractor’s
equivalent of the Purchaser’s Project Manager), and of mediation. It
also provides for adjudication (to be undertaken in accordance with
IChemE's Adjudication Rules) in terms which comply with the
Housing Grants, Construction and Regeneration Act 1996, as
amended by the Local Democracy, Economic Development and
Construction Act 2009.
Not in GT Contract
between [full name] (‘the Contractor’) of [address] and [full name] (‘the
Subcontractor’) of [address]
WHEREAS
I. The Contractor has entered into the Main Contract with [name of Purchaser] (the ‘Purchaser’) for the design, manufacture, supply,
installation, taking over and completion of the Main Contract Plant described therein;
II. The Contractor wishes the Subcontractor to carry out and complete the Subcontract Works defined in the Subcontract as a part of
the Main Contract Works; and
III. The Subcontractor is willing and able to carry out and complete the Subcontract Works in accordance with the Subcontract.
1. The following documents and their attachments (if any) shall together form the contract between the Contractor and the Subcontractor
and the term ‘Subcontract’ shall in all such documents be construed accordingly.
3. The Subcontract Price is the sum of [name(s) of currency(ies) and amount(s) in figures and words],
4. The total aggregate liability of the Subcontractor to the Contractor as provided in Sub-clause 45.3 shall not exceed [name(s) of
currency(ies) and amount(s) in figures and words],
(b) The amount to be stated in accordance with Sub-clause 37.12 of the General Conditions is [name(s) of currency(ies)
and amount(s) in figures and words],
6 The Deductible shall be [name of currency and amount in figures and words],
7. In case of conflict between any of the documents accompanying this Subcontract Agreement, the order of precedence shall be as
stated in Sub-clause 1.2 of the General Conditions.
8. For the purposes of Sub-clauses 6.3, 7.3, 8.3 and 28.3 of the General Conditions, the date of the Subcontractor’s tender shall be
[date],
9. The date for the commencement of the Subcontract Works shall be [date],
10. The Contractor hereby appoints [name] to act as the Contract Manager for the purposes of the Subcontract.
11. The Subcontractor hereby appoints [name] to act as the Subcontract Manager for the purposes of the Subcontract.
12. The bank whose base lending rate is referred to in Sub-clause 1.1 of the General Conditions in the definition of Agreed Rate is
[name of bank or where more than one currency is to be used , the names of the banks and a statement as to which base
lending rate applies to which currency],
13. The relevant take over certificate referred to in the definition of the Defects Liability Period in Sub-clause 1.1 of the General
Conditions shall be [the relevant take over certificate under the Main Contract.] [the relevant Take Over Certificate.]
14. Wherever Profit is expressly referred to in the General Conditions it shall be . . . % of the applicable Cost.
15. Any Notice to be served in accordance with Sub-clause 1.8 of the General Conditions shall be sent to the postal address or fax
number stated below:
16. The Subcontract shall be governed by the laws of England and Wales.
17. The seat of any arbitration proceedings under Clause 49 shall be [place]
18. All documents referring to the Subcontract shall carry the Identification Number: [insert reference number].
Signature: Signature:
Name: Name:
Position: Position:
General Conditions of Subcontract
‘Acceptance Certificate’ has the meaning stated in Sub-clause 36.3 and ‘Accept’,
‘Acceptance’ and ‘Accepted’ shall be construed accordingly.
‘Affiliate’ means any entity that directly or indirectly controls, is controlled by, or is under
common control with another entity. For the purposes of this definition, control means
having the beneficial ownership of more than 50% of the issued share capital of a company
or the legal power to direct or cause the direction of the general management of the
company, and ‘controls’ and ‘controlled by’ shall be construed accordingly.
‘Agreed Rate’ means the base lending rate(s) as may be current from time to time of the
bank(s) stated in the Subcontract Agreement.
‘Applications Software’ means software that has been developed specifically as part of
the Subcontract Works including configuration of Third Party Software or
Subcontractor’s Software.
‘Approved Programme’ means the programme of work approved from time to time in
accordance with Clause 13 (Times of completion and Approved Programme).
Assembly drawings means the general arrangement sheet appended to the specification in
the main contract and/or the subcontract specification and any details assembly drawings,
piping and instrumentation drawings (P&Ids) and manuals procured by the purchaser form
the boiler supply following the date of the notice to proceed in respect of the installation of
the boiler plant (as such drawings and manuals are modified from time to time by the
written instruction of the purchaser)
Availability Liquidated damages has the meaning set out in para 4 of schedule 17
(Performance Guarantees and drainage for failure)
Boiler plant Means the plant and equipment including spare parts forming part of the facility
which is not supplied under the main contract
Boiler Supply Contract the design and supply agreement between the purchaser and
outotec (USA) Inc, defined in the main contract
Capacity Liquidated Damages has the meaning set out in para 4 of schedule 17
(Performance guartees and damages for failure)
Capacity Tests means the capacity tests as set out in schedule 16 (Performance tests and
procedures).
Commercial Handling Agreement means the agreement between the purchaser and
associated British ports
‘Contract Manager1 means the individual named as such in the Subcontract Agreement
subject to Clause 11 (The Contract Manager).
‘Contractor1 means the person named as such in the Subcontract Agreement or his
permitted assigns.
Contractor provided information means the supplementary documents set out in schedule
3
‘Cost’ means any Third party cost and expense properly incurred cost properly incurred by
the Subcontractor in carrying out any of his obligations under the Subcontract, and
‘Costs’ shall be construed accordingly.
‘Decision’ means any decision, certificate, notification, instruction, order, agreement,
approval, rejection or consent.
‘Deductible’ means the sum stated in the Subcontract Agreement being the applicable
insurance deductible under the policy or policies of insurance provided in accordance with
Sub-clause 31.1.
Deductible means the applicable insurance deductible under the policy or policies of
insurance provided
‘Defect’ means any work done or any Subcontract Materials or the Subcontract
Plant or any part of it which does not comply with the Subcontract, provided that such
matter shall not be a Defect if it is caused by:
(a) normal wear and tear;
(b) a failure by the Contractor or the Purchaser to operate and maintain the
Subcontract Plant in accordance with any operating and maintenance manuals
provided by the Subcontractor and/or with good engineering practice; and/or
(c) a failure by the Contractor to comply with any of his obligations under the
Subcontract.
‘Defects Liability Period’ means a period of three hundred and sixty five days, or such
other period as may be established in accordance with Sub-clause 37.9 or 37.11, after the
date of the relevant take over certificate as identified in the Agreement, or if no such
certificate is identified, the relevant take over certificate issued under the Main Contract,
or other commencement date as described in Sub-clause 37.5.
Defects liability period means the period starting on the date of relevant take over
certificate as identified in the subcontract agreement and ending 2 years thereafter or such
other period as may be established in accordance with sub clause 37.9 or 37.11, after the
date of the relevant take over certificate as identified in the subcontract agreement
Defect other means any defect in respect any work done or any subcontract materials or
subcontract plant or any part of it or any part of the subcontractor works or any part of it
which is not deemed to be a defect (Subcontractor Fault)
Defect (Subcontractor Fault) means any work done or any subcontract materials or
subcontract plant or any part of it or any part of the subcontractor works or any part of it
which does not comply with the subcontract and any physical damage to the subcontract
works, the main contract works and or the facility caused by such non-compliance provided
that it is not solely caused by
b) a failure by the purchaser to operate and maintain the facility in accordance with any
operating and maintenance manuals provided by the contractor and/or with good
engineering practice
c) a failure by the contractor to comply with any of his obligations under this subcontract
d) a failure by either of the parties to the boiler supply contract to comply with their
obligations there under and/or
e) a failure by either parties to the connection agreement to comply with their obligations
there under
DNO requirements means the relevant requirements of the DNO imposed on the
purchaser in respect of the sale and export of electricity from the facility set out in the
connection agreement
Facility means the renewable energy facility consented under the planning conditions
for development on the area demised under the lease which comprises the works in
the main contract the works in the boiler supply contract and works in the connection
agreement
‘Final Date for Payment’ has the meaning stated in Sub-clause 41.5.
‘Force Majeure’ has the meaning stated in Sub-clause 14.6. and 14.6a
Foreseeable changes in law means any legislation , the relevant details of which had been
published
a) in a white paper
b) in a parliamentary bill
G59 Connection Test means the test of the same name details of which are set out in
schedule 15
‘Free-lssue Materials’ means machinery, plant and other items of equipment and
materials intended to form part of the Subcontract Plant and other things needed in its
operation, to be supplied by the Contractor.
‘IChemE’ means the Institution of Chemical Engineers, 165-189 Railway Terrace, Rugby,
Warwickshire, UK, CV21 3HQ.
‘Legislation’ means all applicable laws, statutes, bye-laws, regulations and other
measures having the force of law.
Latent defects liability period means the period starting on the date certified in the
construction completion certificate under the main contract and ending 12 years thereafter
Legislation means all applicable laws, statutes, bye-laws, regulations and other measures
having the force of law
Lease means the lease of the site between associated British ports as the landlord and the
purchaser as the tenant
Liquidated damages means any and all (as the context so permits) of those liquidated and
ascertained damages payable by the subcontractor to the contractor in accordance with
the subcontract, other than the damages for delay referred to in sub-clause 37.9, 44.6(a)
Main contract materials means machinery, plant and other items of equipment
and materials intended to form part of the main contract and other things
needed in its operation excluding software to be supplied by the contractor
under the main contract and excluding equipment to be supplied under the
boiler supply contract and/or the connection agreement
Main contract plant means the plant as described in the main contract
specifications which forms part of the main contract to be constructed at the
site under the main contract including any software
‘Main Contract Plant’ means the Plant defined in the Main Contract.
‘Main Contract Works’ means the Works defined in the Main Contract.
Main contract temporary works mean all temporary works and structures of
every kinds constructed at the site by the contractor to facilitate construction
of the facility
Main contract works means the design, engineering and other services to be
provided by the contractor under the main contract including the provision and
construction of the main contract plan, the contestable works, any main
contract temporary works and the subsequent dismantling or removal of the
main contract temporary works when no longer required, and any other work to
be carried out by the contractor in accordance with the contract including the
commissioning of the boiler plant.
Milestone event such event as indicated in schedule 19
Milestone payment date such date as indicated in schedule 19
Minimum Guaranteed steam means limb (i) of the definition of basis conditions
as set out in schedule 15 (take over procedures) as adjusted by the correction
curves in schedule 15
Minimum Performance guarantee has the meaning ser out in para 3.1(d) of
schedule 15
‘Notice’ means a formal notice issued by the Contractor to the Subcontractor or by the
Subcontractor to the Contractor in accordance with Sub-clause 1.8.
‘Performance Test Commencement Period’ means the period within which the
performance tests are to commence as stated in Schedule 11 (Times of completion) or
any extension thereof granted in accordance with Clause 35 (Performance tests).
‘Performance Test Period’ means the period within which the performance tests are to be
carried out and completed, as stated in Schedule 11 or any extension thereof granted in
accordance with Clause 35.
Planned take over date means the date as set out in schedule 11 table 2
Planning conditions means the conditions to the planning consent with reference
14/00923/full
‘Project Manager’ means the individual named as such in the Main Contract.
Related obligations means the obligations and restriction that the subcontractor must
Related provisions means the contractual provisions that the subcontractor must
‘Schedules’ means the schedules listed in the Subcontract Agreement and forming part
of the Subcontract.
‘Site’ means the area within which the Subcontract Plant is to be constructed, together
with all other areas as the Subcontractor shall be permitted to use in connection with the
Subcontract Works, as specified in Schedule 1 (Description of the Subcontract Works).
‘Site Materials’ means (a) any Subcontract Materials from the time of their delivery to the
Site; and (b) any Free-lssue Materials from the time of their delivery to the Site.
‘Special Conditions’ means the conditions of contract entitled Special Conditions (if any).
‘Subcontract Conditions’ means the General Conditions and the Special Condi-
tions.
‘Subcontract Materials’ means machinery, plant and other items of equipment and
materials intended to form part of the Subcontract Plant and other things needed in its
operation excluding software, to be supplied by the Subcontractor under the Subcontract.
‘Subcontract Temporary Works’ means all temporary works and structures of every kind
constructed at the Site by the Subcontractor to facilitate construction of the Subcontract
‘Subcontract Works’ means the design, engineering and other services to be provided by
the Subcontractor including the provision and construction of the
Subcontract Plant and any Subcontract Temporary Works and the subsequent
dismantling or removal of the Subcontract Temporary Works when no longer required,
and any other work to be carried out by the Subcontractor in accordance with the
Subcontract.
‘Take Over Certificate’ has the meaning stated in Sub-clause 33.7, and ‘Take Over’,
Taking Over’ and ‘Taken Over’ shall be construed accordingly.
1.2 The Subcontract documents shall be construed as mutually explanatory of one another. In
the event of conflict between any of the documents comprising the Subcontract, the order
of precedence shall be as follows:
(a) the Subcontract Agreement;
(b) the Special Conditions (if any);
(c) the General Conditions;
(d) the Subcontract Specification;
(e) the Schedules.
The Subcontractor has had the opportunity to scrutinise the documents listed
in this clause 1.2 such documents shall be construed as mutually explanatory
of one another. In the event of conflict between any of the documents
comprising the subcontract, te order of precedence shall be from (a) (highest
priority) to (F) Lowest Priority
1.3 The singular shall include the plural and the plural the singular except where the context
otherwise requires and the words ‘he’, ‘him’ and ‘his’ shall be taken to mean ‘she’, ‘her’ and
‘hers’ where appropriate.
1.4 No Decision required under the Subcontract shall be unreasonably refused or delayed.
1.6 Any communication in accordance with or in connection with the Subcontract shall be in
writing, which shall include handwritten, typewritten or printed documents sent by hand,
post, fax, email or other means resulting in a permanent record.
1.7 The failure of either party to enforce any provision of the Subcontract shall not constitute a
waiver of his right to require complete performance by the other party. A party shall only
have waived his rights under the Subcontract if such waiver shall have been recorded in
writing and signed by a duly authorised representative of that party. No waiver of any
breach of the Subcontract shall constitute a waiver of any subsequent breach of the
Subcontract.
1.9 The headings and marginal notes in the Subcontract Conditions together with the
accompanying Introductory Notes, Guidance on compiling the Subcontract Agreement, its
Annex, the Subcontract Specification and Schedules, and Guide Notes shall not form part
of the Subcontract nor shall they be taken into consideration in the interpretation of the
Subcontract.
2. Co-operation
2.1 The parties and the Contract Manager shall each co-operate with each other in the
discharge of their respective obligations under the Subcontract with the aim of satis-
factorily completing the Subcontract Plant and the Subcontract Works in accordance
with the Subcontract.
2.2 The parties shall deal fairly, openly and in good faith with each other. Each party shall
disclose information which the other might reasonably need in order to exercise his rights
and to perform his obligations under the Subcontract. In particular, each party shall
promptly disclose full information to the other concerning any matter which will or may
prevent the Subcontract Plant and Subcontract Works being completed in accordance
with the Subcontract. The parties shall work together in a manner consistent with their
respective obligations under the Subcontract to resolve or mitigate the effect of any such
matter.
2.3 The parties shall cooperate to enable the contractor and/or the purchaser access to the
facility during its construction and prior to take over in order to allow the contractor and/or
the purchaser to carry out testing and commissioning of the equipment supplied under the
boiler supply contract following its installation and commissioning by the contractor
3. Subcontractor's responsibilities
3.1 In consideration of payment by the Contractor, the Subcontractor shall regularly and
diligently carry out and complete the Subcontract Works in accordance with the
Subcontract.
The subcontractor shall set out any part of the facility that forms part of the
subcontract works and the subcontract plant by reference to points, lines and levels
of reference specified in the subcontract and/or provided to him by the contract
manager and notwithstanding any checking or approval by the contract manager of
the setting our of the facility and/or the subcontract plant, the contractor shall be
responsible for the correctness thereof
3.4 The Subcontract Plant as completed by the Subcontractor shall comply with the
Subcontract and shall be in every respect fit for the purpose for which it is intended as
defined in the Subcontract Specification or in any other provision of the Subcontract.
The subcontract plant as designed and completed by the subcontractor (to the extent
the subcontractor is responsible for the same) shall comply with the subcontract and
shall be in every respect fit for the purpose for which it is intended as defined in the
subcontract specifications the main contract or in any other provision of the
subcontract. An assembly drawing (other than the general arrangement) which does
not contain the same level detail as the precedent installation: drawing shall be
defective for the purposes of the subcontract
3.5 If at any time during the performance of the Subcontract the Subcontractor is of the
opinion that a change to the Subcontract Works or the design or method of operation of
the Subcontract Plant:
(a) is necessary to eliminate a potential defect in the Subcontract Plant ora specific
hazard to any person or party in the performance of the Subcontract Works or in
the operation of the Subcontract Plant which has occurred or would otherwise
occur; or
(b) would improve operating or life cycle costs of the Subcontract Plant; or
(c) would otherwise be beneficial to the Contractor or the Purchaser;
the Subcontractor shall promptly notify the Contract Manager accordingly.
The subcontractor shall promptly notify the contract manager accordingly stating the
reasons for its opinion and where appropriate, submit proposals for a variation in
accordance with clause 17 (variation proposed by the subcontractor)
3.6 The Subcontractor shall at all times have and maintain adequate resources available for
the proper and timely carrying out of the Subcontract Works, including financial
resources, and competent, appropriately qualified and experienced personnel.
3.7 Unless otherwise agreed, the Subcontractor shall at intervals of not more than one
calendar month report to the Contract Manager in accordance with Schedule 21 (Reports
and records) on the progress of the Subcontract Works, supporting his reports with
appropriate documents including any proposed revisions to the Approved Programme.
The Subcontractor shall provide and maintain in accordance with Sub-clause 40.1 records
as required by Schedule 21.
3.8 The Subcontractor shall maintain, and cause Sub-subcontractors to maintain, a quality
assurance system as described in Schedule 6 (Quality assurance and validation). The
existence of such a quality assurance system shall not relieve the Subcontractor from any
of his other duties, obligations or liabilities under the Subcontract. The Subcontractor
shall also prepare and implement a validation plan, if such a requirement is included in
Schedule 6.
3.10 The Subcontractor acknowledges that the Subcontract Plant forms part of the Main
Contract Plant and that the Subcontract Works form part of the Main Contract Works,
and shall avoid putting the Contractor in breach of his obligations under the Main
Contract provided that, subject to Sub-clause 3.4, the Subcontractor shall only be liable
for those matters which have been made known to him in Schedule 22 (Main Contract
particulars).
In carrying out and completing the subcontract works the subcontractor shall take into
account all other works being carried out in relation to the facility including but not limited to
any works being carried out by the contractor’s other subcontractors. The subcontractor
shall co-ordinate the subcontract works with all other works referred to in this subclause
3.12 and shall have no entitlement to an extension of time or an additional payment in
connection with any delay to the subcontract works or any additional costs incurred by the
subcontractor as a result of a failure to comply with this sub-clause 3.13
The subcontractor acknowledges that it has received and familiarised itself with a copy of
the draft connection agreement and that by entering into the subcontract, the subcontractor
shall be deemed to have notice of the full contents of the connection agreement and to
understand its full nature and effect, in particular relating to the:
A) Dno requirement
B) Importance of the works and where relevant the subcontract works meaning the dno
requirement on or before the g59 connection test. Date as set out in schedule 11,
table 1
3.14 save where otherwise expressly provided in this subcontract (the subcontractor shall
perform its obligations under the subcontract so that no act or omission on its part (or no
the part of any of its sub-subcontractors shall:
A) cause, contribute or otherwise give rise to any breach by contractor and/or the
purchaser of any of its obligations pursuant to the connection agreement, the operating
contract, the lease, the project document, the related obligations, the related provisions,
the boiler supply contract, and the commercial handling agreement (third party
agreements) and or
C) Cause, contribute or otherwise give rise to any other liability on the part of the
purchase and/or the contractor pursuant to or in connection with Third party
agreements.
To the extent relevant to the subcontract works, subcontract plant and subcontract
materials, the subcontractor shall comply with the third party agreements and
acknowledges that breach of these obligations may result in the purchaser becoming
liable under the relevant project document and/or in the contractor becoming liable
under or in connection with the main contract.
3.15 The subcontractor shall indemnify, defend and hold harmless the contractor from
any and all claims, judgements, losses, costs, injuries, damages, liabilities and
B) any act or omission, breach of this subcontract, failure to comply with any
legislation or negligence of the csubcontractor and/or its subcontractors in connection
wihtt he subcontract works, the subcontract plant, the subcontract materials and/or
the subcontractors observance or performant of failure to observe or perform its other
obligations under this subcontract.
3.16 The subcontractor shall cooperate with the purchaser and the project manager,
provided that the subcontractor shall not without the prior authority of the contractor
comply with any instruction or direction received by thim directly from the purchaser or
project manager or clientrepresentative as appointed by the purchaser from time to
time. The subcontractor shall immediately inform the contractor of any such direct
instructions or directions
3.17 the subcontractor shall provide the subcontract works usch that the contractors
obligations and requirements under the main contract are faciliteated in particular
those obligations and requirements stated in schedule 15 (take over procedures) and
schedule 18 (performance tests and procedures)
4. Contractor's responsibilities
4.1 The Contractor, through the Contract Manager, shall provide the Subcontractor with the
Documentation described in Schedule 3 (Responsibilities of Contractor) and with all such
further information and Decisions as are referred to in the Subcontract or are necessary
to be provided by the Contractor to permit the Subcontractor to carry out and complete
the Subcontract Works at the times specified in the Subcontract. If no such times are
specified, the Contractor shall make such provision within a reasonable time with regard to
any date stated in Schedule 11 (Times of completion), the Approved Programme, the
actual progress of the Subcontract Works and all other relevant circumstances.
4.2 If the Subcontract provides in Schedule 3 or any Special Condition that the Contractor
shall carry out any work or provide any Free-lssue Materials, other materials, facil
If the subcontract provides in schedule 3 that the contractor shall carry out any work or
provide any materials, facilities or services which are necessary to permit the carrying out
and completion of the subcontract works by the subcontractor then, subject to any express
descriptions thereof in the subcontract, such work, materials, facilities or services shall be
carried out and provided:
4.3
4.4
4.5
4.6
5.3
materials and resources involved. Such records shall be open to inspection by the
Subcontract Manager at all reasonable times.
Subject to any other provision of the Subcontract if the Subcontractor incurs additional
Cost as a result of any breach of contract by the Contractor the Subcontractor shall be
entitled to an addition to the Subcontract Price determined in accordance with and subject
to Clause 19 (Claims).
The Contractor shall provide, or ensure that the Purchaser provides, personnel with
adequate skills and experience:
(a) to carry out their duties under the Subcontract; and
(b) to operate and maintain the Subcontract Plant from the date of the Take Over
Certificate, and shall make such personnel available for training in accordance
with Schedule 9 (Training by Subcontractor).
The Contractor shall ensure that his personnel and anybody working under his or the
Contract Manager’s control shall at all times when at the Site be familiar with and comply
strictly with the requirements stated in Schedules 4 (Health & Safety) and 5
(Environmental protection & waste disposal) and any site safety regulations, safe working
procedures and health and safety instructions issued to the Subcontractor from time to
time by the Contract Manager, the Contractor, the Purchaser or the Project Manager
and shall further ensure that where necessary such personnel have undergone suitable
safety training and certification.
The Subcontractor shall not be liable for the consequences of any errors or omissions in
or arising from work carried out by the Contractor or on the Contractor’s behalf by others
(other than in respect of any design or information which the Subcontractor is required to
verify in accordance with his obligations under the Subcontract).
co-ordination
Every Decision, objection, proposal, claim or report to be issued, given or made under the
Subcontract shall be issued, given or made in writing. If any Decision, objection, proposal,
claim or report is issued, given or made orally, it shall be confirmed in writing by the issuing
party within seven days and shall be effective from the time and date of confirmation.
Records of meetings signed in accordance with Sub-clause 29.3 shall constitute a report in
the context of this Clause 5 and shall have the same effect as a Decision.
5.5 The subcontractor shall provide all documentation, advice consents, comments, approvals,
instructions, notices, requests, submissions, valuations, certificates and other
communications required as part of the subcontract works promptly so as to enable the
contractor to give such notice and provide such information as may be required under the
main contract, including but not limited to any notice required to enable the contractor to
claim and be entitled to such contractual benefits if any as may be claimable under the
main contract on account of compliance with any instruction issued by the contractor
and/or as a result of any other circumstances that may affect this subcontract
notwithstanding any other provision of this subcontract the subcontractors compliance with
this sub-clause 5.5 in respect of any circumstances giving rise to any entitlement of the
subcontractor to additional payment and or an extension of time shall be a condition
precedent to any such entitlement.
6.2 The Contractor shall be responsible for the accuracy of any information provided by him or
on his behalf. Except where the Subcontract expressly requires the Subcontractor to
verify any such information, if any such information proves to be inaccurate and the
Subcontractor consequently incurs any increase in the Cost of performing his obligations
under the Subcontract, the Subcontractor shall be entitled to an addition to the
Subcontract Price determined in accordance with and subject to Clause 19 (Claims).
6.3 The contractor shall be responsible for the accuracy of any information provided by him or
on his behalf relating to the boiler supply contract. The subcontractor has had the
opportunity to scrutinise the contractor provided information listed in schedule 3. If any of
the contractor provided information (other than that relating to the boiler supply contract)
proves to be inaccurate ate and the subcontractor consequently incurs any increase in the
cost of performing his obligations under the subcontract and the cause of such increase in
cost has arisen by reason of any incomplete or inaccurate data in the remainder of the
contractor provided information and an experienced contractor exercising due skill and
care would not have discovered the same when scrutinising the remainder of the
contractor provided information, the subcontractor shall give notice of the same under sub-
clause 5.5 and clause 19 (claims). The contract Manager shall decide to what extent the
discrepancy could not reasonably have been so discovered. If the parties cannot agree
within seven (7) days of the contract manager’s decision, the matter shall be referred for
resolution in accordance with clause 48 (dispute resolution).
6.4 If during the carrying out of the Subcontract Works the Subcontractor encounters on the
Site any physical condition which at the date of the Subcontractor’s tender as stated in
the Subcontract Agreement would not reasonably have been foreseen by a properly
qualified and competent subcontractor having all the information which the Subcontractor
then had or could have obtained by a visual inspection of the Site or by reasonable
enquiry, and if the Subcontractor considers that he will in consequence of such condition
incur an increase in the time or Cost of performing his obligations under the Subcontract,
he shall notify the Contract Manager within ten days of becoming aware of such
unforeseen condition and otherwise shall comply with the requirements of Clause 19. Any
such notification shall:
(a) expressly state that it is given under this Sub-clause 6.3;
(b) specify the condition encountered;
(c) specify the steps which the Subcontractor is taking or proposing to take to
overcome the condition encountered;
(d) contain estimates of the effect on the Approved Programme of the condition and
the additional Cost which the Subcontractor is likely to incur; and
(e) state how the Subcontractor proposes to minimise such effect and additional Cost
and/or time.
The entitlement of the subcontractor to an addition of the contract price under this sub-
clause 6.3 shalll not apply to the extent the physical condition is one which the
subcontractor was required to verify under sub-clause 6.2 or of which the subcontractor is
deemed to have notice under the subcontract or for which the subcontractor is otherwise
responsible under these general conditions.
The contractor and the subcontractor shall in all matters relating to the subcontract
comply with all legislation. The contractor shall obtain, or ensure that the purchaser
obtains, all permits required from government and local authority or any other
necessary permissions in connection with the use of the site for the construction,
operations and maintenance of the facility with the exception of those permissions, if
any specified in schedule 1 (description of the subcontract works), the preparation
and submission of the applications for which together with doing whatever is
reasonable to obtain such permissions shall be the responsibility of the
subcontractor. The subcontractor shall provide all reasonable assistance (both in
respect of scope and timing) to the contractor in obtaining the permits for which the
contractor (or the purchaser) is responsible under this clause
The subcontractor shall be required to obtain and maintain all consents, permits,
licences and permission required for it to perform its obligations as a contractor under
the subcontract, including building regulation consents (as distince form permit,
licences and permission enabling the purchaser to construct an doperate a power
plant such as the environmental permit) including:
7.3 If after the date of the Subcontractor’s tender as stated in the Subcontract Agreement,
there shall be enacted or brought into force any Legislation which causes an increase or
decrease in the Cost to the Subcontractor of carrying out any part of the Subcontract
Works, either party or the Contract Manager may give notification within ten days of such
circumstances and the Contract Manager shall determine an appropriate addition to or
deduction from the Subcontract Price by means of a Variation Order. When reasonably
requested to do so by the Contract Manager the Subcontractor shall assist in such
determination by the provision to the Contract Manager of the make-up of the
Subcontract Price or of any relevant part thereof.
7.4 Notwithstanding anything contained in this Clause 7, all taxes, levies, rates,
charges, national insurance contributions and the like assessed on the Subcontractor
including any changes therein and all taxes, withholdings and the like on or calculated by
reference to the Subcontractor’s profits or deemed profits shall be borne by the Subcon-
tractor. For the avoidance of doubt this Sub-clause 7.4 does not apply to Value Added
Tax, provision for which is made in Sub-clause 41.13.
7.5 Notwithstanding anything contained in this clause 7, but subject to any express
provision to the contrary elsewhere in the subcontract all taxes, levies rates, charges,
national insurance contributions and the like assessed on the subcontractor including any
changes therein and all taxes, withholdings and the like on or calculated by reference to
the subcontractors profits or deemed profits shall be borne by the subcontractor, for the
avoidance of doubt this sub-clause 7.4 does not apply to value added pax provision for
which is made in sub-clause 4.1.13 or foreseeable changes in law
8.2 The Contractor shall be responsible for, or shall ensure that the Purchaser is responsible
for, the payment of all fees, royalties and other charges, if any, that may be payable under
the terms of any licence or permission in respect of the operation or use of the
Subcontract Plant or any part thereof to the extent that they are not included in the
Subcontract Price.
8.3 If any design of the Subcontract Plant provided by the Subcontractor, or any item of the
Subcontract Plant manufactured or supplied by him, or any work done or method
employed by him in carrying out the Subcontract Works should infringe or be claimed to
infringe any patent, registered design, design right, trade mark, copyright or other
intellectual property right protected by law, the Subcontractor shall indemnify the
Contractor against all damages, liabilities, claims, costs and expenses that may result
from such infringement or claimed infringement, provided always that this indemnity shall
not apply to any such patent, registered design, design right, trade mark, copyright or any
other property right protected by law first granted, registered or created after the date of the
Subcontractor’s tender as stated in the Subcontract Agreement nor to any use of the
8.6 In the event of any claim being made or proceedings commenced against the Subcon-
tractor to which the indemnity set out in Sub-clause 8.5 applies, the Subcontractor shall
promptly notify the Contractor who shall:
(a) immediately discuss with the Subcontractor the action(s) that the Contractor
intends to take in dealing with such claim and in conducting such proceedings;
(b) deal with such claim and conduct such proceedings in the Subcontractor’s name;
and
(c) at all times keep the Subcontractor fully informed as to his progress in dealing with
such claim or conducting such proceedings.
If within twenty-eight days of the Subcontractor’s notification the Contractor fails to notify
the Subcontractor that he intends to deal with such claim or conduct such proceedings
then the Subcontractor shall be free to deal with such claim or conduct such proceedings
on his own behalf. Unless the Contractor has failed to notify the Subcontractor within the
period stated above, or fails at any time to comply with the other requirements of this Sub-
clause 8.6, the Subcontractor shall not make any admission prejudicial to such
proceedings.
8.7 The copyright and all other intellectual rights in all Documentation provided by the
Subcontractor under the Subcontract shall remain vested in the Subcontractor or his
Sub-subcontractors as the case may be, subject to the pre-existing rights of the
Contractor or any third party.
8.8 The Contractor and the Purchaser shall have the right to use such Documentation in
connection with the design, construction, operation, maintenance and repair of the
Subcontract Plant. The Contractor and the Purchaser shall have the further right without
additional payment to the Subcontractor to use any such Documentation for the purpose
of making any improvement to or enlargement of the Subcontract Plant, provided that
such improvement or enlargement does not result in the construction of any separate or
additional production plant.
The subcontractor hereby grants to the contractor and the purchaser or shall procure the
grant to the contractor and the purchaser of a perpetual, transferable, non-exclusive,
royalty free, sub-licensable, and irrevocable licence to use such documentation in
connection with the design, construction, operation, maintenance and repair of the
subcontractor plant and/or the facility. Such licence shall include without limitation a right to
use, amend, copy, extend or modify any of the documentation in connection with the
design, construction, operation, maintenance, repair and expansion of the subcontract
pland and/or the facility. The contractor and the purchase shall have the further right
without additional payment ot he subcontractor to use any such documentation for the
8.9 Title in the Applications Software shall pass to the Contractor upon its installation within
the Subcontract Plant. The Contractor shall be entitled to pass such title to the
Purchaser. The Subcontractor shall grant to or obtain for the Contractor and the
Purchaser an irrevocable royalty free licence to use for the lifetime of the Subcontract
Plant all Third Party Software and Subcontractor’s Software necessary for the operation
or maintenance of the Subcontract Plant.
8.10 Within twenty-one days of the issue of the relevant Take-Over Certificate, the Subcon-
tractor shall supply to the Contractor, who shall be entitled to supply to the Purchaser,
9. Subcontracting and third party the Third Party Software and the Subcontractor’s Software, as detailed in the
rights
Subcontract Specification.
9.1 Neither the Contractor nor the Subcontractor shall without the previous consent of the
other transfer any benefit or obligation under the Subcontract to any other person in whole
or in part, except that
(a) the Subcontractor may without such consent transfer the right to receive any
money which is or may become due to him under the Subcontract; and
(b) if so required by the Purchaser under the Main Contract the Contractor may
assign the Subcontract to the Purchaser.
(c) The contractor may assign the subcontract to any affiliate of the contractor
(d) If so required by the purchaser: the subcontractor shall enter into a deed of
novation with the purchaser and the contractor, within 7 days of the contractors
request. If the subcontractor defaults in the execution and/or delivery of deed of
novation requested by the contractor no monies shall fall due to the subcontractor
under this subcontract until the subcontractor has remedied its default.
9.2 The Subcontractor may not subcontract the whole of the Subcontract Works.
Subject to Clause 10 (Nominated Sub-subcontractors) and Schedule 7 (Subcontracting),
the Subcontractor may subcontract any part of the Subcontract Works as the
Subcontractor Contractor considers appropriate.
The subcontracting by the Subcontractor of any part of the Subcontract Works shall not
relieve the Subcontractor in any way from his obligations under the Subcontract.
The subcontracting by the subcontractor of any part of the subcontract works shall
not relieve the subcontractor in any way from his obligations under the subcontract.
9.4 No subcontract shall contain any provision that makes payment to the Subsubcontractor
by the Subcontractor dependent upon the receipt by the Subcontractor of any payment
due under the Subcontract.
9.5 The Subcontractor shall include in any subcontract under which Confidential Information
referred to in Sub-clause 20.2 is to be disclosed to the Sub-subcontractor a provision that
the Sub-subcontractor shall observe the same obligations of confidentiality as those of the
Subcontractor, and that the Contractor or the Purchaser shall be entitled to enforce such
provision directly against the Sub-subcontractor.
9.6 The subcontractor shall include in any subcontract under which confidential information
referred to in sub-clause 20.2 is to be disclosed to the sub-subcontractor a provision that
the sub-subcontractor shall observe the same obligations of confidentially as those of the
9.7 The Contractor agrees that his obligations under Sub-clauses 20.3, 30.11 and 30.14 shall
be capable of being enforced directly by any Sub-subcontractor.
(c) Sub-clauses Clause 37 (Liability for Defects) shall be capable of being enforced
directly by the purchaser
(d) Sub-clauses 20.2, 20.4, 30.13 and 30.15 shall be capable of being enforced
directly by the purchaser
(e) Subclauses 30.10, shall be capable of being enforced directly by the purchaser,
the project manager or any affiliate of the purchaser to whom the relevant
indemnity applies
9.9 Save as expressly provided in this Clause 9, no person other than a party to this
Subcontract shall have any right to enforce any of its terms under the Contracts (Rights of
Third Parties) Act 1999. Save for the rights of the Purchaser under Subclause 9.7, the
Contractor and the Subcontractor may by agreement rescind or vary the Subcontract
without the consent of any beneficiary who has rights to enforce a term of the
Subcontract, even if as a result that beneficiary’s rights to enforce a term of the
Subcontract will be varied or extinguished.
10.1 If the Subcontract provides that any work shall be done or Subcontract Materials or
services supplied by a Sub-subcontractor named in the Subcontract and stated to be a
Sub-subcontractor nominated by the Contractor, the Subcontractor shall enter into a
subcontract in accordance with such nomination. Sub-clauses 10.3,10.4 and 10.5 shall
not apply in respect of that Sub-subcontractor.
10.2 If the Subcontract provides that any work shall be done or Subcontract Materials
or services supplied by a Sub-subcontractor to be nominated by the Contract Manager,
the Contract Manager shall make the necessary nomination at a reasonable time having
regard to the progress of the Subcontract Works and, subject to Sub-clauses 10.3 and
10.4, the Subcontractor shall enter into a subcontract in accordance with such
nomination.
10.4 Upon receipt of any notification under Sub-clause 10.3 and unless otherwise agreed:
(a) the Contract Manager shall withdraw the nomination and nominate another sub-
subcontractor in accordance with Sub-clause 10.2; or
(b) if the Subcontractor and the Contract Manager agree terms the Contract
Manager shall issue a Variation Order confirming the nomination, in which case
the Subcontractor shall enter into a subcontract with the nominated sub-
subcontractor on the terms agreed with the Contract Manager; or
(c) the Contract Manager shall withdraw the nomination and issue a Variation
Order omitting the work, Subcontract Materials or services in question, in which
case the Contractor may enter into a direct contract with the previously
nominated sub-subcontractor.
10.5 In the event that the Subcontractor does not notify the Contract Manager under Sub-
clause 10.3 above, he shall be obliged to accept the Contract Manager’s nomination.
10.6 Subject to the Subcontractor using reasonable endeavours to recover from any
nominated Sub-subcontractor any loss suffered by the Subcontractor as a result of the
failure of that nominated Sub-subcontractor to perform his obligations under the relevant
subcontract, the Contractor shall indemnify the Subcontractor against all damages,
liabilities, claims, costs and expenses that the Subcontractor may suffer as a
consequence of that failure by the nominated Sub-subcontractor provided that:
(a) the Subcontractor shall notify the Contract Manager within a reasonable time of
becoming aware of such failure;
(b) the failure to perform of such Sub-subcontractor did not result from any failure of
the Subcontractor himself (and not any Sub-subcontractor) to exercise the
reasonable skill and care to be expected of a properly qualified and competent
subcontractor; and
(c) the Subcontractor shall not take legal proceedings against that nominated Sub-
subcontractor without the Contractor’s agreement to the action.
10.8 Any disagreement arising under this Clause 10 which is not settled in accordance with
Clause 46 (Disputes) may be referred to an Expert in accordance with Clause 48
(Reference to an Expert).
11.2 The Contract Manager may at any time instruct the Subcontractor to carry out the
Subcontract Works or any part thereof as the Contract Manager may require and the
Subcontractor shall comply with such instruction within a reasonable period to be agreed
between the Contract Manager and the Subcontractor.
The contract manager may at any time instruct the subcontractor to carry out the
subcontract works or any part thereof as the contract manager may require and the
subcontractor shall comply with such instruction, provided it has obtained written
confirmation of the same from the contractor, within a reasonable period to be agreed
between the contract manager and the subcontractor
If the Subcontractor is of the opinion that compliance with an instruction of the Contract
Manager would:
(a) constitute a Variation; or
(b) prevent him or hinder him in fulfilling any obligation under the Subcontract;
(c) be a matter described in paragraph (a), (b), (c), (d) or (e) of Sub-clause 16.6;
he shall so notify the Contract Manager within fourteen days. The Contract Manager
may request the Subcontractor to provide justification for his opinion. The Subcontractor
shall be entitled to an addition to the Subcontract Price for preparing the justification,
determined in accordance with and subject to Clause 19 (Claims).
If the Contract Manager accepts the Subcontractor’s opinion, he shall withdraw the
instruction and if appropriate issue a Variation Order under Clause 16 (Variations).
11.3 The Contractor may from time to time appoint some other individual as Contract
Manager in place of the individual previously so named or appointed and shall notify the
Subcontractor without delay.
11.4 The Contract Manager may notify the Subcontractor of the appointment of any individual
to act as a Contract Manager’s Representative and may from time to time by further
notification change such appointment. Any such Contract Manager’s Representative
shall have authority to reject any designs, workmanship or materials which are not in
accordance with the Subcontract, but the Subcontractor may within seven days of such
rejection and before complying with it appeal against it to the Contract Manager. Any
such Contract Manager’s Representative shall also have authority to receive on behalf
of the Contract Manager any notification to be given to the Contract Manager under the
Subcontract by the Subcontractor, but the Subcontractor shall also send a copy of any
such notification directly to the Contract Manager.
11.5 Subject to Sub-clauses 12.5 and 28.4, the Contract Manager may notify the Subcon-
tractor that he authorises any Contract Manager’s Representative to exercise any of the
powers and functions of the Contract Manager under the Subcontract and may by
further notification cancel or modify any such authority, but not with retrospective effect.
11.6 If in the absence of the necessary authority from the Contract Manager a Contract
Manager’s Representative has given the Subcontractor any Decision which should
have been given by the Contract Manager, the Subcontractor may, within seven days of
receipt, advise the Contract Manager of such Decision. Unless the Contract Manager
withdraws that Decision within seven days of receipt of such advice, the Decision shall
have effect as if it had been given by the Contract Manager. In the event that the
Subcontractor does not advise the Contract Manager of any such Decision within seven
days of receipt, the Decision shall be deemed to have been given with the authority of the
Contract Manager.
11.7 Except as otherwise provided in or under the Subcontract, all communications between
12.1 The Subcontract Manager shall have full authority to act on the Subcontractor’s
behalf in connection with the Subcontract. The Subcontractor shall not replace the
Subcontract Manager without the consent of the Contract Manager. The Subcontractor
shall at all times until the issue of the last Final Certificate ensure that a suitable
individual is appointed to act as Subcontract Manager. The Subcontract Manager shall
appoint a deputy to act in his place in his absence. The Subcontract Manager shall notify
the Contract Manager of the appointment of such a deputy who shall be deemed to have
full authority to act on the Subcontractor’s behalf.
12.2 Whenever the Subcontractor is carrying out work at the Site the Subcontractor shall
ensure that a suitable individual is employed at the Site as Subcontractor’s Site
Manager. The Subcontractor shall notify the Contract Manager of the individual so
appointed as Subcontractor’s Site Manager and shall not make or change such
appointment without the prior consent or requirement of the Contract Manager.
The Subcontractor’s Site Manager shall supervise all work done at the Site by the
Subcontractor and shall receive on behalf of the Subcontractor all Decisions given to
the Subcontractor at the Site by the Contract Manager or any Contract Manager’s
Representative. The Subcontractor’s Site Manager shall be present at the Site during
normal working hours except when on leave, sick or absent for reasons connected with
the proper performance of the Subcontract or as agreed with the Contract Manager.
Whenever the Subcontractor’s Site Manager is absent from the Site during normal
working hours, a suitable individual shall be appointed to act as his deputy. The
Subcontractor’s Site Manager shall not be employed by the Subcontractor to do work
under other contracts without the agreement of the Contract Manager.
From the commencement of the subcontract works at the site until the whole of the
subcontract plant has been accepted by the contractor, the subcontractor shall
ensure that a suitable individual is employed at the site as a subcontractors site
manager. The subcontractor shall notify the contract manager of the individual so
appointed as subcontractors site manager and shall not make or change such
appointment without the prior consent or requirement of the contract manager.
The subcontractors site manager shall supervise all work done at the site by the
subcontractor and shall receive on behalf of the subcontractor all decisions given to
the subcontractor at the site by the contract manager or any contract managers
representative. The subcontractors site manager shall be present at the site during
normal working hours except when on leave, sick or absent for reasons connected
with the proper performance of the subcontract or as agreed with the contract
manager. Whenever the subcontractors site manager is absent from the site during
normal working hours, a suitable individual shall be appointed to act as his deputy.
The subcontractors site manager shall not be employed by the subcontractor to do
work under the other contracts without the agreement of the contract manager.
12.3 The Subcontractor shall provide the further supervisory staff specified in Schedule 8
(Subcontractor’s named personnel). The Subcontractor shall ensure that at all times
there are sufficient suitably qualified and experienced staff to supervise all work being
done by the Subcontractor at the Site and, where required by the Subcontract, to advise
and assist the Contractor and the Purchaser in starting up the Subcontract Plant,
carrying out the performance tests and operating the Subcontract Plant until its
Acceptance.
12.4 The Subcontractor shall not replace any key personnel named in Schedule 8 without the
consent of the Contract Manager.
The Subcontractor shall not replace any key personnel named in schedule 8 without the
consent of the contract manager and subcontractor shall in any event require the consent
of the contract manager with respect to the appointment of any subcontractor personnel
who are to perform or be involved in any aspect of the performance of (a) take over
procedures set out in schedule 15 of the main contract and b) the commissioning tests as
defined in schedule 24 of the main contract
12.5 If the Contract Manager is of the opinion that the Subcontractor’s Site
Manager or any member of the Subcontractor’s supervisory staff at the Site is
incompetent or has misconducted himself or been in material breach of his
duties, he may notify the Subcontractor that he requires such person to leave
the Site with immediate effect. The Subcontractor shall be under an obligation to
act on the Contract Manager’s notification forthwith and to replace such person
as soon as practicable. Provided it is given in good faith and does not amount
to unlawful discrimination, any Decision given by the Contract Manager under
this Sub-clause 12.5 shall be final, conclusive and binding. The Contract
Manager shall not delegate the power to give notification under this Sub-clause
12.5. The Contractor shall have no obligation to pay the Subcontractor for
replacing the person.
13.2 The Subcontractor shall within the time stated in Schedule 11 prepare and submit to the
Contract Manager for his approval a programme of work setting out in any manner that
the Contract Manager may reasonably require the sequence in which and dates by which
the Subcontractor proposes to perform his obligations under the Subcontract and the
date(s) by which the Subcontractor reasonably requires that the Contractor should
provide any further Documentation or information or take any other action to permit the
Subcontractor to perform his obligations. The programme shall take account of all
matters which may affect the completion of the Subcontract Works. If the programme
submitted by the Subcontractor is consistent with any dates and periods specified in the
Subcontract and is otherwise reasonable, the Contract Manager shall approve it and it
shall be the Approved Programme.
The Subcontractor shall use reasonable endeavours to perform his obligations under the
Subcontract in accordance with the Approved Programme.
The Subcontractor shall use reasonable endeavours to perform his obligations under
the subcontract tin accordance with the approved programme provided that this
reasonable endeavours obligation shall not in any way qualify the extent of the
subcontractors liability for delays under clause 15 of these general conditions.
13.3 If required by the Contract Manager, the Subcontractor shall submit details of the
qualifications and experience of the personnel whom the Subcontractor proposes to
employ on the Subcontract Works at various times, and the other resources which he will
have available in order to perform his obligations under the Subcontract and in
accordance with the Approved Programme. The details shall be in such form as required
by the Contract Manager. The Subcontractor shall employ and make available
personnel and resources conforming to such proposals.
13.4 If at any time progress falls behind the Approved Programme, or it becomes clear that it
will fall behind, the Contract Manager may require the Subcontractor either to take such
steps as may be practicable in order to achieve the Approved Programme or to revise
the Approved Programme in the light of the circumstances and to re-submit it to him for
his approval. If the Contract Manager approves the revised programme it shall thereafter
be the Approved Programme.
13.5 Without prejudice to Sub-clause 13.4, if the Contract Manager decides that progress by
the Subcontractor in carrying out the Subcontract Works is likely to prejudice the
Subcontractor’s ability to complete the construction of the Subcontract Plant, or any
Section, in accordance with Sub-clause 13.1, and that this is due to a cause for which the
Subcontractor is responsible, the Contract Manager may notify the Subcontractor to
that effect. Following such notification the Subcontractor shall remedy the potential delay
at his own cost.
13.6 If when the Contract Manager requires the Subcontractor to revise the
Approved Programme the Subcontractor fails to submit a revised programme
within a reasonable time, or if the Subcontractor submits a revised programme
which the Contract Manager is unable to approve for good reason, the Contract
Manager may instruct the Subcontractor to make reasonable revisions to the
programme and the Subcontractor shall as soon as possible make such
revisions and the revised programme shall thereafter be the Approved
Programme.
13.7 The exercise by the Contract Manager of his powers under Sub-clauses 13.4, 13.5 and
14. Delays 13.6 above shall not change any of the Subcontractor’s obligations to the Contractor
under the Subcontract.
14.1 If the Subcontractor is delayed in the performance of any of his obligations under the
Subcontract by any of the matters specified in Sub-clause 14.4 or by Force Majeure he
shall notify the Contract Manager as soon as possible after becoming aware of the delay.
As soon as reasonably possible after that, the Subcontractor shall notify the Contract
Manager of any extension to any date or period specified in the Subcontract for the
completion of such obligations as he considers would be fair and reasonable in the
circumstances. The Subcontractor shall keep records made at the time of the
circumstances, extent and effect of such delay.
The Contract Manager shall as soon as possible, and in any event within fourteen days
of receipt of the Subcontractor’s notification as to the extension to any date or period
specified in the Subcontract that the Subcontractor considers would be fair and
reasonable, notify to the Subcontractor an initial assessment of any extension to any date
or period specified in the Subcontract which the Contract Manager considers
appropriate based on the information available to him at that time.
Thereafter the Contract Manager may from time to time review and notify to the
Subcontractor the need for and amount of any extension to any date or period speci fied
in the Subcontract sought by the Subcontractor having regard to all the information
available to the Contract Manager at the time of any review.
The Contract Manager shall undertake a review having regard to all the information
available to him of the need for and amount of any extension sought by the Subcon-
tractor after the later of either the occurrence of any date or the expiration of any period
specified in the Subcontract or as applicable the occurrence of any extension of any date
or the expiration of any extension of any period stated in the Subcontract.
The Contract Manager shall undertake a final review having regard to all the information
available to him of the need for and amount of any extension sought by the
Subcontractor after the Subcontractor has completed his obligations in respect of any
date or period specified in the Subcontract.
The contract manager shall as soon as possible, and in any event within twenty one
days of receipt of the subcontractors notification as to the extension to any date or
period specified in the subcontract that the subcontractor considers would be fair
and reasonable, notify to the subcontractor an initial assessment of any extension to
any date or period specified in the subcontract which the contract manager
considers appropriate based on the information available to him at that time.
Thereafter the contract manager may from time to time review and notify to the
subcontractor the need for and amount of any extension to any date or period
14.2 In deciding the appropriate extension to any date or period specified in the Subcontract
the Contract Manager shall have regard to the following:
(a) an extension shall only be granted when the matter causing the delay, being a
matter which is specified in Sub-clause 14.4 or is an event of Force Majeure,
affects achieving the completion of the Subcontract Plant or the Subcontract
Works or any part of the Subcontract Plant or the Subcontract Works by any
date or by the end of any period stated in the Subcontract;
(b) all the information currently available to the Contract Manager;
(c) the amount of any extension in respect of a particular cause of delay shall be fair
and reasonable; and
(d) in the event of extension for a cause which occurs at a time when the Subcon-
tractor is already in delay for which no extension is allowable, the delay accrued
prior to the allowable extension shall not be excused.
(e) An extension shall not be granted if the subcontractor has not complied with sub-
clauses 5.5 in relation to the causes of the delay and:
(f) The extent to which any delay is a consequence of failure by the subcontractor to
comply with itss obligations under sub-clause 14.7 or any other obligation under
the subcontract
14.3 The notification to the Subcontractor of any extension to any date or period, or any
change in any extension, shall be by means of a Variation Order stating the appropriate
extension to the dates or periods stated in the Subcontract and the Subcontractor shall
revise the Approved Programme and submit it to the Contract Manager for approval in
accordance with Sub-clause 13.4.
(h) Delay of delivery of the boiler plant by reference to the boiler plant
delivery dates or
(j) Delay to the passing of take over tests as a result of the falirue of the
boiler plant to meet the minimum guaranteed steam or
14.5 If the Contractor is delayed by an event of Force Majeure in the performance of any of
his obligations under the Subcontract, he shall as soon as possible so notify the
Subcontractor and the Contract Manager.
As soon as possible after that the Contractor shall advise the Subcontractor and the
Contract Manager as to the effect of such event of Force Majeure, and shall advise the
Subcontractor and the Contract Manager of any change in the effect of such event of
Force Majeure including the cessation of the event of Force Majeure.
14.6 ‘Force Majeure’ shall mean any circumstance beyond the reasonable control of the
parties which prevents or impedes the due performance of the Subcontract by either
party including the following:
(a) government action or trade embargo; or
(b) war, hostilities or acts of terrorism; or
(c) riot or civil commotion; or
(d) epidemic; or
(e) earthquake, flood, fire or natural physical disaster; or
(f) exceptionally severe weather conditions or the consequences thereof; or
(g) denial of the use of any railway, port, airport, shipping service or other means of
public transport; or
(h) industrial disputes, other than any solely confined to the Subcontractor or his
Sub-subcontractors or their personnel.
The mere shortage of labour, materials, utilities or a breach of contract shall not constitute
Force Majeure unless caused by circumstances which are themselves Force Majeure.
14.6A Force Majeure shall also mean fire and flood provided that
A) the subcontractor has complied with the requirements (including the fire safety
requirements) of the insurers providing the delay in start up insurance and
B) in the event of claims arising from fire and flood the subcontractor shall be
responsible for a deductible amount of £75,000 for each and every loss caused by
flooding and £100,000 for each and every loss in respect of fire and explosion, for
the deductible period under such delay in start up insurance procure by the
purchaser such that the subcontractor shall not be entitled to an extension of time to
14.7 Both parties shall at all times use reasonable endeavours to minimise any delay in the
performance of their obligations under the Subcontract, whatever may be the cause of
such delay.
14.8 In the event that either party is delayed by Force Majeure each party shall bear his own
costs arising from such delay.
14.9 If performance of the Subcontract Works is substantially prevented by Force Majeure for
a continuous period of one hundred and twenty days, either party may by Notice to the
other terminate the employment of the Subcontractor. In the event of such termination
the rights and obligations of the parties shall be the same as if the Contractor had issued
a Notice of Termination under Sub-clause 43.1.
15.2 After liquidated damages for delay have become payable in respect of any part of the
Subcontract Plant or Subcontract Works, if the Contract Manager issues a Variation
Order or any event occurs which delays the Subcontractor and in the opinion of the
Contract Manager properly entitles the Subcontractor in accordance with Clause 14
(Delays) to an extension of time in respect of such further delay to that part of the
Subcontract Plant or Subcontract Works, the Contract Manager shall immediately so
notify the Subcontractor and the Contractor.
The Contractor’s further entitlement to liquidated damages in respect of that part of the
Subcontract Plant or Subcontract Works shall thereupon be suspended until the
Contract Manager notifies the Subcontractor and Contractor that such further delay has
come to an end.
Such suspension shall not invalidate any entitlement to liquidated damages which became
payable before the period of further delay started.
15.1 If the subcontractor fails to achieve Take Over in accordance with Schedule 11,
Table 2, as may be adjusted from time to time by the operation of clause 14 the
subcontractor shall pay the contractor liquidated damages (delay liquidated damages) as
specified in schedule 12 (Liquidated damages for delay). In which event the contractor
may recover the same as a debt. Such delay liquidated damages shall be paid for each
day or delay from the take over date in schedule 11, table 2 (as may be adjusted from
time to time by the operation of clause 14) to the actual take over date. The debt shall
become due and payable upon receipt by the subcontractor of the contract managers
written demand and the final date for payment shall be 21 days thereafter
15.2 After delay liquidated damages have become payable in respect of any part of the
subcontract plant or subcontract works, if the contract manager issues a variation order or
any event occurs which delays the subcontractor and in the opinion of the contract
manager properly entitles the subcontractor in accordance with clause 14 (delays) to an
extension of time in respect of such further delay to that part of the subcontract plant or
subcontract works, the contract manager shall immediately so notify the subcontractor and
the contractor.
The contractor’s further entitlement to delay liquidated damages in respect of that part of
the subcontract plant or subcontract works shall thereupon be suspended until the
Such suspension shall not invalidate any entitlement to delay liquidated damages which
become payable before the period of further delay started.
15.4 The contractors right to terminate the subcontract pursuant to sub-clause 15.3
shall not apply if the subcontractor has
A) Paid the liquidated damages in excess of the limit set out in sub-clause 15.3 (the
excess amount) and
B) Agreed in writing to increase the limit on the subcontractors combined liability for all
liquidated damages by an amount equal to or in excess of the excess amount
provided always that this sub-clause 15.4 shall cease to apply if the subcontractor
has agreed to increase the limit on its liability set out in sub-clause 45.2 (D) to an
amount equal to or in excess of 10% of the contract price
15.6 In the event that the provisions for delay liquidated damages for delay are held
to be unenforceable as a result of a claim, objection, defence, dispute or proceedings
raised or brought by the subcontractor, the subcontractor expressly agrees to pay the
contractor all costs, losses and damages whatsoever (including loss of profit, loss of
use and loss of production) incurred or payable by the contractor arising from or in
consequence of the failure to achieve take over of the subcontract works or the
relevant part thereof on the planned take over date, provided that the amount of
damages payable in such circumstances do not exceed the aggregate amount that
would have been payable had the delay liquidated damages been enforceable.
16.2 At any time during the performance of the Subcontract the Contract Manager may order
a Variation and, subject to this Clause 16, the Subcontractor shall carry it out as if the
Variation were part of the original Subcontract. The Variation shall be valued in
accordance with Clause 18 (Valuation of Variations).
16.3 The Contract Manager may at any time instruct the Subcontractor to prepare or to assist
him in the preparation of a potential Variation and the Subcontractor shall comply with
such instruction and give to the Contract Manager his recommendations for the form and
scope together with an estimate of the Cost and impact on the Approved Programme of
the Variation at such time and in such detail as the Contract Manager shall require.
16.4 Notwithstanding that consequent additions to or deductions from the Subcontract Price
remain to be decided or agreed, the Contract Manager may issue a Variation Order in
accordance with Sub-clause 16.2 if he considers that delaying the Variation Order
pending such decision or agreement would unnecessarily prejudice the satisfactory
completion of the Subcontract Works or cause avoidable harm to the interests of the
Contractor or the Purchaser. In all other cases the Contract Manager shall give the
Subcontractor reasonable opportunity to comment upon any Variation he proposes to
order and shall request the Subcontractor to state his proposal for consequent
adjustments to the Subcontract Works. The Subcontractor shall give his proposal within
seven days of receipt of such request or within such longer period as the Contract
Manager may agree.
16.5 If the Subcontractor is of the opinion that compliance with any Variation Order would
prevent him from or hinder him in fulfilling any obligation under the Subcontract, he shall
so notify the Contract Manager as soon as reasonably possible and not later than ten
days from receipt of the Variation Order giving reasons why he considers he would be so
prevented or hindered. Any Variation Order in respect of which such a notification is
given by the Subcontractor shall cease to be binding unless and until it is confirmed by
the Contract Manager with or without modifications. The obligations of the
Subcontractor shall be as set out in the Variation Order or any modification to it.
16.6 The Subcontractor may object to any Variation ordered or proposed if compliance with it
would:
(a) cause the Subcontractor to infringe any Legislation, including health, safety or
environmental legislation; or
(b) cause the Subcontractor to infringe any patent, registered design, design right,
copyright or other protected right of any third party; or
(c) require the Subcontractor to act in breach of any legally binding undertaking or
agreement with a third party; or
(d) require the Subcontractor to do work or to exercise skills which are not of the kind
he undertakes in the ordinary course of his business, unless the Variation Order
specifies that the work shall be done or those skills shall be provided by a Sub-
subcontractor in accordance with Clause 10 (Nominated Subsubcontractors); or
(e) involve the employment or use of resources beyond the current capacity of the
Subcontractor where he can demonstrate that such resources are unavailable to
him or cannot reasonably be obtained.
Any such objection by the Subcontractor shall be made to the Contract Manager as
soon as reasonably possible and not later than ten days from receipt of the Variation
Order, giving reasons for his objection. In such case the Contract Manager shall notify
the Subcontractor either that he withdraws the Variation Order or proposal, or that he
does not accept the validity of the Subcontractor’s objection. The decision of the
Subcontractor not to object to any Variation ordered or proposed under this Clause 16
shall not affect his right to object to any subsequent Variation Order or proposal.
16.7 Subject to sub-clauses 5.5, the subcontractor shall be entitled to an addition to the
subcontract price determined in accordance with and subject to clause 19 (claims) in
respect of the cost of preparing a potential variation in accordance with subclause 16.3 of
commenting upon a proposed variation in accordance with sub-clause 16.4 or of
responding to a variation order in accordance with sub-clause 16.5 and 16.6 whether or
not any such potential or proposed variation is ordered or amended or such variation order
is confirmed or withdrawn. However, where such variation is a consequence of any failure
by the subcontractor to perform its obligations under the subcontract or is in respect of any
matter for which it has responsibility under the subcontract, the subcontractor shall not be
entitled to any such addition to the subcontract price
16.7 The Subcontractor shall establish and maintain contemporary records of the work,
Subcontract Materials and resources required to undertake any Variation and their Cost
together with such additional records as the Contract Manager may reasonably direct
prior to or at the time of issuing the Variation Order, and all such records shall be open to
inspection by the Contract Manager.
17.2 If the Contract Manager wishes to give the proposal further consideration he shall agree
with the Subcontractor the extent of the detail that he requires the Subcontractor to
prepare in substantiating the proposal or in developing full details of the proposed
Variation, and thereafter the Subcontractor shall undertake such preparatory work. The
Subcontractor shall be entitled to an addition to the Subcontract
Price determined in accordance with and subject to Clause 19 (Claims) in respect of the
Cost of any preparatory work undertaken in accordance with this Sub-clause 17.2.
Any disagreement arising under this Sub-clause 17.2 concerning the Cost of any such
preparatory work which is not settled in accordance with Clause 46 (Disputes) may be
referred to an Expert in accordance with Clause 48 (Reference to an Expert).
If the contract manager wishes to give the proposal further consideration he shall agree
with the subcontractor the extent of the detail that he requires the subcontractor to
prepare in substantiating the proposal or in developing full details of the proposed
variation, and thereafter the subcontractor shall undertake such preparatory work. Subject
to sub-clauses 5.5 the subcontractor shall be entitled to an addition to the subcontract
price determined in accordance with and subject to clause 19 (claims) in respect of the
cost of any preparatory work undertaken in accordance with this subclause 17.2.
However, where such variation is a consequence of any failure by the subcontractor to
perform its obligations under the subcontract or is in respect of any matter for which it has
responsibility under the subcontract, the subcontractor shall not be entitled to any such
Any disagreement arising under this sub-clause 17.2 concerning the cost of any such
preparatory work which is not settled in accordance with clause 46( disputes) may be
referred to an expert in accordance with clause 48 (reference to an expert)
17.3 If the Contract Manager decides that the proposed Variation should be
incorporated into the Subcontract Works or the Approved Programme, he shall so order
and Clause 16 (Variations) shall apply. The Contract Manager may instead order or
propose an alternative Variation under Clause 16. The Contract Manager’s Decision on
any proposal for a Variation or on a detailed proposed Variation under Sub-clauses 17.1
and 17.2 respectively shall be given within fourteen days of receipt of the proposal for a
Variation or of the detailed proposed Variation, or such longer period as the Contract
Manager notifies the Subcontractor within the said fourteen days is reasonably required
for the Contract Manager and the Contractor to consider the proposal for a Variation or
detailed proposed Variation.
Other than in the special circumstances described in Sub-clause 17.4, a Decision of the
Contract Manager not to order a Variation or propose an alternative Variation shall be
final, conclusive and binding.
17.4 The special circumstances referred to in Sub-clause 17.3 are those where the
Subcontractor has stated in his proposal that the object of the Variation is to eliminate a
potential defect in the Subcontract Plant or the Subcontract Works or a hazard to any
person or property in the performance of the Subcontract Works or in the operation or
maintenance of the Subcontract Plant including any breach of a duty imposed by any
health and safety or environmental Legislation.
Any disagreement arising under this Sub-clause 17.4 concerning the Contract
Manager’s Decision not to order a Variation or propose an alternative Variation in such
special circumstances which is not settled in accordance with Clause 46 may be referred
to an Expert in accordance with Clause 48.
If such potential defect or hazard derives from a failure of the Subcontractor or if it should
have been taken into account by the Subcontractor under Clause 6 (Sufficiency of
Subcontract Price), the Subcontractor shall not be entitled to any addition to the
Subcontract Price for the cost of implementing a Variation to the extent that it derives
from the requirement to eliminate the potential defect or hazard.
17.5 If the Subcontractor becomes aware that any item of the Subcontract Plant or any part
of the Subcontract Works to be performed by the Subcontractor has been incorrectly
specified in the Subcontract, the Subcontractor shall immediately notify the Contract
Manager. The Contract Manager and the Subcontractor shall as soon as possible meet
to consider what action and what Variation may be needed.
18.2 Where a fixed price quotation for a Variation is provided by the Subcontractor and
accepted by the Contract Manager the price stated in the quotation and accepted shall
be the addition to or deduction from the Subcontract Price to be made in respect of such
Variation.
18.3 Where so agreed the amount to be added to the Subcontract Price in accordance with
this Clause 18 shall be the additional Cost the Subcontractor properly incurs plus Profit.
19. Claims
19.1 If the Subcontractor intends to claim any additional payment which does notarise out of a
Variation, he shall notify the Contract Manager of such intention within ten days of
becoming aware of the event which gives rise to the claim, and shall establish and
maintain records relevant to the claim, together with such additional records as the
19.2 The Subcontractor shall as soon as possible thereafter submit his claim to the Contract
Manager supported by a written statement of grounds and a summary of material facts
upon which he relies, together with copies of contemporaneous records and any records
made in accordance with Sub-clause 19.1. The Contract Manager may request any
reasonable additional information that he considers necessary to evaluate the claim and
the Subcontractor shall provide such information as soon as reasonably practicable.
19.3 The amount, if any, to be added to the Subcontract Price in respect of any claim by the
Subcontractor shall be such amount as the Contract Manager and the Subcontractor
may agree. In the absence of such agreement, the Contract Manager shall as soon as
practicable decide such amount which shall be calculated in accordance with the rates
and prices contained in Schedule 18 (Valuation of Variations and claims) so far as these
may be applicable (or otherwise it shall be such amount as shall in all the circumstances
be reasonable having regard to Schedule 18) and having regard to any prejudice caused
to the Contractor by any late notice under Sub-clause 19.1. Any such agreement or
decision shall be recorded by means of a Variation Order.
19.4 Where it is stated in the Subcontract that an addition to the Subcontract Price is to be
determined in accordance with this Clause 19, the Subcontractor shall be entitled to the
additional Cost he properly incurs plus Profit. The Subcontractor shall not be entitled to
any Cost incurred as a result of any failure on the part of the Subcontractor to comply
with any of the provisions of the Subcontract including those of this Clause 19.
19.5 Any claim by the Contractor made in accordance with Sub-clause 4.3 shall be submitted
to the Subcontractor as soon as possible after the work to which the costs relate has
been completed and be supported by a written statement of grounds and a summary of
material facts upon which the Contractor relies together with copies of records made in
accordance with Sub-clause 4.3. The Contractor and the Subcontractor may agree the
costs in respect of any claim by the Contractor. In the absence of such agreement, the
Contract Manager shall decide the amount as soon as practicable.
20. Confidentiality
20.1 ‘Confidential Information’ shall mean all Documentation and other technical or
commercial information in any form obtained directly or indirectly from the Purchaser or
the Contractor by the Subcontractor, or directly or indirectly from the Subcontractor by
the Purchaser or the Contractor, or which is generated by the Subcontractor or any
Sub-subcontractor in connection with the Subcontract, whether before or after the date
of the Subcontract other than information:
(a) which is or becomes publicly available other than by any unauthorised action of
either of the parties to this Subcontract; or
(b) which is or comes into the possession of one party other than in breach of a duty
of confidence to the other party; or
(c) which is expressly approved for disclosure by the party to whom the information
relates..
20.2 The Subcontractor shall not, without the previous consent of the Contractor, use, publish
or disclose to any person, nor cause nor permit any of his Affiliates, personnel or Sub-
subcontractors to use, publish or disclose any Confidential Information obtained from
the Purchaser or the Contractor other than for the performance of his duties under the
Subcontract.
The Subcontractor shall not, without the previous consent of the Contractor, use, publish
or disclose to any person, nor cause nor permit any of his Affiliates, personnel or Sub-
subcontractors to use, publish or disclose any Confidential Information obtained from the
Purchaser or the Contractor other than for the performance of his duties under the
Subcontract. If requested by the Contractor, the Subcontractor shall enter into a non-
disclosure agreement directly with the Boiler Supplier with respect to any information
originating from the Boiler Supplier, on the same terms as has the Contractor itself within
seven days of the Contractor’s request. Nothing in the Subcontract shall moderate the
scope or duration of the non-disclosure agreement entered into between the
Subcontractor and the Boiler Supplier. If the Subcontractor defaults in the delivery of any
20.3 Except as permitted in Clause 8 (Patent and other protected rights) the Contractor shall
not and shall ensure that the Purchaser shall not, without the previous consent of the
Subcontractor, use, publish or disclose to any person, nor cause nor permit any of their
Affiliates, or personnel to use, publish or disclose to any person any Confidential
Information obtained from the Subcontractor or any Sub-subcontractor otherwise than
for the design, construction, operation, repair, maintenance, modification, re-use or
removal of the Subcontract Plant and associated facilities.
20.3 Except as permitted in Clause 8 (Patent and other protected rights) the
Contractor shall not and shall ensure that the Purchaser shall not, without the previous
consent of the Subcontractor, use, publish or disclose to any person, nor cause nor permit
any of their Affiliates, or personnel to use, publish or disclose to any person any
Confidential Information obtained from the Subcontractor or any Sub-subcontractor
otherwise than for the design, construction, operation, repair, maintenance, modification,
sale, or financing of the Subcontract Plant and/or the Facility and associated facilities or in
the conduct of legal proceedings in connection therewith provided that nothing in this Sub-
clause shall prevent the Contractor from disclosing Confidential Information to its
professional advisers and to the funders (and their professional advisers) if the recipient is
bound by a confidentiality undertaking to an extent no less stringent than the obligations
imposed on the Contractor under this Subcontract
20.4 The Subcontractor shall not, other than for the purposes of performing the Subcontract
Works, take or permit to be taken any photograph or other image of the whole or any part
of the Subcontract Plant or any other property of the Contractor or of the Purchaser or
his Affiliates, or any physical or virtual model of the Subcontract Plant, without the prior
consent of the Contractor. Any such photograph or other image shall be regarded as
Confidential Information within the terms of Subclause 20.1. No photograph or other
image so taken shall be used for the purposes of publicity without the prior consent of the
Contractor.
20.5 This Clause 20 shall survive and remain in full force for a period of ten years following the
issue of the last Final Certificate under Clause 38 (Final Certificate) or final Default
Certificate under Clause 44 (Termination for Subcontractor’s default), unless otherwise
stated in any Special Conditions.
21. Documentation
21.1 The Subcontractor shall appoint competent persons who shall be responsible for the
checking and approval of all Documentation provided by the Subcontractor. No
Documentation shall be both checked and approved by the same individual. If such
persons are not named in the Subcontract, the Subcontractor shall make such
appointments and shall notify the Contract Manager accordingly.
21.2 The Subcontractor shall submit to the Contract Manager for his approval the Docu-
mentation listed in Schedule 2 (Documentation) under the heading ‘Documentation for
approval’ at the time or times stated in Schedule 11 (Times of completion) or in the
Approved Programme.
Within twenty-one days of the receipt by him of any Documentation for his approval, the
Contract Manager shall return one copy thereof to the Subcontractor with his approval,
conditional approval or rejection endorsed on it. If the Contract Manager fails to take any
such action within the said twenty-one days, the Documentation shall be deemed to have
been approved by the Contract Manager and the Subcontractor shall notify the
Contract Manager accordingly.
21.3 The Contract Manager’s approval of any Documentation submitted to him shall not
relieve the Subcontractor of any of his responsibilities under the Subcontract. The
Subcontractor shall not depart from any approved Documentation unless he has first
submitted amended Documentation to the Contract Manager and obtained his approval
thereof.
21.3 The Contractor’s, the Contract Manager's, the Project Manager’s and/or the
Purchaser’s approval of any Documentation submitted to him shall not relieve the
21.4 The Contract Manager shall not reject any Documentation except on the grounds that
the Documentation is not in accordance with some express provision of the
Subcontract, or that it is not in accordance with good engineering practice or is likely to
have an adverse effect on health or safety or on the environment.
In each case where the Contract Manager rejects any Documentation, he shall give his
reasons and the Subcontractor shall amend and re-submit such amended Docu-
mentation to the Contract Manager.
Any disagreement arising under this Sub-clause 21.4 which is not settled in accordance
with Clause 46 (Disputes) may be referred to an Expert in accordance with Clause 48
(Reference to an Expert).
21.5 If the Contract Manager gives conditional approval to any Documentation subject to any
comment or query, he may have, he shall make such comment or query on or attached to
such Documentation. The Subcontractor may with the Contract Manager’s consent
proceed on the basis of the conditional approval.
The Subcontractor shall in any event re-submit the Documentation with his response to
the comment or query and the Contract Manager shall in accordance with Sub-clause
21.2 approve such Documentation without conditions when it is re-submitted in
accordance with the conditional approval.
21.6 The Contract Manager shall have the right at any time on reasonable notice to examine
any Documentation which has been or is being prepared by the Subcontractor or his
Sub-subcontractors for the purposes of the Subcontract except any Documentation of
a class or description which Schedule 2 or any Special Condition states shall not be
shown to the Contractor or the Contract Manager.
21.6 The Contract Manager and the Project Manager shall have the right at any time
on reasonable notice to examine any Documentation which has been or is being
prepared by the Subcontractor or his Sub-subcontractors for the purposes of the
Subcontract except any Documentation of a class or description which Schedule 2 states
shall not be shown to the Contractor, the Project Manager or the Contract Manager
21.8 Documentation relating to any item subject to statutory design requirements and/or
insurance approval shall be made available to the Contractor and/or his or the
Purchaser’s insurers or their agents at times appropriate for such purposes, taking
account of the Approved Programme.
21.9 At a time or within a period (if any) specified in Schedule 11 and before the Subcontract
Plant is Taken Over in accordance with Clause 33 (Taking Over), the Subcontractor
shall supply the Documentation specified in Schedule 2 under the heading ‘Final
Documentation and Manuals’ forthe Subcontract Plant as actually constructed.
21.10 The Contract Manager shall review the Documentation supplied by the Subcontractor
in accordance with Sub-clauses 21.8 and 21.9 for completeness and accuracy, and may
require it to be amended by the Subcontractor as necessary.
21.11 Whenever the Subcontractor makes any change to the Subcontract Plant as
described in the Documentation provided in accordance with Sub-clause 21.9, he shall,
within a period of fifty days, provide the Contractor with new Documentation revised to
take account of such change.
21.12 The Subcontractor shall promptly correct any error, discrepancy or omission in any
Documentation prepared by him or on his behalf. If the need for correction has arisen by
reason of any incomplete or inaccurate data, Documentation or information provided by
the Contractor or the Contract Manager on which the Subcontractor reasonably relied,
the Subcontractor shall be entitled to an addition to the Subcontract Price determined in
accordance with and subject to Clause 19 (Claims). Otherwise the work of the
21.13 The Subcontractor shall if required by the Contract Manager correct any error,
discrepancy or omission in any Documentation provided to him by the Contractor or the
Contract Manager for the purposes of the Subcontract Works and overcome the
consequences of such error, discrepancy or omission and shall be entitled to an addition
to the Subcontract Price determined in accordance with and subject to Clause 19.
However, if the need for correction has arisen by reason of any inaccurate data,
Documentation or information provided by the Subcontractor and on which the
Contractor or the Contract Manager reasonably relied, the Subcontractor shall himself
bear his additional cost.
21.14The Subcontractor shall reimburse to the Contractor any cost of abortive activity which the Contractor has incurred in
reliance on any Documentation which, in accordance with Sub-clauses 21.12 and 21.13, the Subcontractor is to correct at his own
cost..
21.14 Provided that the Contractor complies with Sub-clause 4.3 and submits a claim in
accordance with Sub-clause 19.5, the Subcontractor shall reimburse to the Contractor
any cost of abortive activity which the Contractor has incurred in reliance on any
Documentation which, in accordance with Sub-clauses 21.12 and 21.13, the
Subcontractor is to correct at his own cost. The liability of the Subcontractor to make
such reimbursements shall not exceed in aggregate one per cent of the Subcontract
Price.
22.1 The Purchaser (and any authorised nominee), Project Manager, Contractor
and/or Contract Manager shall be entitled at all times to have access to any place where
work under the Subcontract is being carried out or Subcontract Materials are being
manufactured or fabricated, for the purpose of checking the progress of manufacture or
fabrication, inspecting and observing the work or carrying out tests on the work or
Subcontract Materials. The Contract Manager shall give reasonable notice of the access
and facilities he, the Purchaser (and any authorised nominee), Project Manager and/or
Contractor require and the Subcontractor shall secure such access and facilities both at
those premises under his own control and those under the control of his Sub-
subcontractors.
22.2 The Subcontractor shall arrange and be responsible for all factory and other off-site tests
and those, if any, carried out at the Site prior to installation, including those listed in
Schedule 13 (Pre-installation tests and procedures), and shall provide the Contract
Manager with copies of the test results in accordance with the quality assurance system
described in Schedule 6 (Quality assurance and validation).
22.2 The Subcontractor shall arrange and be responsible for all factory and other
off-site tests and those, if any, carried out at the Site prior to installation, including those
listed in Schedule 13 (Pre-installation tests and procedures), and shall provide the
Contract Manager with copies of the test results in accordance with the quality assurance
system described in Schedule 6 (Quality assurance and validation) and any other
information reasonably requested by the Contractor for the purpose of bona fide disputes
22.3 Whenever the Subcontractor is ready to conduct a pre-installation test he shall notify the
Contract Manager of the place and time at which he intends to conduct it, the time being
not less than fourteen days later than the date of such notification. The Subcontractor
shall conduct the test at the time and place so notified.
If the Contract Manager and/or the Project Manager do not attend the test, the
Subcontractor shall nevertheless be entitled to carry it out in their absence, and copies of
the test results shall be deemed to be a correct record of the test provided that the test is
carried out and the results are recorded in accordance with the quality assurance system
specified in Schedule 6.
22.4 The Contract Manager may require any additional pre-installation test not described in
Schedule 13 to be conducted for the purpose of deciding whether any work or
Subcontract Materials are in accordance with the Subcontract. The Contract Manager
shall notify the Subcontractor of any such requirement by means of a Variation Order in
sufficient time to enable the Subcontractor to conduct such test without impeding the
performance of his other obligations under the Subcontract. Sub-clauses 22.2 and 22.3
shall apply to any such test. Unless the additional test is one that is normally conducted
as part of the practice of the place where work is being done or Subcontract Materials
are being manufactured or fabricated, the Subcontractor shall be entitled to an addition
to the Subcontract Price determined in accordance with and subject to Clause 19
(Claims).
22.5 The Subcontractor shall provide or shall arrange for the provision of all labour, materials
and equipment necessary for the proper carrying out of all pre-installation tests under this
Clause 22.
22.6 If any item of work or Subcontract Materials fails to pass any pre-installation test, the
Subcontractor shall either rectify or replace the relevant item and, unless the Contract
Manager dispenses with a repetition of the test, shall repeat the test following a further
notification given under Sub-clause 22.3. The period of such notification may however be
less than fourteen days if a lesser period is reasonable in the circumstances.
22.7 The Subcontractor shall be responsible for the cost of any repeat inspection or test in the
event of an inspection or test failure.
22.8 The rights of the Contract Manager under this Clause 22 may be exercised by any
authorised nominee of the Contract Manager. The rights of the Project Manager under
Sub-clause 22.1 may be exercised by any authorised nominee of the Project Manager.
23.1 The Contractor shall give the Subcontractor access to and possession of the Site or
parts of the Site:
(a) by or before the relevant date or dates specified in the Subcontract; or
(b) if no such date or dates are specified, then in accordance with the Approved
Programme; or
(c) if there is no Approved Programme, or if no such date or dates are specified
then in reasonable time to permit the Subcontractor to perform his obligations
under the Subcontract.
Such access and possession shall continue until the issue of the Take Over Certificate.
Following issue of the Take Over Certificate and in accordance with the Subcontract the
Contractor shall allow such access as is necessary for the Subcontractor to correct
Defects and to perform his other rights and obligations under the Subcontract.
23.2 Unless the Subcontract otherwise provides, the Contractor shall arrange that the Site
includes a suitable right of access for the Subcontractor from a convenient point on the
public highway.
The Subcontractor shall be deemed to have satisfied himself as to the suitability and
availability of routes to the Site and of the power, water and other utilities which he
chooses to use. The Subcontractor shall obtain any permission that may be required
from the relevant authorities for the use of such route or utility. Except for information
provided in accordance with Sub-clause 4.1, the Contractor does not guarantee and
makes no representation as to the suitability or availability of any route or utility but shall
provide such assistance as the Subcontractor may reasonably require in obtaining any
necessary permission for the use of any route or utility.
The Subcontractor shall be deemed to have satisfied himself as to the suitability and
availability of routes to the Site and of the power, water and other utilities which he
chooses to use. The Subcontractor shall obtain any permission that may be required from
the relevant authorities for the use of such route or utility. Except for information provided
in accordance with Sub-clause 4.1, the Contractor does not guarantee and makes no
representation as to the suitability or availability of any route or utility but shall provide
such assistance as the Subcontractor may reasonably require in obtaining any necessary
permission for the use of any route or utility. If the Subcontract Works involve the use by
the Subcontractor of waterborne transport, this Sub-clause 23.2 shall be construed as
though 'road' or 'route' includes a river, canal, lock, dock, sea wall or other structure
related to a waterway, berth or port and 'traffic' includes any kind of waterborne craft, and
shall have effect accordingly.
23.3 The Subcontractor shall use every reasonable means to prevent any of the roads
(including temporary roads), railways (if any), and all associated bridges and other
structures connecting with or on routes to the Site from being damaged by any traffic
(including in particular, any traffic deemed to be ‘extraordinary traffic’ within the meaning
of Legislation) generated by the Subcontractor or any Sub-subcontractor. In order to
avoid unnecessary damage to any such roads, railways, bridges or other structures, the
Subcontractor shall select appropriate routes and vehicles or restrict and distribute loads
such that the movement to or from the Site of Subcontractor’s Equipment, Subcontract
Materials (and, if in the Subcontractor’s possession, any Free-lssue Materials) or plant
is limited as far as reasonably possible.
The Subcontractor shall use every reasonable means to prevent any of the roads
(including temporary roads), railways (if any), and all associated bridges and other
structures connecting with or on routes to the Site from being damaged by any traffic
(including in particular, any traffic deemed to be 'extraordinary traffic' within the meaning
of Legislation) generated by the Subcontractor or any Sub-subcontractor. In order to
avoid unnecessary damage to any such roads, railways, bridges or other structures, the
Subcontractor shall select appropriate routes and vehicles or restrict and distribute loads
such that the movement to or from the Site of Subcontractor's Equipment, Subcontract
Materials or plant is limited as far as reasonably possible.
The Subcontractor shall indemnify the Contractor against all claims for damage to any
such roads, railways, bridges or other structures caused by such traffic, including, but not
limited to, claims made by any competent authority directly against the Contractor and/or
the Purchaser pursuant to any applicable Legislation
If the Subcontract Works involve the use by the Subcontractor of waterborne transport,
this Sub-clause 23.3 shall be construed as though ‘road’ or ‘route’ includes a river, canal,
23.4 The Subcontractor shall ensure that every aspect of and all operations connected with
the Subcontract Works are carried out so as not to damage or to interfere unnecessarily
with any of the operations being carried out by others on or about the Site or with the
convenience of the public or the access to or to the occupation and use of any public or
private property.
23.4 The Subcontractor shall ensure that every aspect of and all operations
connected with the Subcontract Works are carried out so as not to damage or to interfere
unnecessarily with any of the operations being carried out by others on or about the Site
or with the convenience of the public or the access to or to the occupation and use of any
public or private property, including, for the avoidance of doubt, the activities of
Associated British Ports and their tenants at the Barry Port
23.5 The Subcontractor shall permit the Purchaser, the Project Manager, the Contractor
and the Contract Manager and their personnel to enter the Site at all reasonable hours
for the purpose of inspecting the Subcontract Works, receiving training or carrying out
their work whether or not under or in connection with the Subcontract or the Main
Contract. The Subcontractor shall also permit other contractors or suppliers engaged by
the Contractor or the Purchaser whether or not under or in connection with the Main
Contract to enter the Site and carry out work or deliver goods at all reasonable hours, but
unless the Subcontract expressly provides otherwise, the Subcontractor shall not be
required to allow them to have such access or facilities as would significantly interfere
with the performance of his obligations under the Subcontract.
23.6 The Subcontractor shall not permit to enter the Site any person whose presence on the
Site is not necessary for the carrying out of the Subcontract Works or for the carrying out
of other work on behalf of the Contractor or the Purchaser without the prior consent of
the Contract Manager.
23.7 The Subcontractor shall take full account of and comply with the Contractor’s and the
Purchaser’s site and security rules for contractors and ensure that his Sub-
subcontractors do likewise.
24.2 Unless otherwise agreed with the Contract Manager, the Subcontractor shall not deliver
or cause to be delivered anything to the Site until adequate facilities have been provided
at the Site for its proper unloading and storage.
24.5 The Subcontractor shall bear the risk and be liable for any loss of or damage to
Subcontract Materials until they are delivered to the Site irrespective of any fault or
negligence of the Contractor or the Contract Manager.
24.6 If the Subcontractor first takes possession of any Free-lssue Materials at a location
other than the Site, then the Subcontractor shall bear the risk and be liable for any loss
of or damage to any such Free-lssue Materials from the time when the Subcontractor
first takes possession of them until delivery to the Site irrespective of any fault or
negligence of the Contractor or the Contract Manager.
25.2 Whenever the ownership of any Subcontract Materials passes to the Contractor or the
Purchaser prior to delivery to the Site, the Subcontractor shall arrange for the
Subcontract Materials to be marked as the Contractor’s or Purchaser’s property as the
case may be and shall ensure that they are stored and handled separately from other
materials.
25.3 When so requested, the Subcontractor shall provide to the Contract Manager proof of
ownership and its transfer to the Contractor or the Purchaser.
26.1 The Contractor and the Subcontractor shall comply with all health, safety and envir-
onmental Legislation.
Without prejudice to the generality of the foregoing obligation, the Subcontract Works
shall be carried out in compliance with the Health and Safety at Work Act 1974 (as
amended by Schedule 2 to the Consumer Protection Act 1987) and all applicable
Regulations made thereunder, including the Construction (Design and Management)
Regulations 2007 or any statutory re-enactment or amendment thereof for the time being
in force.
26.2 The Subcontractor shall be responsible for the safety of his own operations and those of
any Sub-subcontractor and shall ensure that:
(a) a safe working environment is maintained at all times;
(b) all persons on the Site, whether or not employed by the Subcontractor or any
Sub-subcontractor, are properly protected from risk of injury and danger to
health arising out of or in connection with the carrying out of the Subcontract
Works;
(c) all property under his control is properly protected from damage or loss;
(d) it does not cause damage or loss to any equipment supplied under the Boiler Supply Contract and feedstock supplied by the
Purchaser to enable testing and commissioning to take place and the resulting ash;
(e)
(f) all construction activities are subject to appropriate risk assessment and that
relevant construction method statements are issued;
(g) any hazardous material is identified and suitable safety notices issued; and
(h) any hazardous material for which he is responsible is safely contained or
removed from the Site.
26.3 The Subcontractor shall be responsible for the provision of all necessary safety
equipment, materials, first aid and emergency arrangements throughout the duration of
the construction activities as further described in Schedule 4 (Health & Safety) except as
may be provided by the Contractor as further described in Schedule 3 (Responsibilities
of Contractor).
26.4 The Subcontractor shall ensure that his personnel, Sub-subcontractors, and
anybody working under their control shall be familiar with, and shall at all times comply
strictly with, the requirements stated in Schedules 4 and 5 (Environmental protection &
waste disposal) and any site safety regulations, safe working procedures and health and
safety instructions issued to the Subcontractor from time to time by the Contract
Manager or the Contractor and shall further ensure that where necessary his or his Sub-
subcontractor’s personnel have undergone suitable safety training and certification.
26.5 Without prejudice to the Subcontractor’s general responsibility for safety as stated in
Sub-clauses 26.1 and 26.2, the Subcontractor shall:
(a) take due notice of all instructions or advice given by the Contractor’s or the
Purchaser’s designated Health and Safety Supervisor; and
(b) nominate a competent person to be responsible for the proper observance of all
safety requirements and procedures during work on the Site.
26.6 The Subcontractor shall ensure that none of his or any Sub-subcontractor’s
personnel performs any activity relating to the performance of the Subcontract Works
under the influence of intoxicating liquor, drugs or other similar substances.
26.7 The Subcontractor shall indemnify the Contractor against any clean-up cost that results
from any escape or release of hazardous or polluting material:
(a) from any Subcontractor’s Equipment or Subcontract Temporary Works;
or
(b) which occurred prior to the issue of the relevant Take Over Certificate and was
caused by a failure of the Subcontractor to exercise the reasonable skill and care
to be expected of a properly qualified and competent subcontractor; or
(c) which occurred after the issue of the relevant Take Over Certificate and before
the issue of the relevant Final Certificate and was sudden or accidental and was
caused by a failure of the Subcontractor to exercise the reasonable skill and care
to be expected of a properly qualified and competent subcontractor.
Each indemnity shall relate only to clean-up costs that are reasonably incurred in order to
comply with Legislation, the Lease, or as a result of the reasonable requirements of a
regulatory body
Liability for any loss or damage which may result from the escape or release of hazardous
or polluting material other than clean-up costs shall be in accordance with Clause 30
(Care of the Subcontract Works).
27.2 The facilities and services to be provided by the Subcontractor shall include but not be
limited to: temporary roads and parking; temporary offices, stores and warehousing;
communications; sanitary and canteen facilities for persons engaged in the Subcontract
Works; cleaning and other services; and all necessary or specified safety, security, fire-
fighting, first aid and other medical facilities.
27.2 The facilities and services to be provided by the Subcontractor shall include all
those required for the successful completion of the subcontract works with the exclusion
of those facilities and services provided by the Contractor as stated in Schedule 3
27.3 All temporary buildings, structures, equipment and facilities provided by the Subcon-
tractor at the Site shall be properly maintained and cleaned by the Subcontractor, and at
all times during the carrying out of the Subcontract Works the Site shall be kept by the
Subcontractor in a safe, clean and orderly condition and reasonably free from waste
materials and rubbish.
27.6 The Subcontractor shall not remove Subcontractor’s Equipment from the Site or
dismantle or remove Subcontract Temporary Works without the prior consent of the
Contract Manager, but the Contract Manager shall not refuse consent if the
Subcontractor’s Equipment or Subcontract Temporary Works are no longer required
for the carrying out of the Subcontract Works.
28.3 The Subcontractor shall comply with any general agreement made between repre-
sentatives of workmen and employers who will be engaged in work at the Site as to the
rates of wages and allowances to be paid to and general working conditions for workmen
employed at the Purchaser’s premises where the Site is situated, provided that such
agreement was either already in force at the date of the Subcontractor’s tender as stated
in the Subcontract Agreement or is one to which the Subcontractor is already or
becomes a party.
28.4 The Subcontractor shall ensure the immediate removal from the Site of any person,
other than the Subcontractor’s Site Manager or a member of his Site staff to whom Sub-
clause 12.5 applies, whom the Contract Manager shall by notice require to be removed
for reason of misconduct, incompetence or material breach of any of the rules,
requirements, regulations, procedures and instructions referred to in Sub-clauses 23.7
and 26.4. Provided it is given in good faith and does not amount to unlawful
discrimination, any Decision given by the Contract Manager under this Sub-clause 28.4
shall be final, conclusive and binding. The Contract Manager shall not delegate the
power to give a notice under this Subclause 28.4. The Contractor shall have no obligation
to pay the Subcontractor for replacing the person.
28.5 Unless otherwise stated in the Subcontract, the Subcontractor shall not, except in an
emergency, carry out any work on the Site at times outside the normal working hours, if
any, specified in Schedule 1 (Description of the Subcontract Works) without the prior
agreement of the Contract Manager.
29. Meetings
29.1 Meetings to review progress and discuss matters relating to the Subcontract Works shall
be held on a regular basis on dates to be fixed by the Contract Manager. The
Subcontractor also may request that a meeting be held at another time if the circum-
stances require it, and the Contract Manager shall not unreasonably reject such a
request. Meetings shall be attended by the Contract Manager or the Contract
Manager’s Representative and by the Subcontract Manager or Subcontractor’s Site
Manager and may be attended by other persons, including the Project Manager and/or
representatives of Sub-subcontractors, as appropriate.
29.2 The Contract Manager shall provide a person to record the proceedings of each
meeting. Within seven days of the meeting the Contract Manager shall give two copies
of the records signed by him to the Subcontract Manager. If the Subcontract Manager
accepts the records as sufficient and accurate, he shall sign one copy and return it to the
Contract Manager within a further seven days. If not, the Subcontract Manager shall
agree any modification with the Contract Manager and the amended copies shall be
signed by both of them. If agreement cannot be reached upon any modification to the
record of the meeting, the disagreements remaining shall be noted and attached to all
copies of the record.
29.3 Only records signed by both the Subcontract Manager and the Contract Manager
shall constitute approved records for the purposes of Sub-clause 5.3.
30.2 In this Clause 30, ‘Personnel’ of a legal entity means any person engaged by and working
under the direction and control of that legal entity.
30.3 The Subcontract Plant and Subcontract Temporary Works shall be under the
care and control of the Subcontractor until the Subcontract Plant is Taken Over
by the
30.5 The Subcontractor shall have no liability for loss or damage to the Subcontract
Plant, Site Materials and Subcontract Temporary Works if such loss or damage
is due to a Contractor’s Risk.
30.6 Subject to Sub-clause 30.5, the Subcontractor’s liability for the loss of or damage to the
Subcontract Plant, Site Materials and Subcontract Temporary Works, including his
obligations under Sub-clause 30.4, shall be limited to:
(a) the lesser of:
(i) the Deductible; or
(ii) the actual value of each claim to which the Deductible shall apply;
plus
(b) any cost that the Subcontractor would have incurred under Clause 37 (Liability
for Defects) if replacement or rectification of any Defect in the Subcontract Plant
and/or Subcontract Temporary Works had been put in hand immediately prior to
the physical loss of or damage to the Subcontract Plant and/or Subcontract
Temporary Works.
30.7 The Contractor shall indemnify the Subcontractor in respect of any Cost of making good
loss of or damage to the Subcontract Plant, Site Materials and/or Subcontract
Temporary Works in accordance with Sub-clause 30.4 that is in excess of the
Subcontractor’s liability under Sub-clause 30.6 irrespective of any fault or negligence of
the Subcontractor or any Sub-subcontractor.
30.8 To the extent that the Cost of making good loss of or damage to the Subcontract Plant,
Site Materials and/or Subcontract Temporary Works in accordance with Sub-clause
30.4 exceeds the Subcontractor’s liability under Sub-clause 30.6 the performance of
such obligation shall be conditional upon:
(a) the Contractor confirming that sufficient funds are available to the Subcontractor
from the Contractor to implement and complete such work; and
(b) the terms of payment of such funds are agreed between the Subcontractor and
the Contractor.
30.8 To the extent that the Cost of making good loss of or damage to the Subcontract
Plant, Site Materials and/or Subcontract Temporary Works in accordance with
Sub-clause 30.4 exceeds the Subcontractor's liability under Sub-clause 30.6 the
performance of such obligation shall be conditional upon:
(a) the Contractor confirming that sufficient funds are available to the Subcontractor
from the Contractor to implement and complete such work; and
(b) the terms of payment of such funds are agreed between the Subcontractor and
the Contractor.
To the extent that the Purchaser and/or the Contractor is unable to recover such
Cost under an insurance policy as a result of the act or omission of the
Subcontractor or its agents, employees or sub-contractors, the Subcontractor
shall reimburse such funds to the Contractor 15 Business Days of an invoice.
Such liability to reimburse shall be outside of all caps/limits of liability and the
Contractor may set off against such amount any undisputed amounts owing to it
by the Subcontractor.
30.10 The Subcontractor shall indemnify the Purchaser, the Contractor, the Project Manager
and any Affiliate of the Purchaser or of the Contractor against all damages, liabilities,
claims, costs and expenses in respect of the death, illness or injury to:
(a) Personnel of the Subcontractor; and
(b) Personnel of a Sub-subcontractor;
irrespective of any fault or negligence of the Purchaser, the Contractor, the Project
Manager or any Affiliate of the Purchaser or of the Contractor.
30.11 The Contractor shall indemnify the Subcontractor and any Sub-subcontractor
against all damages, liabilities, claims, costs and expenses in respect of the death, illness
or injury to:
(a) Personnel of the Purchaser, the Contractor or the Project Manager;
(b) Personnel of any Affiliate of the Purchaser or of the Contractor;
(c) Personnel of any other contractor employed by the Purchaser or the Contractor
and not by the Subcontractor; and
(d) the Project Manager or the Contract Manager;
irrespective of any fault or negligence of the Subcontractor or any Subsubcontractor.
30.12
30.12 The Subcontractor shall indemnify the Contractor against all losses, damages, liabilities,
claims, costs and expenses of the Subcontractor and/or any Sub-subcontractor which it
suffers or incurs in respect of loss of or damage to:
30.13 The Subcontractor shall indemnify the Purchaser and the Contractor and any
Affiliate of the Purchaser or of the Contractor against all losses, damages, liabilities,
claims, costs and expenses in respect of loss of or damage to:
(a) the property of the Purchaser (other than any Free-lssue Materials which form
part of the Site Materials or which are covered by Sub-clause 24.6);
(b) the property of the Contractor (other than Subcontract Plant, Site
Materials, Subcontract Temporary Works and any Free-lssue Materials
which are covered by Sub-clause 24.6); and
(c) the property of any Affiliate of the Purchaser or of the Contractor;
to the extent caused by the wrongful or negligent act or omission of the Subcontractor,
any Sub-subcontractor, or the Personnel of the Subcontractor or any Sub-
subcontractor. The Subcontractor’s total aggregate liability to the Purchaser, the
Contractor and any Affiliate of the Purchaser or of the Contractor shall be limited to the
amount as may be stated in the Subcontract Agreement or, if no such sum is stated, to
£5,000,000 (five million pounds) in respect of any one incident or series of incidents
arising from any one event.
30.14 Subject to Sub-clause 30.13, the Contractor shall indemnify the Subcontractor and any
Sub-subcontractor against all damages, liabilities, claims, costs and expenses in respect
of loss of or damage to:
(a) the property of the Purchaser (other than any Free-lssue Materials which form
part of the Site Materials or which are covered by Sub-clause 24.6);
30.15 Subject to Sub-clause 30.11 and 30.14, the Subcontractor shall indemnify the
Purchaser and the Contractor against all damages, liabilities, claims, costs and
expenses in respect of loss of or damage to:
(a) the property of a third party; and
(b) the death, illness or injury to a third party;
to the extent caused by the wrongful or negligent act or omission of the Subcontractor,
any Sub-subcontractor, or the Personnel of the Subcontractor or any Sub-
subcontractor.
30.16 The Subcontractor shall indemnify the Contractor against all damages, liabilities, claims,
costs and expenses which it suffers or incurs in respect of loss of loss or damage to:
(b) feedstock supplied by the Purchaser to enable testing and commissioning to take place
and the resulting ash;
to the extent caused by any act or omission or breach of law of the Subcontractor, any Sub-
subcontractor, or the Personnel of the Subcontractor or any Sub-subcontractor.
31. Insurance
31.1 The Contractor shall provide and maintain, or shall ensure that the Purchaser provides and
maintains, a policy or policies of insurance in the joint names of the Contractor,
Subcontractor and Sub-subcontractors, covering all risks (subject to standard
exclusions) of loss of or damage to the Subcontract Plant, Site Materials and
Subcontract Temporary Works to the full cost of their reinstatement
31.2 The Subcontractor shall procure or arrange the provision of an all risk policy or policies of
insurance in the joint names of the Contractor and the Subcontractor covering the full
replacement value of all Subcontract Materials against loss or damage until delivery to
the Site. If the Subcontractor first takes possession of any Free- Issue Materials at a
location other than the Site, then the policy shall additionally cover such Free-lssue
Materials from the time when the Subcontractor first takes possession of them until
delivery to the Site.
The insurance shall contain a waiver of all rights of subrogation against the Contractor,
the Purchaser and the Project Manager.
31.3 The Subcontractor shall procure or arrange the provision of a policy or policies of
insurance covering loss or damage to the Subcontractor’s Equipment to the full
replacement value of the Subcontractor’s Equipment and becoming effective on the
commencement of the Subcontract Works or the date of the Subcontract Agreement
(whichever is earlier) and remaining in place until the issue of the last Final Certificate.
The insurance shall contain a waiver of all rights of subrogation against the Contractor,
the Purchaser and the Project Manager.
31.4 The Subcontractor shall provide and maintain a policy or policies of third party liability
insurance with insurers approved by the Contractor covering liability for death, illness or
injury to persons and loss of or damage to property for such sum as the Subcontractor
considers appropriate, but in any event not less than £10,000,000 (ten million pounds).
The insurance shall contain an indemnity to principals clause. The insurance shall
become effective on the commencement of the Subcontract Works or the date of the
Subcontract Agreement (whichever is sooner) and shall remain in place until the issue of
the last Final Certificate.
31.5 The Subcontractor and the Contractor shall each effect and maintain Employer’s Liability
insurance in accordance with Legislation.
31.6 The provisions of this Clause 31 shall not oblige the Subcontractor to take out and
maintain a policy of professional indemnity insurance.
[The provisions of this Clause 31 shall not oblige the Subcontractor to take out and maintain a
policy of professional indemnity insurance.]
31.7 The Subcontractor shall obtain the approval of the Contractor in respect of the insur-
ances to be provided under Sub-clause 31.2 and each party shall provide to the other
details of the other insurances he is required to provide (or ensure are provided) by the
Subcontract or by Legislation. Each party shall also provide details in a timely manner of
any additions or restrictions thereto which may be made from time to time. Each party
shall provide to the other evidence of the payment of premiums.
If either party fails to produce satisfactory evidence that he has obtained and maintained
any insurance required by the Subcontract (or that he has ensured that such insurance
has been obtained and maintained) the other party shall be free, having given seven days
notice of his intention, to provide and maintain such insurance and pay the premium as
may be necessary for that purpose. The cost of such premium shall be reimbursed by the
defaulting party within twenty-eight days of being notified of the amount.
The Subcontractor shall obtain the approval of the Contractor in respect of the insurances
to be provided by the Subcontractor under this clause 31 and each party shall provide to
the other details of the other insurances he is required to provide (or ensure are provided)
by the Subcontract or by Legislation. Each party shall also provide details in a timely
manner of any additions or restrictions thereto which may be made from time to time.
Each party shall provide to the other evidence of the payment of premiums.
If either party fails to produce satisfactory evidence that he has obtained and maintained any
insurance required by the Subcontract (or that he has ensured that such insurance has
been obtained and maintained) the other party shall be free, having given seven days
notice of his intention, to provide and maintain such insurance and pay the premium as
may be necessary for that purpose. The cost of such premium shall be reimbursed by the
defaulting party within twenty-eight days of being notified of the amount
31.8 The Subcontractor shall not (and shall procure that none of its Sub-subcontractors shall
not) take any action or fail to take any reasonable action, or (insofar as it is reasonably
within its power) permit anything to occur in relation to it, which would entitle any insurer
to refuse to pay any claim under any insurance policy which either party and/or the
Purchaser is obliged to take out and maintain in accordance with the Subcontract and/or
the Main Contract. The Subcontractor shall provide information reasonably requested by
the Contractor for the purpose of bona fide disputes or insurance claims.
32.2 As soon as the Subcontract Plant, or any part of it, is in the opinion of the Subcontractor
substantially complete and ready for inspection he shall so notify the Contract Manager
by means of a draft of a certificate (a Construction Completion Certificate), listing the
parts of the Subcontract Plant considered to be substantially complete and also the
criteria (which may include any test) listed in Schedule 14 (Criteria for the completion of
construction) which apply to such parts of the Subcontract Plant. The Subcontractor
shall propose a programme for such inspection and for any tests, commencing not sooner
than ten days nor later than seventeen days after the date of the notification unless the
Contract Manager agrees otherwise. If the Contract Manager requires the Subcontract
Plant to comply with any criteria which are not included in Schedule 14, he shall order a
Variation.
32.3 Unless otherwise agreed between the Contract Manager and the Subcontractor, the
Subcontractor shall begin such inspection and tests at the time notified and carry them
out in accordance with the quality assurance system specified in Schedule 6 (Quality
assurance and validation). The Project Manager and the Contract Manager shall be
entitled to attend and observe them. The Subcontractor shall give the Project Manager
and the Contract Manager every reasonable facility to satisfy themselves as to the
results of the tests.
32.4 Unless the Subcontract otherwise provides, or the Subcontractor and the Contract
Manager otherwise agree, the Subcontractor shall provide all labour, materials and
equipment necessary for the carrying out of the inspection and tests.
32.5 If the Project Manager and/or the Contract Manager do not attend any inspection or test
in accordance with Sub-clause 32.3, the Subcontractor shall nevertheless be entitled to
carry it out in their absence, and copies of the test results shall be deemed to be a correct
record of the test provided that the test is carried out and the results are recorded in
accordance with the quality assurance system specified in Schedule 6.
32.6 Upon satisfactory completion of any such inspection and tests, the Contract Manager
shall complete and issue to the Subcontractor with a copy to the Contractor the
completed Construction Completion Certificate confirming that the Subcontractor has
demonstrated to the Contract Manager that the Subcontract Plant or any part of it is
substantially complete and in a condition such that any procedures needed to be carried
out before the Subcontract Plant is put into operation may be safely carried out. Such
Construction Completion Certificate may include a note of any minor items requiring
completion before the issue of a Take Over Certificate.
32.7 If the Contract Manager is not satisfied that the Subcontract Plant or any part of it listed
in a draft Construction Completion Certificate in accordance with Subclause 32.2 is
substantially complete (including complying with the criteria required by Schedule 14), he
may endorse the draft Construction Completion Certificate
accordingly, stating in what way the Subcontract Plant or part is incomplete (including
not being in accordance with Schedule 14). The Subcontractor shall then complete the
Subcontract Plant or part as necessary and shall repeat the procedure described in Sub-
clause 32.2.
Sub-clause 22.7 shall apply to any repeat inspection or test.
32.9 Any disagreement arising underthis Clause 32 concerning the issue of a Construction
Completion Certificate which is not settled in accordance with Clause 46 (Disputes) may
be referred to an Expert in accordance with Clause 48 (Reference to an Expert).
33.2 As soon as the construction of the Subcontract Plant has been demonstrated to be
complete in accordance with Clause 32 (Completion of construction) and is, in the opinion
of the Subcontractor, ready for carrying out any of the take over procedures (which may
include take over tests) specified in Schedule 15 (Take Over procedures), the
Subcontractor shall so notify the Contract Manager and shall specify a time not sooner
than ten days and not later than seventeen days after the date of the notification when the
Subcontractor intends to begin to carry out such procedures. If the Contract Manager
requires the Subcontractor to carry out any take over procedures which are not included
in Schedule 15, he shall order a Variation.
33.3 Unless otherwise agreed between the Contract Manager and the Subcontractor, the
Subcontractor shall begin such procedures at the time notified and carry them out in
accordance with the quality assurance system specified in Schedule 6 (Quality
assurance and validation). The Project Manager and the Contract Manager shall be
entitled to attend and observe them. The Subcontractor shall give the Project Manager
and the Contract Manager every reasonable facility to satisfy themselves as to the
results of any take over tests.
33.4 Unless the Subcontract otherwise provides, or the Subcontractor and the Contract
Manager otherwise agree, the Subcontractor shall provide all labour, materials and
equipment necessary for the carrying out of the take over procedures.
33.5 If the Project Manager and/or the Contract Manager do not attend any take over
procedure in accordance with Sub-clause 33.3, the Subcontractor shall nevertheless be
entitled to carry it out in their absence, and copies of the test results shall be deemed to
be a correct record of the test provided that the test is carried out and the results are
recorded in accordance with the quality assurance system specified in Schedule 6.
33.6 If the Subcontract Plant fails to pass a take over test, the Subcontractor, after making
such adjustments as he considers necessary, shall repeat such test at a time agreed
between the Subcontractor and the Contract Manager, or notified in accordance with
Sub-clause 33.2, and the Project Manager and the Contract Manager shall be entitled
to attend and observe the test. If the Contract Manager is of the opinion that any such
adjustment made by the Subcontractor makes it desirable, he may require the
Subcontractor to repeat any take over test which has already been successfully carried
out, and the Subcontractor shall do so. Subject only to this Sub-clause 33.6 the
Subcontractor shall not be bound to repeat for the purposes of this Clause 33 any take
over test that has already been successfully carried out.
Sub-clause 22.7 shall apply to any repeat take over test.
33.7 As soon as any minor items referred to in Sub-clause 32.6 have been completed and,
subject to Sub-clause 33.10, all the procedures specified in Schedule 15 have been
successfully carried out, including any which affect the operability or safety of the
Subcontract Plant, the Contract Manager shall issue a certificate (a Take Over
Certificate) for the Subcontract Plant to the Subcontractor with a copy to the
Contractor stating that the Subcontractor has satisfied the requirements of the
Subcontract Specification and Schedule 15, whereupon the Subcontract Plant, apart
from any parts that are excluded from the Taking Over by the terms of the
33.8 As soon as shall be reasonably possible afterthe issue of the Take Over Certificate the
Subcontractor shall complete to the satisfaction of the Contract Manager all items noted
on the Take Over Certificate as not being complete at the date of the Take Over
Certificate. If the Subcontractor fails so to do the Contract Manager may
arrange for such work to be carried out by others in accordance with Sub-clause 37.6.
33.9 Notwithstanding the failure of the Subcontract Plant to pass any take over test or if
certain procedures have not been carried out, the Contract Manager may with the
Subcontractor’s consent issue a Take Over Certificate in respect of the Subcontract
Plant. Such a Certificate may either exclude from Taking Over such parts of the
Subcontract Plant as are specified, being parts for which the specified procedures have
not been carried out, or may specify the take over tests which the Subcontract Plant has
failed to pass. In either case the Subcontractor shall carry out any omitted procedure or
repeat any test which the Subcontract Plant has not passed as and when required by the
Contract Manager who shall give ten days notice of such requirement. The
Subcontractor shall become entitled to a separate Take Over Certificate as soon as the
applicable take over procedures have been completed satisfactorily.
33.10 If in the opinion of the Subcontractor he has been prevented from carrying out any take
over procedure as provided in this Clause 33 by reason of any act or omission of the
Contractor or of the Contract Manager, or of the Purchaser or of the Project Manager,
or of some other contractor employed by the Contractor or the Purchaser, then when
any other relevant take over procedures have been successfully completed, the
Subcontractor may request the Contract Manager to issue a Take Over Certificate.
The Contract Manager shall, if in his opinion such action is reasonable, issue such a
Certificate which shall have effect as stated in Sub-clause 33.7. The Subcontractor shall
during the Defects Liability Period carry out any omitted take over procedure as and
when required by the Contract Manager who shall give ten days notice of such
requirement.
Any disagreement arising under this Sub-clause 33.10 concerning the Contract
Manager’s refusal to issue such a Take-Over Certificate which is not settled in
accordance with Clause 46 may be referred to an Expert in accordance with Clause 48.
The Contract Manager or the Contractor has the right to prevent the Subcontractor from performing
any of the Take Over Tests. If the Take Over Tests are not able to commence or are
suspended in part or whole because of a delay which is caused by or is the responsibility
of the Contractor the Subcontractor shall be entitled to an extension of time (subject to
and in accordance with clauses 14.4(c), (d) or (e) inclusive) and the Subcontractor shall
notify the Contract Manager under clause 14.1. As soon as reasonably possible after the
suspension of the Schedule 15 testing, the Subcontractor and the Contract Manager shall
agree the scope of the Schedule 15 testing that remains to be completed. In any
notification issued under sub-clause 14.1 the Subcontractor shall include an assessment
of the length of the delay.
Any disagreement arising under this Sub-clause 33.10 which is not settled in accordance
with Clause 46 may be referred to an Expert in accordance with Clause 48.
33.11 Any effect on the results of a deferred take over procedure conducted in accordance with
Sub-clause 33.9 or 33.10 which can reasonably be shown to be due to the prior use of the
Subcontract Plant by the Contractor or the Purchaser shall be taken into account in
assessing such results.
If the Subcontractor incurs any additional Cost as a result of such a deferment, other
than any Cost resulting from any breach of contract by the Subcontractor, he shall be
entitled to an addition to the Subcontract Price determined in accordance with and
33.12 If the Contractor has Taken Over the Subcontract Plant as a result of the issue of a
Take Over Certificate in accordance with Sub-clauses 33.9 or 33.10 and subsequently
the Subcontract Plant fails to satisfy the requirements of any relevant take over
procedure which had previously failed or been omitted then, subject to the Subcontractor
having been given a reasonable opportunity to carry out such take over procedure
including making any necessary adjustments to the Subcontract Plant, the Contract
Manager may issue a cancellation certificate to the Subcontractor with a copy to the
Contractor stating that any Acceptance Certificate which has been deemed to be issued
in terms of Sub-clause 36.1 is cancelled. The
33.13 After the issue of a Take Over Certificate, and until the Final Certificate has been
issued, the Subcontractor shall have the right of access, together with the Contractor
and with any relevant Sub-subcontractor, during all reasonable working hours at their
own risk and cost to inspect any part of the Subcontract Plant and to take notes of the
related working, performance and maintenance records. Access shall only be allowed to
the Subcontractor’s and any Sub-subcontractor’s personnel whose names have
previously been communicated to the Contract Manager. Subject to the Contract
Manager’s and the Project Manager’s approval, the Subcontractor may at his own risk
and cost make any tests which he considers desirable, provided such tests do not
interfere unreasonably with the Purchaser’s use or maintenance of the Plant.
33.13 After the issue of a Take Over Certificate, and until the Final Certificate has
been issued, the Subcontractor shall have the right of access by himself or with any
relevant Sub-subcontractor, during all reasonable working hours at their own risk and cost
to inspect any part of the Subcontract Plant and to take notes of the related working,
performance and maintenance records under the supervision of the Contract Manager.
Access shall only be allowed to the Subcontractor's and any Sub-subcontractor's
personnel whose names have previously been communicated to the Contract Manager.
Subject to the Contract Manager's approval, the Subcontractor may at his own risk and
cost make any tests which he considers desirable, provided such tests do not interfere
unreasonably with the Purchaser's use or maintenance of the Facility.
34.1 Unless otherwise agreed with the Contract Manager, the Subcontractor shall
within ten days after the Contractor has Taken Over the Subcontract Plant dismantle and
remove all Subcontract Temporary Works and remove from the Site all waste and debris,
Subcontractor's Equipment, including temporary buildings and structures, and other
things of his, other than those that are necessary for the proper performance of the
Subcontractor's remaining obligations and shall leave the Site in an orderly and safe
condition.
34.2 As soon as the whole of the Subcontract Plant has been Accepted the Subcontractor
shall remove all his equipment and other possessions from the Site other than such
things as are then known to be required for making good Defects under Clause 37
(Liability for Defects) and any Subcontract Materials which are to be handed over to the
Contractor in accordance with Sub-clause 34.5.
or
34.4 The ownership of all Subcontract Materials removed from the Site in accordance with
Sub-clause 34.3 (a)(ii), (b) and (c) shall revert to the Subcontractor upon removal.
Subcontract Materials falling within the description of Sub-clause 34.3 (a)(i) shall be
marked as the Purchaser’s or the Contractor’s property, as instructed by the Contract
Manager, and stored and handled separately from other materials.
34.5 The Subcontractor shall remove any surplus Subcontract Materials, except that if the
parties shall so agree any surplus Subcontract Materials shall be handed over to the
Contractor by the Subcontractor before he leaves the Site and an addition to the
Subcontract Price shall be determined in accordance with and subject to Clause 19
(Claims) to take account of such Subcontract Materials being additional to the
requirements of the Subcontract Works.
If the Contractor shall so require, the Subcontractor shall remove surplus Free- Issue
Materials and dispose of them on behalf of the Contractor. The proceeds of such
disposal may be deducted from any sums that would otherwise be payable under the
Subcontract by the Contractor, or at the Contractor’s option paid by the Subcontractor
to the Contractor immediately following such disposal. Otherwise such surplus Free-
lssue Materials shall be handed over by the Subcontractor before he leaves the Site.
35.2 If the Subcontract provides for the performance of the Subcontract Plant to be tested in
Sections, Sub-clauses 35.3 to 35.17 shall apply as if a reference to the Subcontract
Plant were a reference to a Section.
35.3 The performance tests to be carried out on the Subcontract Plant shall be those
specified in Schedule 16 (Performance tests and procedures). If any unspecified test is
subsequently proposed, the Subcontractor and the Contract Manager shall discuss
whether such tests should be carried out. If they agree that the test should be carried out,
the Contract Manager shall order the test as a Variation.
35.4 The performance tests shall be commenced within the Performance Test
Commencement Period. If the performance tests have not been commenced within the
Performance Test Commencement Period the Contract Manager shall decide, subject
to Sub-clause 35.7, an appropriate extension to the Performance Test Commencement
Period.
If the performance tests have not been commenced within the Performance Test
Commencement Period because of a delay which is caused by or is the responsibility of
the Contractor and if the Subcontractor incurs additional Cost as a consequence of such
delay the Subcontractor shall be entitled to an addition to the Subcontract Price
determined in accordance with and subject to Clause 19 (Claims).
If the performance tests have not been commenced within the Performance Test
Commencement Period because of a delay which is caused by or is the responsibility of
the Subcontractor he shall not be entitled to an addition to the Subcontract Price as a
consequence of such delay.
If the performance tests have not been commenced within the Performance Test
Commencement Period because of a delay which is neither caused by nor is the
responsibility of either the Contractor or the Subcontractor the Subcontractor shall not
be entitled to an addition to the Subcontract Price as a consequence of such delay.
35.5 The performance tests shall be carried out by the Purchaser or the Contractor in the
presence of the Subcontractor, unless the Subcontractor fails or declines to attend. The
Contractor shall notify the Subcontractor and the Contract Manager at least ten days in
advance of the Purchaser’s or his readiness to carry out the performance tests, including
a proposal for the time at which the tests should commence. The Subcontractor shall
confirm, at least four days before the time proposed by the Contractor, if he will attend
35.6 The performance tests shall be carried out within the Performance Test Period.
If the performance tests have not been completed within the Performance Test Period
because of a delay which is caused by or is the responsibility of the Contractor the
Contract Manager shall, but only if the Subcontractor so agrees and subject to Sub-
clause 35.7, decide an appropriate extension to the Performance Test
Period. If the Subcontractor thereby incurs additional Cost the Subcontractor shall be
entitled to an addition to the Subcontract Price determined in accordance with and
subject to Clause 19.
If the performance tests have not been completed within the Performance Test Period
because of a delay which is caused by or is the responsibility of the Subcontractor the
Contract Manager shall, but only if the Contractor so agrees and subject to Sub-clause
35.7, decide an appropriate extension to the Performance Test Period. The
Subcontractor shall not be entitled to an addition to the Subcontract Price under this
Sub-clause 35.6 as a consequence of such delay.
If the performance tests have not been completed within the Performance Test Period
because of a delay which is neither caused by nor is the responsibility of either the
Contractor or the Subcontractor the Contract Manager shall, subject to Sub-clause
35.7, decide an appropriate extension to the Performance Test Period. The
Subcontractor shall not be entitled to an addition to the Subcontract Price under this
Sub-clause 35.6 as a consequence of such delay.
35.7 Notwithstanding any other provision of the Subcontract, the Performance Test
Commencement Period and the Performance Test Period shall end no later than
the end of the Defects Liability Period.
35.8 The performance tests shall be carried out as far as practicable under the conditions
detailed in Schedule 16. The Purchaser or the Contractor shall perform the perfor-
mance tests using suitably trained and experienced operators and in accordance with the
manuals provided by the Subcontractor in accordance with Clause 21 (Documentation)
and such other instruction as the Subcontractor may give in the course of carrying out
such tests. If any such instruction conflicts in any way with or significantly adds to the
manuals, the Subcontractor shall issue it as soon as possible as an amendment to the
manuals.
35.9 Subject to Sub-clause 35.7 every performance test shall be carried out to completion
unless an authorised representative of the Purchaser, the Contractor, the Project
Manager, the Contract Manager or the Subcontractor shall order it to be stopped
because its continuance would be unsafe or could damage the Subcontract Plant or
other property, or the Purchaser or the Contractor stops the test for any other reason.
35.10 The Contract Manager shall be responsible for ensuring that data collected during the
performance tests are a true and correct record of the tests.
The results of the performance tests shall be compiled and evaluated jointly by the
Contractor, the Contract Manager and the Subcontractor. In the absence of agreement
on the results of the performance tests, the Contract Manager shall determine the
results. Any effect on the results of the performance tests caused by prior operation of the
Subcontract Plant or arising from a delay, other than a delay which is caused by or is the
responsibility of the Subcontractor, shall be taken fully into account in assessing such
results.
Any necessary adjustments to the results of the performance tests to take account of
actual operating conditions and/or allowances for measurement tolerances shall be made
in accordance with Schedule 16, or if not stated in Schedule 16, in accordance with
good engineering practice.
35.11 If the Subcontract Plant fails to pass any performance test or if any performance test is
stopped before its completion the Contractor shall, or shall ensure that the Purchaser
shall, within a reasonable time:
(a) permit access to the Subcontract Plant by the Subcontractor to investigate the
causes of any failure to pass a performance test;
35.12 If by the end of the Performance Test Period the Subcontract Plant has failed any
performance test and provided that the results of the performance tests are within any
limit for the application of liquidated damages specified in Schedule 17, the
Subcontractor shall pay any liquidated damages due to the Contractor in accordance
with Schedule 17.
(a) It is expressly agreed that these Performance Liquidated damages do not constitute a
penalty and the parties hereby agree that the liquidated damages set out in Schedule 17
represent a genuine pre-estimate of losses likely to be suffered by the Contractor in the
event of a shortfall in Subcontract Plant performance and/or reliability and that such
Performance Liquidated Damages shall, subject to paragraph (b) below and save as
regards the Contractor's rights under Sub-clause 35.14 and to terminate the Subcontract
pursuant to Clause 44.2, be the Contractor's sole and exclusive remedy for the
performance shortfall referred to in this Sub-clause 35.12. The Contractor and the
Subcontractor expressly agree that each shall not raise any claim objection or defence
challenging the validity of, or otherwise questioning the reasonableness of, the
Performance Liquidated Damages specified in Schedule 17.
(b) In the event that the provisions for Performance Liquidated Damages set out in
this Sub-clause are held to be unenforceable as a result of a claim, objection, defence,
dispute or proceedings raised or brought by the Subcontractor, the Subcontractor
expressly agrees to pay the Contractor all costs, losses and damages whatsoever
(including loss of profit, loss of use and loss of production) incurred or payable by the
Contractor arising from or in consequence of the failure to pass the Performance Tests
within the Performance Test Period provided that the aggregate amount of damages
payable in such circumstances do not exceed the amount that would have been payable
had the Performance Liquidated Damages been enforceable.
35.13 If by the end of the Performance Test Period the results of any performance test remain
outside any limit for the application of liquidated damages specified in Schedule 17, the
Contractor may at his option but subject to Sub-clause 35.7 instruct the Contract
Manager to extend the Performance Test Period and instruct the Subcontractor to
investigate or to co-operate with the Contract Manager or others in the investigation of
the reasons for the shortfall in performance.
The Subcontractor shall bear his own cost of any such additional work, including any
costs associated with any repeat performance test.
35.14 Subject to Sub-clause 35.13, if by the end of the Performance Test Period the results of
any performance test are outside any limit for liquidated damages specified in Schedule
17 the Contract Manager shall determine the amount of compensation due from the
Subcontractor to the Contractor for failure of the Subcontract Plant to comply with a
35.14 Subject to Sub-clause 35.13, if by the end of the Performance Test Period the
results of any Performance Test are outside any limit for Performance Liquidated
Damages specified in Schedule 17 the Contract Manager shall determine the amount of
compensation due from the Subcontractor to the Contractor for failure of the Subcontract
Plant to comply with a guarantee stated in Schedule 17 and/or the Contractor may
terminate under Sub-clause 44.2
35.15 Subject to Sub-clause 35.16 if by the end of the Defects Liability Period:
(a) any performance test has been started but not completed (other than a repeat
performance test as described at (b) below); or
(b) any repeat performance test, to be carried out after the Subcontractor has made
any adjustment or modification to the Subcontract Plant as a consequence of a
failed earlier test, has not been completed (whether or not such repeat test was
started);
the Contract Manager shall determine the amount of compensation (if any) due from the
Subcontractor to the Contractor in respect of the performance guarantee associated with
any circumstance described at (a) or (b) above having regard to all relevant
circumstances and the results (if any) obtained from any completed or partially completed
performance test.
35.16 If for any reason which is not the responsibility of the Subcontractor any performance test
has not been started for the first time in sufficient time to allow its completion by the end
of the Defects Liability Period such performance test shall be deemed to have been
passed.
35.16 Notwithstanding any other provision of the Subcontract, where, at the end of
the Performance Test Period, the Performance Tests (or any repetition thereof)
demonstrate the Subcontract Plant's non-compliance with the Minimum Performance
Guarantee and/or that the Purchaser has been deprived of substantially the whole of the
benefit of the Subcontract Works, such failure shall be deemed to constitute a material
breach of the Subcontract which is not capable of remedy and the Contractor may
proceed to terminate the Subcontract in accordance with Sub-clause 44.2(c).
35.18 Any disagreement arising under this Clause 35 which is not settled in accordance with
Clause 46 (Disputes) may be referred to an Expert in accordance with Clause 48
(Reference to an Expert).
36.2 If the Subcontract provides for the performance of the Subcontract Plant to be tested in
Sections, Sub-clauses 36.3 to 36.5 shall apply as if a reference to the Subcontract Plant
were a reference to a Section.
36.3 As soon as the Subcontract Plant has passed all the performance tests or otherwise
Sub-clause 35.17 has been complied with, the Contract Manager shall issue to the
Subcontractor a certificate (an ‘Acceptance Certificate’) with a copy to the Contractor
stating that the Subcontract Plant is Accepted by the Contractor as from the date
thereof. The Acceptance Certificate shall list any known Defects which the
Subcontractor is bound to make good under Clause 37 (Liability for Defects) and any
minor items still remaining to be completed following the issue of a Take Over Certificate
under Sub-clause 33.7.
36.4 Acceptance of the Subcontract Plant by the Contractor shall not affect the obligations
of the Subcontractor under Clause 37.
36.5 At any time after Taking Over the Subcontract Plant, the Contractor may notify the
Subcontractor that he elects to Accept the Subcontract Plant, expressly stating that his
notification is given under this Sub-clause 36.5. The Contract Manager shall not have
authority to give such notification on the Contractor’s behalf.
The Contract Manager shall then issue an Acceptance Certificate. The Acceptance of
the Subcontract Plant under this Sub-clause 36.5 shall constitute a waiver by the
Contractor of any remaining obligation of the Subcontractor to ensure that the
Subcontract Plant passes the performance tests.
37.2 If at anytime before the Subcontract Plant is Taken Over in accordance with Clause 33
(Taking Over) or during the Defects Liability Period, the Contract Manager:
(a) decides that any matter is a Defect; and
(b) as soon as reasonably practicable notifies the Subcontractor of the particulars of
the Defect;
the Subcontractor shall as soon as reasonably practicable make good the Defect so
notified and the Contractor shall so far as may be necessary place the Subcontract
Plant at the Subcontractor’s disposal for this purpose. The Subcontractor shall, if so
required by the Contract Manager, submit his proposals for making good any Defect to
the Contract Manager for his approval.
37.3 Subject to Sub-clause 37.12, if any Defect arises from any breach of the Subcontract by
the Subcontractor the Subcontractor shall bear his own cost of making good the Defect.
In the case of any other matter made good by the Subcontractor, the work done by the
Subcontractor shall be the subject of a Variation.
Subject to Sub-clause 37.12; the Subcontractor shall bear his own cost of making good
the any Defect (Subcontractor Fault).
In the case being notified by the Contract Manager of a Variation Order relating to rectification of a
Defect (Other), the Subcontractor shall respond in accordance with the provisions and
procedures of Clause 16 (Variations). Any disagreement arising under this Sub-clause
37.2 which is not settled in accordance with Clause 46 (Disputes) may be referred to an
Expert in accordance with Clause 48 (Reference to an Expert).
37.4 If a Defect is made good after the issue of a Take Over Certificate the Contract
Manager may require the Subcontractor to repeat any appropriate take over test for the
purpose of establishing that the Defect has been made good. Sub-clause 22.7 shall apply
to any such repeat test.
37.5 If in the course of making good any Defect which arises during the Defects Liability
Period the Subcontractor repairs, replaces or renews any part of the Subcontract Plant,
this Clause 37 shall apply to that part of the Subcontract Plant so repaired, replaced or
renewed and the Defects Liability Period for such part shall commence afresh from the
date that the repair, replacement or renewal of such part was completed.
37.6 If the Subcontractor does not make good within a reasonable time any Defect which he
is liable to make good under Sub-clause 37.2 or complete any item noted on a Take
Over Certificate as described in Sub-clause 33.8 then the Contractor may, in addition to
any other remedies or relief available to him under the Subcontract, proceed to do the
work in such a manner as the Contract Manager may decide, including the employment
of a third party, provided that the Contractor gives at least ten days notice of his intention.
37.7 If the Purchaser or the Contractor reasonably requires that any Defect notified to the
Subcontractor under Sub-clause 37.2 which arises during the Defects Liability Period
be made good urgently and the Subcontractor is unable or fails to comply within a
reasonable time, the Purchaser or the Contractor may, in addition to any other remedies
or relief available to him under the Subcontract and without further notification, proceed
to do the work in such a manner as the Project Manager or the Contract Manager may
decide, including the employment of a third party.
37.7 If the Purchaser or the Contractor notifies the Subcontractor that any Defect
(Subcontractor Fault) is a Defect that is causing the Facility to be unable to export
electricity or is reducing electrical output and the Subcontractor is unable or fails to
commence works within 24 hours of such notification (or such other time as may be
reasonably agreed between the Subcontractor and the Contract Manager having due
regard for the practicalities of procuring the necessary materials to carry out the making
good), or if having commenced such works he ceases or suspends such work or does not
make good within a reasonable time (having regard to the urgency of the matter) the
Purchaser and/or Contractor may, in addition to any other remedies or relief available to
him under the Subcontract and without further notification, proceed to do the work in such
a manner as the Project Manager and/or Contract Manager may decide, including the
immediate employment of a third party.
37.8 If the Contractor, or as applicable the Purchaser, has made good a Defect in accor-
dance with Sub-clause 37.6 or 37.7, the Subcontractor shall reimburse the Contractor
his reasonable costs, or as applicable pay to the Contractor the Purchaser’s reasonable
costs, of so doing provided that the Contractor complies with Subclause 4.3 and submits
a claim in accordance with Sub-clause 19.5. The Contract Manager and the
Subcontractor may agree the amount to be paid by the Subcontractor, or in the absence
of agreement the Contract Manager shall determine such amount as may be reasonable.
Such amount shall be:
(a) deducted from any money that would otherwise be payable under the
Subcontract; or
(b) paid by the Subcontractor to the Contractor.
Any disagreement arising under this Sub-clause 37.8 which is not settled in accordance
with Clause 46 (Disputes) may be referred to an Expert in accordance with Clause 48
(Reference to an Expert).
37.9 If the Subcontract Plant cannot be used because of a Defect to which this Clause 37
applies, the Defects Liability Period shall be extended by a period equal to the period
during which it cannot be used. Similarly the Defects Liability Period shall be extended
by any period wherein the Subcontract Plant cannot be used by reason of the
37.9 If the Subcontract Plant and/or the Facility cannot be used because of a Defect
(Subcontractor Fault) to which this Clause 37 applies, the Defects Liability Period shall be
extended by a period equal to the period during which it cannot be used. Similarly the
Defects Liability Period shall be extended by any period wherein the Facility cannot be
used by reason of the Subcontractor putting or attempting to put the Subcontract Plant
into such condition that it passes any relevant Take Over procedure under Clause 33 or
any relevant Performance Test under Clause 35 (Performance tests). If a Defect
(Subcontractor Fault) is unable to be repaired because there is no required spare part at
the Site, and as a result of the Defect the Facility is unable to export electricity or there is
reduced electrical output, then the Contractor may also charge to the Subcontractor daily
liquidated damages at the rate set out in Schedule 12 during the period from the date of
receipt of the notification to the Contractor of such defect until the date on which the
Defect is made good to the satisfaction of the Contract Manager. The Parties agree that
such amount is a genuine pre-estimate of the power income losses during the outage.
37.10 If for any reason the Purchaser or the Contractor does not allow the Subcontractor
the necessary access to repair or correct any Defect, including permitting the
Subcontractor to remove any defective Subcontract Materials, the Subcontractor
shall have no obligation to make such repair. However if the Contractor merely defers the
timing of such repair or corrective work for his own or the Purchaser’s convenience the
Subcontractor shall be entitled to an addition to the Subcontract Price determined in
accordance with and subject to Clause 19 (Claims) in respect of any additional Cost
which the Subcontractor incurs as a consequence of such deferment, irrespective of the
underlying liability for the cost of the repair or corrective work. In no circumstance shall
the Contractor require the deferment of the commencement of any repair or correction
beyond the end of the relevant Defects Liability Period or any extension in accordance
with this Clause 37.
37.10 If any part of the Subcontract Plant has a guaranteed working life under normal
running conditions stated in Schedule 10 (Parts with limited working life and spare parts)
to be less than the period stated in Sub-clause 1.1 in the definition of the Defects Liability
Period, then the Defects Liability Period for such part shall be the guaranteed working life
so stated
37.11 If any part of the Subcontract Plant has a guaranteed working life under normal running
conditions stated in Schedule 10 (Parts with limited working life and spare parts) to be
less than the period stated in Sub-clause 1.1 in the definition of the Defects Liability
Period, then the Defects Liability Period for such part shall be the guaranteed working
life so stated.
37.11 The Contractor may claim in relation to Latent Defects at any time during the
Latent Defects Liability Period
37.12 If in making good Defects which appear in the Subcontract Plant after the date of the
relevant Acceptance Certificate the Subcontractor incurs any Cost in excess of the
amount stated in the Subcontract Agreement he shall be entitled to an addition to the
Subcontract Price equal to such excess provided that the Subcontractor submits a claim
in accordance with and subject to Clause 19.
38.2 If Clause 37 continues to apply to any part of the Subcontract Plant, the Contract
38.3 The Subcontractor shall have no right or obligation to do any further work to any part of
the Subcontract Plant after a Final Certificate has been issued in respect of that part
and that Final Certificate shall constitute conclusive evidence for all purposes and in any
proceedings whatsoever between the Contractor and the Subcontractor that the
Subcontractor has completed that part of the Subcontract Plant and made good all
Defects therein in all respects in accordance with his obligations under the Subcontract.
Where there is more than one Final Certificate the last to be issued shall be identified as
being the last Final Certificate.
No Final Certificate shall be conclusive as stated above if it was procured by any fraud
on the part of the Subcontractor or any Sub-subcontractor.
38.4 Save where there is an allegation of fraud, any disagreement arising under this Clause 38
concerning whether or not a Final Certificate should have been issued which is not
settled in accordance with Clause 46 (Disputes) may be referred to an Expert in
accordance with Clause 48 (Reference to an Expert).
39.2 Any money paid in respect of any indemnity under the Subcontract shall not form an
addition to the Subcontract Price, except as may be agreed in accordance with Sub-
clause 30.8(b) for any payment under the indemnity set out in Sub-clause 30.7.
40.2 The Contractor shall have the right at any time to carry out audits of such books and
records and related documents referred to in Sub-clause 40.1 and to have such audits
carried out by an auditing firm appointed by the Contractor. Such audit shall commence
no later than three hundred and sixty five days after the date of the last Final Certificate.
It shall not extend to the make-up of any fixed or unit rate or price.
40.2 The Contractor, the Contract Manager, the Purchaser and/or the Project
Manager shall have the right at any time to carry out audits of such books and records
and related documents referred to in Sub-clause 40.1 and to have such audits carried out
by an auditing firm appointed by the Contractor. Such audit shall commence no later than
three hundred and sixty five days after the date of the last Final Certificate under the Main
Contract. It shall not extend to the make-up of any fixed or unit rate or price.
41. Payment
41.1 The Contractor shall pay the Subcontractor the Subcontract Price in instalments as
provided in Schedule 19 (Subcontract Price and payment).
The Contractor shall pay the Subcontractor the Subcontract Price in instalments as
provided in Schedule 19 (Subcontract Price and payment) provided that:
(a) if the Subcontractor does not provide, within 7 days of a request from the Contractor,
collateral warranties executed by the Subcontractor and/or the collateral warranties
executed by the Sub-subcontractor in such form and in favour of such parties as
requested by the Contractor, the Contractor shall be entitled to withhold payment from the
Subcontractor for each collateral warranty not provided;
(b) the task or Milestone Payment against each task or Milestone Event shall become due
only when the task or Milestone Event has been achieved in full or an agreed percentage
whether before or on the relevant task or Milestone Payment Date;
(c) a task or Milestone Payment against a task or Milestone Event may become
due in any order of achievement.
41.2 If any instalment is to be paid upon the completion of a specified task or milestone, the
Subcontractor shall only be entitled to apply for payment for that instalment when he can
provide evidence of completion of the task or milestone as stated in Schedule 19.
41.3 The Subcontractor shall submit a request for payment to the Contract Manager at
intervals of not less than one calendar month showing:
(a) the Subcontractor’s assessment of the amount to be paid for Subcontract
Works carried out up to the end of the period for which it is submitted, together
with any other scheduled payment as may have become payable;
plus
(b) the amounts to which the Subcontractor considers himself entitled in connection
with all other matters for which provision is made under the Subcontract;
less
(c) the total of all sums previously certified by the Contract Manager for payment.
41.3 The Subcontractor shall submit a request for payment to the Contract Manager five
Business Days before the end of each calendar month showing:
(a) the task or Milestone Events in respect of which the Subcontractor considers it is entitled
to payment, plus
(a) the amounts to which the Subcontractor considers himself entitled in connection with all
other matters for which provision is made under the Subcontract;
less
(b) the total of all sums previously certified by the Contract Manager for payment.
The Subcontractor's requests for payment shall be supported by all relevant documentary evidence
appropriately itemised.
The Subcontractor's final request for payment shall state that it is his final request for payment.
41.4 Within fourteen days of the receipt of an interim request for payment, or in the case of the
final request for payment within fifty-six days of its receipt, the Contract Manager shall
issue a certificate to the Subcontractor and the Contractor for the instalment to which
the request for payment relates. The certificate shall show the sum which the Contract
Manager considers to be due at the payment due date determined in accordance with
Sub-clause 41.5, and the basis on which it has been calculated. The total certified shall
comprise all sums listed in the Subcontractor’s statement which, in the opinion of the
Contract Manager, are properly payable under the Subcontract and shall show
separately any elements within the sums certified in respect of nominated Sub-
subcontractors. The Contract Manager may in any certificate delete, correct or modify
any sum previously certified by him as he shall consider proper.
41.4 Within [twenty one] days of the receipt of an interim request for payment, or in
the case of the final request for payment within [seventy] days of its receipt, the Contract
Manager shall issue a certificate to the Subcontractor and the Contractor for the
instalment to which the request for payment relates. The certificate shall show the sum
which the Contract Manager considers to be due at the payment due date determined in
accordance with Sub-clause 41.5, and the basis on which it has been calculated. The
total certified shall comprise all sums listed in the Subcontractor's statement which, in the
opinion of the Contract Manager, are properly payable under the Subcontract. The
Contract Manager may in any certificate delete, correct or modify any sum previously
certified by him as he shall consider proper.
41.5 Any sum certified and notified as due in accordance with Sub-clause 41.4 shall be due for
payment fourteen days (or fifty-six days in the case of the final request for payment) after
the date of receipt by the Contract Manager of the Subcontractor’s request for payment
in accordance with Sub-clause 41.3. The Contractor shall pay the amount so notified by a
date (the Final Date for Payment) which shall be thirty-five days (or seventy-seven days
in the case of the final request for payment) after the date of receipt by the Contract
Manager of the Subcontractor’s request for payment in accordance with Sub-clause
41.3.
41.5 Any sum certified and notified as due in accordance with Sub-clause 41.4 shall
be due for payment [twenty one] days (or fifty-six days in the case of the final request for
payment) after the date of receipt by the Contract Manager of the Subcontractor's request
for payment in accordance with Sub-clause 41.3. The Contractor shall pay the amount so
notified by a date (the “Final Date for Payment”) which shall be [forty] days (or seventy-
seven days in the case of the final request for payment) after the date of receipt by the
Contract Manager of the Subcontractor's request for payment in accordance with Sub-
clause 41.3.
41.7 If the Contractor intends to pay less than the sum due in accordance with Sub-clause
41.4 or 41.6 for any reason including any sum that may be due from the Subcontractor to
the Contractor under the Subcontract or any sum not payable in accordance with Sub-
clause 44.5, the Contractor shall notify the Subcontractor not later than one day before
the Final Date for Payment, specifying the amount he considers to be due on the date
the notice is given and the basis on which that sum is calculated.
41.7 Without prejudice to any other remedy which he may have, the Contractor shall
be entitled to deduct from any payment due to the Subcontractor any sums which are due
from the Subcontractor to the Contractor under the Subcontract. If the Contractor intends
to pay less than the sum due in accordance with Sub-clause 41.4 or 41.6 for any reason
including any sum that may be due from the Subcontractor to the Contractor under the
Subcontract or any sum not payable in accordance with Sub-clause 44.5, the Contractor
shall notify the Subcontractor not later than one day before the Final Date for Payment,
specifying the amount he considers to be due on the date the notice is given and the
basis on which that sum is calculated
41.8 If the Contractor does not make payment in full by the Final Date for Payment of the
amount of an instalment:
(a) in accordance with any notice issued under Sub-clause 41.7; or
(b) certified and notified in accordance with Sub-clause 41.4; or
(c) where applicable in accordance with Sub-clause 41.6;
or if either party does not make any payment due under any other provision of the
Subcontract by the Final Date for Payment the amount not paid shall bear interest
compounded daily from the Final Date for Payment until the amount not paid is received
by the other party at an annual rate which is two per cent above the Agreed Rate for the
first month of delay. The annual rate of interest shall be increased by a further two
percent at the end of each further month of delay, up to the end of the third month. If the
delay exceeds three months the annual rate of interest shall thereafter be ten per cent
above the Agreed Rate.
41.8 Subject to Sub-clauses 41.14 and 41.15, if the Contractor does not make payment in full
by the Final Date for Payment of the amount of an instalment:
or if either party does not make any payment due under any other provision of the
Subcontract by the Final Date for Payment the amount not paid shall bear interest
compounded daily from the Final Date for Payment until the amount not paid is received
by the other party at an annual rate which is two per cent above the Agreed Rate for the
first month of delay. The annual rate of interest shall be increased by a further two
percent at the end of each further month of delay, up to the end of the third month. If the
delay exceeds three months the annual rate of interest shall thereafter be eight per cent
above the Agreed Rate.
41.9 If the Contractor does not make payment in full by the Final Date for Payment of the
amount of an instalment:
(a) in accordance with any notice issued under Sub-clause 41.7; or
(b) certified and notified in accordance with Sub-clause 41.4; or
(c) where applicable in accordance with Sub-clause 41.6;
the Subcontractor may issue a Notice to the Contractor informing him of the
Subcontractor’s intention to suspend performance of any or all of his obligations under
the Subcontract. If such failure shall continue for seven days after the issue of such
41.9 Subject to Sub-clauses 41.14 and 41.15, if the Contractor does not make payment in full
by the Final Date for Payment of the amount of an instalment
the Subcontractor may issue a Notice to the Contractor informing him of the Subcontractor's
intention to suspend performance of any or all of his obligations under the Subcontract. If
such failure shall continue for seven days after the issue of such Notice, then at any time
thereafter and provided such failure is still continuing, the Subcontractor may suspend
further performance of any or all as applicable of his obligations under the Subcontract
until payment is made.
The Contract Manager shall determine by means of a Variation Order an extension to the
Approved Programme and appropriate dates in Schedule 11, Table 2 (Times of
completion) for the full period of suspension plus any reasonable additional time incurred
by the Subcontractor in resuming his obligations and those of his Sub-subcontractors. If
the Subcontractor incurs additional Cost as a result of such suspension and subsequent
resumption he shall be entitled to an addition to the Subcontract Price determined in
accordance with and subject to Clause 19 (Claims).
41.10 If the suspension of performance of any, but not all, of the Subcontractor’s obligations in
accordance with Sub-clause 41.9 continues for a period of sixty days the Subcontractor
at any time thereafter may with immediate effect issue a Notice to the Contractor and
copied to the Contract Manager that such obligation is excluded from the Subcontract.
Thereafter the Contract Manager shall by means of a Variation Order confirm the
exclusion together with the applicable deduction from the Subcontract Price.
If the suspension of performance of all of the Subcontractor’s obligations in accordance
with Sub-clause 41.9 continues for a period of sixty days the Subcontractor at any time
thereafter may with immediate effect terminate his employment under the Subcontract by
a Notice issued to the Contractor and copied to the Contract
Manager and thereupon the rights and obligations of the parties shall be as stated in
Clause 43 (Termination by the Contractor for convenience).
41.13 The Subcontract Price excludes Value Added Tax and to the extent that the tax is
properly chargeable, the Contractor shall pay such tax as an addition to payments
otherwise due to the Subcontractor.
41.14 If the Subcontractor becomes Insolvent (as defined in s113 of the Housing Grants, Construction and
Regeneration Act 1996 (as amended)) after the prescribed period, the Contractor shall not be required to pay
the Subcontractor the notified sum on or before the final date for payment.
41.15 If the Purchaser is Insolvent (as defined in s113 of the Housing Grants, Construction and Regeneration
Act 1996 (as amended)) the Contractor shall not be obliged to make any further payment to the Subcontractor of
any amount which is due or may become due to the Subcontractor unless the Contractor has received payment
in respect thereof from the Purchaser and then only to the extent of such receipt.
42.2 The Contract Manager may subsequently instruct the Subcontractor to resume some or
all of the suspended Subcontract Works. Upon receipt of such an instruction the
Subcontractor shall resume such Subcontract Works as are ordered to be resumed as
soon as is reasonably practicable.
42.3 Any extension of the relevant dates or periods stated in Schedule 11 (Times of
completion) notified by the Contract Manager in accordance with Clause 14 (Delays)
shall take account of the additional time required by the Subcontractor in re-establishing
his activities and those of his Sub-subcontractors.
42.4 If the Subcontractor incurs any additional Cost as a consequence of complying with an
instruction to suspend any part of the Subcontract Works given by the Contract
Manager, other than an instruction given by reason of the Subcontractor’s default, he
shall be entitled to an addition to the Subcontract Price determined in accordance with
and subject to Clause 19 (Claims).
42.5 If the Subcontractor’s performance of any of the Subcontract Works is suspended for a
continuous period of ninety days, other than by reason of the Subcontractor’s default, at
any time thereafter and provided that such performance is still suspended, the
Subcontractor may issue a Notice to the Contractor and to the Contract Manager
requiring that the Contract Manager shall within fourteen days of such Notice either
issue an instruction to resume the suspended Subcontract Works, or issue a Variation
Order excluding that part of the Subcontract Works to which the instruction to suspend
applies. If the Contract Manager shall fail to do so then upon the expiry of such period of
notice the employment of the Subcontractor shall unless otherwise agreed be deemed to
have been terminated and thereupon the rights and obligations of the parties shall be as
43.2 The Subcontractor shall upon receipt of the Notice of Termination cease the carrying
out of the Subcontract Works, other than such work as the Contract Manager may
instruct. The Subcontractor shall upon completion of such work remove any
Subcontractor’s Equipment from the Site and withdraw from the Site leaving it in a safe
and tidy condition.
The Contract Manager shall issue a Take Over Certificate in respect of any part of the
Subcontract Plant for which a Take Over Certificate has not been issued, and shall if
the Subcontractor is required to carry out any further work prior to his withdrawal from
the Site or to provide any Subcontract Materials or Documentation applicable to the
Subcontract Plant issue any further Take Over Certificate as may be appropriate.
Thereafter Clauses 37 (Liability for Defects) and 38 (Final Certificate) shall apply.
43.3 As soon as practicable after receipt of the Notice of Termination, the Subcontractor
shall if so required by the Contractor:
(a) ensure that his Sub-subcontractors cease work in accordance with and subject
to Sub-clause 43.2 so far as is possible by the exercise by the Subcontractor of
such powers of termination, omission or cancellation as are available to him in the
relevant subcontracts; and/or
(b) to the extent permitted by the sub-subcontract, assign any sub-subcontract to the
Contractor or the Purchaser.
43.4 Upon receipt of the Notice of Termination or on such later date as may be specified in
the Notice of Termination, the Subcontractor shall transfer to the Contractor to the
extent desired by the Contractor all or any rights held by the Subcontractor relating to
Subcontract Materials, Subcontract Temporary Works and the Subcontract Plant
together with the obligations connected with them. The Subcontractor shall also deliver
to the Contractor all erection plans, schedules and Documentation and other data
prepared by the Subcontractor or Sub-subcontractors in connection with the
Subcontract Works and all Confidential Information and all other Documentation
supplied to the Subcontractor by or on behalf of the Contractor in connection with the
Subcontract Works.
43.5 Within ninety days 100 days of the Subcontractor’s withdrawal from the Site, or if the
Subcontractor has not entered the Site before receipt of the Notice of Termination
within ninety days of his receipt of the Notice of Termination, the Contract Manager
shall, subject to Sub-clause 43.7, issue to the Contractor and to the Subcontractor a
certificate (a Termination Certificate’) which shall state:
(a) the total amount (if any) due to the Subcontractor under the Subcontract for the
Subcontract Works carried out prior to the receipt by the Subcontractor of the
Notice of Termination;
43.6 As soon as practicable, the Subcontractor and the Contractor shall provide the
Contract Manager with all such information and documents as he may reasonably
require for the purpose of issuing the Termination Certificate.
43.7 If by the expiry of the period specified in Sub-clause 43.5 it is not possible for the
Contract Manager to issue a Termination Certificate by reason of any matter which
prevents the determination of the amounts referred to in Sub-clause 43.5, the Contract
Manager shall, at the expiration of such period, issue a provisional Termination
Certificate which shall contain the best estimate that can be made of any amounts
referred to in Sub-clause 43.5 and of the resultant balance due. As soon thereafter as the
determination of the amounts referred to in Sub-clause 43.5 becomes practicable, the
Contract Manager shall issue a final Termination Certificate which shall operate as a
correction or adjustment of the provisional Termination Certificate.
If in the Contract Manager’s opinion it is appropriate to do so, he may issue more than
one provisional Termination Certificate prior to the issue of the final Termination
Certificate.
Payment of the balance due under any Termination Certificate shall be made between
the Contractor and the Subcontractor in accordance with any provisional or final
Termination Certificate and Clause 41 (Payment) shall apply as appropriate.
43.6 As soon as practicable, the Subcontractor and the Contractor shall provide the
Contract Manager with all such information and documents as he may reasonably require
for the purpose of issuing the Termination Certificate.
43.8 Nothing in this Clause 43 shall affect the continuing operation of Sub-clauses 9.6, 9.7 and
9.8 and Clauses 8 (Patent and other protected rights), 20 (Confidentiality), 45 (Limitations
on liabilities and remedies), 46 (Disputes), 47 (Adjudication), 48 (Reference to an Expert),
49 (Arbitration) and 50 (Related issues under the Main Contract) and, to the extent that
the Subcontractor has carried out the Subcontract Works, Clauses 30 (Care of the
Subcontract Works), 31 (Insurance) and 37 (Liability for Defects).
44.1 If:
(a) the Subcontractor or any of its Affiliates goes into liquidation (other than a voluntary
liquidation for the purposes of reconstruction or amalgamation) ceases to carry on
business or an arrangement or composition with or for the benefit of creditors is entered
into by or in relation to either the Subcontractor or any of its Affiliates or a petition is
(c) the Subcontractor assigns the Contract or sub-lets the whole of the Works without the
consent of the Purchaser; or
(d) the Subcontractor has failed to pay or allow any Liquidated Damages due in accordance
with the Subcontract within 20 Business Days of receipt of the Contractor's written notice
confirming that the same have become due and payable; or
(g) breach of the Subcontractor's obligations directly causes the termination of the Lease
and/or Environment Permit; or
(h) the Subcontract Works have failed to pass the Take Over Tests by the Longstop Take
Over Date;
then, without prejudice to any other rights or remedies accrued under the Subcontract,
the Contractor may forthwith by notice terminate the employment of the Subcontractor
under the Subcontract
(b) fails to proceed regularly and diligently with the Subcontract Works; or
(d) any of his Sub-subcontractors in breach of the Bribery Act 2010 or fails to comply with a
reasonable instruction from the Contractor in relation to any suspected breach the Bribery
Act 2010; or
then, without prejudice to any other rights or remedies which the Contractor may possess, the
Contractor may issue a Notice to the Subcontractor of such default.
If the Subcontractor fails to commence the rectification of the default within a period of fourteen
days after receipt of such Notice, and thereafter fails diligently to pursue the rectification
of such default, the Contractor may terminate the employment of the Subcontractor under
the Subcontract.
The Contractor may at any time give to the Subcontractor a second or subsequent Notice
of the same default without reasonable cause he wholly suspends or abandons (or
threatens to suspend or abandon) the carrying out of the Subcontract Works before their
completion.
44.3 Upon termination of the Subcontractor’s employment under Sub-clause 44.1 or 44.2:
(a) except as the Contract Manager may direct or permit, the Subcontractor shall
forthwith leave the Site and shall have no right to re-enter the Site or to undertake
any work, including the rectification of any Defect or to remove any
Subcontractor’s Equipment, Subcontract Temporary Works or Subcontract
Materials;
(b) the Contractor may himself or through others complete the Subcontract
Works and he or they may enter upon the Site and use the
Subcontractor’s Equipment, Subcontract Temporary Works and
Subcontract Materials and the Contractor shall not be liable to the
Subcontractor for any fair wear or tear or accidental damage that may
occur to the Subcontractor’s Equipment, Subcontract Temporary Works
or Subcontract Materials;
(c) the Subcontractor shall deliver promptly to the Contractor all erection plans,
schedules and Documentation and other data prepared by the Subcontractor or
Sub-subcontractors in connection with the Subcontract Works and all
Confidential Information and all other Documentation supplied to the
Subcontractor by or on behalf of the Contractor in connection with the
Subcontract Works; and
(d) the Subcontractor shall, if so required by the Contractor and to the extent
(a) except as the Contract Manager may direct or permit, the Subcontractor shall
forthwith leave the Site and shall have no right to re-enter the Site or to undertake
any work, including the rectification of any Defect (Subcontractor Default) or to
remove any Subcontractor's Equipment, Subcontract Temporary Works or
Subcontract Materials;
(b) the Contractor may himself or through others complete the Subcontract Works to
a standard necessary to pass the Performance Tests and he or they may enter
upon the Site and use the Subcontractor's Equipment, Subcontract Temporary
Works and Subcontract Materials and the Contractor shall not be liable to the
Subcontractor for any fair wear or tear or accidental damage that may occur to the
Subcontractor's Equipment, Subcontract Temporary Works or Subcontract
Materials;
(c) the Subcontractor shall deliver promptly to the Contractor all erection plans,
schedules and Documentation and other data prepared by the Subcontractor or
Sub-subcontractors in connection with the Subcontract Works and all Confidential
Information and all other Documentation supplied to the Subcontractor by or on
behalf of the Contractor in connection with the Subcontract Works; and
44.5 Upon the termination of the Subcontractor’s employment under this Clause 44 the
Contractor shall have no obligation to make any further payment, whether or not such
payment shall have been certified by the Contract Manager prior to termination, other
than as may be certified in accordance with Sub-clause 44.6,44.7 or 44.9.
The Contractor shall issue any necessary notice under Sub-clause 41.7.
44.6 Within ninety days of the completion of the Subcontract Works in accordance with Sub-
clause 44.3 (b) (including all testing and remedying of Defects, such that the total cost to
be incurred by the Contractor has been incurred) the Contract Manager shall, subject to
Sub-clause 44.9, issue to the Contractor and the Subcontractor a certificate (a ‘Default
Certificate’) which shall give a full statement of account including:
Having allowed for all previous payments made to the Subcontractor and any sum due to
the Contractor from the Subcontractor, the Default Certificate shall state the balance
due to or from the Subcontractor.
44.7 If within sixty days of the date of the termination of the Subcontractor’s employment the
Contractor has not taken steps to complete the Subcontract Works and the
Subcontract Plant in accordance with Sub-clause 44.3, the Default Certificate shall be
issued by the Contract Manager to the Contractor and the Subcontractor
within ninety days of such date of the termination. The Default Certificate shall state the
total amount (if any) due to the Subcontractor under the Subcontract for the
Subcontract Works carried out prior to the termination of the Subcontractor’s
employment less the amount of any additional cost properly incurred by the Contractor
for any necessary work authorised by the Contract Manager in connection with the
termination.
Having allowed for all previous payments made to the Subcontractor and any sum due to
the Contractor from the Subcontractor, the Default Certificate shall state the balance
due to or from the Subcontractor.
If within sixty days of the date of the termination of the Subcontractor's employment the
Contractor has not taken steps to complete the Subcontract Works and the Subcontract
Plant in accordance with Sub-clause 44.3, the Default Certificate shall be issued by the
Contract Manager to the Contractor and the Subcontractor within ninety days of such
date of the termination. The Default Certificate shall state the total amount (if any) due to
the Subcontractor under the Subcontract for the Subcontract Works carried out prior to
the termination of the Subcontractor's employment less the amount of any additional cost
properly incurred by the Contrac¬tor for any necessary work authorised by the Contract
Manager in connection with the termination.
Having allowed for all previous payments made to the Subcontractor and any sum due to
the Contractor from the Subcontractor, the Default Certificate shall state the balance due
to or from the Subcontractor.
44.8 As soon as practicable, the Subcontractor and the Contractor shall provide the
Contract Manager with all such information and documents as he may reasonably
require for the purpose of issuing the Default Certificate.
44.9 If by the expiry of the period specified in Sub-clause 44.6 or 44.7 it is not possible for the
Contract Manager to issue a Default Certificate by reason of any matter which prevents
the determination of the amounts referred to in Sub-clause 44.6 or 44.7, the Contract
Manager shall, at the expiration of such period, issue a provisional Default Certificate
which shall contain the best estimate that can be made of any amounts referred to in
Sub-clause 44.6 or 44.7 and of the resultant balance due. As soon thereafter as the
determination of the amounts referred to in Sub-clause 44.6 or 44.7 becomes practicable,
the Contract Manager shall issue a final Default Certificate which shall operate as a
correction or adjustment of the provisional Default Certificate.
If in the Contract Manager’s opinion it is appropriate to do so, he may issue more than
one provisional Default Certificate prior to the issue of the final Default Certificate.
44.10 Any disagreement arising under this Clause 44 concerning the amounts payable by or to
the Subcontractor which is not settled in accordance with the provisions of Clause 46
(Disputes) may be referred to an Expert in accordance with Clause 48 (Reference to an
Expert).
44.11 Payment of the balance due under any Default Certificate shall be made between the
Contractor and the Subcontractor in accordance with any provisional or final Default
Certificate and Clause 41 (Payment) shall apply as appropriate.
44.13 Nothing in this Clause 44 shall affect the continuing operation of Sub-clauses 9.6, 9.7 and
9.8 and Clauses 8 (Patent and other protected rights), 20 (Confidentiality), 45 (Limitations
on liabilities and remedies), 46 (Disputes), 47 (Adjudication), 48 (Reference to an Expert),
49 (Arbitration) and 50 (Related issues under the Main Contract) and, to the extent that
the Subcontractor has carried out the Subcontract Works, Clauses 30 (Care of the
Subcontract Works), 31 (Insurance) and 37 (Liability for Defects).
(ii) any sum included within the Delay Liquidated Damages for delay under Sub-
clause 15.1; or
(iii) any sum included within the Performance Liquidated Damages for failure to pass
Performance Tests under Sub-clause 35.12; or
(v) the Subcontractor’s liability under any indemnity in this agreement and/or under
Sub-clauses 3.11, 3.14, 3.15 and/or 5.5; or
(vii) any such losses suffered by a third party (excluding any Affiliate of
the Contractor or the Subcontractor) to the extent included in any award for
damages to or settlement with the third party in connection with a claim covered
by the indemnities under Sub-clauses 8.3, 8.5, 26.7 and 30.
45.2 Save as set out at Sub-clause 45.3 below and excluding Sub-clause 45.2(a), in no
circumstances whatsoever shall the aggregate liability of the Subcontractor to the
Contractor under or for breach of this Subcontract or otherwise in relation to the
Subcontract Works or in tort (whether or not involving negligence) or for breach of
statutory duty exceed the sum stated in the Subcontract Agreement, if any.
(a) the Subcontractor's liability for Delay Liquidated Damages pursuant to Clause 15 shall be
limited to a sum equal to [10%] of the Contract Price;
(b) the Subcontractor's liability for Performance Liquidated Damages pursuant to Sub-clause
35.12 shall be limited to a sum equal to:
(c) and the Subcontractor's combined liability for Performance Liquidated Damages, shall be
limited to a sum equal to [15%] of the Contract Price.
The parties agree that Performance Liquidated Damages and Availability Liquidated
Damages shall count towards the aggregate liability cap but Delay Liquidated Damages
shall not count towards the aggregate liability cap.
45.3 The total aggregate liability of the Subcontractor to the Contractor arising out of or in
connection with the Subcontract and the Subcontract Works, other than liability arising
under Sub-clause 8.3 and 26.7 and Clauses 30 (Care of the Subcontract Works) and 31
(Insurance), shall not exceed the amount stated in the Subcontract Agreement.
For the purposes of this Sub-clause 45.3 any deduction from or abatement of the
Subcontract Price to which the Contractor may become entitled as a result of:
(a) a Defect; or
(b) any other failure of the Subcontractor to comply with the terms of the
Subcontract;
shall be deemed to be a liability of the Subcontractor to the Contractor.
The Subcontractor does not exclude or restrict its liability for any of the following and no
liability for the same shall be taken into account in determining whether any of the
limits of liability set out at in this Clause 45 have been reached or exceeded:
(a) payments made by the Subcontractor to the extent that the Subcontractor is
entitled to receive corresponding payments pursuant to the terms of any of the
insurance policies required to be effected and maintained in accordance with
Clause 31 (or would have been so entitled but for any breach of the
Subcontractor's obligations under the Subcontract);
(b) the Subcontractor's liability in the event of any abandonment of the Works, wilful
default, fraud, fraudulent misrepresentation or corruption on the part of the
Subontractor or any Affiliate;
(c) the Subcontractor’s liability for death or personal injury; or
(d) the Subcontractor’s liability under any indemnity in this Subcontract and/or under
Sub-clauses 3.11, 3.14, 3.15, 5.5 and/or 30.
45.4 Sub-clauses 45.1 and 45.3 shall apply whether or not either party shall be held to have
repudiated the Subcontract.
45.5 Any exclusion or limitation of liability under the Subcontract shall as between the parties
exclude or limit such liability in contract, tort/delict including negligence or otherwise.
46. Disputes
46.1 The Contractor and the Subcontractor shall endeavour to avoid the escalation of
problems into disputes as defined in Sub-clause 46.4 and to avoid disputes both between
themselves and with third parties including Sub-subcontractors. The parties
acknowledge and agree that this shall not prejudice any right either party may have under
Clause 47 to refer any dispute or difference to adjudication at any time, if that party so
wishes, notwithstanding the definition of ‘dispute’ in Sub-clause 46.4.
46.2 In order to avoid the development of disputes and to facilitate their clear definition and
early resolution, the procedures set out in Clauses 46 (Disputes), 47 (Adjudication), 48
(Reference to an Expert) and 49 (Arbitration) shall be applied as appropriate.
46.3 If the Subcontractor is dissatisfied with any Decision or valuation of the Contract
Manager, or of any person to whom the Contract Manager may have delegated any of
his authority or responsibility, or if the Contractor or the Subcontractor is dissatisfied
with any other matter arising under or in connection with the Subcontract, either party
may at any time refer such dissatisfaction to the Contract Manager giving full details of
the nature of the matter. The Contract Manager shall give a Decision on the matter
(giving the reasons for such Decision) to the Contractor and the Subcontractor within
twenty-eight days of such reference to him.
46.4 The Contractor and the Subcontractor agree that no matter shall constitute or give rise
to a dispute unless it has been referred to the Contract Manager under Subclause 46.3
and:
(a) the Contract Manager has failed to give his Decision on the matter within the
prescribed time; or
(b) a Decision given within the prescribed time is either unacceptable to the
Contractor and/or the Subcontractor or has not been implemented within twenty-
one days of the Decision;
and, as a consequence, either the Contractor or the Subcontractor has issued to the
other a Notice (a ‘Notice of Dispute’) setting out the nature of the dispute with a copy to
the Contract Manager. For the purposes of the performance of the Subcontract Works
and all matters arising out of or in connection with the Subcontract, the word ‘dispute’
shall be construed in accordance with this Subclause 46.4.
46.5 Notwithstanding the existence of any dispute or any reference to the Contract Manager
under Sub-clause 46.3, the Contractor and the Subcontractor shall continue to perform
their obligations under the Subcontract.
46.6 The parties shall attempt in good faith to negotiate a settlement of any dispute or
difference.
46.7 If a dispute cannot be resolved by negotiation the parties may by agreement refer it to
mediation in accordance with the procedures of the Centre for Effective Dispute
Resolution (CEDR), the Chartered Institute of Arbitrators (ClArb) or some other appro -
priate body.
46.8 No Decision, opinion, direction, or valuation given by the Contract Manager shall
disqualify him from being called as a witness and giving evidence before any third party,
an Expert, adjudicator or arbitrator on any matter whatsoever relating to a dispute.
47.3 Unless the adjudicator has already been appointed, he is to be appointed to a timeta ble
with the object of securing his appointment and referral of the dispute to him within seven
days of the service of the Notice of Adjudication. The adjudicator shall be appointed in
accordance with the Adjudication Rules.
47.4 The adjudicator shall reach his decision within twenty-eight days of referral or such other
longer period as may be agreed between the parties after the dispute has been referred.
47.5 The adjudicator may extend the period of twenty-eight days by up to fourteen days with
the consent of the party by whom the dispute was referred.
47.7 The adjudicator may take the initiative in ascertaining the facts and the law.
47.8 The decision of the adjudicator shall be binding until the dispute is finally determined by
legal proceedings, by arbitration or by agreement.
47.9 The adjudicator may correct his decision so as to remove a clerical or typographical error
arising by accident or omission.
47.10 The adjudicator may include in his decision a direction as to the allocation of his fees and
expenses as between the parties.
47.11 The adjudicator shall not be liable for anything done or omitted in the discharge or
purported discharge of his functions as adjudicator unless the act or omission is in bad
faith. Furthermore, any personnel of the adjudicator acting in connection with the carrying
out of the adjudication shall be similarly protected from liability.
48.2 The Expert shall decide all disputes referred to him as an expert and not as an arbitrator.
Any decision of the Expert may revise or overrule any Decision of the
Contract Manager other than any decision expressly stated in the Subcontract to be
final, conclusive and binding.
48.3 The powers of the Expert to decide disputes shall include decisions as to factual issues
and the interpretation of the Subcontract.
48.4 The Contractor and the Subcontractor shall give the Expert every assistance in deciding
any dispute referred to him and shall give him access to the Site and to their premises
and shall provide him with any information and Documentation that he may reasonably
require.
48.5 The Expert shall have power by his decision to fix the reasonable amount of his fees in
connection therewith and they shall be borne in equal shares between the Contractor
and the Subcontractor.
48.6 If the Subcontractor has complied with any Decision of the Contract Manager
which is overruled by the Expert, and has thereby suffered or incurred any loss or
additional expense in the performance of the Subcontract, then provided that the
Subcontractor has notified the Contract Manager that he disputes such Decision before
complying with it, the Expert may in his discretion award the Subcontractor a reasonable
sum in respect of such loss or additional expense, notwithstanding that the overruling of
the Decision would not otherwise entitle the Subcontractor to any additional payment
under the Subcontract.
48.7 The Contractor and the Subcontractor hereby agree to be bound by any decision of the
Expert under this Clause 48, which decision shall be final, conclusive and binding, and
shall comply with any direction given therein and shall not question the correctness of any
such decision or direction in any proceedings.
48.8 Neither the Contractor nor the Subcontractor shall be entitled to suspend performance
of the Subcontract by reason of the reference of a dispute to an Expert.
48.9 Any dispute which is referred to an Expert ceases to be referable to arbitration under
Clause 49 (Arbitration).
48.10 A limitation period on actions in litigation or arbitration which applies to the Subcontract
under the applicable law shall apply also to the issue of a Notice to refer a dispute to an
Expert in accordance with Sub-clause 48.1.
48.11 If
49. Arbitration
49.1 Any dispute, other than failure to give effect to a decision of an adjudicator given under
Clause 47 (Adjudication) or of an Expert given under Clause 48 (Reference to an Expert),
which has not been referred to an Expert in accordance with Clause 48 shall be referred
to a single arbitrator by one party serving a Notice (a ‘Notice of Arbitration’) on the
other.
49.2 The arbitration shall be conducted in accordance with the procedure set out in the edition
of the ‘Arbitration Rules’ published by IChemE current at the time of the appointment of
the arbitrator. The arbitrator shall be appointed in accordance with the Arbitration Rules.
49.3 The arbitrator shall have full power to open up, review, revise or overrule any Decision of
the Contract Manager, other than any Decision expressly stated in the Subcontract to
be final, conclusive and binding.
Neither party shall be limited in arbitration to the evidence or arguments put to the
Contract Manager or to an adjudicator in accordance with Sub-clause 46.3 and Clause
47 respectively.
49.4 The Contractor and the Subcontractor agree to be bound by any decision, award or
ruling of an arbitrator under this Clause 49 and shall comply therewith. The Contractor
and the Subcontractor hereby agree to exclude any right to appeal to the Court under
the Arbitration Act 1996.
49.5 If the Subcontractor has complied with any Decision of the Contract Manager
which is overruled by the arbitrator, and has thereby suffered or incurred any loss or
additional expense in the performance of the Subcontract, then provided that the
Subcontractor has notified the Contract Manager that he disputes such Decision before
complying with it, the arbitrator may in his discretion award the Subcontractor a
reasonable sum in respect of such loss or additional expense, notwithstanding that the
overruling of the Decision would not otherwise entitle the Subcontractor to any additional
payment under the Subcontract.
49.6 Neither the Contractor nor the Subcontractor shall be entitled to suspend performance of
the Subcontract by reason of the reference of a dispute to arbitration.
49.7 The Parties agree that any dispute under the Main Contract which, in
whole or in part, is also a dispute under this Subcontract may be joined
with the dispute under the Subcontract and vice-versa for the purposes
of resolution under Clause 49
50.2 In the event that any dispute arising between the Contractor and the Subcontractor
which is referable to arbitration is substantially the same as a dispute arising or which has
arisen between the Contractor and the Purchaser (and/or the Project Manager) and
which is also referable to arbitration under the Main Contract, then, subject to an
arbitrator not having been appointed under the Subcontract, the Contractor shall be
entitled to require the Subcontractor to be joined as a party to such reference and such
Subcontract dispute shall be referred to the arbitral tribunal appointed or to be appointed
pursuant to the provisions of the Main Contract.
The purpose of this section is to provide an aide-memoire to help • In Paragraph 14: the amount (expressed as a percentage) of
users of this handbook to prepare a complete set of documentation Profit to be added to any Cost - a value which will normally
to accompany the Conditions of Subcontract. As mentioned in the be part of the Subcontractor’s tender;
Introduction, more extensive guidance is given in the Red, Green • In Paragraph 15: the names and/or positions of appropriate
and Burgundy Books. These should be referred to as appropriate. senior personnel, their addresses and fax numbers for the
Like the Red Book, but not the Green and Burgundy Books, the receipt of formal Notices - see the guidance below;
Yellow Book is drafted as a price-based contract. • In Paragraph 17: the seat of any arbitration that might arise
It is not intended to give a comprehensive or definitive from the Subcontract; and
statement of the commercial or legal position, nor does this • In Paragraph 18: the Identification Number for all documents
section form part of the General Conditions or of any contract. referring to the Subcontract.
The date for the commencement of the Subcontract Works is
needed in Paragraph 9 because it could be earlier or later than the
The Subcontract Agreement date of the Subcontract Agreement, and is relevant to the periods
for completion in Schedule 11 (Times of completion). It may also be
Examination of the Subcontract Agreement will underline the required for any Special Condition which is included in the
importance of using this document in preference to other forms Subcontract.
such as a purchase order if the Subcontract is to read as a The requirement to give the name or position, address and fax
consistent whole, if only because several of the key terms in the number of senior personnel of each of the Contractor and
General Conditions are defined in Clause 1 (Definitions, inter- Subcontractor is to facilitate the issuing of formal Notices in
pretation, waiver and Notices) by reference to the Subcontract accordance with Sub-clause 1.8 of the General Conditions. While
Agreement. Users should be particularly careful to note Paragraph day-to-day communications under the Contract are to be between
2 of the Subcontract Agreement, and to ensure that the Subcontract the Contract Manager and the Subcontract Manager (see Sub-
Specification and all the relevant Schedules conform to the wording clause 11.7 of the General Conditions), it is recognised that certain
of Paragraph 1 of the Subcontract Agreement and have been communications should be directly between the parties at a senior
signed. The Subcontract Agreement includes at Paragraph 2 an level - e.g. CEO, Director or Company Secretary. It may be more
entire agreement clause. For administrative reasons some appropriate to state the position of the person (e.g. CEO) rather
companies issue a Purchase Order for all subcontracts. Care must than his/her name. There are many references in the General
be taken to ensure that any terms or conditions printed on the back Conditions to one party notifying the other (e.g. Sub-clauses 4.3,
of any purchase order cannot be taken as applying to the 7.3, 8.4, 14.5 or 41.7 to list but a few), but these all relate to general
Subcontract. matters under the Subcontract. Notices under Sub-clause 1.8 relate
In addition to entering the date of the Subcontract Agreement to termination and similar high-level matters which are to be dealt
(usually entered by hand when the document is finally signed) and with in a formal way, probably after the taking of legal advice by the
the names and addresses of the parties, the following must be party issuing the Notice. Notices issued in accordance with Sub-
entered in the body of the Subcontract Agreement: clause 1.8 are referred to in Sub-clauses 1.1, 14.9 and 41.9, and
Clauses 42 (Suspension of the Subcontract Works), 43
• In Paragraph 3: the Subcontract Contract Price, which must
(Termination by the Contractor for convenience), 44 (Termination
be stated as the total amounts in each of the stated
for Subcontractor default), 46 (Disputes), 47 (Adjudication), 48
currencies (see also the guidance on compiling Schedule 19
(Reference to an Expert) and 49 (Arbitration).
(Subcontract Price and payment));
If the parties wish the law of the Subcontract to be other than
• In Paragraph 4: the total aggregate liability of the Subcon-
English law then paragraph 16 should be amended accordingly.
tractor to the Contractor (again this may be in more than one
It is advisable that persons entering into a subcontract ensure
currency);
that the person signing on behalf of the other party has the
• In Paragraph 5: at (a) and (b) the two sums (again these may
necessary authority to sign.
be in more than one currency) applicable to the Subclauses
A further matter which may be appropriate and which should be
which are referred to;
dealt with in the Subcontract Agreement is that of conditions
• In Paragraph 6: the amount of the Deductible and the
precedent. In some instances the parties will need to enter into the
applicable currency;
Subcontract by signing the Subcontract Agreement but then have a
• In Paragraph 8: the date of the Subcontractor’s tender;
period of time within which certain actions must be
• In Paragraph 9: the date for commencement of the
Subcontract Works;
• In Paragraph 10: the name of the Contract Manager;
• In Paragraph 11: the name of the Subcontract Manager;
• In Paragraph 12: the name of the bank (or banks, if there are
to be more than one currency of payment) whose base rate
will determine the Agreed Rate;
• In Paragraph 13: delete the text in the square brackets which
is NOT to apply, as well as all square brackets;
taken by one or other of the parties (e.g. making of the Main shall comply with the Subcontract and shall be in every respect
Contract), and only when those actions are complete will the fit for the purpose for which it is intended as defined in the
Subcontract come into full effect. Such matters are called conditions Subcontract Specification or in any other provision of the
precedent. The following clause covers the more frequently required Subcontract.’
conditions precedent for subcontracts to deliver elements of major
A Subcontract without an adequate Subcontract Specification is
projects. The clause may need adapting to suit the particular
almost certain to lead to delays and disputes and in all probability
requirements. The Parties may wish to consider who will pay for
higher costs.
wasted costs if the Subcontract never comes into full effect. Note
The Specification should identify the engineering standards and
the further details that would be required to be included in the
codes of practice that are to be used, with great care taken to
Subcontract according to the clause as drafted.
provide sufficient detail to avoid any ambiguity in the definition. In
particular, where third party inspectorates will eventually rule on the
sufficiency or suitability for purpose of the Subcontract Plant, this
EXAMPLE ADDITIONAL PARAGRAPH TO INSERT IN THE AGREEMENT
must be clearly stated. Where the acceptance of the Subcontract
19. The Subcontract shall come into force on whichever is the later Plant by a third party inspector may have to be based on
of the following: regulations which are open to interpretation, the Contractor has a
right to expect the Subcontractor to design the Subcontract Plant so
(a) The date specified in the Subcontract Agreement
as to comply with any reasonable interpretation.
as the date for commencement of the Subcontract
If the Main Contract specifies such matters as corrosion
Works;
allowances or the design life of specific items, the relevant details
(b) The date on which any necessary legal financial or
must be incorporated here.
administrative requirements specified in the
If the Subcontract Plant includes a process unit, its capability to
Special Conditions as conditions precedent to the
make the desired product at a required rate from specified
coming into force of the Subcontract have been
feedstocks will form a principal feature of this document. A similar
fulfilled.
requirement may apply to items of equipment, and if their
The party responsible for meeting any precondition of performance could be affected by conditions such as ambient
effectiveness shall notify the other party when the temperature or fluctuations in the supply of energy, other utilities or
precondition has been met. feedstock, the applicable conditions must be stated. If the Main
Provided that if all the requirements stated above have not Contract specifies the performance at the end of the working life of
been met and notified by [date] this Subcontract materials or catalysts and for performance tests this must be
Agreement shall be of no effect. indicated in the Subcontract Specification.
Any spare or replaceable parts to be supplied with the equip-
ment should also be detailed, making clear whether their cost forms
part of the Subcontract Price or whether they are to be paid for
The Annex to the Subcontract Agreement separately.
For more extensive guidance and discussion, the user should refer XX. Contractor's right to review design work
to the Guide Notes attached to the applicable Main Contract Form
(i.e. Red, Green or Burgundy Book) published by IChemE when
considering implications for the Subcontract. Points of particular XX.1 The Contractor will require to review the design work carried
relevance to the Subcontract are given below. out by the Subcontractor relating to those parts of the
For ease of reference, a listing of the Guide Notes included in Subcontract Plant or aspects of the design of the
each of the Main Contract forms is included at Appendix A. Subcontract Plant so designated in the Subcontract
Specification. The Subcontractor shall keep the
Contractor informed of the progress of such design work
by the preparation of reports at appropriate stages and in
Guide Note A: Reviews and information any event at intervals of not more than thirty days
starting from the commencement of such work. The
The Contractor may require the Subcontractor to check information Subcontractor shall afford reasonable access during
provided by the Contractor before he uses it, or may wish to rely on normal working hours for the Contract Manager or his
some special expertise of the Subcontractor in designing and designated representatives to the personnel carrying out
constructing a particular type of plant, in which case a Special such work, and shall provide the Contract Manager with
Condition may be required such as the following: a copy of any document relating to such work, at the
request of the Contract Manager or his designated
representative.
EXAMPLE CLAUSE
The Contractor may require the Subcontractor to carry out Book is simply that a Variation which is within the 25% or 5% rule
design work of an innovative nature for a part of a plant about which as set out in Sub-clause 16.6(a) or (b) of the Main Contract Forms
the Contractor has some views but which he cannot define in writing might represent anything up to 100% (or even more) of a particular
at the time the Subcontract is finalised. As a result, the Contractor Subcontractor’s work. Thus to duplicate the restriction at the
could propose a Special Condition giving him the right to review the subcontract level may leave the Contractor unable to fulfil his
Subcontractor’s design work at an earlier stage than the submission obligations.
of Documentation for approval provided in Schedule 2 Nevertheless Sub-clause 16.6 provides the Subcontractor with
(Documentation). For example: protection at (e), which will cover for example if the difficulty is the
Guide Note C: Variations availability of resources such as manufacturing capacity.
Similarly the Subcontractor should be aware that there could be
Unlike the Main Contract Forms the Yellow Book does not contain a major reduction in his work and he should ensure his contract
within Sub-clause 16.6 a restriction on the aggregate value of protects him from any real loss in this event.
Variations, a restriction which is to protect the Contractor from the Careful and prompt use of the Variation procedure to record
possibility of the overall size or value of the Main Contract either detailed changes of the Subcontract Specification and Description
being much larger or much smaller than that originally envisaged. of the Subcontract Works is essential for the good management of
The reason for not including such a restriction in the Yellow the project and for the avoidance of disputes. Full discussion and
cooperation between the parties during the Variation procedure also
avoids disputes.
The Contractor must take care to ensure that any Special Condi-
tions in the Main Contract which have the effect of varying the
insurance provisions of the Main Contract General Conditions are
reflected in the Conditions of Subcontract through a Special
Condition.
For a more general consideration of this topic the reader is
referred to Guide Note I (Insurance) in the Red, Green or Burgundy
Book as applicable.
The following sample certificates are given as an indication only of the likely content of each certificate. Users should take care to ensure
that the words used in a certificate accurately reflect the terms of the Contract as they apply to the particular situation in which a certificate is
issued.
Contractor:
Subcontractor:
In my opinion the parts of the Subcontract Plant listed above are substantially complete and meet the above-mentioned criteria listed in
Schedule 14. In accordance with Sub-clause 32.2 of the General Conditions I therefore propose the above programme for inspection and
tests, commencing on [date].
Signed:...........................................................
Name: ............................................................
Date: .........................................................
* In accordance with Sub-clause 32.7 of the General Conditions the parts of the Subcontract Plant listed above do not meet the criteria in
Schedule 14 as listed above in the following significant respects:
* In accordance with Sub-clause 32.6 of the General Conditions I hereby certify that the parts of the Subcontract Plant listed above were
substantially complete in accordance with Sub-clause 32.6 of the General Conditions as of [date] and in such a condition that the relevant
take over procedures may be carried out.
* In accordance with Sub-clause 32.6 of the General Conditions I require the following minor items to be completed before the issue of a
Take Over Certificate covering the parts of the Subcontract Plant listed above:
Signed:...........................................................
Name: ............................................................
Date: .........................................................
Contract Manager
* Delete as applicable
Sample Take Over Certificate
Subcontract Title and Identification Number:
Contractor:
Subcontractor:
Date of Certificate:
(Alternative A—where the Subcontract Plant or any Section is being Taken Over under Sub-clause 33.7 or 33.10)
(1) In accordance with Sub-clause [33.7/33.10] of the General Conditions I hereby certify that the [Subcontract Plant]/[Section(s) of
the Subcontract Plant listed below], apart from any parts of the [Subcontract Plant]/[Section(s) listed below], [has]/[have]
satisfied the requirements of the Subcontract Specification and Schedule 15 of the Subcontract and the Subcontractor has complied
with Sub-clause 21.9 of the General Conditions and therefore such [Subcontract Plant]/[Section(s) of the Subcontract Plant
listed below] [is]/[are] Taken Over by the Contractor as from the Take Over time and date stated below.
(2) The following parts of the [Subcontract Plant]/[Section(s) of the Subcontract Plant] are excluded from Taking Over:
(3) The following minor items of work are still to be completed in accordance with Sub-clause 33.8 of the General Conditions,
(a) .......................
(4) The following Take Over procedures have been omitted by operation of Sub-clause 33.10 of the General Conditions and still remain
to be carried out by the Subcontractor in accordance with Clause 33 (Taking Over) of the General Conditions.
(a) .......................
(b) .................................
(2) The following parts of the [Subcontract Plant]/[Section] are excluded from Taking Over for the reason(s) stated:
(a) because the take over procedures have not been carried out...............
(b) because the take over tests have not been passed .............
(3) The following minor items of work are still to be completed in accordance with the terms of Sub-clause 33.8 of the General
Conditions:
(a) .......................
(b) .................................
(4) The following take over procedures have been omitted by operation of Sub-clause 33.9 of the General Conditions and still remain to
be carried out by the Subcontractor in accordance with the terms of Clause 33 (Taking Over) of the General Conditions:
(a) .......................
(b) .................................
Signed:
Name:
Contract Manager
Subcontract Title and Identification Number:
Contractor:
Subcontractor:
Date of Certificate:
(1) In accordance with Clause 36 of the General Conditions I hereby certify that the [Subcontract Plant]/ [Section (s) of the Subcontract
Plant listed below] have:
*(b) passed all the performance tests, except for those performance tests for which the appropriate [liquidated damages
have/compensation has] been paid or allowed for by the Subcontractor
106 Copyright :© 2013 Institution of Chemical Engineers
Sample Acceptance Certificate
and I therefore issue this Certificate in accordance with Sub-clause 36.3 of the General Conditions;
*(c) been Accepted by the Contractor by notice of election issued to the Subcontractor in accordance with Sub-clause 36.5 of the
General Conditions.
*(2) Known Defects to be made good by the Subcontractor and minor items still remaining to be completed in accordance with Sub-clause
36.3 of the General Conditions are listed in the attached ‘punch list’.
Signed:
Name:
Contract Manager
Contractor:
Subcontractor:
Date of Certificate:
(1) In accordance with Sub-clause 38.1 of the General Conditions I hereby certify that in respect of the [Subcontract Plant]/[Section
(s) of the Subcontract Plant listed below]:
(a) the Defects Liability Period has expired; and
(b) the Subcontractor has made good all Defects that have appeared during the Defects Liability Period.
(c) the Acceptance Certificate has been issued in respect of the [Subcontract Plant]/[Section(s) of the Subcontract Plant
listed above],
*(3) The following items are excluded from this Final Certificate in accordance with Sub-clause 38.2 of the General Conditions:
*(4) This is the last Final Certificate to be issued under the Subcontract.
Signed:..........................................................
Name: ...........................................................
Contract Manager
* If this is the last Final Certificate, (3) should be deleted. If this is not the last Final Certificate, (4) should be deleted.
Abbreviations used under the heading ‘other’ are as follows: Agt. = Agreement; App. = Appendix; GN = Guide Note; IN = Introductory Note;
Sch. = Schedule; Specn. = Specification.
Clause Page Other Page
A
Acceptance, definition 1.1 7
Acceptance Certificate: 1.1,36 7,46
cancellation of 33.12 41
access to Site:
by Contractor and Contract Manager 23.5 31
by Subcontractor 23.1, 33.13 31,42
accuracy of data, Contractor’s responsibility for 6.2 14
additions. See Variations
adjudication 47 58 GN F 73
Affiliate 1.1,30.10 7,36
Agreed Rate 1.1 7 Sch. 19 70
Agreement:
guidance on completing GN 61
Alcohol 26.6 33
Approved Programme: 13 21 Sch. 11 67
definition 1.1 7
provision of 13 21
arbitration 49 59 GN F 73
assignment and sub-subcontracting 9 17 Sch. 7 66
audit 40 49
B
bankruptcy, Subcontractor’s default 44.1 53
bank’s base lending rate 7
1.1
c
cancellation certificate 33.12 41
cancellation of Acceptance Certificate 33.12 41
care of the Works 30 35
Certificate:
Acceptance 1.1, 36 7,46
Construction Completion 32 39 Sch. 14 68
Default 44.6 54
Final 1.1, 38 7,48
for payment of Subcontract Price, instalment 41.4 49
Take Over. See Take Over Certificate
Termination 43.5-43.8 52-53
Documentation required by law or the 27.5 34
Contract
change of law 7.3 15
to Contractor 3.5 12
communication to be in writing 1.6 10
completion of construction 32 39 Sch. 14 68
completion times 13 21 Sch. 11 67
conditions of employment 28.1 34
Confidential Information: 20.1 27 GN B 72
confidentiality: 20 27 GN B 72
obligations of Sub-subcontractor 9.6 17
consent under contract, refusal or delay of 1.4 10
construction, completion of: 32 39
by sections 32.1 39 Specn. 62
criteria for 32.2 39 Sch. 11, Sch. 14 67 68
D
damage to property of and injury to third parties 30.15 37 GN D 73
damages, liquidated:
for delay 15,45.1 23, 56 Sch. 12 67
for failure of performance tests 35.12-35.15,45.1 45, 56 Sch. 17 69
damages, general for failure of performance 35.14, 35.15 45
tests
day 1.5 10
Decisions: 1.1,5 713
challenges to 5.2 13
deductible, insurance 31.1 37
default by Subcontractor 44 53
default certificate 44.6 54
Defect:
definition 1.1 7
liability for 37 46 GN E 73
limitation of Subcontractor’s liability 37.12 48
definition of terms 1.1 7
delay, damages for 15 23 Sch. 12 67
delays and extensions of time 14 22 Sch. 11 67
delivery to Site 24 32
description of Subcontract Works Sch. 1 62
design standards and codes Sch. 1, Sch. 6 62,
dispute: 44 53
adjudication 47 58 GN F 73
arbitration 49 59 GN F 73
mediation 46.7 57 GN F 73
reference to an Expert 48 58 GN F 73
dispute resolution GN F 73
Documentation: 21 28 Sch. 2 63
Subcontractor’s responsibilities on approval 21.3 28
copyright of 8.7 16
definition 1.1 7
delivery of on termination 41.4 49
errors in 21.12-21.14 29 Sch. 2 63
excluded from inspection 21.6 29 Sch. 2 63
Final, and manuals 21.9 29
for approval 21.2 28 Sch. 2 63
for information only 21.7 29 Sch. 2 63
not available to Project Manager 21.6 29
Contractor’s responsibilities 4.1 12
F
fees, royalties Final Certificate Final Date for Payment
firefighting equipment first aid 26.2 33 Sch.5
Force Majeure 26 33
Free-issue materials 26.1 33 Sch. 4
Free-issue materials, delivery to Site 26.5 33
G 28.5 35
good relations
guarantee, from Sub-subcontractors guarantee,
performance
H 47 58
hazardous materials health and safety and 49 59
environment health and safety legislation health and 48 58
safety supervisor, 12.5, 28.4 20, 35
Subcontractor’s hours
of work at Site 30.4, 30.6, 30.9, 30.10, 36,37 GN D
30.12, 30.13, 30.15
/ 30.5,30.7,30.11, 30.14 36,37
IChemE: 30.11, 30.12, 30.14 36,37
appointment of an adjudicator 30.10, 30.11, 30.15 36,37 GN D
appointment of an arbitrator appointment 22 30 Sch. 13
of an Expert incompetence of 41 49 Sch. 19
Subcontractor’s staff indemnification: of 31 37 GN D
Contractor 31.1, 31.2 37,38 GN D
31.1 37 GN D
of Subcontractor of Sub-
31.4 38 GN D
subcontractors injury, liabilities for
inspection and pre-installation tests
instalments of payment insurance: joint
names
of Materials, Temporary Works and Plant of
third parties
Clause Page Other
21.4 28
21.11 29
26.6 33
14.6 23
33 Sch.5
26 Sch.5
26.1 33 Sch.5
V
validation 3.8 12 Sch. 6 65
valuation of variations 18 26
Variations: 16 24 GN C 72
definition 1.1 7
extension of time for 14.4 23
regarding nominated Sub-subcontractor 10.4 18
Subcontractor’s 3.5,17 12, 25 Sch. 18, GN C 69,72
valuation of 18 26 Sch. 18 69
visitors to Site 23.6 32
w
wages 28.1, 28.3 34
waste materials 27.3 34 Sch. 5 64
Reimbursable Contract
The Green Book
Subcontract
The Yellow Book
Minor Works
The Orange Book
Adjudication Rules
The Grey Book
Arbitration Rules
The Pink Book
ISBN 978-0-85295-545-1