Professional Documents
Culture Documents
Work Procedure For STB Steel Erection
Work Procedure For STB Steel Erection
No 0-WD861-CA731-00315
WORK PROCEDURE FOR STEEL Rev. No. A
ERECTION
TABLE OF CONTENTS
1.0. PURPOSE……………………………………………………………………………3
2.0. SCOPE………………………………….…………………………………………….3
3.0. REFERENCE………………………….……………………………………………..3
7.0. TOLERANCE………………………………………………………………………...5
11.0. ATTACHMENT………………………………………………………………………13
2
Masinloc Power Plant Expansion Project Doc. No 0-WD861-CA731-00315
WORK PROCEDURE FOR STEEL Rev. No. A
ERECTION
1.0. PURPOSE
Ensure works and procedure associated to steel erection for the executed in compliance
with the technical specifications of the Masinloc Power Plant Expansion Project.
2.0. SCOPE
The present work instruction is applicable to steel erection for building in of Masinloc Power
Expansion Project.
3.0. REFERENCE
AISC 303-05 Code of Standard Practice for Steel Buildings and Bridges. (Section 7. 5)
Approved related erection drawing and shop drawing
a. Column shall be prepared before erected, erection ladder and flat form will be
installed prior to erection. Flat form shall be erected on 1 meter below from column
splice area. Fabricated lifting lugs in 25mm thick with 6 pieces of M24 bolts should
be fixed at each column. Two Ø 25mm wire rope sling shall be used and two 12
tons shackle for lifting of the column.
b. Wire rope shall be set at top part of each column to support it after the erection. Lift
the column at designated location and secure the wire rope support. Adjacent
foundation should be used as anchors/dead man and support wire rope shall be
removed after the erection beam/ girder connecting the two column.
4
Masinloc Power Plant Expansion Project Doc. No 0-WD861-CA731-00315
WORK PROCEDURE FOR STEEL Rev. No. A
ERECTION
c. Install safety line post on girders or beams and set Ø 10mm wire rope as life line
prior to erection. Guide ropes shall be tied to steel members during erection for safe
guiding. Secure the member to be erected and check the preparation. Install sling
belt at the member and lock it with shackle then attach the other end to crane hook
for lifting. Tie a rope at the end of the member to serve as guide when lifting. Lift the
member slowly to designated position and fix it, insert bolt and hand tight at joint
point to secure the member.
d. Prepare crane girder before erection by installing safety line post on crane girder
and set Ø 10mm wire rope as life line prior to erection. Guide ropes shall be tied to
steel members during erection for safe guiding the lifted piece. Secure the member
to be erected and check the preparation. Install sling belt at the member and lock it
with shackle, attach the other end to crane hook for lifting. Tie a rope at the end of
the member to serve as guide when lifting. Lift the member slowly to designated
position and fix it, insert bolt and hand tight at joint point to secure the member.
f. All members to be erected shall be checked for the weight and shall use lifting belt
or wire that has the lifting capacity greater than the weight of member to be lifted.
g. Safety net shall be installed every under the beam of each floor and truss.
h. Before releasing the steel structure from crane hook, erector must install at least
10% of bolt and hand tight prior to release of crane hook.
i. The final bolt tightening, structure levelling and alignment shall be checked
according to the applicable drawing, standards and specification.
j. Scaffolding access shall be provided upon erection of floor for access, otherwise
permanent stair access can be installed to use
7.0. TOLERANCE
The tolerances for erection shall not exceed those indicated in section 7.13 AISC Code
of Standard Practice for Steel Building and Bridges (AISC 303)
5
Masinloc Power Plant Expansion Project Doc. No 0-WD861-CA731-00315
WORK PROCEDURE FOR STEEL Rev. No. A
ERECTION
6
Masinloc Power Plant Expansion Project Doc. No 0-WD861-CA731-00315
WORK PROCEDURE FOR STEEL Rev. No. A
ERECTION
Flow of Erection Sequences below will be carried out step by step started from the
first section and continue to other sections until finish.
7
Masinloc Power Plant Expansion Project Doc. No 0-WD861-CA731-00315
WORK PROCEDURE FOR STEEL Rev. No. A
ERECTION
(Anchor bolt materials should be already inspected and approved prior to the
settlement of installation.)
Levelling and chipping for roughing concrete surface by chipping hammer and
chisel.
9.4. Padding
9.5.8. Install the wire rope/ guy wires to support the column.
9.6. Girder Erection
※ Span of columns should be about +20 - +30mm wider than dimension described
in the drawing. After main reached at setting position, the span should be
adjusted by chain blocks, etc.
9
Masinloc Power Plant Expansion Project Doc. No 0-WD861-CA731-00315
WORK PROCEDURE FOR STEEL Rev. No. A
ERECTION
The bolts which the center line is vertical, shall always be assembled with the nut
before lifting or erection.
The defects in the alignment of holes shall exclusively be corrected with a reamer
for sheet metal work. Using any thermal cutting is strictly forbidden.
9.9.2. Preparation of the contact surface; the contact surface of the elements to be
assembled shall be prepared according to the indications given of the
detailed drawing of the structure, in particular; absence of grease, oil.
9.9.3. Tightening of bolt; even though this section describes the installation of bolts,
in order to assure quality it is considered that the right execution of this work
must be performed according to the indications follows; before tightening of
bolt, the parts that will be connected must correctly assembled and fixed. It
must be verified that the parts have a correct alignment to install the quantity
of bolts required by the assembly drawings. The tightening sequence of the
structural bolt (high tension bolt) will be performed as follows;
10
Masinloc Power Plant Expansion Project Doc. No 0-WD861-CA731-00315
WORK PROCEDURE FOR STEEL Rev. No. A
ERECTION
Install bolts and nuts according to the assembly drawings taken under
consideration the type, grade or other additional indication of the
manufacturer. Also, it must be verified that the tightening of the nut is not
forced.
All impact wrenched (_call ‘torque tool’ from now on) must be calibrated
every working day with a tension calibrator.
All torque tools must be calibrated with a minimum of 3 bolts. If proper
tension is achieved with 3 bolts in a row, then the torque tools will be
approved for work that day.
If the torque tool does not achieve proper tension with 3 bolts, then a fourth
bolt will be used. If proper tension is achieved with fourth bolt, that torque
tool will be approved for work that day. The maximum number to be used
calibration is 5.
If the torque tools does not achieve proper calibration with a maximum of 5
bolts, then that torque tool condition should be rechecked.
9.9.6 Inspection
Final inspection for bolt tightening shall be carried out for fastener
randomized by selection of inspector among the day work.
11
Masinloc Power Plant Expansion Project Doc. No 0-WD861-CA731-00315
WORK PROCEDURE FOR STEEL Rev. No. A
ERECTION
The inspector must check if there is any loose bolt & broken nut.
Inspection test report will be required only for high tension bolts and is not
required for regular bolt.
9.10. Grouting
9.10.1. Grouting shall be done with non-shrink grouting materials as below:
Non Shrink Grout
9.10.2. After grouting has reached the required curing period as per guideline of
manufacturer of grouting materials, all anchor bolts or set bolts shall be
retightening up to hammer tight unless otherwise indicated.
9.11. Painting
9.11.1. Grinding and touch-up paint damaged parts.
9.11.2. Touch-up paint for bolts
10.1. All personnel must wear appropriate PPE at all times. Personnel are empowered to
stop work if safety precautions are not in place.
10.2. The Job Site Supervisor shall ensure that all Safety requirements are put in
practice, copy of JHA (Attached) are available on site for guidance and consultation.
10.3. Contractor Safety Representative shall carry out the safety site inspection to ensure
the safety requirements laid out in the safe work plan are followed during and after
the completion of the works.
10.4. Job Site Supervisor and Safety Representative shall be present at all time while
works are in progress.
10.5. Appropriate PTW to be prepared and implemented, modification without OWNER
approval is prohibited.
12
Masinloc Power Plant Expansion Project Doc. No 0-WD861-CA731-00315
WORK PROCEDURE FOR STEEL Rev. No. A
ERECTION
10.6. Assessed risk as necessary and communicated to concerned parties prior to start of
any work.
10.7. Safety briefing / Tool box talk must be conducted by Supervisors prior to start of
work in the language of workforce.
10.8. Incidents and injuries, damaged to property or near misses should be reported.
10.9. Good housekeeping to be maintained during the execution of activity.
10.10. A clear and good communication must be maintained by all personnel involved on
the activity.
10.11. Personnel must be trained/experienced and familiarized with the scope of works to
be undertaken. The location of marshalling point must be identified, emergency
evacuation procedure must be clear to all workers, exercises must be conducted.
10.12. Contractor Safety Manager / Representative shall review Safety Action Plan.
11.0. ATTACHMENT
13
Masinloc Power Plant Expansion Project Doc. No 0-WD861-CA731-00315
WORK PROCEDURE FOR STEEL Rev. No. A
ERECTION
Attachment # 01
14
JOB ENVIRONMENTAL SAFETY ANALYSIS
Rev.00 300MW Masinloc Coal Fired Power Plant
Date / Time MARCH 27, 2017 Prepared by(Sub-con) :ESTRELLA ATIENZA Authorized Environmental Person(VPCI) : Authorized Safety Person(VPCI) :
Revision
Revised by : Authorized Environmental Person(VPCI) : Authorized Safety Person(VPCI) :
Date
Acknowledgement by other crew
Additional Hazards Identified Additional Control Implemented Members
(Yes/No)
1ST
2ND
3RD
4TH
Only authorized
personnel are allowed on
working area
Environmental hazard due to oil spill Never used In case of leakage of Inspect the equipment
malfunctioning equipment, a dip tray for possible leakage prior
equipment at site should be provided to to start work
avoid soil contamination
and to avert Only authorized and
environmental issue approved equipment
YES
should be permitted to
brought inside the
construction site
Availability of fire
watcher, fire
extinguisher and fire
blanket during
equipment repair for
possible fire
Got hit by sharp objects Conduct Pre-Job Safety Wear proper personal
Meeting to all personnel protective equipment:
prior to start the work hard hat, safety goggles, YES
long sleeve, working
gloves, visibility vest,
including safety shoes
Assign personnel to
continuous monitoring
on working area
Personal Injury(eye, head, foot, body, Only authorized Wear proper personal
hand) personnel are allowed to protective equipment:
working on working area hard hat, safety goggles, YES
long sleeve, working
gloves, visibility vest,
including safety shoes
Hit by hand tools Inspect all hand tools Wear proper personal
prior to start the work protective equipment:
hard hat, safety goggles, YES
Follow the proper use of long sleeve, working
hand tools gloves, visibility vest,
including safety shoes
Safety awareness
regarding heat stroke /
YES
heat stress should be
discuss prior to start the
work
Provide appropriate
resting shelter and
drinking station intended
to the workers involved
with the tasks
2 Surveying Works Injury due to improper handling of tools Conduct Pre-Job Safety
and equipment Meeting to all personnel
prior to start the work YES
Hit by the structural steel that being Ensure the place of the
erect instrument and
personnel conducting
surveying works is away
from the working radius
of the lifting equipment YES
Only authorized
personnel are allowed to
working on working area
Injury due to ergonomic stress Follow the proper body
positioning during the
surveying works YES
Hit by hand tools Inspect all hand tools Wear proper personal
prior to start work protective equipment:
hard hat, safety goggles,
Only authorized long sleeve, working
personnel are allowed to YES
gloves, visibility vest,
working on working area including safety shoes
Personal Injury(eye, head, foot, body, Only authorized Wear proper personal
hand) personnel are allowed to protective equipment:
working on working area hard hat, safety goggles,
long sleeve, working
gloves, visibility vest,
including safety shoes
Assign personnel to
continuous monitoring
on working area
Safety awareness
regarding heat stroke /
heat stress should be
discuss prior to start the YES
work
Provide appropriate
resting shelter and
drinking station intended
to the workers involved
with the tasks
Installation of Ladder and Platform to Hit by hand tools Inspect all hand tools Wear proper personal
the Column prior to start the work protective equipment:
hard hat, safety goggles,
long sleeve, working
gloves, visibility vest,
including safety shoes
Assign personnel to
continuous monitoring
the activity on working
area
Slip / Trip Injury Maintain good
housekeeping on
working area
Proper segregation of
materials on working
area
Personal Injury (eye, head, foot, body, Authorized personnel are Wear proper personal
hand) allow to work on working protective equipment:
area hard hat, safety goggles,
long sleeve, working
gloves, visibility vest,
including safety shoes
Safety awareness
regarding heat stroke /
heat stress should be
discuss prior to start the
work
Provide appropriate
resting shelter and
drinking station intended
to the workers involved
with the tasks
3 Erection of Column Hit by the column that being lift Use tagline to control the Inspect all the lifting Wear proper personal
movement of the column gears prior to start the protective equipment:
that being lift and to work hard hat, safety goggles,
avoid accident long sleeve, working
gloves, visibility vest,
Barricade and signage Assign personnel to including safety shoes YES
should be put in place to continuous monitoring
warn the personnel that the activity on working
passing by area
Accident due to fall of column Barricade and signage Only certified rigger
should be put in place to should rig the column
warn the personnel that during erection
passing by
Injury due to removal of shackle and Use vertical lifeline in Conduct Pre-Job Safety Wear proper personal
sling removing of the shackle Meeting to all personnel protective equipment:
and sling on the column prior to start the work hard hat, safety goggles,
long sleeve, working
Ensure the personnel gloves, visibility vest,
shall have training on including safety shoes
Working At Heights
Slip / Trip Injury Remove all unnecessary Barricade and signage Maintain good
materials on the working should be put in place to housekeeping on
area warn the personnel work working area YES
on the working area Properly segregate all
the materials on the
working area
Assign personnel to
continuous monitoring
on working area
Personal Injury (eye, head, foot, body, Authorized personnel are Wear proper personal
hand) allow to work on working protective equipment:
area hard hat, safety goggles, YES
long sleeve, working
gloves, visibility vest,
including safety shoes
Safety awareness
regarding heat stroke /
heat stress should be
discuss prior to start the
work
YES
Provide appropriate
resting shelter and
drinking station intended
to the workers involved
with the tasks
4 Erection of Beam and Girder Hit by the beam and girder that being Use tagline to control the Inspect all the lifting Wear proper personal
lift movement of the beam gears prior to start the protective equipment:
and girder that being lift work hard hat, safety goggles,
and to avoid accident long sleeve, working
gloves, visibility vest,
Barricade and signage Assign personnel to including safety shoes YES
should be put in place to continuous monitoring
warn the personnel that the activity on working
passing by area
Only authorized /
certified operator should
operate the equipment
Accident due to fall of beam and girder Barricade and signage Only certified rigger
should be put in place to should rig the beam and
warn the personnel that girder during erection
passing by
Inspect all the lifting
gears prior to start the
work
YES
Authorized personnel are
allowed to work on
working area
Injury due to removal of shackle and Use vertical lifeline in Conduct Pre-Job Safety Wear proper personal
sling removing of the shackle Meeting to all personnel protective equipment:
and sling on the beam prior to start the work hard hat, safety goggles,
and girder long sleeve, working
Ensure the personnel gloves, visibility vest,
shall have training on including safety shoes
Working At Heights
Authorized personnel
should remove the YES
shackle and sling on the
column that being erect
Only authorized
personnel are allowed to
work on the working
area
Slip / Trip Injury Remove all unnecessary Barricade and signage Maintain good
materials on the working should be put in place to housekeeping on
area warn the personnel work working area YES
on the working area
Properly segregate all
the materials on the
working area
Assign personnel to
continuous monitoring
on working area
Personal Injury (eye, head, foot, body, Authorized personnel are Wear proper personal
hand) allow to work on working protective equipment:
area hard hat, safety goggles, YES
long sleeve, working
gloves, visibility vest,
including safety shoes
Injury due to bad weather condition In case of bad weather
condition / heavy rains,
work should be stop
immediately
YES
Always update / monitor
the weather condition
Safety awareness
regarding heat stroke /
heat stress should be
discuss prior to start the
work YES
Provide appropriate
resting shelter and
drinking station intended
to the workers involved
with the tasks
5 Erection of Braces Hit by the braces that being lift Use tagline to control the Inspect all the lifting Wear proper personal
movement of the braces gears prior to start the protective equipment:
that being lift and to work hard hat, safety goggles,
avoid accident long sleeve, working
gloves, visibility vest,
Barricade and signage Assign personnel to including safety shoes YES
should be put in place to continuous monitoring
warn the personnel that the activity on working
passing by area
Accident due to fall of braces Barricade and signage Only certified rigger
should be put in place to should rig the braces
warn the personnel that during erection
passing by
Injury due to removal of shackle and Use vertical lifeline in Conduct Pre-Job Safety Wear proper personal
sling removing of the shackle Meeting to all personnel protective equipment:
and sling on the braces prior to start the work hard hat, safety goggles,
long sleeve, working
Only authorized gloves, visibility vest,
personnel are allowed to including safety shoes
work on the working
Slip / Trip / Fall Injury Remove all unnecessary Barricade and signage Maintain good
materials on the working should be put in place to housekeeping on
area warn the personnel work working area YES
on the working area
Properly segregate all
the materials on the
working area
Assign personnel to
continuous monitoring
on working area
Personal Injury (eye, head, foot, body, Authorized personnel are Wear proper personal
hand) allow to work on working protective equipment:
area hard hat, safety goggles, YES
long sleeve, working
gloves, visibility vest,
including safety shoes
Safety awareness
regarding heat stroke /
heat stress should be
discuss prior to start the
work
YES
Provide appropriate
resting shelter and
drinking station intended
to the workers involved
with the tasks
6 Assembly of Trusses Hit by the truss parts that being lift Use tagline to control the Inspect all the lifting Wear proper personal
movement of the truss gears prior to start the protective equipment:
parts that being lift and work hard hat, safety goggles,
to avoid accident long sleeve, working
gloves, visibility vest,
Barricade and signage Assign personnel to including safety shoes YES
should be put in place to continuous monitoring
warn the personnel that the activity on working
passing by area
Only authorized /
certified operator should
operate the equipment
Accident due to fall of truss parts Barricade and signage Only certified rigger
should be put in place to should rig the truss parts
warn the personnel that during erection
passing by
Use guy wire to support Inspect all the lifting
the truss parts to avoid gears prior to start the
falling work
Injury due to removal of shackle and Use vertical lifeline in Conduct Pre-Job Safety Wear proper personal
sling removing of the shackle Meeting to all personnel protective equipment:
and sling on the truss prior to start the work hard hat, safety goggles,
parts long sleeve, working
Ensure the personnel gloves, visibility vest,
shall have training on including safety shoes
Working At Heights
Slip / Trip / Fall Injury Remove all unnecessary Barricade and signage Maintain good
materials on the working should be put in place to housekeeping on
area warn the personnel work working area YES
on the working area
Properly segregate all
the materials on the
working area
Assign personnel to
continuous monitoring
on working area
Personal Injury (eye, head, foot, body, Authorized personnel are Wear proper personal
hand) allow to work on working protective equipment:
area hard hat, safety goggles, YES
long sleeve, working
gloves, visibility vest,
including safety shoes
Safety awareness
regarding heat stroke /
heat stress should be YES
discuss prior to start the
work
Provide appropriate
resting shelter and
drinking station intended
to the workers involved
with the tasks
7 Erection of Assembly Truss Hit by the assembly truss that being lift Use tagline to control the Inspect all the lifting Wear proper personal
movement of the gears prior to start the protective equipment:
assembly truss that being work hard hat, safety goggles,
lift and to avoid accident long sleeve, working
gloves, visibility vest,
Barricade and signage Assign personnel to including safety shoes YES
should be put in place to continuous monitoring
warn the personnel that the activity on working
passing by area
Only authorized /
certified operator should
operate the equipment
Accident due to fall of assembly truss Barricade and signage Only certified rigger
should be put in place to should rig the assembly
warn the personnel that trusses during erection
passing by
Injury due to removal of shackle and Use vertical lifeline in Conduct Pre-Job Safety Wear proper personal
sling removing of the shackle Meeting to all personnel protective equipment:
and sling on the prior to start the work hard hat, safety goggles,
assembly truss long sleeve, working
gloves, visibility vest,
Ensure the personnel
including safety shoes
shall have training on
Working At Heights
Slip / Trip / Fall Injury Remove all unnecessary Barricade and signage Maintain good
materials on the working should be put in place to housekeeping on
area warn the personnel work working area YES
on the working area
Properly segregate all
the materials on the
working area
Assign personnel to
continuous monitoring
on working area
Personal Injury (eye, head, foot, body, Authorized personnel are Wear proper personal
hand) allow to work on working protective equipment:
area hard hat, safety goggles, YES
long sleeve, working
gloves, visibility vest,
including safety shoes
Safety awareness
regarding heat stroke /
heat stress should be
discuss prior to start the
work
YES
Provide appropriate
resting shelter and
drinking station intended
to the workers involved
with the tasks
8 Erection of Roof Beam and Braces Hit by the roof beam and braces that Use tagline to control the Inspect all the lifting Wear proper personal
being lift movement of the roof gears prior to start the protective equipment:
beam and braces that work hard hat, safety goggles,
being lift and to avoid long sleeve, working
accident gloves, visibility vest,
including safety shoes YES
Barricade and signage Assign personnel to
should be put in place to continuous monitoring
warn the personnel that the activity on working
passing by area
Accident due to fall of roof beam and Barricade and signage Only certified rigger
braces should be put in place to should rig the roof beam
warn the personnel that and braces during
passing by erection
Injury due to removal of shackle and Use vertical lifeline in Conduct Pre-Job Safety Wear proper personal
sling removing of the shackle Meeting to all personnel protective equipment:
and sling on the roof prior to start the work hard hat, safety goggles,
beam and braces long sleeve, working
gloves, visibility vest,
including safety shoes
Slip / Trip / Fall Injury Remove all unnecessary Barricade and signage Maintain good
materials on the working should be put in place to housekeeping on
area warn the personnel work working area YES
on the working area Properly segregate all
the materials on the
working area
Assign personnel to
continuous monitoring
on working area
Personal Injury (eye, head, foot, body, Authorized personnel are Wear proper personal
hand) allow to work on working protective equipment:
area hard hat, safety goggles, YES
long sleeve, working
gloves, visibility vest,
including safety shoes
Safety awareness
regarding heat stroke /
heat stress should be
discuss prior to start the
work
YES
Provide appropriate
resting shelter and
drinking station intended
to the workers involved
with the tasks
9 Erection of Crane Girder Hit by the crane girder that being lift Use tagline to control the Inspect all the lifting Wear proper personal
movement of the crane gears prior to start the protective equipment:
girder that being lift and work hard hat, safety goggles,
to avoid accident long sleeve, working
gloves, visibility vest,
Barricade and signage Assign personnel to including safety shoes YES
should be put in place to continuous monitoring
warn the personnel that the activity on working
passing by area
Only authorized /
certified operator should
operate the equipment
Accident due to fall of crane girder Barricade and signage Only certified rigger
should be put in place to should rig the crane
warn the personnel that during erection
passing by
Injury due to removal of shackle and Use vertical lifeline in Conduct Pre-Job Safety Wear proper personal
sling removing of the shackle Meeting to all personnel protective equipment:
and sling on the crane prior to start the work hard hat, safety goggles,
girder long sleeve, working
gloves, visibility vest,
including safety shoes
Slip / Trip / Fall Injury Remove all unnecessary Barricade and signage Maintain good
materials on the working should be put in place to housekeeping on
area warn the personnel work working area YES
on the working area
Properly segregate all
the materials on the
working area
Assign personnel to
continuous monitoring
on working area
Personal Injury (eye, head, foot, body, Authorized personnel are Wear proper personal
allow to work on working protective equipment:
hand) area hard hat, safety goggles, YES
long sleeve, working
gloves, visibility vest,
including safety shoes
Safety awareness
regarding heat stroke /
heat stress should be
discuss prior to start the
work
YES
Provide appropriate
resting shelter and
drinking station intended
to the workers involved
with the tasks
10 Erection of Purlins Hit by the purlins that being lift Use tagline to control the Inspect all the lifting Wear proper personal
movement of the purlins gears prior to start the protective equipment:
that being lift and to work hard hat, safety goggles,
avoid accident long sleeve, working
gloves, visibility vest,
Barricade and signage Assign personnel to including safety shoes YES
should be put in place to continuous monitoring
warn the personnel that the activity on working
passing by area
Accident due to fall of purlins Barricade and signage Only certified rigger
should be put in place to should rig the purlins
warn the personnel that during erection
passing by
Injury due to removal of shackle and Use vertical lifeline in Conduct Pre-Job Safety Wear proper personal
sling removing of the shackle Meeting to all personnel protective equipment:
and sling on the purlins prior to start the work hard hat, safety goggles,
long sleeve, working
gloves, visibility vest,
including safety shoes
Slip / Trip / Fall Injury Remove all unnecessary Barricade and signage Maintain good
materials on the working should be put in place to housekeeping on
area warn the personnel work working area YES
on the working area
Properly segregate all
the materials on the
working area
Assign personnel to
continuous monitoring
on working area
Personal Injury (eye, head, foot, body, Authorized personnel are Wear proper personal
hand) allow to work on working protective equipment:
area hard hat, safety goggles, YES
long sleeve, working
gloves, visibility vest,
including safety shoes
11 Erection of Girth Hit by the girth that being lift Use tagline to control the Inspect all the lifting Wear proper personal
movement of the girth gears prior to start the protective equipment:
that being lift and to work hard hat, safety goggles,
avoid accident long sleeve, working
gloves, visibility vest,
Barricade and signage Assign personnel to including safety shoes YES
should be put in place to continuous monitoring
warn the personnel that the activity on working
passing by area
Accident due to fall of column Barricade and signage Only certified rigger
should be put in place to should rig the girth
warn the personnel that during erection
passing by
Injury due to removal of shackle and Use vertical lifeline in Conduct Pre-Job Safety Wear proper personal
sling removing of the shackle Meeting to all personnel protective equipment:
and sling on the girth prior to start the work hard hat, safety goggles,
long sleeve, working
gloves, visibility vest,
including safety shoes
Slip / Trip / Fall Injury Remove all unnecessary Barricade and signage Maintain good
materials on the working should be put in place to housekeeping on
area warn the personnel work working area YES
on the working area
Properly segregate all
the materials on the
working area
Assign personnel to
continuous monitoring
on working area
Personal Injury (eye, head, foot, body, Authorized personnel are Wear proper personal
hand) allow to work on working protective equipment:
area hard hat, safety goggles, YES
long sleeve, working
gloves, visibility vest,
including safety shoes
Safety awareness
regarding heat stroke /
heat stress should be
discuss prior to start the
work
YES
Provide appropriate
resting shelter and
drinking station intended
to the workers involved
with the tasks
13 Disposal of waste materials Injury due to improper disposal of Disposal of material Wear appropriate YES
waste materials should be coordinated to personal protective
the concerned equipment during
department removal and disposal of
waste materials.
Proper segregation of
waste materials should
be initiated and these
will be disposed into a
designated landfill area
authorized by the client.
※EMERGENCY PLAN DESCRIPTION
VPCI EHSS Manager
JinGon Lee:
In case of Emergency: 0977-824-7318
1. Immediately stop the work.
2. Remove / unplug all electrical equipment Safety Supervisor GTC Inc.
3. Sound the alarm to warn the other workers Estrella Atienza:
4. Inform the emergency response team 0927-287-6702
5. Go to the nearest master point
How a rescue Emergency Contact GTC Global Safety Officer
willbeexecuted? In case of injury occurred: JastineElamparo:
[Describe it] 1. The first aider should be the one to respond on the incident area Numbers 0999-150-8642
2. Inform the rescue/medical team for further medication
GTC Global Nurse
In case of oil spill occurred: Kimberly Ebanez:
1. Immediately call environmental in-charge for the proper procedure 0909-904-1171
in containing the oil spillage.
GTC Global First Aider
Angelica Ebitner:
0930-633-7273
GTC Shelter – Near
Comfort Room
Tools and Exact location of
Spine Board, First Aid Kit
Equipment needed Emergency First Aid
■5 X 5 INITIATIVE
1 2 3 4 5
Masinloc Power Plant Expansion Project Doc. No 0-WD861-CA731-00315
WORK PROCEDURE FOR STEEL Rev. No. A
ERECTION
Attachment # 02
Risk Assessment
15
RISKASSESSMENT
300MW MasinlocCoalFired Power Plant
Activity: STRUCTURAL STEEL ERECTION OF STEAM TURBINE BUILDING
BASERISK BASERISK
TYPEOF DAMAGE (WITHOUTCONTROL (WITHCONTROL)
TASK/JOBSTEPS LISTOFHAZARDS MITIGATING CONTROLS
L C Risk L C Risk
Conduct Pre-Job Safety Meeting to all personnel prior to start the work
Ensure all manpower should follow the proper manual handling procedure in
Fractured / Personal
Got hit by materials 2 2 C preparation of materials to be used on this particular activity 1 3 D
Injury
Horse playing should be avoided in the working area to mitigate unsafe act of
person
Assign spotter / flagman to assist the operator in maneuvering of the equipment
Serious Physical Injury / Ensure only authorized / certified operator will operate the equipment
Hit by moving equipment 3 5 A 1 3 E
Fatality Only authorized personnel are allowed on working area
Barricade and signage should be put in place to warn the public
Inspect the equipment for possible leakage prior to start work
Only authorized and approved equipment should be permitted to brought inside the
construction site
Environmental hazard due to oil spill Soil Contamination 2 3 C Availability of fire watcher, fire extinguisher and fire blanket during equipment 1 3 E
repair for possible fire
In case of leakage of equipment, a dip tray should be provided to avoid soil
contamination and to avert environmental issue
A. Preparation of tools,
materials and Conduct Pre-Job Safety Meeting to all personnel prior to start the work
machines Got hit by sharp objects Minor Physical Injury 2 2 D Wear proper personal protective equipment: hard hat, safety goggles, long sleeve, 1 3 D
working gloves, visibility vest, including safety shoes
Horse playing at work should not be permitted nor tolerated and therefore strictly
Injury due to horse play Minor Physical Injury 2 3 C prohibited 1 3 D
Assign personnel to continuous monitoring on working area
Fractured / Minor Ensure the area is free from any obstruction prior to start the work
Slip / Tripping Injury 2 3 C 1 3 D
Physical Injury Maintain good housekeeping on working area
Only authorized personnel are allowed to working on working area
Personal Injury(eye, head, foot, body,
hand)
Minor Physical Injury 2 2 D Wear proper personal protective equipment: hard hat, safety goggles, long sleeve, 1 3 D
working gloves, visibility vest, including safety shoes
Inspect all hand tools prior to start the work
Hit by hand tools Minor Physical Injury 2 2 D 1 3 D
Follow the proper use of hand tools
Proper man-handling should be exercised to prevent ergonomic stress
Fractured / Personal Follow the proper body positioning in preparation of tools and materials
Injury due to improper body positioning 2 3 C 1 3 D
Injury
In case of bad weather condition / heavy rains, work should be stop immediately
Injury due to bad weather condition Minor Physical Injury 2 2 D 1 3 E
Always update / monitor the weather condition
Availability of first aider on working area for possible emergency
Safety awareness regarding heat stroke / heat stress should be discuss prior to start
Fractured / Personal
Injury due to heat s stroke / heat stress 2 3 C the work 1 2 E
Injury
Provide appropriate resting shelter and drinking station intended to the workers
involved with the tasks
Injury due to improper handling of tools Conduct Pre-Job Safety Meeting to all personnel prior to start the work
Minor Physical Injury 2 3 C 1 3 D
and equipment Follow proper manual handling of tools and equipment
Ensure the place of the instrument and personnel conducting surveying works is
Hit by the structural steel that being away from the working radius of the lifting equipment
Serious Physical Injury 2 3 C 1 3 D
erect Do not allow surveying works while lifting is in progress
Only authorized personnel are allowed to working on working area
Injury due to ergonomic stress Minor Physical Injury 2 3 C Follow the proper body positioning during the surveying works 1 3 D
Safety awareness regarding heat stroke / heat stress should be discuss prior to start
Fractured / Personal the work
Injury due to heat stroke / heat stress 2 3 C 1 2 E
Injury
Provide appropriate resting shelter and drinking station intended to the workers
involved with the tasks
Horse playing at work should not be permitted nor tolerated and therefore strictly
Injury due to horse play Minor Physical Injury 2 3 C prohibited 1 3 D
Assign personnel to continuous monitoring on working area
Personal Injury (eye, head, foot, body, Wear proper personal protective equipment: hard hat, safety goggles, long sleeve, 1
Minor Physical Injury 2 2 D 3 D
hand) working gloves, visibility vest, including safety shoes
In case of bad weather condition / heavy rains, work should be stop immediately
Injury due to bad weather condition Minor Physical Injury 2 2 D 1 3 E
Always update / monitor the weather condition
Availability of first aider on working area for possible emergency
Safety awareness regarding heat stroke / heat stress should be discuss prior to start
Fractured / Personal
Injury due to heat stroke / heat stress 2 3 C the work 1 2 E
Injury
Provide appropriate resting shelter and drinking station intended to the workers
involved with the tasks
Inspect all the lifting gears prior to start the work
Assign personnel to continuous monitoring the activity on working area
Only authorized / certified operator should operate the equipment
Hit by the beam and girder that being lift Minor Physical Injury 2 3 C Use tagline to control the movement of the beam and girder that being lift and to 1 3 D
avoid accident
Barricade and signage should be put in place to warn the personnel that passing by
Use megaphone to warn the personnel working at the working area
Inspect the equipment prior to start the lifting works
Only authorized / certified operator should operate the equipment
Property Damage / Place the equipment on the firm and stable ground prior to the work
Collapse of equipment 3 5 A 1 3 D
Serious Physical Injury Proper planning should be initiated prior to start the work
E. Erection of Beam and Girder In case of bad weather condition / heavy rains, work should be stop immediately
Authorized personnel are allow to work on working area
Only certified rigger should rig the beam and girder during erection
Serious Physical Injury
Accident due to fall of beam and girder 3 4 A Inspect all the lifting gears prior to start the work 1 4 D
/ Fatality
Authorized personnel are allowed to work on working area
Conduct Pre-Job Safety Meeting to all personnel prior to start the work
Ensure the personnel shall have training on Working At Heights
Injury due to removal of shackle and Authorized personnel should remove the shackle and sling on the column that being
Minor Physical Injury 2 3 C 1 3 D
sling erect
Only authorized personnel are allowed to work on the working area
Use vertical lifeline in removing of the shackle and sling on the beam and girder
Slip / Trip Injury Minor Physical Injury 2 3 C Maintain good housekeeping on working area 1 3 D
Properly segregate all the materials on the working area
Injury due to ergonomic stress Minor Physical Injury 2 3 C Follow the proper body positioning in erection of beam / girder 1 3 D
Horse playing at work should not be permitted nor tolerated and therefore strictly
Injury due to horse play Minor Physical Injury 2 3 C prohibited 1 3 D
Assign personnel to continuous monitoring on working area
Personal Injury (eye, head, foot, body, Wear proper personal protective equipment: hard hat, safety goggles, long sleeve, 1
Minor Physical Injury 2 2 D 3 D
hand) working gloves, visibility vest, including safety shoes
In case of bad weather condition / heavy rains, work should be stop immediately
Injury due to bad weather condition Minor Physical Injury 2 2 D 1 3 E
Always update / monitor the weather condition
Availability of first aider on working area for possible emergency purpose
Safety awareness regarding heat stroke / heat stress should be discuss prior to start
Fractured / Personal
Injury due to heat stroke / heat stress 2 3 C the work 1 2 E
Injury
Provide appropriate resting shelter and drinking station intended to the workers
involved with the tasks
Inspect all the lifting gears prior to start the work
Assign personnel to continuous monitoring the activity on working area
Only authorized / certified operator should operate the equipment
Hit by the braces that being lift Minor Physical Injury 2 3 C Use tagline to control the movement of the braces that being lift and to avoid 1 3 D
accident
Barricade and signage should be put in place to warn the personnel that passing by
Use megaphone to warn the personnel working at the working area
Inspect the equipment prior to start the lifting works
Only authorized / certified operator should operate the equipment
Property Damage / Place the equipment on the firm and stable ground prior to the work
Collapse of equipment 3 5 A 1 5 D
Serious Physical Injury Proper planning should be initiated prior to start the work
In case of bad weather condition / heavy rains, work should be stop immediately
Authorized personnel are allow to work on working area
Only certified rigger should rig the braces during erection
F. Erection of Braces
Serious Physical Injury Inspect all the lifting gears prior to start the work
Accident due to fall of braces 3 4 A 1 4 D
/ Fatality Authorized personnel are allowed to work on working area
Use guy wire to support the braces to avoid falling
Conduct Pre-Job Safety Meeting to all personnel prior to start the work
Only authorized personnel are allowed to work on the working
Ensure the personnel shall have training on Working At Heights
Authorized personnel should remove the shackle and sling on the braces that being
Injury due to removal of shackle and
Minor Physical Injury 2 3 C erect 1 3 D
sling
Use full body harness when removing the shackle and sling on the column that being
erect
Use rope grab on lifeline when ascending and descending at the braces for the
removal of shackle and sling
Maintain good housekeeping on working area
Slip / Trip / Fall Injury Minor Physical Injury 2 3 C 1 3 D
Properly segregate all the materials on the working area
Injury due to ergonomic stress Minor Physical Injury 2 3 C Follow the proper body positioning in erection of braces 1 3 D
Horse playing at work should not be permitted nor tolerated and therefore strictly
Injury due to horse play Minor Physical Injury 2 3 C prohibited 1 3 D
Assign personnel to continuous monitoring on working area
Horse playing at work should not be permitted nor tolerated and therefore strictly
Injury due to horse play Minor Physical Injury 2 3 C prohibited 1 3 D
Assign personnel to continuous monitoring on working area
Personal Injury (eye, head, foot, body, Wear proper personal protective equipment: hard hat, safety goggles, long sleeve, 1
Minor Physical Injury 2 2 D 3 D
hand) working gloves, visibility vest, including safety shoes
In case of bad weather condition / heavy rains, work should be stop immediately
Injury due to bad weather condition Minor Physical Injury 2 2 D 1 3 E
Always update / monitor the weather condition
Availability of first aider on working area for possible emergency
Safety awareness regarding heat stroke / heat stress should be discuss prior to start
Fractured / Personal
Injury due to heat stroke / heat stress 2 3 C the work 1 2 E
Injury
Provide appropriate resting shelter and drinking station intended to the workers
involved with the tasks
Use tagline to control the movement of the rafter that being lift and to avoid
accident
Barricade and signage should be put in place to warn the personnel that passing by
Hit by the rafter that being lift Minor Physical Injury 2 3 C 1 3 D
Use megaphone to warn the personnel working at the working area
Inspect all the lifting gears prior to start the work
Assign personnel to continuous monitoring the activity on working area
Inspect the equipment prior to start the lifting works
Only authorized / certified operator should operate the equipment
Property Damage / Place the equipment on the firm and stable ground prior to the work
Collapse of equipment 3 5 A 1 5 D
Serious Physical Injury Proper planning should be initiated prior to start the work
In case of bad weather condition / heavy rains, work should be stop immediately
Authorized personnel are allow to work on working area
Only certified rigger should rig the rafter during erection
Serious Physical Injury Inspect all the lifting gears prior to start the work
Accident due to fall of rafter 3 4 A 1 4 D
H. Erection of Rafter / Fatality Authorized personnel are allowed to work on working area
Use guy wire to support the rafter to avoid falling
Conduct Pre-Job Safety Meeting to all personnel prior to start the work
Ensure the personnel shall have training on Working At Heights
Authorized personnel should remove the shackle and sling on the rafter that being
erect
Injury due to removal of shackle and
Minor Physical Injury 2 3 C Only authorized personnel are allowed to work on the working area 1 3 D
sling
Use full body harness when removing the shackle and sling on the assembly truss
that being erect
Use rope grab on lifeline when ascending and descending at the assembly truss for
the removal of shackle and sling
Maintain good housekeeping on working area
Slip / Trip / Fall Injury Minor Physical Injury 2 3 C 1 3 D
Properly segregate all the materials on the working area
Injury due to ergonomic stress Minor Physical Injury 2 3 C Follow the proper body positioning in erection of rafter 1 3 D
Horse playing at work should not be permitted nor tolerated and therefore strictly
Injury due to horse play Minor Physical Injury 2 3 C prohibited 1 3 D
Assign personnel to continuous monitoring on working area
Personal Injury (eye, head, foot, body, Wear proper personal protective equipment: hard hat, safety goggles, long sleeve, 1
Minor Physical Injury 2 2 D 3 D
hand) working gloves, visibility vest, including safety shoes
In case of bad weather condition / heavy rains, work should be stop immediately
Injury due to bad weather condition Minor Physical Injury 2 2 D 1 3 E
Always update / monitor the weather condition
Availability of first aider on working area for possible emergency
Safety awareness regarding heat stroke / heat stress should be discuss prior to start
Fractured / Personal
Injury due to heat stroke / heat stress 2 3 C the work 1 2 E
Injury
Provide appropriate resting shelter and drinking station intended to the workers
involved with the tasks
Use tagline to control the movement of the roof beam and braces that being lift and
to avoid accident
Barricade and signage should be put in place to warn the personnel that passing by
Use megaphone to warn the personnel working at the working area
Hit by the roof beam and braces that
Minor Physical Injury 2 3 C Inspect all the lifting gears prior to start the work 1 3 D
being lift
Assign personnel to continuous monitoring the activity on working area
Only authorized / certified operator should operate the equipment
Wear proper personal protective equipment: hard hat, safety goggles, long sleeve,
working gloves, visibility vest, including safety shoes
Inspect the equipment prior to start the lifting works
Only authorized / certified operator should operate the equipment
Property Damage / Place the equipment on the firm and stable ground prior to the work
Collapse of equipment 3 5 A 1 5 D
Serious Physical Injury Proper planning should be initiated prior to start the work
In case of bad weather condition / heavy rains, work should be stop immediately
Authorized personnel are allow to work on working area
I. Erection of Roof Beam and Only certified rigger should rig the roof beam and braces during erection
Braces
Inspect all the lifting gears prior to start the work
Accident due to fall of roof beam and Serious Physical Injury
3 4 A Authorized personnel are allowed to work on working area 1 4 D
braces / Fatality
Barricade and signage should be put in place to warn the personnel that passing by
Use guy wire to support the roof beam and braces to avoid falling
Use full body harness when removing the shackle and sling on the roof beam and
braces that being erect
Use rope grab on lifeline when ascending and descending at the roof beam and
braces for the removal of shackle and sling
Injury due to removal of shackle and
Minor Physical Injury 2 3 C Conduct Pre-Job Safety Meeting to all personnel prior to start the work 1 3 D
sling
Ensure the personnel shall have training on Working At Heights
Authorized personnel should remove the shackle and sling on the roof beam and
braces that being erect
Only authorized personnel are allowed to work on the working area
Maintain good housekeeping on working area
Slip / Trip / Fall Injury Minor Physical Injury 2 3 C 1 3 D
Properly segregate all the materials on the working area
Injury due to ergonomic stress Minor Physical Injury 2 3 C Follow the proper body positioning in erection of roof beam and braces 1 3 D
Horse playing at work should not be permitted nor tolerated and therefore strictly
Injury due to horse play Minor Physical Injury 2 3 C prohibited 1 3 D
Assign personnel to continuous monitoring on working area
Personal Injury (eye, head, foot, body, Wear proper personal protective equipment: hard hat, safety goggles,
Minor Physical Injury 2 2 D 1 3 D
hand) long sleeve, working gloves, visibility vest, including safety shoes
In case of bad weather condition / heavy rains, work should be stop immediately
Injury due to bad weather condition Minor Physical Injury 2 2 D 1 3 E
Always update / monitor the weather condition
Availability of first aider on working area for possible emergency
Safety awareness regarding heat stroke / heat stress should be discuss prior to start
Fractured / Personal
Injury due to heat stroke / heat stress 2 3 C the work 1 2 E
Injury
Provide appropriate resting shelter and drinking station intended to the workers
involved with the tasks
Use tagline to control the movement of the purlins that being lift and to avoid
accident
Barricade and signage should be put in place to warn the personnel that passing by
Hit by the purlins that being lift Minor Physical Injury 2 3 C Use megaphone to warn the personnel working at the working area 1 3 D
Inspect all the lifting gears prior to start the work
Assign personnel to continuous monitoring the activity on working area
Only authorized / certified operator should operate the equipment
Inspect the equipment prior to start the lifting works
Only authorized / certified operator should operate the equipment
Property Damage / Place the equipment on the firm and stable ground prior to the work
Collapse of equipment 3 5 A 1 5 D
Serious Physical Injury Proper planning should be initiated prior to start the work
In case of bad weather condition / heavy rains, work should be stop immediately
Authorized personnel are allow to work on working area
Accident due to fall of purlins Only certified rigger should rig the purlins during erection
J. Erection of Serious Physical Injury Inspect all the lifting gears prior to start the work
3 4 A 1 4 D
Purlins / Fatality Authorized personnel are allowed to work on working area
Use guy wire to support the purlins to avoid falling
Injury due to removal of shackle and Conduct Pre-Job Safety Meeting to all personnel prior to start the work
sling Ensure the personnel shall have training on Working At Heights
Authorized personnel should remove the shackle and sling on the purlins that being
erect
Minor Physical Injury 2 3 C Only authorized personnel are allowed to work on the working area 1 3 D
Use full body harness when removing the shackle and sling on the column that being
erect
Use rope grab on lifeline when ascending and descending at the column for the
removal of shackle and sling
Slip / Trip / Fall Injury Maintain good housekeeping on working area
Minor Physical Injury 2 3 C 1 3 D
Properly segregate all the materials on the working area
Injury due to ergonomic stress Injury due to ergonomic stress
Minor Physical Injury 2 3 C 1 3 D
Injury due to horse play Horse playing at work should not be permitted nor tolerated and therefore strictly
Minor Physical Injury 2 3 C prohibited 1 3 D
Assign personnel to continuous monitoring on working area
Personal Injury (eye, head, foot, body, Wear proper personal protective equipment: hard hat, safety goggles, long sleeve,
hand) Minor Physical Injury 2 2 D working gloves, visibility vest, including safety shoes 1 3 D
Injury due to bad weather condition In case of bad weather condition / heavy rains, work should be stop immediately
Minor Physical Injury 2 2 D 1 3 E
Always update / monitor the weather condition
Injury due to heat stroke / heat stress Availability of first aider on working area for possible emergency
Safety awareness regarding heat stroke / heat stress should be discuss prior to start
Fractured / Personal
2 3 C the work 1 2 E
Injury
Provide appropriate resting shelter and drinking station intended to the workers
involved with the tasks
Hit by the girth that being lift Use tagline to control the movement of the girth that being lift and to avoid accident
Barricade and signage should be put in place to warn the personnel that passing by
Minor Physical Injury 2 3 C Use megaphone to warn the personnel working at the working area 1 3 D
Inspect all the lifting gears prior to start the work
Assign personnel to continuous monitoring the activity on working area
Collapse of equipment Inspect the equipment prior to start the lifting works
Only authorized / certified operator should operate the equipment
Property Damage / Place the equipment on the firm and stable ground prior to the work
3 5 A 1 5 D
Serious Physical Injury Proper planning should be initiated prior to start the work
In case of bad weather condition / heavy rains, work should be stop immediately
Authorized personnel are allow to work on working area
Only certified rigger should rig the girth during erection
Inspect all the lifting gears prior to start the work
Serious Physical Injury
Accident due to fall of girth 3 4 A Authorized personnel are allowed to work on working area 1 4 D
/ Fatality
K. Erection of Girth Barricade and signage should be put in place to warn the personnel that passing by
Use guy wire to support the girth to avoid falling
Use full body harness when removing the shackle and sling on the column that being
erect
Use rope grab on lifeline when ascending and descending at the column for the
removal of shackle and sling
Injury due to removal of shackle and
Minor Physical Injury 2 3 C Ensure the personnel shall have training on Working At Heights 1 3 D
sling
Authorized personnel should remove the shackle and sling on the column that being
erect
Only authorized personnel are allowed to work on the working area
Use vertical lifeline in removing of the shackle and sling on the girth
Maintain good housekeeping on working area
Slip / Trip / Fall Injury Minor Physical Injury 2 3 C 1 3 D
Properly segregate all the materials on the working area
Injury due to ergonomic stress Minor Physical Injury 2 3 C Follow the proper body positioning in erection of column 1 3 D
Injury due to horse play Minor Physical Injury 2 3 C Horse playing at work should not be permitted nor tolerated and therefore strictly 1 3 D
prohibited
Assign personnel to continuous monitoring on working area
Personal Injury (eye, head, foot, body, Wear proper personal protective equipment: hard hat, safety goggles, long sleeve,
Minor Physical Injury 2 2 D 1 3 D
hand) working gloves, visibility vest, including safety shoes
In case of bad weather condition / heavy rains, work should be stop immediately
Injury due to bad weather condition Minor Physical Injury 2 2 D 1 3 E
Always update / monitor the weather condition
Availability of first aider on working area for possible emergency
Safety awareness regarding heat stroke / heat stress should be discuss prior to start
Fractured / Personal
Injury due to heat stroke / heat stress 2 3 C the work 1 2 E
Injury
Provide appropriate resting shelter and drinking station intended to the workers
involved with the tasks
Adequate lighting must be provided ensuring a safe working environment for those
Poor illumination Minor Physical Injury 2 3 C persons who have to work during the hours of darkness prior to start the work 1 3 D
Ensure all lighting should be in good condition
Fractured / Personal Must use clear safety goggles instead of dark for the clear vision
Eye injury 2 3 C 1 3 D
Injury Conduct Pre-Job Safety Meeting to all personnel prior to start the work
Safety briefing should be initiated prior to start the work regarding the safe work on
the working area during night / overtime work
L. Night work / Overtime Incident bitten by mosquito, snake, Physical Injury / Advice all personnel working at overtime / night work to rest only on the designated
Activity 3 5 A 1 3 E
insect etc. Fatality resting shelter
Inspect the working area to avoid insect bites
Provide snake catcher
Maintain good housekeeping on working area
Fractured / Personal Proper segregation of materials on working area
Accident due to slip / trip / fall hazard 2 3 C 1 3 D
Injury Ensure the area is free from any obstruction prior to start the work
Install adequate lighting on access way and especially on working area
Disposal of material should be coordinated to the concerned department
Injury due to improper disposal of waste Fracture /
M. Disposal of waste materials materials Personal Injury
2 3 C Proper segregation of waste materials should be initiated and these will be disposed 1 3 D
into a designated landfill area authorized by the client.
PREPARED BY : APPROVED BY :
AlmostCertain
5 10 15 20 25
5
Likely
4 8 12 16 20
4
Probable
3 6 9 12 15
3
Occasional
2 4 6 8 10
2
Unlikely
1 2 3 4 5
1
Likelihood
VeryLow Low Moderate High VeryHigh
12 1 2 3 4 5
Consequence
16-25 Unacceptable/Intolerable A
10-15 Substantial B
6-9 ModeratetoAcceptablewithReview C
3-5 Tolerable D
1-2 Acceptable E
Masinloc Power Plant Expansion Project Doc. No 0-WD861-CA731-00315
WORK PROCEDURE FOR STEEL Rev. No. A
ERECTION
Attachment # 03
Lifting Plan
16
Masinloc Power Plant Expansion Project Doc. No 0-WD861-CA731-00315
WORK PROCEDURE FOR STEEL Rev. No. A
ERECTION
Attachment # 04
Load Charts
17
GR-500N-1-00103/JA-02
GR-500N
CRANE SPECIFICATIONS
CRANE CAPACITY JIB
9.7m Boom 51,000kg at 3.0m (12part-line) Quick-turn type (2-staged type which stores alongside
16.0m Boom 30,000kg at 4.5m ( 8part-line) below the base boom section and extendible from under
22.3m Boom 20,000kg at 5.5m ( 6part-line) the boom (with 2nd stage being a pull-out type))
28.6m Boom 12,500kg at 8.0m ( 4part-line) Hydraulic non-stage offset (5°-60°
) type
34.9m Boom 11,000kg at 8.0m ( 4part-line) SINGLE TOP
38.05m Boom 9,000kg at 9.0m ( 4part-line) Single sheave. Mounted on main boom head for single
41.2m Boom 7,000kg at 10.0m ( 4part-line) line work.
8.0m Jib 3,500kg at 74° ( 1part-line) HOIST
12.7m Jib 2,500kg at 74° ( 1part-line) Hydraulic motor driven planetary gear reducer
Single top 4,500kg ( 1part-line) Automatic brake
MAX.LIFTING HEIGHT With high-speed unwind function
Boom 42.2m 2 single winches
Jib 55.2m With flow regulator valve with pressure compensation
MAX.WORKING RADIUS BOOM ELEVATION
Boom 34.0m 2 double-acting hydraulic cylinders
Jib 38.6m With flow regulator valve with pressure compensation
BOOM LENGTH SWING
9.7m - 41.2m Hydraulic motor driven planetary gear reducer
BOOM EXTENSION Swing bearing
31.5m Swing free/lock changeover type
BOOM EXTENSION SPEED Negative brake
31.5m/120s OUTRIGGERS
JIB LENGTH Fully hydraulic X-type (floats mounted integrally)
8.0m - 12.7m Slides and jacks each provided with independent
MAIN WINCH SINGLE LINE WINDING SPEED operation device.
125m/min (5th layer) Fully extended width 7.4m
Middle extended width 6.8m, 5.5m, 4.1m
MAIN WINCH HOOK SPEED
Minimum extended width 3.5m
10.4m/min (12 part-line)
OPERATION METHOD
MAIN WINCH SINGLE LINE UNWINDING SPEED
Hydraulic pilot valve operation
<Reference>
Standard 125m/min (5th layer) MAX. VERTICAL LOAD CAPACITY OF OUTRIGGER
High speed 190m/min (5th layer) 38.3t
AUXILIARY WINCH SINGLE LINE WINDING POWER TAKE-OFF
SPEED PTO wet multi-plate clutch
110m/min (3th layer) HYDRAULIC PUMPS
AUXILIARY WINCH HOOK SPEED 2 variable piston pumps
110m/min (1 part-line) 3 gear pumps
AUXILIARY WINCH SINGLE LINE UNWINDING HYDRAULIC OIL TANK CAPACITY
SPEED 601 liters
<Reference> SAFETY DEVICES
Standard 110m/min (3th layer) Automatic moment limiter (AML)
High speed 165m/min (3th layer) Swing automatic stop device
BOOM ELEVATION ANGLE Elevation slow down and stop device
-0°
- 83.5° Over-winding cutout device
Working area control device
BOOM ELEVATION SPEED
Outrigger extension width detector
-0°
- 83.5°
/62s
Winch drum lock (auxiliary winch)
SWING ANGLE Level gauge
360°continue Hook safety latch
SWING SPEED Hydraulic safety valve
2.2min -1 (rpm) Telescopic counterbalance valve
WIRE ROPE Elevation counterbalance valve
Main Winch: 18mm x 224m (Diameter x Length) Power tilt counterbalance valve
Spin-resistant wire rope Jack pilot check valve
Auxiliary Winch: 18mm x 120m (Diameter x Length) Swing lock
Spin-resistant wire rope EQUIPMENT
BOOM Air-conditioner with dehumidifier
6-section hydraulically telescoping boom of hexagonal Hydraulic oil temperature indication lamp
box construction Radio
(stages 2,3: synchronized; stages 4,5,6: synchronized) Oil cooler
BOOM EXTENSION Visual-type winch drum rotation indicator
3 double-acting hydraulic cylinders Operation pedals
2 wire rope type telescoping device ISO arrangement: for telescoping/auxiliary hoisting
TADANO arrangement: for elevating/telescoping
Television (option)
- 2 -
GR-500N-1-00103/JA-02
- 3 -
GR-500N-1-00103/JA-02
Unit:ton
Outriggers fully extended (7.4 m) -360°-
Boom
length
9.7 m 16.0 m 22.3 m 28.6 m 34.9 m 38.05 m 41.2 m
Working
radius
2.5 m 51.0 30.0 20.0 12.5
3.0 m 51.0 30.0 20.0 12.5
3.5 m 45.0 30.0 20.0 12.5 11.0
4.0 m 39.5 30.0 20.0 12.5 11.0 9.0
4.5 m 35.5 30.0 20.0 12.5 11.0 9.0
5.0 m 32.0 29.0 20.0 12.5 11.0 9.0 7.0
5.5 m 29.0 27.0 20.0 12.5 11.0 9.0 7.0
6.0 m 26.5 25.0 19.2 12.5 11.0 9.0 7.0
6.5 m 24.0 23.2 18.0 12.5 11.0 9.0 7.0
7.0 m 21.3 17.0 12.5 11.0 9.0 7.0
8.0 m 18.2 15.0 12.5 11.0 9.0 7.0
9.0 m 15.0 13.4 11.5 10.2 9.0 7.0
10.0 m 12.3 11.9 10.5 9.3 8.5 7.0
11.0 m 10.2 9.9 9.6 8.5 7.8 6.8
12.0 m 8.5 8.25 8.8 7.8 7.2 6.4
13.0 m 7.1 6.9 7.9 7.1 6.6 6.0
14.0 m 5.9 6.9 6.6 6.1 5.6
16.0 m 4.3 5.2 5.7 5.3 4.9
18.0 m 3.0 4.0 4.5 4.6 4.3
20.0 m 3.1 3.5 3.7 3.85
22.0 m 2.35 2.75 3.0 3.1
24.0 m 1.7 2.1 2.35 2.5
26.0 m 1.65 1.85 2.0
28.0 m 1.25 1.4 1.55
30.0 m 0.9 1.0 1.2
32.0 m 0.7 0.9
34.0 m 0.6
A(°) 0∼83.5 16∼83.5 26∼83.5
Standard hook 51 t hook 25 t hook
A= Boom angle range (for the unladen condition)
- 4 -
GR-500N-1-00103/JA-02
[BOOM]
Unit:ton
Outriggers middle extended (6.8 m) -Over sides-
Boom
length
9.7 m 16.0 m 22.3 m 28.6 m 34.9 m 38.05 m 41.2 m
Working
radius
2.5 m 51.0 30.0 20.0 12.5
3.0 m 50.0 30.0 20.0 12.5
3.5 m 43.0 30.0 20.0 12.5 11.0
4.0 m 38.0 30.0 20.0 12.5 11.0 9.0
4.5 m 34.1 30.0 20.0 12.5 11.0 9.0
5.0 m 30.7 29.0 20.0 12.5 11.0 9.0 7.0
5.5 m 27.7 27.0 20.0 12.5 11.0 9.0 7.0
6.0 m 25.3 25.0 19.2 12.5 11.0 9.0 7.0
6.5 m 23.0 23.2 18.0 12.5 11.0 9.0 7.0
7.0 m 21.3 17.0 12.5 11.0 9.0 7.0
8.0 m 16.4 15.0 12.5 11.0 9.0 7.0
9.0 m 13.0 12.7 11.5 10.2 9.0 7.0
10.0 m 10.6 10.3 10.5 9.3 8.5 7.0
11.0 m 8.7 8.5 9.5 8.5 7.8 6.8
12.0 m 7.2 7.1 8.1 7.8 7.2 6.4
13.0 m 6.1 6.0 6.9 7.1 6.6 6.0
14.0 m 5.1 6.0 6.4 6.1 5.6
16.0 m 3.65 4.5 4.9 5.1 4.9
18.0 m 2.55 3.3 3.8 4.05 4.2
20.0 m 2.5 3.0 3.2 3.35
22.0 m 1.8 2.3 2.5 2.65
24.0 m 1.2 1.75 1.9 2.05
26.0 m 1.25 1.45 1.6
28.0 m 0.85 1.05 1.2
30.0 m 0.5 0.7 0.85
32.0 m 0.5
A(°) 0∼83.5 21∼83.5 26∼83.5 34∼83.5
Standard hook 51 t hook 25 t hook
A= Boom angle range (for the unladen condition)
- 5 -
GR-500N-1-00103/JA-02
[BOOM]
Unit:ton
Outriggers middle extended (5.5 m) -Over sides-
Boom
length
9.7 m 16.0 m 22.3 m 28.6 m 34.9 m 38.05 m 41.2 m
Working
radius
2.5 m 45.0 30.0 20.0 12.5
3.0 m 45.0 30.0 20.0 12.5
3.5 m 41.0 30.0 20.0 12.5 11.0
4.0 m 36.8 30.0 20.0 12.5 11.0 9.0
4.5 m 33.2 30.0 20.0 12.5 11.0 9.0
5.0 m 30.2 27.0 20.0 12.5 11.0 9.0 7.0
5.5 m 25.9 24.0 20.0 12.5 11.0 9.0 7.0
6.0 m 21.4 21.0 19.2 12.5 11.0 9.0 7.0
6.5 m 18.2 18.0 17.0 12.5 11.0 9.0 7.0
7.0 m 15.2 15.1 12.5 11.0 9.0 7.0
8.0 m 11.9 11.6 12.0 11.0 9.0 7.0
9.0 m 9.5 9.15 10.2 10.0 9.0 7.0
10.0 m 7.65 7.35 8.35 8.7 8.5 7.0
11.0 m 6.25 6.0 7.0 7.3 7.6 6.8
12.0 m 5.15 4.9 5.85 6.3 6.5 6.4
13.0 m 4.2 4.0 5.0 5.5 5.6 5.6
14.0 m 3.25 4.2 4.7 4.9 5.0
16.0 m 2.05 3.0 3.5 3.7 3.8
18.0 m 1.15 2.1 2.6 2.75 2.9
20.0 m 1.35 1.9 2.05 2.25
22.0 m 0.7 1.25 1.5 1.7
24.0 m 0.8 1.0 1.2
26.0 m 0.6 0.8
A(°) 0∼83.5 23∼83.5 36∼83.5 43∼83.5 48∼83.5
Standard hook 51 t hook 25 t hook
A= Boom angle range (for the unladen condition)
- 6 -
GR-500N-1-00103/JA-02
[BOOM]
Unit:ton
Outriggers middle extended (4.1 m) -Over sides-
Boom
length
9.7 m 16.0 m 22.3 m 28.6 m 34.9 m 38.05 m 41.2 m
Working
radius
2.5 m 40.0 30.0 20.0 12.5
3.0 m 40.0 30.0 20.0 12.5
3.5 m 34.3 30.0 20.0 12.5 11.0
4.0 m 27.0 27.0 20.0 12.5 11.0 9.0
4.5 m 22.2 21.5 20.0 12.5 11.0 9.0
5.0 m 18.5 17.4 17.0 12.5 11.0 9.0 7.0
5.5 m 15.8 14.5 14.2 12.5 11.0 9.0 7.0
6.0 m 13.3 12.5 12.0 12.5 11.0 9.0 7.0
6.5 m 11.2 10.6 10.4 11.4 11.0 9.0 7.0
7.0 m 9.2 9.0 10.0 10.2 9.0 7.0
8.0 m 6.9 6.8 7.8 8.1 8.3 7.0
9.0 m 5.4 5.25 6.2 6.7 6.9 6.9
10.0 m 4.3 4.1 5.0 5.6 5.8 5.9
11.0 m 3.4 3.15 4.05 4.65 4.9 5.0
12.0 m 2.6 2.45 3.3 3.85 4.1 4.2
13.0 m 1.85 1.75 2.7 3.2 3.5 3.55
14.0 m 1.15 2.15 2.65 2.9 3.0
16.0 m 1.2 1.8 2.0 2.1
18.0 m 1.1 1.3 1.45
20.0 m 0.75 0.95
A(°) 0∼83.5 38∼83.5 46∼83.5 52∼83.5 55∼83.5 59∼83.5
Standard hook 51 t hook 25 t hook
A= Boom angle range (for the unladen condition)
- 7 -
GR-500N-1-00103/JA-02
[BOOM]
Unit:ton
Outriggers minimum extended (3.5 m) -Over sides-
Boom
length
9.7 m 16.0 m 22.3 m 28.6 m 34.9 m 38.05 m 41.2 m
Working
radius
2.5 m 30.0 20.0 14.0 9.0
3.0 m 30.0 20.0 14.0 9.0
3.5 m 25.6 20.0 14.0 9.0 8.5
4.0 m 21.0 19.0 14.0 9.0 8.5 7.0
4.5 m 17.4 16.0 14.0 9.0 8.5 7.0
5.0 m 14.2 13.4 13.0 9.0 8.5 7.0 6.0
5.5 m 12.2 11.4 10.7 9.0 8.5 7.0 6.0
6.0 m 10.4 9.6 9.3 9.0 8.5 7.0 6.0
6.5 m 8.5 8.3 8.0 8.7 8.5 7.0 6.0
7.0 m 7.2 6.9 7.7 7.6 7.0 6.0
8.0 m 5.5 5.2 6.0 6.2 6.3 6.0
9.0 m 4.2 3.9 4.7 5.0 5.1 5.3
10.0 m 3.2 2.9 3.7 4.0 4.2 4.4
11.0 m 2.4 2.1 3.0 3.3 3.5 3.65
12.0 m 1.8 1.5 2.3 2.7 2.9 3.1
13.0 m 1.2 0.9 1.85 2.2 2.4 2.55
14.0 m 1.35 1.75 1.95 2.1
16.0 m 1.0 1.2 1.4
A(°) 0∼83.5 44∼83.5 51∼83.5 59∼83.5 63∼83.5 65∼83.5
Standard hook 51 t hook 25 t hook
A= Boom angle range (for the unladen condition)
- 8 -
[JIB]
Outriggers fully extended (7.4 m) -360°-
Jib length 41.2 m boom + 8.0 m jib 41.2 m boom + 12.7 m jib
Offset 5° 25° 45° 60° 5° 25° 45° 60°
Boom angle Working Total rated Working Total rated Working Total rated Working Total rated Working Total rated Working Total rated Working Total rated Working Total rated
(°) radius (m) loads (t) radius (m) loads (t) radius (m) loads (t) radius (m) loads (t) radius (m) loads (t) radius (m) loads (t) radius (m) loads (t) radius (m) loads (t)
83.5 5 .6 3. 5 8. 3 2. 4 10.2 1. 6 11. 0 1. 0 6 .6 2. 5 10. 5 1. 4 13.4 0. 9 15. 3 0. 5
76.0 12.9 3. 5 15. 1 2. 4 16.6 1. 6 17. 1 1. 0 14.9 2. 5 18. 3 1. 4 20.7 0. 9 21. 6 0. 5
74.0 14.8 3. 5 16. 8 2. 4 18.3 1. 6 18. 6 1. 0 17.0 2. 5 20. 2 1. 4 22.4 0. 9 23. 2 0. 5
72.0 16.6 3 .3 5 18. 5 2. 4 19.8 1. 6 20. 0 1. 0 19.0 2. 4 22. 0 1. 35 24.1 0. 9 24. 6 0. 5
70.0 18.3 3. 0 20. 2 2. 4 21.3 1. 6 21. 5 1. 0 20.8 2. 2 23. 6 1. 25 25.7 0 .8 5 26. 1 0. 5
68.0 20.0 2. 7 21. 8 2. 2 22.9 1. 6 22. 8 1. 0 22.5 2. 0 25. 3 1. 2 27.2 0 .8 5 27. 4 0. 5
65.0 22.1 2. 3 23. 9 1. 9 25.0 1 .5 5 24. 8 1. 0 25.0 1. 8 27. 7 1. 1 29.4 0. 8 29. 5 0. 5
60.0 25.7 1 .7 5 27.4 1. 5 28.4 1 .3 5 28.1 1. 0 28.9 1. 4 31.5 1. 0 32.8 0 .7 5 32.8 0. 5
55.0 29.0 1. 3 30.6 1. 2 31.3 1. 1 32.6 1. 1 35.0 0 .8 5 36.0 0 .7 5
53.0 30.3 1 .0 5 31. 7 0. 95 32.5 0 .9 5 34. 0 0. 85 36.2 0 .7 5 37. 1 0. 65
50.0 32.1 0 .6 5 33.4 0. 6 34.0 0. 6 35.9 0 .5 5 38.0 0 .4 5 38.6 0. 4
A( °) 49∼83. 5 59∼83. 5 49∼83. 5 59∼83. 5
A= Boom angle range (for the unladen condition)
- 9 -
Outriggers middle extended (6.8 m) -Over sides-
Jib length 41.2 m boom + 8.0 m jib 41.2 m boom + 12.7 m jib
Offset 5° 25° 45° 60° 5° 25° 45° 60°
Boom angle Working Total rated Working Total rated Working Total rated Working Total rated Working Total rated Working Total rated Working Total rated Working Total rated
(°) radius (m) loads (t) radius (m) loads (t) radius (m) loads (t) radius (m) loads (t) radius (m) loads (t) radius (m) loads (t) radius (m) loads (t) radius (m) loads (t)
83.5 5 .6 3. 5 8. 3 2. 4 10.2 1. 6 11. 0 1. 0 6 .6 2. 5 10. 5 1. 4 13.4 0. 9 15. 3 0. 5
76.0 12.9 3. 5 15. 1 2. 4 16.6 1. 6 17. 1 1. 0 14.9 2. 5 18. 3 1. 4 20.7 0. 9 21. 6 0. 5
74.0 14.8 3. 5 16. 8 2. 4 18.3 1. 6 18. 6 1. 0 17.0 2. 5 20. 2 1. 4 22.4 0. 9 23. 2 0. 5
72.0 16.6 3 .3 5 18. 5 2. 4 19.8 1. 6 20. 0 1. 0 19.0 2. 4 22. 0 1. 35 24.1 0. 9 24. 6 0. 5
70.0 18.3 3. 0 20. 2 2. 4 21.3 1. 6 21. 5 1. 0 20.8 2. 2 23. 6 1. 25 25.7 0 .8 5 26. 1 0. 5
68.0 20.0 2. 7 21. 8 2. 2 22.9 1. 6 22. 8 1. 0 22.5 2. 0 25. 3 1. 2 27.2 0 .8 5 27. 4 0. 5
65.0 22.1 2. 3 23.9 1. 9 25.0 1 .5 5 24.8 1. 0 25.0 1. 8 27.7 1. 1 29.4 0. 8 29.5 0. 5
60.0 25.7 1. 7 27.4 1. 5 28.4 1 .3 5 28.1 1. 0 28.9 1. 4 31.5 1. 0 32.8 0 .7 5 32.8 0. 5
55.0 28.9 0. 9 30. 5 0. 8 31.2 0. 8 32. 3 0. 75 34.9 0 .6 5 35. 8 0. 55
53.0 30.1 0 .6 5 31.6 0. 6 32.4 0. 6 33.6 0 .5 5 36.1 0. 5 36.9 0. 4
A( °) 52∼83. 5 59∼83. 5 52∼83. 5 59∼83. 5
A= Boom angle range (for the unladen condition)
GR-500N-1-00103/JA-02
[JIB]
83.5 5.6 3.5 8.3 2.4 10.2 1.6 11.0 1.0 6.6 2.5 10.5 1.4 13.4 0.9 15.3 0.5
76.0 12.9 3.5 15.1 2.4 16.6 1.6 17.1 1.0 14.9 2.5 18.3 1.4 20.7 0.9 21.6 0.5
74.0 14.8 3.5 16.8 2.4 18.3 1.6 18.6 1.0 17.0 2.5 20.2 1.4 22.4 0.9 23.2 0.5
72.0 16.6 3.35 18.5 2.4 19.8 1.6 20.0 1.0 19.0 2.4 22.0 1.35 24.1 0.9 24.6 0. 5
70.0 18.3 3.0 20.2 2.4 21.3 1.6 21.5 1.0 20.8 2.2 23.6 1.25 25.7 0.85 26.1 0.5
68.0 19.7 2.35 21.6 2.05 22.9 1.6 22.8 1.0 22.4 1.95 25.3 1.2 27.2 0.85 27.4 0.5
65.0 21.8 1.65 23.7 1.45 24.9 1.3 24.8 1.0 24.7 1.4 27.7 1.1 29.4 0.8 29.5 0.5
62.0 23.9 1.1 25.6 0.95 26.8 0.85 26.9 0.8 26.8 0.85 29.8 0.7 31.4 0.65 32.8 0.5
60.0 25.2 0.7 27.0 0.6 28.0 0.6 28.1 0.55 28.2 0.55
A(°) 59∼83.5 61∼83.5
A= Boom angle range (for the unladen condition)
- 10 -
Outriggers middle extended (4.1 m) -Over sides-
Jib length 41.2 m boom + 8.0 m jib 41.2 m boom + 12.7 m jib
Offset 5° 25° 45° 60° 5° 25° 45° 60°
Boom angle Working Total rated Working Total rated Working Total rated Working Total rated Working Total rated Working Total rated Working Total rated Working Total rated
(°) radius (m) loads (t) radius (m) loads (t) radius (m) loads (t) radius (m) loads (t) radius (m) loads (t) radius (m) loads (t) radius (m) loads (t) radius (m) loads (t)
83.5 5.6 3.5 8.3 2.4 10.2 1.6 11.0 1.0 6.6 2.5 10.5 1.4 13.4 0.9 15.3 0.5
76.0 12.9 3.5 15.1 2.4 16.6 1.6 17.1 1.0 14.9 2.5 18.3 1.4 20.7 0.9 21.6 0.5
74.0 14.6 2.9 16.8 2.4 18.3 1.6 18.6 1.0 16.8 2.35 20.2 1.4 22.4 0.9 23.2 0.5
72.0 16.1 2.1 18.3 1.75 19.8 1.6 20.0 1.0 18.5 1.75 21.9 1.3 24.1 0.9 24.6 0.5
70.0 17.6 1.5 19.7 1.25 21.1 1.1 21.5 1.0 20.0 1.2 23.4 0.9 25.6 0.75 26.1 0.5
68.0 19.1 1.0 21.2 0.85 22.5 0.75 22.8 0.7 21.6 0.8
A(°) 67∼83.5 69∼83.5
A= Boom angle range (for the unladen condition)
GR-500N-1-00103/JA-02
Boom length 9. 7m 16.0 m 22. 3m 28.6 m 34. 9m 38.0 5m 41.2 m Jib/Single top
Number of
part lines 12 8 6 4 4 4 4 1
7. The hoisting performance for the "Over sides" range will differ according to the extended width of the outriggers.
Operations should be performed in accordance with the performance corresponding to the extended width.
Also, although the hoisting performances for the "Over front" and "Over rear" ranges are equivalent to those of the
"outriggers fully extended" condition, the front and rear ranges (angle a) will differ according to the width to which the
outriggers are extended in the left and right directions.
Angle a° 45 35 25 20
- 11 -
GR-500N-1-00103/JA-02
Unit:ton
Stationary Travelling at 1.6km/h or less
Boom length 9.7m 16.0m 22.3m 9.7m 16.0m 22.3m
Working radius Front -360°- Front -360°- Front -360°- Front -360°- Front -360°- Front -360°-
3.0 m 20.0 12.5 15.0 10.0 14.5 8.0 10.5 6.5
3.5 m 20.0 12.5 15.0 10.0 14.5 8.0 10.5 6.5
4.0 m 20.0 11.0 15.0 10.0 11.0 5.5 14.5 8.0 10.5 6.5 8.0 4.5
4.5 m 18.0 9.0 15.0 8.5 11.0 5.5 12.9 6.8 10.5 6.5 8.0 4.5
5.0 m 16.0 7.4 15.0 7.0 11.0 5.5 11.5 5.8 10.5 5.3 8.0 4.1
5.5 m 14.3 6.2 14.0 5.7 11.0 5.3 10.3 4.8 10.5 4.4 8.0 3.55
6.0 m 12.8 5.2 13.0 4.8 11.0 4.4 9.3 4.0 10.0 3.7 8.0 3.05
6.5 m 11.7 4.35 12.0 4.05 10.0 3.7 8.6 3.35 9.3 3.15 8.0 2.55
7.0 m 11.0 3.4 9.2 3.0 8.5 2.7 7.4 1.65
8.0 m 9.0 2.3 7.7 2.0 7.0 1.85 6.4 0.95
9.0 m 7.0 1.3 6.4 1.0 5.9 1.1 5.4
10.0 m 5.7 5.4 4.8 4.5
11.0 m 4.7 4.5 3.9 3.7
12.0 m 4.0 3.8 3.3 3.1
13.0 m 3.4 3.2 2.8 2.6
14.0 m 2.7 2.2
16.0 m 1.8 1.5
18.0 m 1.0 0.85
A(°) 0∼78 39∼78 22∼78 60∼78 0∼78 45∼78 22∼78 63∼78
Standard hook 25 t hook 25 t hook
4. "Over front" crane operations should be performed only when the AML "over-front area indicator lamp" is lit. The
boom must be kept inside a 2°area over front of the carrier when performing "Over front" crane operations without
the outriggers.
Approx. 2°
5. The total rated load for the single top shall be the value obtained by subtracting the weight of the hook mounted on
the boom from the total rated load of the boom and must not exceed 4.5t.
6. High-speed unwind function should not be performed without outriggers.
Booms over 22.3m in length and jibs should not be used without outriggers.
7. The "Drive Mode Selection" switch should be set to "4-wheel / Lo" for travelling while hoisting a load and the shift
lever should be set to first.
8. When travelling while hoisting a load, the swing brake should be applied, the load should be kept as close to the
ground as possible but not touching the ground and the speed should be kept at 1.6km/h or less. In particular, any
abrupt steering, starting or braking must be avoided.
9. Crane operations should not be performed when travelling while hoisting a load.
- 12 -
GR-500N-1-00103/JA-02
12
.7
m
8.0 jib
m
jib
41.2
m bo
om
38.0
5m
boo
m
34.9
mb
oom
22
.3
m
bo
om
16
.0
m
bo
om
9.7
m
bo
om
- 13 -
DIMENSIONS (1/100)
GR-500N-1-00103/JA-02
(Total width)
Min.
Max.
- 14 -
(Total height)
(Distance between axes)
(Distance between axes)
(Total length)
ROUGH TERRAIN CRANE
【SPECIFICATION】
■CRANE Specification ■CARRIER Specification
Maximum lifting capacity 70ton×2.5m Maximum traveling speed 49km/h
Boom length 10.0m ― 44.5m (6 section) Gradeability (tan θ) 60% (computed at G.V.W. = 39,750kg)
Fly jib length 8.3m-13.2m (2 section, offset 7°― 60°) Minimum turning radius 11.2m (2 wheel steer)
(center of extreme outer tire) 6.44m (4 wheel steer)
Maximum rated lifting 45.5m (Boom)
height 58.6m (jib) ●Engine
Main Model Mitsubishi 6D24-TLE2A
Hoisting 160m / min. (at 5th layer)
winch
line speed 4 cycle, 6 cylinders, water cooled, direct injection turbo-charged
Auxiliary Type
(winch up) 150m / min. (at 4th layer) diesel engine with intercooling
winch
Piston displacement 11.945L
Main (Parts of line; 16) : 10m / min. (at 5th layer)
Hoisting hook winch Max. power 257kW at 2,200min-1
speed Max. torque 1,275N・m at 1,500min-1
(winch up) Auxiliary (
Parts of line; 1) : 150m / min. (at 4th layer)
winch Fuel due to KATO's recommendation only
Boom derricking angle 0°― 84° ●Equipment and structure
Boom derricking time 66sec / (0°― 84°) Drive system 4×4
Boom extending speed 135sec (10.0m ― 44.5m) Engine mounted 3 elements
Torque converter
Slewing speed 1.8min-1 1 stage (with lock up clutch)
Tail slewing radius 3,550mm Remote mounted full automatic 6 forward & 2 reverse speed with
Transmission
transfer differencial
●Equipment and structure
Number of speeds 6 forward & 2 reverse speed
Box-shaped, 6-section hydraulically terescopic type
Boom type (Boom section 2 / 3, 4 / 5 / 6 simultaneously operated) Front Planetary, drive/steer type
Axles
2 sections (2nd section of hydraulically terescopic type) Rear Planetary, drive/steer type
Jib type (offset angles 7°― 60°) Front & Hydro-pneumatic suspension
Suspension
Boom extension/ Rear Hydraulic locking device with suspension cylinder
Three hydrauric cylinders and wire ropes used together
retraction equipment Service Air-over hydraulic disk brake on 4 wheels
Boom derricking/lowering Two hydraulic cylinders of direct acting type with pressure- brake (front and rear independent circuit)
equipment compensated flow control valve Parking Spring applied, electrically air released parking brake mounted on
Brake system
Driven by axial plunger type hoisting motor through planetary gear brake front axle, internal expanding type
Winch system
reduction. Controlled independently by respective operating lever. Auxiliary
Main & Auxiliary winches Exhaust brake, Hydraulic retarder
Equipped with automatic brake. brake
Slewing equipment Ball bearing type Full hydraulic power steering
Hydraulic H-beam type Steering Completely independent front and rear steering
Type (with float and vertical cylinder in single unit) (with automatic rear wheel steering lock system)
62133000
1
■RATED LIFTING CAPACITY
10.0m ― 44.5m Boom
(Unit : Metric ton) (Unit : Metric ton)
2
44.5m Boom+8.3m SLJib
(7.6m) (7.2m) (6.5m)
Outriggers fully extended (7.6m) (over side and over rear) Outriggers intermediately extended (7.2m) (over side) Outriggers intermediately extended (6.5m) (over side)
Boom Offset 7° Offset 25° Offset 45° Offset 60° Boom Offset 7° Offset 25° Offset 45° Offset 60° Offset 7° Offset 25° Offset 45° Offset 60°
Boom
angle Working Load Working Load Working Load Working Load angle Working Load Working Load Working Load Working Load angle Working Load Working Load Working Load Working Load
(° ) radius (m) (ton) radius (m) (ton) radius (m) (ton) radius (m) (ton) (° ) radius (m) (ton) radius (m) (ton) radius (m) (ton) radius (m) (ton) (° ) radius (m) (ton) radius (m) (ton) radius (m) (ton) radius (m) (ton)
84 5.8 4.00 8.6 3.00 10.4 1.90 11.2 1.00 84 5.8 4.00 8.6 3.00 10.4 1.90 11.2 1.00 84 5.8 4.00 8.6 3.00 10.4 1.90 11.2 1.00
80 10.3 4.00 12.8 3.00 14.4 1.90 14.7 1.00 80 10.3 4.00 12.8 3.00 14.4 1.90 14.7 1.00 80 10.3 4.00 12.8 3.00 14.4 1.90 14.7 1.00
77 13.4 4.00 15.8 3.00 17.0 1.85 17.3 1.00 77 13.4 4.00 15.8 3.00 17.0 1.85 17.3 1.00 77 13.4 4.00 15.8 3.00 17.0 1.85 17.3 1.00
75 15.5 4.00 17.5 3.00 18.7 1.80 19.0 1.00 75 15.5 4.00 17.5 3.00 18.7 1.80 19.0 1.00 75 15.5 4.00 17.5 3.00 18.7 1.80 19.0 1.00
73 17.3 3.70 19.3 2.75 20.3 1.75 20.7 1.00 73 17.3 3.70 19.3 2.75 20.3 1.75 20.7 1.00 73 17.3 3.70 19.3 2.75 20.3 1.75 20.7 1.00
70 19.9 3.20 21.8 2.45 22.8 1.65 23.1 1.00 70 19.9 3.20 21.8 2.45 22.8 1.65 23.1 1.00 70 19.7 2.90 21.8 2.45 22.8 1.65 23.1 1.00
68 21.7 2.90 23.5 2.25 24.5 1.60 24.6 1.00 68 21.7 2.80 23.5 2.25 24.5 1.60 24.6 1.00 68 21.2 2.35 23.3 2.00 24.5 1.60 24.6 1.00
65 24.1 2.30 25.8 2.05 26.8 1.55 26.8 1.00 65 23.8 2.10 25.7 1.85 26.8 1.55 26.8 1.00 65 23.5 1.60 25.5 1.40 26.7 1.30 26.8 1.00
63 25.7 1.80 27.3 1.70 28.3 1.50 28.2 1.00 63 25.3 1.65 27.1 1.45 28.2 1.40 28.2 1.00 63 25.0 1.20 27.0 1.00 28.1 0.95 28.2 1.00
60 27.7 1.35 29.4 1.20 30.3 1.15 60 27.5 1.10 29.3 1.00 30.2 0.95 60 27.2 0.65 29.1 0.60 30.1 0.55
57 29.8 0.90 31.4 0.80 32.3 0.75 57 29.6 0.70 31.3 0.60 32.2 0.55 Critical
54 31.8 0.55 33.4 0.45 34.0 0.45 Critical 59° 59° 59° 62°
56° 56° 56° 62° boom angle
Critical boom angle Standard hook for 5 ton (Hook mass : 120kg)
53° 53° 53° 62°
boom angle Standard hook for 5 ton (Hook mass : 120kg) Parts of line 1
Standard hook for 5 ton (Hook mass : 120kg) Parts of line 1
Parts of line 1
Outriggers fully extended (7.6m) (over side and over rear) Outriggers intermediately extended (7.2m) (over side) Outriggers intermediately extended (6.5m) (over side)
Boom Offset 7° Offset 25° Offset 45° Offset 60° Boom Offset 7° Offset 25° Offset 45° Offset 60° Boom Offset 7° Offset 25° Offset 45° Offset 60°
angle Working Load Working Load Working Load Working Load angle Working Load Working Load Working Load Working Load angle Working Load Working Load Working Load Working Load
(° ) radius (m) (ton) radius (m) (ton) radius (m) (ton) radius (m) (ton) (° ) radius (m) (ton) radius (m) (ton) radius (m) (ton) radius (m) (ton) (° ) radius (m) (ton) radius (m) (ton) radius (m) (ton) radius (m) (ton)
84 7.2 2.50 11.0 1.50 14.3 1.00 15.7 0.60 84 7.2 2.50 11.0 1.50 14.3 1.00 15.7 0.60 84 7.2 2.50 11.0 1.50 14.3 1.00 15.7 0.60
80 11.8 2.50 15.5 1.50 18.2 1.00 19.5 0.60 80 11.8 2.50 15.5 1.50 18.2 1.00 19.5 0.60 80 11.8 2.50 15.5 1.50 18.2 1.00 19.5 0.60
77 15.3 2.50 18.6 1.50 21.0 1.00 22.2 0.60 77 15.3 2.50 18.6 1.50 21.0 1.00 22.2 0.60 77 15.3 2.50 18.6 1.50 21.0 1.00 22.2 0.60
75 17.5 2.50 20.6 1.50 22.9 1.00 23.8 0.60 75 17.5 2.50 20.6 1.50 22.9 1.00 23.8 0.60 75 17.5 2.50 20.6 1.50 22.9 1.00 23.8 0.60
73 19.6 2.50 22.5 1.45 24.8 1.00 25.4 0.60 73 19.6 2.50 22.5 1.45 24.8 1.00 25.4 0.60 73 19.6 2.50 22.5 1.45 24.8 1.00 25.4 0.60
70 22.5 2.20 25.2 1.40 27.3 1.00 27.8 0.60 70 22.5 2.20 25.2 1.40 27.3 1.00 27.8 0.60 70 22.5 2.20 25.2 1.40 27.3 1.00 27.8 0.60
68 24.5 2.05 27.0 1.35 29.0 1.00 29.4 0.60 68 24.5 2.05 27.0 1.35 29.0 1.00 29.4 0.60 68 24.2 1.80 27.0 1.35 29.0 1.00 29.4 0.60
65 27.2 1.85 29.6 1.30 31.4 1.00 31.5 0.60 65 27.1 1.65 29.6 1.30 31.4 1.00 31.5 0.60 65 26.6 1.25 29.4 1.10 31.4 1.00 31.5 0.60
63 28.9 1.50 31.2 1.25 32.9 0.95 32.9 0.60 63 28.7 1.30 31.1 1.20 32.9 0.95 32.9 0.60 63 28.3 0.90 31.0 0.80 32.7 0.70 32.9 0.60
60 31.2 1.05 33.6 0.95 35.3 0.90 60 31.0 0.85 33.4 0.80 34.9 0.75 Critical
58 32.5 0.85 35.2 0.70 36.5 0.70 58 32.3 0.65 34.9 0.55 36.2 0.45 62° 62° 62° 62°
boom angle
55 34.5 0.55 37.2 0.40 38.3 0.40 Critical
57° 57° 57° 62° Standard hook for 5 ton (Hook mass : 120kg)
Critical boom angle
54° 54° 54° 62°
boom angle Standard hook for 5 ton (Hook mass : 120kg) Parts of line 1
Standard hook for 5 ton (Hook mass : 120kg) Parts of line 1
Parts of line 1
3
■When the outriggers are not used
(Unit : Metric ton)
4
■Notes for the lifting capacity chart
■When the outriggers are used ■When the outriggers are not used
1. The lifting capacity charts are based on the jib stowed on the 1. The lifting capacity charts are based on the jib stowed on the
boom side. boom side.
2. The lifting capacity chart indicates the maximum load which can 2. The lifting capacity chart indicates the maximum load the crane
be lifted by this crane provided it is level and standing on firm can lift when its body is level on firm level ground with all tires
level ground. The values in the chart include the mass of the inflated to the rated pressure and the suspension cylinder
main hook and slings for boom operation, and auxiliary hook completely retracted. The values in the chart include the mass
and slings for jib operation. [70 ton hook (mass: 530kg), 48 ton of the main hook and slings.
hook ( mass: 470kg), 34 ton hook ( mass: 330kg), 5 ton hook Within the chart the figures in the area bordered with a thick line
(mass: 120kg) ] are based on structural limitations while other figures are
Within the chart the figures in the area bordered with a thick line determined by stability limitations.
are based on structural limitations while other figures are [Tire pressure: 800kPa (8.0kgf/cm2)]
determined by stability limitations. 3. The working radii are the actual values allowing for boom
3. The working radii are the actual values allowing for boom and jib deflection. Therefore you must always operate the crane on the
deflection. Therefore you must always operate the crane on the basis of the working radius.
basis of the working radius. 4. The lifting capacity differs between the front area capacity and
4. The jib working radius is based on the jib mounted on the end of the full range capacity. When slewing from the front to the side,
the 44.5m boom. When operating at other boom lengths, use take care that the crane could not be over loaded.
the boom angle alone as the criterion.
5. Do not operate the jib when the outriggers are completely
retracted.
6. The lifting capacities for the over sides vary with the outrigger
extension width. Therefore for each outrigger extension Stationary
Pick and carry
Crane operation crane-on-rubber
condition you should work according the lifting capacity chart. operation
operation
Use the front area lifting capacity chart for the front area lifting Area α◦ 1 1
capacity, and the lifting capacity chart of outrigger full extension
for the rear area lifting capacity. 5. The lifting capacity of the rooster sheave is the lifting capacity of
the boom minus the mass of the 34 ton hook (330kg), with an
upper limit of 5,000kg.
[The hook for use with the rooster shave is the 5 ton hook (mass:
120kg) with one part of line.]
Outrigger Full extension
Intermediate
Intermediate
6. Do not work with the jib or with a boom length of more than
(7.6m) extension Full retraction 23.8m.
extension status (7.2 ― 5.4m) extension (4.3m)
5
■WORKING RANGE
62133000
6
■Minimum path width
●Left turn in two-wheel steering mode ●Left turn in 4-wheel steering mode
■Overall view
7
■Overall view
* KATO products and specifications are subject to improvements and changes without notice.
C02651
10.2008-3000 (TI) 1 We acquired the "ISO 9001" certification which is
an international standard for quality assurance.
8
CONTACT US
Tutt Bryant Heavy Lift & Shift locations
Darwin
Port Hedland
Karratha
Ormeau
Muswellbrook
Redcliffe
Singleton
Dandenong Doveton
Western Region
Perth 08 9230 0500 per@tuttbryant.com.au
Karratha 08 9143 0089 krt@tuttbryant.com.au
Port Hedland 08 9172 2288 porthedland@tuttbryant.com.au
Northern Region
Darwin 08 8924 1333 dwn@tuttbryant.com.au
Eastern Region
Brisbane (Ormeau) 07 5540 8700 bne@tuttbryant.com.au
Melbourne (Dandenong) 03 9554 0300 mel@tuttbryant.com.au
Melbourne (Doveton) 03 9793 7755 mel@tuttbryant.com.au
Sydney 02 9646 6000 syd@tuttbryant.com.au
Hunter Region
Muswellbrook 02 6541 6444 mbk@tuttbryant.com.au
Attachment # 05
Manpower Loading
18
MASINLOC POWER PLANT EXPANSION PROJECT
STEAM TURBINE BUILDING
I INDIRECT 18 12 19 23 26 26 20
1 Manager 1 1 1 2 2 2 2
2 Engineer 1 1 1 1 1 1 1
3 QA/QC Inspector 1 - 1 1 1 1 1
5 Site Engineer 1 1 1 1 1 1 1
9 Supervisor 2 - 2 2 2 2 2
4 Secretary 2 2 2 2 2 2 2
10 Material Controller 1 1 1 1 1 1 1
6 Safety Officer 2 1 3 6 6 6 3
7 Expediter 1 1 1 1 1 1 1
8 First Aider 3 2 3 3 6 6 3
9 Driver 2 1 2 2 2 2 2
10 Technician 1 1 1 1 1 1 1
II DIRECT 95 27 60 103 103 72 43
1 General Foreman 1 1 1 1 1 1 1
2 Foreman 5 2 4 5 5 4 2
3 Leadman 6 2 5 5 5 5 3
4 Erector 50 5 25 60 60 30 15
5 Welder 6 1 3 6 6 6 3
6 Scaffolder - - - - - - -
7 Fire Watcher 10 3 6 10 10 10 4
8 Rigger 3 1 3 3 3 3 2
9 Surveyor 1 1 1 1 1 1 1
10 Surveyor Aide 2 2 2 2 2 2 2
11 Electrician 3 1 2 2 2 2 2
12 Crane Operator - - - - - - -
13 Payloader Forklift Operator - - - - - - -
14 Warehouseman 1 1 1 1 1 1 1
15 Tool Keeper 1 1 1 1 1 1 1
16 Skilled Helper 6 6 6 6 6 6 6
*Note: All Schedule and quantity are subject to change depending on necessity and availability