Professional Documents
Culture Documents
A Probabilistic Approach To Transformer Overloading Afzal Majid Mubarak A. Al-Mulhim
A Probabilistic Approach To Transformer Overloading Afzal Majid Mubarak A. Al-Mulhim
A Probabilistic Approach To Transformer Overloading Afzal Majid Mubarak A. Al-Mulhim
Approximately, 25% of the SEC/ER load is contributed • Temperature above 300C prevails during a period of
by residential/commercial and light industrial customers. more than six months.
These customers are supplied power mostly at 13.8 kV
distribution voltage through 115/13.8 kV or 69/13.8 kV • Temperature of 400C and above prevails during a
area substations. These area substations are supplied period of more than three months.
power at 115 kV or 69 kV from 230/115 kV or 230/69
kV bulk supply stations.
θ = Αverage Temperature
Summer 38 oC
Winter 19 oC
Fall/Spring 29 oC
Figure 1 – Annual Temperature Duration Curve
5. LOAD CHARACTERISTICS
6. COST DATA
Figure 3 - Daily Maximum Demand and Average Temperature The costs for different types of transformers, are given
in Table-1. These material costs are of study quality and
Figure 4 shows the annual load duration curves (LDC) do not include the cost of terminations and the
for the SEC/ER system and the most densely populated associated equipment such as relay panels, surge
area in the Eastern Province of Saudi Arabia. From the arresters and foundations etc. It should be noted that the
load duration curves, the following is noted: cost of associated equipment and installation may vary
from 30% to more than 100% of the transformer cost.
• Peak load of 80% or more occurs for a period of 4
months. Table-I Standard Transformers and Material Costs.
• During the low load period, the load ranges
between 20~50% of the annual peak. Voltage Ratio Transformer Sizes (*) Cost ($)
100/133/167 MVA 1,965,000
150/200/250 MVA 2,288,000
230/115 kV
200/250/300 MVA 2,611,000
300/400 MVA 3,256,000
100/133/167 MVA 1,907,000
230/69 kV 135/180 MVA 2,053,000
150/200/250 MVA 2,200,000
30/40 MVA 667,000
115/13.8 kV
50/67 MVA 763,000
30/40 MVA 533,000
69/13.8 kV
50/67 MVA 733,000
* ONAN/ONAF/ONAF2
Figure 4 – Annual Load Duration Curves
Figure 6 shows the different cost components of a
The actual daily load profile is very unique. On an typical 69/13.8 kV substation. It is noted that, regardless
hourly basis, the large dependence of the demand on of the substation design optimization, transformer rating
temperature is quite apparent. plays a vital role in deciding the substation firm capacity
and contributes to 24% of the overall substation cost.
Figure 5 shows the typical summer daily load and Keeping in view that almost 76% of the capital cost
temperature profiles for a 69/13.8 kV substation. It is accounts for the substation facilities other than the
noted that hourly load profile shows a time lag of 2 to transformers, it becomes quite important to increase the
3-hour between the maximum temperature and the transformer utilization factor in order to effectively
maximum demand. This is because of the dominantly air increase the substation capacity before substation
conditioning load. The figure also reveals the high daily reinforcement or installation of a new substation.
load factor of about 89%, during summer, in the
SEC/ER system.
not exceeding 115oC), during an annual load cycle
provided at other times during the same year the hot
spot temperature is kept below 98oC to compensate for
additional loss of life which takes place during operation
above 98oC.
3) Transformer failures are generally remedied by load The following points should be kept in focus while
transfer and then replacement with a spare which is establishing the Transformer Overloading Criteria:
assumed to be always available.
* The overloading criteria should not be too optimistic
4) Transformer failures are rare and random. and it should be applicable to all the transformers at
different locations and regardless the age of the
5) Appropriate protection schemes are employed to transformer.
limit the overload in order to prevent sudden and
catastrophic failure. * It should be chosen such that the other accessories
and substation components are not exposed to
Transformers can be operated at hot spot temperature undesirable operating conditions which they are not
above 98oC, but below 140oC (with top oil temperature designed for.
N = Total number of equal time intervals
* It should also encompass the possibility of more
severe contingency conditions. IEC Loading Guide [1] describes three general types of
transformer overloading which are defined primarily by
* The economic gain should be carefully calculated the overload duration and reflect the generally accepted
before any criteria is adopted. concept that risk of accelerated aging or loss-of-life can
be tolerated for short periods of time.
* The transformer parameters such as top oil
temperature rise, average oil temperature rise should ‘Normal Cyclic Loading’ – for overloading conditions
be chosen such that they cover the whole spectrum that may occur continually over an extended period of
of transformers. time or may be throughout the life time of the
transformer. It is the most conservative rating in terms
* Adequacy of transmission circuits and other allied of allowable equipment temperature.
facilities should be taken into account.
‘Long-time Emergency Cyclic Loading’- for
8. TRANSFORMER LOADING GUIDES overloading conditions that are quite rare and generally
result from the prolonged outage (of undefined duration)
Transformers can supply loads beyond their nameplate of some system components that will not be reconnected
ratings as per IEC354 [1] and ANSI C57.91 [2], for before a steady state temperature rise is reached in the
various periods of time with normal or accelerated aging transformer. This is not a normal operating condition
of their insulation life depending upon several factors. and its occurrence is expected to be rare, but it may
The loading guides provide recommendations on both persist for weeks or months and can lead to considerable
short term and long term overloading . aging. However, it should not be the cause of
breakdown due to thermal destruction or reduction in
As a result of operation at increased temperatures, the dielectric strength.
transformer insulation ages at an increased rate.
Consequently, the expected life of the transformer is ‘Short-time Emergency Loading’- for abnormally
shortened. In fact, the normal insulation life is not an heavy loads due to more unlikely events causing serious
absolute indicator of the life of a transformer. Rather, it disturbance in the system, resulting in the hot spot
is a value that is based on the past experience and temperature to dangerous levels and a temporary
laboratory testing and represents average time of the reduction in the dielectric strength. Acceptance of this
degradation of the insulation to a point where it is no loading condition may be preferred over other
longer safe for continued operation without a high risk alternatives but the load at the transformer must be
of failure. An average life of 180,000 hours has been reduced rapidly or it should be disconnected from the
used in the study [2]. system within a short time in order to avoid its failure.
Typically, it would be less than half an hour (t<30
IEC loading guide [1] does not define the life time of minutes). The permissible duration of this load is less
the insulation. Instead it relies solely on ‘the relative than the thermal time constant of the transformer and
loss of life’ and a reference temperature of 98 oC at depends upon the ambient temperature.
which the transformer will have ‘normal life’ The
temperature gradient causing the degradation rate to In general, planned overloads are tolerated and winding
double is assumed to be 6 K. The relative aging rate (V) hotspot temperatures are allowed to exceed 980C. Under
is defined as: expedient emergency short-term overload conditions,
the winding hot spot temperature is almost universally
restricted to 140 0C [4].
Reliability related costs involve loss of life of It is the probability that restoration to service occurs
equipment, loss of revenue and customer costs related to before time ‘t’, given that the unit entered the outage
the interruption of service. Quantification of these costs state at time t=0.
involve simulation of the system conditions associated
with equipment loss of life, repair and service Monte-Carlo method is used to simulate the life history
interruption. of a transformer. Random sampling of an outage event is
done by generating a random number (between 0 and 1)
to simulate the outage event and using the in-service
distribution, the time when the transformer enters into an
outage state is identified. Likewise, the time when the
transformer is restored is identified by generating
another random number and using the out-of-service
distribution. Depending upon the load and temperature
at the time of the simulated event, the remaining
transformer may get overloaded. An overload that is
beyond the transformer nameplate rating will cause the
Figure 9 – Two-State Model
transformer aging at a higher rate.
At any time, a transformer at a substation can be in
Each simulation run consists of at least 1000
either of the two states: in-service and out-of-service,
replications. In each replication, a random transformer
and the state changes randomly from time to time. The
outage is selected during one year of operation. A limit
transition to the out-of-service state is an outage event
is set on the magnitude of overload and the
and the transition to the in-service state is the
corresponding outage duration is computed. During
restoration. The entire process consists of repetitions of
outage, the transformer overload, loss-of-life and MWH
outage-to-restoration and restoration-to-outage process.
load curtailed is computed. The average values are
A transformer is modeled with a constant failure rate
computed and converted into economic figures for
(λ) and a constant repair rate (µ). If a transformer was
trade-off analysis.
restored to service at time t=0, the average outage rate
(λ) of a transformer is defined as the probability that a
The following data was used in the study:
transformer experiences an outage at time t. Similarly, if
a transformer entered into an outage state at time t=0,
Ambient Temperature : 20/30/40 oC
then restoration rate (µ) can be defined as the
probability that the transformer is restored at time t, i.e. (winter/fall/summer)
the transformer remained in the outage state up to time Cost of Energy not Served : 1000 $/MWH
‘t’. For a constant outage rate, R(t), the probability of Mean Time to Failure : 87600 hrs (10 years)
survival of a transformer at time ‘t’, is given by: Mean Time to Repair : 672 hours
Interest Rate : 10%
R(t) = e-λt : 20.5 Years
Transformer Useful Life
And, the in-service duration distribution is given by:
Each simulation was performed using the hourly load
-λt profile for a specific annual peak load i.e. the maximum
Fi (t) = 1 - e
overload that each transformer would be exposed to
under contingency conditions. The transformer was
Where, λ is the failure rate, i.e.
assumed to operate in the same fashion every year
λ = 1/MTTO throughout the entire useful life of the equipment. The
MTTO= Mean Time to Outage purpose of these computations is to identify the
maximum level of overload that a transformer can
Fi (t) is the probability that a transformer experience Ist tolerate before an additional unit is needed.
outage prior to time ‘t’ given that it was restored at time
t=0. In other words, the in-service duration distribution- Each substation is assumed to have two identical
means that the transformer has survived up to time ‘t’ transformers. The hourly load profile at each substation
when it enters into a failure state. is according to its historical loadings. The hourly loads
were scaled up according to the ratio of the specified
annual peak load (overload limit) divided by the It should be noted that in the probabilistic calculations,
observed peak load. the relationship between the cost of loss-of-life and the
maximum transformer loading was studied without
Simulations were also carried out for a fixed outage regards to temperature limits.
duration of 7 days. This was done to study the
practicality and economic aspects of Transformer It is noted that the costs of energy-not-served are
Overloading Criteria with regards to ‘Transformer substantially higher than the costs of transformer loss-
Replacement Strategy’. For these simulations, a of-life, suggesting that some degree of transformer
representative temperature profile was used instead of overload, and hence, loss-of-life, has to be tolerated
fixed temperatures for different seasons and load before load curtailment is considered. In other words,
shedding was allowed in order to limit the transformer curtailing load as soon as the transformer is loaded to
hotspot temperature. Also, it was assumed that the 100% of its rating is not an economic option.
transformer will operate under the same conditions for 7
days. The amount of load shedding (MWH curtailed) When the cost of loss-of-life exceeds the capital
and the loss-of-life were computed. recovery factor (CRF), then it is more economical to add
a new transformer by substation reinforcement or install
11. STUDY RESULTS a new substation. For example, in the case of a 115/13.8
kV transformer, the break even point is about 170%
The results from the transformer loss-of-life using normal parameters and about 160% using more
computations, are presented in the section. pessimistic assumptions (maximum summer ambient
temperature equal to 50oC). This means that the
An outage event which results in a transformer overload substation annual peak load can grow to about 160% to
above 100% of its rating, a transformer loss-of-life is 170% of the transformer rating before third transformer
computed Also, the MW and the hours of overload are needs to be installed.
recorded to give an annual MWH exposure. This
number represents the amount of load which must be
curtailed if transformer overload is to be avoided
completely. The amount of load curtailed (also called
energy-not-served, or ENS) is converted to economic
figures.