H5161.

17Form 2Lighting fixture Installation


2.0.1 This chapter applies to the installation quality acceptance of lighting fixtures with a reted volatge of 500V and below.
2.0.2 The installation quality acceptance of lighting fixtures should meet the requirements of Table 2.0.2

Single loop
Process Test Items Nature Quality Standard Quality acceptance
conclusion

Lamp Model Specification Meet the requirements of design


Inspection Exterior Intact, no defects

Component assembly Complete, stronge connection


Lamp stand
The cross-section meets the requirements
assembly Lead wire Master of the design documents. The lamp terminal
is connected tightly and has good insulation

Centerline shift <50mm


Light pole
assembly vertical error <1.5%

Connection Master Tighten, not withstand tension

Screw lamp holder wiring Correct


Power wiring
The bandage is tight, uniform, and not lower
Insulation treatment at wiring
than the original insulation strength

Meet the requirements of design documents


Installation location Master
and GB 50617

Fixed Meet the requirements of product techincal


Fixed way
documents
Fixing bolt situation and fixing bolt
points

Horizontal and vertical, height on the same


Rows of lamps in the same room
plane, centerline deviation <5mm
Adjustment
Embedded ceiling decorative lights Border on a straight line

Orientation meets the requirements of design


Battery board installation
documents

Don't put it upside down, damp, or expose to the


Battery
Solar lighting sun
installation
Wiring Battery, battery board, load

Internal protection Fully functional and correct


Bracket connection Firm and reliable
Explosion proof mark Clear and correct
Fastening butterfly bolt Firm, no rust

Sealing washer Intact

Explosion proof Annex Complete


Lighting
Rated voltage of cable or insulated
installation Master >500V
conductor
Insulated wire threading Master Steel pipe Laying
Steel pipe, Cable Grounding Master Grounding at the entrance to the hazardous area
Number of threaded mouths >5mm

Power Meet the requirements of design documents


Light bulb
Connect with lamp holder Tight, not loose

Cover No damage, tightly integrated with lamps


Accessories( starter, rectifier, etc Complete, firmly fixed, easy to maintain
Other Emergency lighting Clear signs and correct instructions

36V and below lighting transformer Comply with GB 50303 regulations

Meet the requirements of product techincal


Seal lamps with special requiremnets Master
documents

Outer wall, lamp pole, lamp holder


Master Comply with GB 50169 regulations
ground
Acceptance Conclusion:

Acceptance signature unit

Construction unit

Supervision unit
H5161.17Form-3 Lighting distribution box (board) installation
3.0.1 This chapter applies to the installation quality acceptance of lighting distribution boxes( boards) with rated voltages of 500v and below.
3.0.2 The installation quality acceptance of the lighting distribution box (baord) Should meet the requirements of Table 3.0.2

Process Test Item Nature Quality Standard Quality acceptance result

Meet the requirements of design


Model specificaiton
Inspection documents
Exterior Intact, no defects
Meet the requirements of design
Locaiton, height
documents

Board Vertical deviation <1.5%


Cabinet
installation installation Meet the requirements of GB50617
The bottom plate is high
or design documents
Cabinet fixation Cell

Load distribution Meet the requirements of design


documents

Switch Matching with the load, flexible


movements, jamming

Scew fuse No looseness of the base, in line with


GB 50617
Wire and terminal connection Fasten
Internal
inspection Fixed on the neutral line confluence
Neutral connection
mix, complete number
Fixed on the ground bus bar, complete
Protection line connection
nnumbers
Box(board) grounded Master Flat, good conduction
Movable door(board) ground
Master Good conduction
preparation
Wiring Correct and firm
Acceptance Conclusion:

Acceptance signature unit

Construction unit

Supervision unit
H5161.17-4.0.2 Reocrds and visas
4.0.1 This chapter applies to the records and vias of lighting circuit power-on inspection
4.0.2 The lighting circuit power-on inspection record and visa shall meet the requirements of Table 4.0.2

Project number Table number

Acceptance check range

Test result Remarks


Check item
Lighting box logo
ground

Quality is greather than 10KG


Strength test with fixture
5 double the weight of the lamp>15mm

Cable identification plate


inspection
Check before
power on Lighting switch naming and circuit
comparison
Check the capacity and design of
switched and fuses
The minimum value of loop Ambient temperature C
insulation >> 0.5Mohm wet Degree %
Light box sealing and intenal
cleaning

Surge current protection action


test

Emergency light trial investment


tets
automatic switching test of
Power on
emergency lighting power
inspection
Four readings of kawasaki kashiwa
in th form of regular help

Photoelectric controller test

heming system invested 24h time Year month day hours to month day hours
Inspection findings

Construction unit Year month day

supervision unit Year month day


Construction unit Year month day