Professional Documents
Culture Documents
Daily Concrete Plan (Autorecovered)
Daily Concrete Plan (Autorecovered)
Daily Concrete Plan (Autorecovered)
APROX START
S.NO CHAINAGE SIDE STRUCTURE TYPE COMPONENT GRADE OF CONCRETE QTY (CUM) Ach. (QTY) POUR BY REQUIRED BY REMARKS
TIME
CHAINAGE 214+260 TO 236+000 (BAR KA PARA PLANT)
1 214+606 RHS MJB PIER P2 NO. 2&3 10 BUCKET 8:00AM KHEMCHAND
2 215+253 RHS SVUP WALL A1&A2 2ND LIFT 20 BOOM PLACER 8:00AM KHEMCHAND
3 217+782 LHS FLYOVER ABUTMENT A1 PIER NO.2 BUCKET 8:00AM KHEMCHAND
9
4 217+782 RHS FLYOVER ABUTMENT A2 PIER NO. 3 FIRST LIFT BUCKET 8:00AM KHEMCHAND
5 217+782 RHS FLYOVER ABUTMENT A2 PIER NO. 1&2 STATRTR 1.1
CHAINAGE 236+000 TO 243+000 (238 PLANT)
1 242+341 RHS SVUP RETAINING WALL 3RD LIFT A2 SIDE 6 BOOM PLACER RAVI
2 238+066 MJB 48.5 BOOM PLACER FARUK
3 238+066 MJB PILE P4/03 40 FARUK
4 238+066 GIRDER 49.5 BOOM PLACER FARUK
CHAINAGE 243+000 TO 247+310 (BONLI PLANT)
1 246+838 LHS SVUP PCC 17.8 MANUALLY HIMANSHU