Professional Documents
Culture Documents
Current Limitation in High Temperature Superconducting Transformers and Impact On The Grid
Current Limitation in High Temperature Superconducting Transformers and Impact On The Grid
(*) EDF – Division Recherche & Développement –1 Avenue du général de Gaulle – 92141 Clamart Cedex
-2-
one shown in Fig. 1, the time needed to detect, localise log (current)
and interrupt selectively the faulty feeder adds up to at
least 250 ms for conventional protection equipment. In
case of a main breaker failure, the delay and breaker
opening time of the next higher voltage level result in a
total fault duration that easily exceeds 1 s. In overhead
line networks it is common practice to apply automatic T1
log (voltage)
N=2 T2>T1
reclosure patterns. For short “open” periods the time T3>T2
integral of the “closed” periods represents a good T4>T3
approximation of the thermal load on the equipment.
Ic2
Normal transients, like the starting of large electric Ic3
motors, may reach amplitudes of an order of 2 p.u. Such
transients are not allowed to trip the protection system. Ic4 Ic1
In an electrical grid, where the feeding voltage is C p ⋅ density ⋅ (Tc − Top ) ⋅ ρ el / V 2 > t fault (1)
constant to a good approximation, the maximum fault where
current flowing in the conductor is determined by the I- tfault duration of the fault
V-curve of the HTS material. In parallel to the HTS Cp average specific heat of HTS material and
material a bypass conductor in good electrical contact is metallic bypass in contact with it.
needed to spread out the effect of local inhomogeneities density average density of HTS material and metallic
in the HTS material, as to avoid hot spots. The parallel bypass
resistances of HTS material and electrical bypass Tc critical temperature of the HTS at rated current
determine the rate and power density at which heat is and the related magnetic field
generated. Top rated operating temperature of the HTS
V voltage gradient along the conductor
Fig. 1 gives an example of typical Current - Voltage
ρel current dependent, overall combined resistivity
(I-V) curves of an HTS conductor for different
of HTS conductor and electrical bypass,
temperatures. HTS conductors exhibit a rather wide flux
averaged over the fault duration.
flow regime extending significantly above the critical
current Ic, where superconductivity noticeably enhances
The second condition for recovery under rated current is
the conductivity.
that the heat flux at the surface of conductor and bypass
be smaller than the steady state heat transfer available at
that instant.
jop ⋅ ρ el ⋅ d < h ⋅ (Tc − Top ) ⋅ (α + 1) / α
2 *
(2)
-3-
ρel*
20
is the current dependent average resistivity of 100
critical current 16-18 A DC
imposed current : 20 A peak
the conductor with its electrical bypass at the 15
50
end of the fault current limiting event, averaged 10
over time 0
Current (A)
Voltage (V)
h is the effective heat transfer coefficient -50 current 5
-10
-250
It is essential to note that due to the wide flux flow -300 -15
region, in HTS conductors ρel assumes very small
instantaneous values during the off-peak moments of the Fig. 2: Current and voltage traces of a 1 m section of
ac cycle, resulting in the low average resistivity allowing composite conductor during and after a fault of 150 ms
fast recovery.
1.3. Accessibility by conductor design and physical Fig. 2 shows current and voltage traces of a 1 m section
limits of this composite conductor during and after a fault of
150 ms. The critical current of this sample was 16 – 18
The amplitude of the first fault current peak is A. The conductor was insulated with about 0.2 mm thick
dominated by the flux flow resistance of the HTS polymer. The peak voltage gradient during the fault was
material. As the conductor heats up, the resistance of the 0.15 V/cm. It is recognised that the voltage decreases
bypass determines the short circuit current. Common slowly after the fault, under more than critical current.
alloys have resistivities of up to 100 µΩ.cm. The heat Once the current drops back to its operational level
capacity effective during the short term current limiting (after the fault clears), the voltage is significantly
event is limited by the low thermal conductivity of high reduced and is observed to decay slowly with time. This
resistivity materials. Handling and manufacturing behaviour confirms the possibility of fast operational
constraints put a lower limit on the thickness of BSCCO recovery. The behaviour is consistent with numerical
HTS conductors. Therefore the specific surface area for simulations using the IV curves of Fig. 1 which imply a
heat exchange cannot be increased infinitely. There is no temperature rise in the wire remaining below the
physical lower limit to overall operational r.m.s. current superconducting critical temperature. The time until
density; however economic considerations suggests a complete restoration of superconductivity at the
target of 10 A/mm2 or higher. The thermal conductivity operational temperature, i.e. the ability to take overloads
of electrical insulation will limit the available cooling. without going normal-conducting, was about two
Reducing the voltage gradient (electric field) can reduce seconds. Measurements on improved samples of up to
the energy deposition per unit mass, however mass and 60 meters in length have since confirmed the feasibility
cost of the transformer will increase inversely with of fast operational recovery.
gradient.
No refrigeration machine will be able to remove heat at
the rate it is generated during a fault. Therefore an 2.2. Input to the transformer design
interim heat sink in the form of solid material or liquid When designing a current limiting device, one first
coolant being heated or evaporated has to be provided. selects the desired operating current and the desired
max. fault current. Assuming no electrical bypass the I-
2. SELF LIMITING WIRE V-curve yields the maximum voltage gradient along the
conductor. For a given operating voltage this determines
2.1. Proof of the self limiting effect the conductor length. In order to maintain a good current
limitation and long fault holding times one selects an
We designed an HTS conductor, capable of limiting a electrical bypass with high heat capacity and resistivity;
fault current to about 10 times critical current in the first equ. 1 can be used as a coarse check whether the desired
peak and to return to the superconducting state while fault holding time can be reached with the materials to
carrying a current of Ic after fault durations of several be used. Since the heat transfer is usually limited, equ. 2
100 ms. To achieve basic current limiting capability, can be used to adjust the overall operating current
silver was alloyed with a base metal to increase the density and the thickness of the conductor.
matrix resistivity of the BSCCO tape to the order of
several µΩ.cm. To achieve operational recovery
capability, this modified HTS tape was then soldered
between two metallic tapes of about ten times the
superconductor thickness.
-4-
HV line
HV/M V
Circuit
Breaker Q
Q
CB R R
Feeders
Fig. 3: Standard HV/MV configuration
I (A)
Short-circuit current
Fault atQ
Rated current Fault atR Fig. 5: Short circuit currents and temperature in the
windings
0
The main result from these calculations is that the first
peak is reduced to less than 9 p.u. and then 2.5 p.u. r.m.s
Fault 2 cleared Fault 1 cleared Time after 700 ms. A conventional transformer with uSC = 7.2
by CB 2 by CB 1
% would lead to a 13.9 p.u. r.m.s. short-circuit current
Fig. 4: Main and back-up protection principles
and to 34.8 p.u. (full asymmetry factor = 2.5) for the
first peak, to be compared to 9 p.u. Fault current
As a consequence, two conditions are necessary:
limitation is instantaneously efficient and leads to
Condition 1: The transformer must thermally reduced stresses on downstream devices during faults.
withstand a long duration short-circuit after which the
-5-
It was then found that the critical temperature (ca. 110 heavily loaded areas.
K) is reached in 580 ms. CB R must clear a fault in less
than 580 ms (condition 2). Condition 1 is reached if the The second example deals with a generation application.
short-circuit is cleared by CB Q in about 1s. The first part of this study showed the advantage in
terms of voltage stability for HTS FCL step-up
These maximum short-circuit durations are compatible transformers (uSC = 6 %) compared to conventional ones
with some protection scheme, but may appear as too (uSC = 14 %). Simulations were made in order to see the
short for other applications or other designs. These influence of the step-up transformer. Three faults were
durations are very design sensitive and may vary simulated: Case 1.1 and 1.2 close to the generator and
significantly, but our goal is to optimise the transformer case 2 a little bit further away, as shown in Fig. 6.
design to match the operational constraints. However,
technical progress toward numerical protection and
increased communication between circuit-breakers are
likely to make it possible to reduce the time needed for
protection to clear a fault. Moreover, Power Quality is case 2
becoming a very strong requirement from customers and Step-up
transformer
utilities and reducing fault duration is a part of the
answer to that problem. case 1.1 case 1.2
~
From a utility point of view, this current limitation
capability is one of the main interests for High 110 kV
4. CONCLUSION
G ~ Current limitation in High Temperature
Generator step-up transformer load Superconducting Transformers appears to be achievable,
120 MVA
using a self limiting and recovering HTS conductor.
Xd
RT
XT
Experimental proof of this effect was achieved on
several lengths. This capability is fully used in a
~ E U
Q
U
L
R L
X
L transformer and will lead to numerous advantages,
especially if protections are quick enough to clear faults
Fig. 7: Model network for step-up transformer study rapidly, avoiding overheating of the transformer.
Numerical protection and increased communication
An extra added value to the step-up HTS transformer between circuit-breakers will improve this situation very
application is related to power generation savings. The soon.
data of the generator are taken from an existing
generator and the network is described in Fig.7. The This paper illustrates examples of system benefits
impedance values during normal operation for the step- derived from this technology, such as reduced stresses
up transformers are : conventional [0.5% + j⋅14%], HTS on downstream devices, reduced load losses, more
[0.02% + j⋅6.0%]. The values assumed for normal compact transformers, increased voltage stability,
operation refer to all HTS transformer types with HRS reduced generator ratings … These benefits are already
wire and therefore reduced impedance in normal of common interests for both utilities and transformer
operation. manufacturers.