COMMENT RESOLUTION SHEET

PROJECT EPC REVITALIZATION PROJECT OF RCC RU VI BALONGAN


Document No U2004-015-G67-CO01-T-0496
Title Requisition for Scaffolding Work
Rev 0A

NO. PERTAMINA and WOOD Comment CSO Answer


1 - Design scope is included in Preparation of Work Plan, Procedures and Calculation prior to
Starting the each Subcontractor Work in Attachment #2
- Scaffolding for old/new cyclone assembly covered in Part 6 Scope Overview (item no.2)
- As per my experience when use Mammoet ptc-35 services, they will not require scaffolding during
assembly ringer crane.
- Scaffolding for disinvestment reactor structure will be add as per comments

2 -Work packs prepared by CSO


-Detail requirement and volume prepare by mechanical contractor and approved by CSO
- Conventional tube
- Scaffold that erected from existing structural platform will transport by crane, if crane is not
possible due to the space and if volume not too big it will transported to the height by pulley

3 - Added in 7.2.7-c in new 0A revision


- Added in new 0A revision (for removal on all boiler modules)

4 Noted, this check item will included in the method statement

5 - Added in 7.2.7-a in new 0A revision

6 - Added in 7.2.7-b in new 0A revision


- burner set deleted

7 - Added in new 0A revision