Professional Documents
Culture Documents
Introduction To Quantity Surveying Part 2 20210617
Introduction To Quantity Surveying Part 2 20210617
QUANTITY SURVEYING
June 17, 2021
PROCUREMENT
- It is an acquisition process used to secure services, goods, and work from external sources or
contractors.
a) You may go for a procurement contract when you do not have the expertise to carry out the
job.
b) You do not have the capacity to do it on your own.
c) You lack the capacity to handle the requirement.
d) A resource can be produced outside your firm at a significant discount.
However, before going for a procurement contract, you must analyze whether it would be cost-
effective to do it yourself or if you should outsource it. If the benefits of outsourcing outweigh the
“do it yourself”, outsourcing is advisable.
Procurement Routes
1) Lump Sum Contract – the contractor is required to provide a lump sum price for a particular
work defined in the procurement process.
a. Lump Sum Contract based on Drawings and Specifications.
b. Lump Sum Contract based on Bill of Quantities.
2) Design and Build Contractor – The Contractor is responsible for the design and construction
as well as the management of the project.
a. Turnkey Contract – Design and Build but it also includes “Furnish and Fit-out”.
TENDERING
- It is the process by which bids are invited from interested contractors to carry out specific
packages of construction work. It should adopt and observe the key values of fairness,
clarity, simplicity, and accountability, as well as reinforce the idea that the apportionment of
risk to the party best assess and manage it, is a fundamental to the success of a project.
(National Building Specification, NBS)
1) Open Tendering – allows anyone to submit a tender to supply the goods or service that are
required.
2) Selective Tendering – allows contractors/ suppliers to submit tenders by invitation.
3) Negotiated Tendering – appropriate for highly specialist contracts or for extending the
scope of an existing contract.
4) Serial Tendering – preparation of tenders based on a typical or notion bill of quantities or
schedules of works. The rates submitted can be then used to value works over a series of
similar projects.
5) Framework Tendering – invite tenders from suppliers of goods and services to be carried
out over a period on a call-off basis as and when required.
6) Single-stage and two-stage tendering
a. Single-stage Tendering – is the more traditional route.
Used when all the information necessary information to calculate a realistic price is
available during tendering.
b. Two-stage Tendering – allow an early appointment of supplier, prior to completion
of all the information required to enable them to offer a fixed price.
8) Tender Clarification
9) Tender Report
10) Negotiation Award
-In essence these differences amount to the fact that while procurement relates to how the services
of a contractor are purchased, tendering relates to how the successful contractor is ultimately
selected. The distinction might seem slight but is in a candidate’s best interest to have a clear picture
in their minds of where the division lies.
TENDER DOCUMENTS