This document is a comment resolution sheet for an EPC revitalization project. It addresses 9 comments from PERTAMINA and WOOD regarding a requisition for scaffolding work. The answers provide additional details and scope clarifications to the scaffolding design, work packs, transport methods, and inclusion of removal work for various modules. Revisions were made to the document to address the comments.
This document is a comment resolution sheet for an EPC revitalization project. It addresses 9 comments from PERTAMINA and WOOD regarding a requisition for scaffolding work. The answers provide additional details and scope clarifications to the scaffolding design, work packs, transport methods, and inclusion of removal work for various modules. Revisions were made to the document to address the comments.
This document is a comment resolution sheet for an EPC revitalization project. It addresses 9 comments from PERTAMINA and WOOD regarding a requisition for scaffolding work. The answers provide additional details and scope clarifications to the scaffolding design, work packs, transport methods, and inclusion of removal work for various modules. Revisions were made to the document to address the comments.
PROJECT EPC REVITALIZATION PROJECT OF RCC RU VI BALONGAN
Document No U2004-015-G67-CO01-T-0496 Title Requisition for Scaffolding Work Rev 0A
NO. PERTAMINA and WOOD Comment CSO Answer
1 - Design scope is included in Preparation of Work Plan, Procedures and Calculation prior to Starting the each Subcontractor Work in Attachment #2 - Scaffolding for old/new cyclone assembly covered in Part 6 Scope Overview (item no.2) - As per my experience when use Mammoet ptc-35 services, they will not require scaffolding during assembly ringer crane. - Scaffolding for disinvestment reactor structure will be add as per comments
2 -Work packs prepared by CSO
-Detail requirement and volume prepare by mechanical contractor and approved by CSO - Conventional tube - Scaffold that erected from existing structural platform will transport by crane, if crane is not possible due to the space and if volume not too big it will transported to the height by pulley
3 - Added in 7.2.7-c in new 0A revision
- Added in new 0A revision (for removal on all boiler modules)
4 Noted, this check item will included in the method statement