Rate Analysis-All Activities
Rate Analysis-All Activities
SI No Activity uom Coefficient Rate Amount Coefficient Rate Amount Total Amount Remarks
1 Mass Excavation/cum
2 Manual Excavation/cum
b Shifting of surplus earth from premises cum 1.00 12.00 12.00 12.00
Backfilling and consolidation with
3 available earth/cum
Back filling in layers of not more than 30 CM as
per instructions at site including watering,
Backfilling and consolidation
compaction/leveling.etc. complete with
cum 1.00 34.00 34.00 34.00 available earth
Backfilling and consolidation with
4 purchased earth/cum
Back filling in layers of not more than 30 CM as
per instructions at site including watering,
Backfilling and consolidation
compaction/leveling.etc. complete with
cum 1.00 71.50 71.50 71.50 purchased earth
4 Surface trimming/sqm
6 Antitermite treatment/sqm
7 Soling/sqm
28 Sobha Mayflower
Rate Analysis for Earthwork activity
SI No Activity uom Coefficient Rate Amount Coefficient Rate Amount Total Amount
RMC M-25 Footings with
1
pumping/cum
a RMC M25 cum 1.00 3,115.00 3,115.00 1.00 18.00 18.00 3,133.00
b Lift charges cum 1.00 21.00 21.00 21.00
c Concreting mason Man day 0.10 175.00 17.50 17.50
d Concreting mason helper Man day 0.10 85.00 8.50 8.50
e Vibrator operator Man day 0.10 120.00 12.00 12.00
2 RMC M10- Retaining Wall
a RMC M10 cum 1.00 2,615.00 2,615.00 1.00 94.00 94.00 2,709.00
b Polythene for flooring kg 1.00 43.00 43.00 43.00
c Lift charges cum 1.00 21.00 21.00 21.00
d Concreting mason Man day 0.10 175.00 17.50 17.50
e Concreting mason helper Man day 0.10 85.00 8.50 8.50
3 RMC M-40 Columns
a RMC M40 cum 1.00 3,740.00 3,740.00 1.00 177.00 177.00 3,917.00
b Lift charges cum 1.00 21.00 21.00 21.00
c Concreting mason Man day 0.10 175.00 17.50 17.50
d Concreting mason helper Man day 0.10 85.00 8.50 8.50
e Vibrator operator Man day 0.10 120.00 12.00 12.00
5 RMC M-25 Beams
a RMC M25 cum 1.00 3,115.00 3,115.00 1.00 25.00 25.00 3,140.00
b Lift charges cum 1.00 21.00 21.00 21.00
c Concreting mason Man day 0.10 175.00 17.50 17.50
d Concreting mason helper Man day 0.10 85.00 8.50 8.50
e Vibrator operator Man day 0.10 120.00 12.00 12.00
f Food allowance for night cum 1.00 1.04 1.04 1.04
6 RMC M-20 Slabs
a RMC M20 cum 1.00 3,015.00 3,015.00 1.00 18.00 18.00 3,033.00
b Lift charges cum 1.00 21.00 21.00 21.00
c Concreting mason Man day 0.10 175.00 17.50 17.50
d Concreting mason helper Man day 0.10 85.00 8.50 8.50
e Vibrator operator Man day 0.10 120.00 12.00 12.00
SI No Activity uom Coefficient Rate Amount Coefficient Rate Amount Total Amount Remarks
SI No Activity uom Coefficient Rate Amount Coefficient Rate Amount Total Amount Remarks
Adjustable prop Nos 1.25 850.00 1,062.50 1,062.50
Nails kg 0.10 37.00 3.70 3.70
Miscellanous sqm 1.00 25.00 25.00 25.00
Polythene for flooring kg 0.01 43.00 0.43 0.43
Columns,beams,slabs shuttering sqm 1.00 43.00 43.00 43.00
4 Beams/sqm (10 repetitions)
Silver Oak runner 6" x 4" cum 0.03 9,057.94 271.74 271.74
Silver Oak runner 4" x 3" cum 0.02 279.38 5.59 5.59
Base plate Nos 1.50 260.00 390.00 390.00
Horizontal 2m Nos 2.00 312.00 624.00 624.00
Horizontal 1m Nos 1.50 176.00 264.00 264.00
Vertical 1m Nos 1.50 350.00 525.00 525.00
Stirrup head Nos 1.50 270.00 405.00 405.00
C Clamps Nos 2.50 165.00 412.50 412.50
Nails kg 0.10 37.00 3.70 3.70
Miscellanous sqm 1.00 25.00 25.00 25.00
Polythene for flooring kg 0.01 43.00 0.43 0.43
Beam box making sqm 1.00 3.58 3.58 3.58
Columns,beams,slabs shuttering sqm 1.00 43.00 43.00 43.00
Note : Labour Rate is inclusive of Making , Remaking and Fixing and removal charges
Material Rate is inclusive of Wooden materials , MS Materials , Shuttering consumables and Machineries.
10 10mm Sadarahalli Granite flooring in Common Area SQM 689 258 947
11 10mm sadarahalli Granite for staircase tread Sqm 660 439 1099
12 20mm Sadarahalli GraniteCoping in Balcony Rmt 309 67 376
13 Terracotta tiling for flat slab Sqm 163 103 266