A Probabilistic Approach To Transformer Overloading Afzal Majid Mubarak A. Al-Mulhim

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

21, rue d'Artois, F-75008 Paris

http://www.cigre.org 12-112 Session 2002


© CIGRÉ

A Probabilistic Approach to Transformer Overloading

AFZAL MAJID* MUBARAK A. AL-MULHIM

Systems Planning Department


Saudi Electricity Company, Eastern Region Branch

KINGDOM OF SAUDI ARABIA

SUMMARY to stress the system to undesirable levels with the aim of


economic gain. Therefore, it should essentially be based
This paper presents the results of a comprehensive
on system historical data and characteristics. Also, it
value based reliability planning analysis of substation
should be well defined and understood.
capacity addition with the long-range perspective for
different types of applications in the Saudi Electricity
2. PLANNING CRITERIA
Company in the Eastern Province (SEC/ER) system. The
analysis involves quantification and comparison of
The Old Paradigm:
major costs associated with the installation and
operation of power system components to determine the
SEC/ER has adopted single contingency (N-1) criteria
most attractive transformer overloading criteria. The
for bulk as well as residential/commercial substations.
main emphasis is on the explicit recognition of inherent
Accordingly, substations are planned with at least two
overloading capability of transformer and its
power transformers but keeping the load up to the
acceptance under critical system conditions may be
capacity of (N-1) transformers, only, so that in the event
preferable over other alternatives.
of a transformer failure, service continuity to the
customers is maintained.
KEYWORDS: Power, System Planning, Transformer
Overloading
Firm capacity (in MVA) of a substation with N identical
transformers is defined as:
1. INTRODUCTION
Firm Capacity = Transformer Rating x (N-1)
Deregulation is fostering a new competitive
environment where strong market forces will exist,
The New Paradigm:
depressing the price of wholesale energy. Therefore,
instead of relying on ‘built-in’ and ‘undefined’ margins,
The main emphasis is on the explicit recognition of
a probabilistic approach should be adopted to optimize
inherent transformer overloading capability and
capital investment on installation and operation of
acceptance of limited customer outages under single
power infrastructure so as to sustain the strong market
contingency conditions, in an effort to optimize capital
forces and maintain the market share.
investment on system expansion.
Transformer overloading above nameplate rating offers
Therefore, reinforcement projects are initiated to
flexibility in operation as well as economic benefits. The
increase the capacity of a substation or installation of a
intent of transformer overloading is to adopt a trade-off
new substation only after the load at an existing
between increased loss of life and the costs associated
substation exceeds the capacity of (N-1) transformers,
with the loss of service. However, transformer
by a certain factor. Alternatively, the substation firm
overloading criteria, if not carefully selected, would tend
capacity (in MVA) may be redefined as:
_______________________________________________________________________________________________
SPD, SEC-ER, Rm. 1-200E, P.O. Box 5190, Dammam 31422, Saudi Arabia
Firm Capacity = Transformer Rating x (N-1) x F Figure 1 shows the (typical) annual temperature duration
Where, F = Overload Factor (>1) for SEC/ER system. Figure 2 shows the mean of daily
maximum and average temperature for 1999. It is noted
3. THE EXISTING SYSTEM that:

Approximately, 25% of the SEC/ER load is contributed • Temperature above 300C prevails during a period of
by residential/commercial and light industrial customers. more than six months.
These customers are supplied power mostly at 13.8 kV
distribution voltage through 115/13.8 kV or 69/13.8 kV • Temperature of 400C and above prevails during a
area substations. These area substations are supplied period of more than three months.
power at 115 kV or 69 kV from 230/115 kV or 230/69
kV bulk supply stations.

Standard transformer ratings for different types of


substations that are generally used in the SEC/ER
system, are given in Table-I.

Transformers are connected in parallel to ensure system


reliability and security during contingency conditions. In
this mode, their aging rate is consistent with units
operating at 50~67% of their nameplate rating.
Therefore, there is a potential to operate these
transformers, during contingency conditions, at loads
greater than their nameplate ratings and above normal
temperatures without adverse results provided this is Figure 2 - Mean of Daily Average and Maximum Temperature
done knowledgably.
The weighted ambient temperature [1] is defined as a
SEC/ER transformers are generally designed to keep hot constant temperature which during a specified time,
spot temperature at 98oC or below when operated at causes the same aging of the transformer insulation as a
100% of the nameplate rating at an average ambient variable ambient temperature acting during that time.
temperature of 30oC. Under these operating conditions,
the transformer loss of life is taken as unity. If the hot It should be noted that if the aging and hotspot
spot temperature is above 98oC, the loss of life is more temperature calculations are limited to a few days of
than unity. In other words, the rate of aging is high when operation with load beyond nameplate rating, it may be
the hot spot temperature is higher than 98oC. found more suitable to use actual temperature profile
that is expected for that period.
4. ENVIRONMENTAL CONDITIONS
IEC-354 [1] recommends a method for calculating the
The climate in the Eastern Province of Saudi Arabia is weighted ambient temperature for use in transformer
characterized as very harsh with intense heat, humidity loss-of-life calculations where the ambient temperature
and frequent strong winds. Heavy rains and sand storms is variable. The weighted ambient temperature is
occasionally occur. The atmosphere is highly corrosive calculated using the following equation:
particularly near the coastal area. During summer,
ambient temperature reaches up to 50o C. Whereas, the
monthly average of hottest month is about 400C. The θ E = θ + 0.01(∆θ) 1.85
yearly average ambient temperature is 30oC. Where,

θE = Weighted Ambient Temperature

θ = Αverage Temperature

∆θ = Μean Value of Maxima-Mean Value of Minima

For the SEC/ER system, the following weighted ambient


temperatures are calculated:

Summer 38 oC
Winter 19 oC
Fall/Spring 29 oC
Figure 1 – Annual Temperature Duration Curve
5. LOAD CHARACTERISTICS

The load demand undergoes large seasonal variations.


Figure 3 shows the average temperature and load profile
for the year 1999 in SEC/ER system. It is noted from
Figure 3 that the area load is largely dependent on the
ambient temperature. A major component of residential
and commercial load is air-conditioning. Accordingly,
the peak load occurs during summer.

Figure 5 – Daily Load, Temperature Profiles and LDC

Figure 5 also shows typical load duration curve for a


typical summer day. It is noted from this curve that load
above 85% of the peak may last for more than 12 hours.

6. COST DATA

Figure 3 - Daily Maximum Demand and Average Temperature The costs for different types of transformers, are given
in Table-1. These material costs are of study quality and
Figure 4 shows the annual load duration curves (LDC) do not include the cost of terminations and the
for the SEC/ER system and the most densely populated associated equipment such as relay panels, surge
area in the Eastern Province of Saudi Arabia. From the arresters and foundations etc. It should be noted that the
load duration curves, the following is noted: cost of associated equipment and installation may vary
from 30% to more than 100% of the transformer cost.
• Peak load of 80% or more occurs for a period of 4
months. Table-I Standard Transformers and Material Costs.
• During the low load period, the load ranges
between 20~50% of the annual peak. Voltage Ratio Transformer Sizes (*) Cost ($)
100/133/167 MVA 1,965,000
150/200/250 MVA 2,288,000
230/115 kV
200/250/300 MVA 2,611,000
300/400 MVA 3,256,000
100/133/167 MVA 1,907,000
230/69 kV 135/180 MVA 2,053,000
150/200/250 MVA 2,200,000
30/40 MVA 667,000
115/13.8 kV
50/67 MVA 763,000
30/40 MVA 533,000
69/13.8 kV
50/67 MVA 733,000
* ONAN/ONAF/ONAF2
Figure 4 – Annual Load Duration Curves
Figure 6 shows the different cost components of a
The actual daily load profile is very unique. On an typical 69/13.8 kV substation. It is noted that, regardless
hourly basis, the large dependence of the demand on of the substation design optimization, transformer rating
temperature is quite apparent. plays a vital role in deciding the substation firm capacity
and contributes to 24% of the overall substation cost.
Figure 5 shows the typical summer daily load and Keeping in view that almost 76% of the capital cost
temperature profiles for a 69/13.8 kV substation. It is accounts for the substation facilities other than the
noted that hourly load profile shows a time lag of 2 to transformers, it becomes quite important to increase the
3-hour between the maximum temperature and the transformer utilization factor in order to effectively
maximum demand. This is because of the dominantly air increase the substation capacity before substation
conditioning load. The figure also reveals the high daily reinforcement or installation of a new substation.
load factor of about 89%, during summer, in the
SEC/ER system.
not exceeding 115oC), during an annual load cycle
provided at other times during the same year the hot
spot temperature is kept below 98oC to compensate for
additional loss of life which takes place during operation
above 98oC.

An example of transformer overload and rise in hot spot


temperature during contingency condition, is shown in
Figure 7.

Figure 6 –Cost Components of a Typical 69/13.8 kV Substation

The average cost of a typical conventional 69/13.8 kV


indoor type substation with two 30/40 MVA
transformers, is $10.7 million, including the cost of
underground cables. The cost of an outdoor type
115/13.8 kV substation is slightly higher than that of an
indoor type 69/13.8 kV substation because of various
factors involved.
Figure 7 – Transformer Overload Event
Further, a factor called the Capital Recovery Factor
(CRF) is used in the study. It is the cost of a transformer The major consequences of operating transformers
spread over its useful life, and is given by: above their nameplate ratings are:

 Higher operating temperature reduces the life of


insulation at increasingly higher rates. Therefore,
long term overloading policies do not permit
Where, winding hotspot temperature which substantially
P = Capital Cost of Transformer reduces the life a transformer.
i = Interest Rate (p.u.)
n = Transformer Life (years)  Bubble formation which is believed to occur when
hot spot temperature adjacent to oil exceeds 140 0C
This factor is used to estimate the cost of loss-of-life of approximately. Therefore, overloads have to be
a transformer. restricted to avoid this hazard.

7. TRANSFORMER OVERLOADING  Usually heavy loading can cause high temperatures


within the winding with a high aging rate of the
The transformer overloading concept is based on the insulating paper.
following:
It may be necessary to accept overloading the
1) Transformers have the ability to withstand overloads transformer or even customer outages to some extent,
for short periods with additional loss of life. in case of emergency conditions, because it may be
preferable to other alternatives such as huge capital
2) Typical peak load condition lasts only for a limited investment on new facilities or load shedding to a large
period of time. extent.

3) Transformer failures are generally remedied by load The following points should be kept in focus while
transfer and then replacement with a spare which is establishing the Transformer Overloading Criteria:
assumed to be always available.
* The overloading criteria should not be too optimistic
4) Transformer failures are rare and random. and it should be applicable to all the transformers at
different locations and regardless the age of the
5) Appropriate protection schemes are employed to transformer.
limit the overload in order to prevent sudden and
catastrophic failure. * It should be chosen such that the other accessories
and substation components are not exposed to
Transformers can be operated at hot spot temperature undesirable operating conditions which they are not
above 98oC, but below 140oC (with top oil temperature designed for.
N = Total number of equal time intervals
* It should also encompass the possibility of more
severe contingency conditions. IEC Loading Guide [1] describes three general types of
transformer overloading which are defined primarily by
* The economic gain should be carefully calculated the overload duration and reflect the generally accepted
before any criteria is adopted. concept that risk of accelerated aging or loss-of-life can
be tolerated for short periods of time.
* The transformer parameters such as top oil
temperature rise, average oil temperature rise should ‘Normal Cyclic Loading’ – for overloading conditions
be chosen such that they cover the whole spectrum that may occur continually over an extended period of
of transformers. time or may be throughout the life time of the
transformer. It is the most conservative rating in terms
* Adequacy of transmission circuits and other allied of allowable equipment temperature.
facilities should be taken into account.
‘Long-time Emergency Cyclic Loading’- for
8. TRANSFORMER LOADING GUIDES overloading conditions that are quite rare and generally
result from the prolonged outage (of undefined duration)
Transformers can supply loads beyond their nameplate of some system components that will not be reconnected
ratings as per IEC354 [1] and ANSI C57.91 [2], for before a steady state temperature rise is reached in the
various periods of time with normal or accelerated aging transformer. This is not a normal operating condition
of their insulation life depending upon several factors. and its occurrence is expected to be rare, but it may
The loading guides provide recommendations on both persist for weeks or months and can lead to considerable
short term and long term overloading . aging. However, it should not be the cause of
breakdown due to thermal destruction or reduction in
As a result of operation at increased temperatures, the dielectric strength.
transformer insulation ages at an increased rate.
Consequently, the expected life of the transformer is ‘Short-time Emergency Loading’- for abnormally
shortened. In fact, the normal insulation life is not an heavy loads due to more unlikely events causing serious
absolute indicator of the life of a transformer. Rather, it disturbance in the system, resulting in the hot spot
is a value that is based on the past experience and temperature to dangerous levels and a temporary
laboratory testing and represents average time of the reduction in the dielectric strength. Acceptance of this
degradation of the insulation to a point where it is no loading condition may be preferred over other
longer safe for continued operation without a high risk alternatives but the load at the transformer must be
of failure. An average life of 180,000 hours has been reduced rapidly or it should be disconnected from the
used in the study [2]. system within a short time in order to avoid its failure.
Typically, it would be less than half an hour (t<30
IEC loading guide [1] does not define the life time of minutes). The permissible duration of this load is less
the insulation. Instead it relies solely on ‘the relative than the thermal time constant of the transformer and
loss of life’ and a reference temperature of 98 oC at depends upon the ambient temperature.
which the transformer will have ‘normal life’ The
temperature gradient causing the degradation rate to In general, planned overloads are tolerated and winding
double is assumed to be 6 K. The relative aging rate (V) hotspot temperatures are allowed to exceed 980C. Under
is defined as: expedient emergency short-term overload conditions,
the winding hot spot temperature is almost universally
restricted to 140 0C [4].

The aging calculations are based on the determination of


Where,
winding hot spot temperature. In the study, IEC method
θh = Hot Spot Temperature is used in calculating the winding hot spot temperature
and loss of life. For OF cooling, the steady state winding
With varying operating conditions and temperature, the hotspot temperature can be calculated as:
relative aging rate (relative loss-of-life) over a certain
period of time is then equal to:

For transient temperature, the oil temperature rise (i.e.


Where,
for bottom oil) is given by the following equation:
n = number of each time interval
compensated and there is essentially no additional loss
of life.

The capital cost (material only) of a 69/13.8 kV 40


Definitions of different parameters in these equations MVA transformer is assumed to be $0.53 million. For a
are given in [1]. useful transformer life of 21 years, the cost of each
overloading incident because of transformer loss of life,
would be approximately $19,200 per incident.

On the other hand, the saving in capital investment using


the 15% overloading criteria would be $76,267 per year
per substation, assuming $0.27 million per MVA capital
cost. This indicates that there is a net economic gain
of approximately $57,067 per substation per year, if
the transformer fails during that year and
approximately $76,267 if the transformer does not
fail.

However, if an attempt is made to establish the


Figure 8 – Permissible Overloads for Standard Transformer overloading criteria over 15% (say 20%), the resulting
hotspot temperature exceeds the 140oC limit, and hence
Using the above equations and the tables given in [1], it not possible regardless of the aging rate and the net
can be shown that (Figure 8) if a standard IEC economic gain. This approach has drawbacks because it
transformer is operated at 30oC, it can be loaded to does not consider that:
120% of its nameplate rating at an increased aging rate,
if the hot spot temperature is allowed to reach the 140oC * Transformer outages are rare and random.
limit and 116% of its nameplate rating if the hotspot * Transformer overloads are of varying magnitude and
temperature is limited to 130oC maximum. Therefore, it duration.
is concluded that a standard transformer can be safely * Load can be transferred to other neighboring
operated at 115% of its nameplate rating during substations within a few hours.
contingency conditions at an increased aging rate. This * For a short duration, a transformer can handle load
conclusion can be easily generalized for transformers in more than 115% of its nameplate rating (Figure 8).
the SEC/ER system.
In spite of the drawbacks of this approach, it is
9. DETERMINISTIC APPROACH concluded that there is a potential of economic gain if
transformers are planned for overloading by 15%
SEC/ER has adopted an overloading criteria of 15% for beyond their nameplate ratings.
emergency operation. However, this criteria is not used
for planning purposes. In this section, a brief description 10. STUDY METHODOLOGY
of the approach is given to establish the 15%
overloading criteria applicable for 69/13.8 kV There are two fundamental approaches for reliability
substations with two 30/40 MVA transformers. The evaluation of power system components: Analytical
approach and the conclusions are similar for the other techniques and Monte Carlo methods. Analytical
types of transformers. A flat load profile and an techniques involve assessment of system failure by
overload duration of 12 hours has been assumed. modeling which is based on the past outage statistics of
the system. In Monte Carlo methods, system
A transformer would be loaded to a maximum of 57.5% contingency conditions are simulated through random
of its nameplate rating throughout its lifetime except variables representing specific contingency conditions.
during the period when it experiences overloading under In this study, the focus is on establishing the transformer
contingency conditions. Assuming that it takes 12 days overloading criteria by using a probability model and
to replace the failed transformer and there is no load simulating outage conditions using Monte Carlo
transfer, calculations show that the transformer hotspot technique. Such a study would tend to recommend a
could rise to 133oC (θα=35 oC) and the aging rate will higher overloading criteria. However, the important
be accelerated to 23 ‘normal days’ per day resulting in factors that should be considered are given in Section 7.
the transformer loss of life equivalent to 276 ‘normal For the purpose of this study , it is assumed that:
days’ per incident, during the assumed overload
duration. Whereas, the loss of life would be not more a) Transformer outage rate is computed for different
than 11 ‘normal days’ for the rest of the year. So, the substation arrangements and for the overall system.
transformer loss of life under contingency is well
b) For certain applications, the outage duration can be Likewise, the out-of-service duration distribution is
considered as constant depending upon the time given by:
required for load transfer or transformer µt
Fo (t)= 1 - e-
replacement. Where,
µ = 1/MTTR
c) Load and temperature profiles are standardized. MTTR= Mean Time to Restoration

Reliability related costs involve loss of life of It is the probability that restoration to service occurs
equipment, loss of revenue and customer costs related to before time ‘t’, given that the unit entered the outage
the interruption of service. Quantification of these costs state at time t=0.
involve simulation of the system conditions associated
with equipment loss of life, repair and service Monte-Carlo method is used to simulate the life history
interruption. of a transformer. Random sampling of an outage event is
done by generating a random number (between 0 and 1)
to simulate the outage event and using the in-service
distribution, the time when the transformer enters into an
outage state is identified. Likewise, the time when the
transformer is restored is identified by generating
another random number and using the out-of-service
distribution. Depending upon the load and temperature
at the time of the simulated event, the remaining
transformer may get overloaded. An overload that is
beyond the transformer nameplate rating will cause the
Figure 9 – Two-State Model
transformer aging at a higher rate.
At any time, a transformer at a substation can be in
Each simulation run consists of at least 1000
either of the two states: in-service and out-of-service,
replications. In each replication, a random transformer
and the state changes randomly from time to time. The
outage is selected during one year of operation. A limit
transition to the out-of-service state is an outage event
is set on the magnitude of overload and the
and the transition to the in-service state is the
corresponding outage duration is computed. During
restoration. The entire process consists of repetitions of
outage, the transformer overload, loss-of-life and MWH
outage-to-restoration and restoration-to-outage process.
load curtailed is computed. The average values are
A transformer is modeled with a constant failure rate
computed and converted into economic figures for
(λ) and a constant repair rate (µ). If a transformer was
trade-off analysis.
restored to service at time t=0, the average outage rate
(λ) of a transformer is defined as the probability that a
The following data was used in the study:
transformer experiences an outage at time t. Similarly, if
a transformer entered into an outage state at time t=0,
Ambient Temperature : 20/30/40 oC
then restoration rate (µ) can be defined as the
probability that the transformer is restored at time t, i.e. (winter/fall/summer)
the transformer remained in the outage state up to time Cost of Energy not Served : 1000 $/MWH
‘t’. For a constant outage rate, R(t), the probability of Mean Time to Failure : 87600 hrs (10 years)
survival of a transformer at time ‘t’, is given by: Mean Time to Repair : 672 hours
Interest Rate : 10%
R(t) = e-λt : 20.5 Years
Transformer Useful Life
And, the in-service duration distribution is given by:
Each simulation was performed using the hourly load
-λt profile for a specific annual peak load i.e. the maximum
Fi (t) = 1 - e
overload that each transformer would be exposed to
under contingency conditions. The transformer was
Where, λ is the failure rate, i.e.
assumed to operate in the same fashion every year
λ = 1/MTTO throughout the entire useful life of the equipment. The
MTTO= Mean Time to Outage purpose of these computations is to identify the
maximum level of overload that a transformer can
Fi (t) is the probability that a transformer experience Ist tolerate before an additional unit is needed.
outage prior to time ‘t’ given that it was restored at time
t=0. In other words, the in-service duration distribution- Each substation is assumed to have two identical
means that the transformer has survived up to time ‘t’ transformers. The hourly load profile at each substation
when it enters into a failure state. is according to its historical loadings. The hourly loads
were scaled up according to the ratio of the specified
annual peak load (overload limit) divided by the It should be noted that in the probabilistic calculations,
observed peak load. the relationship between the cost of loss-of-life and the
maximum transformer loading was studied without
Simulations were also carried out for a fixed outage regards to temperature limits.
duration of 7 days. This was done to study the
practicality and economic aspects of Transformer It is noted that the costs of energy-not-served are
Overloading Criteria with regards to ‘Transformer substantially higher than the costs of transformer loss-
Replacement Strategy’. For these simulations, a of-life, suggesting that some degree of transformer
representative temperature profile was used instead of overload, and hence, loss-of-life, has to be tolerated
fixed temperatures for different seasons and load before load curtailment is considered. In other words,
shedding was allowed in order to limit the transformer curtailing load as soon as the transformer is loaded to
hotspot temperature. Also, it was assumed that the 100% of its rating is not an economic option.
transformer will operate under the same conditions for 7
days. The amount of load shedding (MWH curtailed) When the cost of loss-of-life exceeds the capital
and the loss-of-life were computed. recovery factor (CRF), then it is more economical to add
a new transformer by substation reinforcement or install
11. STUDY RESULTS a new substation. For example, in the case of a 115/13.8
kV transformer, the break even point is about 170%
The results from the transformer loss-of-life using normal parameters and about 160% using more
computations, are presented in the section. pessimistic assumptions (maximum summer ambient
temperature equal to 50oC). This means that the
An outage event which results in a transformer overload substation annual peak load can grow to about 160% to
above 100% of its rating, a transformer loss-of-life is 170% of the transformer rating before third transformer
computed Also, the MW and the hours of overload are needs to be installed.
recorded to give an annual MWH exposure. This
number represents the amount of load which must be
curtailed if transformer overload is to be avoided
completely. The amount of load curtailed (also called
energy-not-served, or ENS) is converted to economic
figures.

For each transformer, the capital cost of a replacement


transformer [Table-I] is used in calculating the CRF
which is then multiplied by the loss-of-life in years to
give the cost of loss-of-life per year. The cost of the
energy-not-served (ENS) is assumed to be incurred Figure 11 – Present Worth Cost for 230/69 kV Substation
every year. The numbers are then accumulated over 20.5
years of identical operation and present worthed to get Similar observations are made from the results of loss-
the cost of ENS. of-life computations for 230/69 kV transformers. The
break-even point between the cost of loss-of-life and the
CRF is noted to be at 171%.

Figure 10 – Present Worth Cost for 115/13.8 kV Substation

Figure 10 shows the results of loss-of-life computations


for 115/13.8 kV transformers, assuming that each Figure 12 – Present Worth Cost for 69/13.8 kV Substation
transformer is operated in a similar fashion for every
year of its useful life. The cumulative present worth cost Figure 12 shows the results of loss-of-life computations
of loss-of-life and cost of ENS for different levels of for 69/13.8 kV transformer, assuming that the overload
overloads, are shown in this figure. period would last for 7 days continuously and during
this period no load transfer takes place. Instead, load Figure 13 shows the cost savings for 69/13.8 kV
curtailment is carried out during the outage events substations. These savings can be realized by deferring
causing the hotspot temperature to exceed beyond the the new substation or reinforcement projects. The
acceptable limit. This is the reason for lower savings are quite substantial and it is noted that an
incremental increase in loss-of-life at higher overload overloading criteria of 130% would results in a
limits. The cost of load curtailment for such events is reduction of cost per MVA by 23% and a saving of $3.7
also shown. The transformer is assumed to have million in case of a new substation and $1.6 million in
identical operation every year throughout its life time. It case of reinforcement.
is interesting to note that the there is almost no risk if the
transformer is allowed to be overloaded to 130% of its It should be generally acceptable that transformers are
rating, or very limited risk if it is allowed to be not routinely overloaded. Weather and load conditions
overloaded to 150% should always be taken into account to determine the
overload magnitude and duration because the
12. CONCLUSIONS recommended overload may cause transformer
operating temperature to exceed the acceptable
As demonstrated, it is concluded that the present operating limit, resulting in customer outages.
concept of firm capacity, i.e. (N-1) criteria or even 15%
emergency overloading criteria is quite conservative. A The probabilistic calculations, however, do point out
substantial savings can be realized by allowing the that occasional loadings of up to 130% may be a more
transformers to overload during contingency conditions. reasonable criterion, balancing risk of customer outages
and economics.
In the SEC/ER system, load curtailment has never been
an option regardless of the overloading criteria. Instead, 13. ACKNOWLEDGEMENT
capital investments are made to install new facilities or
reinforce the existing ones. The acceptance of loss-of- The authors wish to take this opportunity to thank Mr.
life merely helps and relaxes the planning criteria Joseph Pilleteri of Systems Planning Department of
resulting in substantial cost savings through deferral of SEC/ER, for his continuous support and valuable
capital investment. Employing an overloading criteria comments during the development of this paper.
as a part of System Planning virtually raises the firm
capacity of a substation at the cost of reduction of life of 14. REFERENCES
the transformer. Reliability calculations indicate that an
overload up to 50% may be allowed with reasonable [1] Loading Guide for Oil Immersed Power
loss-of-life and limited risk but, in fact, a transformer Transformers [IEC-354 (1991)]
alone can not be considered as an independent
component in the system. It is in fact a component of a [2] IEEE Guide for Loading Oil Immersed
complete system in which the capability of other Transformers [IEEE-C57.91-1995]
elements cannot be ignored.
[3] Lifetime Evaluation of Transformers
From economical perspective and, as well as, keeping in [CIGRE WG12.09]
view the capability of the allied facilities and the risk of
load shedding, an overloading criterion of 130% for [4] ‘Survey of Power Transformer Overloading Field
planning and operation of power transformers appears to Practices’. [CIGRE WG 12-09]
be quite practical, assuming that a desired amount of
load in excess of transformer rating can be removed [5] ‘Survey of Power Transformer Overload Field
within a specified period either by load transfer or Practices’ [CIGRE WD 12.09]
customer interruption for a limited period of time.

Figure 13 – Cost Savings for 69/13.8 kV Substation

You might also like