Professional Documents
Culture Documents
Prakash Report
Prakash Report
ON
PART - 1
CONTROLL BLASTING TECHNIQUES
SUBMITTED BY
PRAKASH (18UMIE1222, 3RD YEAR)
UNDER GUIDANCE OF
DR. SHUSHIL BHANDARI
SIR [CEO at MINE
0
CONTENTS
CHAPTER NO. TOPIC PAGE NO.
A ABSTRACT 2-3
B TABLE OF FIGURES 3
CHAPTER 4 CONCLUSION 22
REFERENCES 23
1
ABSTRACT
Blasting is a process of breaking the rock mass to excavate
the ore and materials. Many open blasting operations are
faced with the apparently conflicting requirements of
providing large quantities of fragmented rock and of
minimizing the amount of damage inflicted upon the
surrounding slopes. A slope in strong hard rock is not
necessarily stable, nor is a slope in weathered weak rock
necessarily unstable. In some case the reverse is true,
depending on the geometry of joints and weak planes.
Many slope failures in hard rock occur with no or very
little warning. Detection and monitoring may not be
feasible, or require sophisticated instruments and
procedures that are not practical at some locations. An
important element in avoiding catastrophes is to study
the site geology for dangerous conditions, implement the
types of blasting procedures that minimize failures, and
evaluate the potential use of reinforcement or other
mechanical stabilizing procedures.
LIST OF FIGURES
FIGURE NO. TITLE PAGE NO.
1 LINE DRILLING PATTERN 7
2 TRIM(CUSHION) BLASTING 8
PATTERN
3 SMOOTH(CONTOUR) BLASTING 9
PATTERN
4 PRINCIPAL OF PRE-SPLITTING 11
5 MUFFLE BLASTING 12
6 AIR DECKING PATTERN 13
7 BLAST PATTERN FOR TEST 17
NO.
1 & ITS RESULT
8 BLAST PATTERN FOR TEST NO. 19
2 & ITS RESULT
9 BLAST PATTERN FOR TEST 20
NO.
3
CHAPTER – 1
INTRODUCTION
To mitigate adverse impact of blasting in opencast and
underground mines
All techniques have one common objective that is better
distribution of explosive charge specially at the periphery of
the blast in order to minimize stressing and fracturing of
the rock beyond the excavation line.
Open pit mine and quarries are carrying out mega blasts
very often in order to enhance their production and thus
quantity of explosive consumption is increasing.
Increased population and spread of urbanization near
the mining sites have affected more people by blasting.
Increased public awareness and involvement of various
govt. agencies mining and environment laws and
regulations are becoming more and more strict in order to
prevent damages of properties, structures etc.
To improve overall environmental and safety
standards To Optimize overall cost
To get required fragmentation
To prevent environmental hazards of blasting
To achieve overall good % recovery of deposit
Over break
Reduce ground vibrations
Reduce fractures within remaining rockwalls
Reduce noise
Reduce dilution/ waste of ore
CHAPTER – 2
CONTROL BLASTING TECHNIQUES
preventing/controlling back-break;
controlling excessive ground vibrations;
filtering the effects of explosive gases from
production blasting
3.1 – INTRODUCTION
The main objectives of pre-splitting in open pit mining
operations are: preventing/controlling back-break;
controlling excessive ground vibrations; and filtering the
effects of explosive gases from production blasting.
Presplitting in open pit mining is performed by arranging
a row of blasting holes behind the main blast pattern
(production holes). These holes will be blasted before or
at the same time with production holes and separate the
remaining rock mass from the blasting block. This artificially
created free surface has been shown to be successful in
controlling back break. The separating surface attenuates
propagation of expanding gases to the remaining rock
mass i.e. the final Walls. In this method, a buffer row is
placed in front of the pre-split to achieve better back-
break control. Buffer holes are a row of lightly loaded
blast holes in between the production and pre-split holes
and are intended to adequately fragment the rock
between the buffer row and the final wall without over-
break. With regard to securing the desired
fragmentation, the blast design is significantly important.
However, it must be noted that the fragmentation, too,
encounters problems because many factors are out of
reach of the blast engineer hence solution seems to be
difficult.
Design of blast experiments is a method of defining
optimal pattern of presplitting. In this study, pre-splitting
is tested in GOLEGOHAR iron mine.
The rest of the paper is as follows: first, the case study
is introduced and the results of three sets of pre-splitting
experiments are discussed. Finally, the conclusion of the
case study is summarized
CONCLUSION: