Professional Documents
Culture Documents
Chapter II Methods of Comparing Alternative Proposals
Chapter II Methods of Comparing Alternative Proposals
G5WSEEF- E 1
Engineering Economics & Management
𝐴1 𝐴2 𝐴𝑛
𝑃(𝑖) = 1
+ 2
+⋯+ 𝑊ℎ𝑒𝑟𝑒: 𝑃(𝑖) = 𝑁𝑃𝑊 𝑐𝑎𝑙𝑐𝑢𝑙𝑎𝑡𝑒𝑑 𝑎𝑡 𝑖
(1 + 𝑖) (1 + 𝑖) (1 + 𝑖)𝑛
𝐴𝑛 = 𝑛𝑒𝑡 𝑐𝑎𝑠ℎ 𝑓𝑙𝑜𝑤 𝑎𝑡 𝑝𝑒𝑟𝑖𝑜𝑑 𝑛
𝑖 = 𝑀𝐴𝑅𝑅 (𝑜𝑟 𝑐𝑜𝑠𝑡 𝑜𝑓 𝑐𝑎𝑝𝑖𝑡𝑎𝑙)
𝑛 = 𝑠𝑒𝑟𝑣𝑖𝑐𝑒 𝑙𝑖𝑓𝑒 𝑜𝑓 𝑡ℎ𝑒 𝑝𝑟𝑜𝑗𝑒𝑐𝑡
“A” will be positive if the corresponding period has a net cash inflow or negative if there is a net
cash outflow. In this context, a positive NPW means the equivalent worth of the inflows is
greater than the equivalent worth of the outflows, so, the project makes a profit. Therefore, if the
P(i) is positive for a single project, the project should be accepted; if negative it should be
rejected. The decision rule is:
If P(i)>0, accept the investment
If P(i)=0, remain indifference
If P(i)<0 reject the investment
Comparison of Alternatives with Equal Life Span
Example-1: Alternatives with equal life span:
An engineer is in need of an automobile for business purposes and finds that a suitable one can
be obtained by either of two methods: (a) lease a car for Birr 10,000 per month for two years,
paid monthly at the end of each month, or (b) purchase the same type of car for Birr 500,000
now and sell it in two years for Birr 300,000. In either case, the engineer pays all operating
maintenance and insurance costs. He can borrow fund for either alternative from the local bank
at 9% interest. Which is the least costly alternative, assuming interest is compounded monthly?
Solution
Since the life spans of both alternatives are equal, the alternatives can be compared directly by
finding the net present worth of each and selecting the one with least cost.
i. Lease: The NPW of the lease alternative is present worth of the 24 payments of Birr
10,000 per month.
P1 = -Birr 10,000(P/A, i, N) = -Birr 10,000(P/A, 9/12%, 24)
(1+𝑖)𝑁 −1
= -Birr 10,000(P/A, 0.75%, 24), P/A = )
𝑖(1+𝑖)𝑁
24
(1+0.0075) −1
P1 = -Birr 10,000( 24 ) = -Birr 10,000(21.8891) = -Birr 218.891.50
0.0075(1+0.0075)
G5WSEEF- E 2
Engineering Economics & Management
ii. Purchase: The NPW of the purchase alternative is the present worth of the purchase
price minus the present worth of the income from the resale at the end of two years.
P2 = -Birr 500,000 purchase price
1
P3 = F (P/F, i, N) = Birr 300,000(P/F, 0.75%, 24) P/F = ((1+𝑖)𝑁 )
1 1
P3 = 𝐹((1+𝑖)𝑁 ) = Birr 300,000((1+0.0075)24 ) = Birr 250,749.4212 (resale value)
Comparing the present worth, it is apparent that the cost of the lease alternative is much less
expensive than the cost of the purchase alternative. So, leasing the car is recommendable.
2.2 The Annual Payments Method of Comparing Alternatives: It is a method of reducing all
cash flows involved in each proposal to an equivalent series of periodic payment. The major
advantage of the annual worth method of comparing alternatives on the basis of periodic
payments is that the complication of unequal lives between alternatives is automatically taken
into account without any extra computations.
Example
1. Two roofs are under consideration for a building needed for 20yrs. Their anticipated costs
and life’s are given below in the table. By using Annual worth method, suggest which roof
would you select and why?
Roof C Roof D
Cost new (Birr) 50,000 25,000
Replacement cost (Birr) - Rise 8%/yr
Life of roof (yr.) 20 10
Salvage value (Birr) 0 0
Interest rate (%) 10 10
Solution
0.1(1+0.1)20
Roof C A1 = -Birr 50,000 (A/P, 10%, 20) = -Birr 50,000( ) = -Birr 5,875/yr.
(1+0.1)20 −1
0.1(1+0.1)20
Roof D A2 = -Birr 25,000 (A/P, 10%, 20) = -Birr 25,000( ) = -Birr 2,937/yr.
(1+0.1)20 −1
A3 = -Birr 25,000 (F/P, 8%, 10) (P/F, 10%, 10) (A/P, 10%, 20)
G5WSEEF- E 3
Engineering Economics & Management
Step 3. Convert the present worth obtained into its 20year Annual equivalence
0.1(1+0.1)20
A3 = P (A/P, i, N) = -20,808.98(A/P, 10%, 20) = -20,808.98((1+0.1)20 −1) = -Birr 2,445/yr
$125,000
$50,000
Time (year) 0 1 2 3 4 5
$300,000 $20,000
The equivalent uniform annual worth of Alternative-1 i.e. AW1 is computed as follows;
G5WSEEF- E 4
Engineering Economics & Management
0.1(1+0.1)5 0.1
AW1= -300000((1+0.1)5−1) + (50000-20000) +125000((1+0.1)5−1)
AW1= -$28,665
The cash flow diagram of Alternative-2 i.e. Fig. 2.2 is shown here again for ready reference.
$70,000
$45,000
Time (year) 0 1 2 3 4 5
$200,000 $35,000
Now the equivalent uniform annual worth of Alternative-2 i.e. AW2 is calculated as follows;
Now putting the values of different compound interest factors in the above expression;
0.1(1+0.1)5 0.1
AW2= -200000((1+0.1)5−1)+ (45000-35000) +70000((1+0.1)5−1)
AW2= -$31,294
G5WSEEF- E 5
Engineering Economics & Management
From this comparison, it is observed that Alternative-1 will be selected as it shows lower
negative equivalent uniform annual worth compared to Alternative-2.
2.3 Future worth Method of Computing Alternative.
Future worth (FW) comparisons of alternative investments or projects are frequently used when
the owner or manager expects to sell or otherwise liquidate the investment at some future date
and wants to estimate of net worth at that future date.
Example
1. An Engineering consultant reviewed records of the expenditure from year zero to 5 which is
as shown in the figure. Out of that he selected only the 3 largest amounts. What return can he
expect at the 10th year at an interest rate of 5% per year. Calculate the future worth by both
present and future worth analysis. Construct a cash flow diagram for the same.
year 1, 175
year 0, 600 year 2, 300
year 3, 135
year 5, 400 year 4, 250
Solution: 3 Largest amounts are 600[year 0], 400[year 5], and 300[year 2]
1. By Future worth analysis
F = 600 (F/P, 5%, 10) + 300 (F/P, 5%, 8) + 400 (F/P, 5%, 5)
F = 600(1 + 0.05)10 + 300(1 + 0.05)8 + 400(1 + 0.05)5 = 977.34+443.24+510.51
F= 1931.11
2. By Present worth analysis
First let us find the present worth and then convert it in to the future worth.
P= 600 (P/F, 5%, 0) + 300 (P/F, 5%, 2) + 400 (P/F, 5%, 5)
1 1 1
P= 600((1+0.05)0) + 300((1+0.05)2) + 400((1+0.05)5) = 600+272.11+313.41
P= 1185.50
F= 1185.50 (F/P, 5%, 10) = 1185.50(1 + 0.05)10
G5WSEEF- E 6
Engineering Economics & Management
F= 1931.11
Both the calculations give the same future worth value.
Cash flow diagram
+ 1931.11
i=5%
0 1 2 3 4 5 6 7 8 9 10
300
400
- 600
2. A construction company is considering the purchase of one of the two new front-end loaders
whose data are listed below. Use Future worth analysis to find which loader is preferred.
Front End Loader A Front End Loader B
First cost (Birr) -100,000 -40,000
Annual net income +16,000 +13,000
Useful life (yrs.) 10 5
Replacement cost escalation NA 10%/yr. compounded
Salvage value (Birr) +10,000 +10,000
Interest rate (%) 8 8
FW (A) = -100,000 (F/P, 8%, 10) +16,000 (F/A, 8%, 10) + 10,000
(1+0.08)10 −1
= -100,000(1 + 0.08)10 + 16,000( ) + 10,000 = -215,900 + 231,792 +10,000
0.08
= +Birr 25,886
FW (B) = -40,000 (F/P, 8%, 10) -40,000 (F/P, 10%, 5) (F/P, 8%, 5) +13,000 (F/A, 8%, 10)
+10,000 + 10,000 (F/P, 8%, 5)
(1+0.08)10 −1
= -40,000(1 + 0.08)10-40,000(1 + 0.1)5 (1 + 0.08)5+13,000( 0.08
)+10,000+10,000(1 + 0.08)5
G5WSEEF- E 7
Engineering Economics & Management
3. A Computer company has invested 50,000 Birr now. Find its equivalence value 3 years
earlier with a discount rate of 20% / year. Draw the cash flow diagram.
Solution:
F = 50,000 Birr, i = 20%, N = 3 years
P = F (P/F, i, N)
1
P = 50,000 (P/F, 20%, 3) =50,000((1+0.2)3)
P = 28,935 Birr
+
P = 28,935
i = 20 %
-3 -2 -1 0 1 2 3
- F = 50,000
2.4 Rate of return method of comparing alternative
A return of Birr 6 interest per year on a deposit of birr 100 is easily understood to imply a rate of
return of 6%
Step by step procedure for finding ROR.
Step 1. Make a guess at a trial rate of return.
Step 2. Count the costs as negative (-) and the income or savings as positive (+). Then find the
equivalent net worth of all costs and income. Use present worth, annual worth or future worth.
Step 3. If the equivalent net worth is positive, then the income from the investment is worth
more than the cost of the investment and the actual present return is higher than the trial rate, (i).
Step 4. Adjust the estimates of the trial rate, of return and proceed with steps 2 and 3 again until
one of (i) is found that results in a positive (+) equivalent net worth, and another higher value of
(i) is found with a negative (-) equivalent net worth.
Step 5. Solve for the correct value of (i) by interpolation.
Example
1. Assume a bond sells for Birr 950. The bond holder will receive Birr 60 per year interest as
well as Birr 1,000 (the face amount of this bond) at the end of ten years. Find ROR.
Solution
G5WSEEF- E 8
Engineering Economics & Management
Find the interest rate at which the present worth of the income equals the present worth of the
cost.
Step 1. Let trial i = 7%
10
(1+0.07) −1
Step 2. Income P1 = Birr 60 (P/A, 7%, 10) = Birr 60 ( 10 ) = Birr 421.44
0.07(1+0.07)
1
Income P2 = Birr 1000 (P/F, 7%, 10) = Birr 1000((1+0.07)10)= Birr 508.30
G5WSEEF- E 9
Engineering Economics & Management
15 years with no significant salvage value. The presently owned truck can be sold now for
10,000. If it is kept, it will cost 0.15 per ton-mile for O&M, and have an expected life of five
years, and no salvage value. Use i = 10%, find the break-even point in terms of ton miles per
year.
Solution
The annual equivalent to the capital investment cost is
0.1(1+0.1)15
A (new truck) = 30,000 (A/P, 10%, 15) = 30,000((1+0.1)15 −1) =3,944/yr
0.1(1+0.1)5
A (present truck) = 10,000 (A/P, 10%, 5) =10,000((1+0.1)5−1) = 2,638/yr
The total annual cost for each year for each alternative is simply the annual equivalent capital
cost plus the annual O&M cost as follows:
Total annual cost (new truck) = A1
A1= 3,944/yr + (0.10/ton-mi) (X ton-mi/yr)
Total annual cost (present truck) = A2
A2 = 2,638/yr + (0.15/ ton- mi) (X ton-mi/ yr)
The break- even value to x- may be found by solving the equations simultaneously.
For new truck y = 0.10X + 3,944
For present truck y = 0.15X + 2,638
X= 3,944-2.638=26,120 ton-mi/yr
Graphical solution is also possible by drawing the graphs of the two equations; see the result in
the graph below.
Note:
G5WSEEF- E 10
Engineering Economics & Management
If the contractor’s annual production is below 26,120 mile-tone, the old truck is more economical
and if it is greater than 26,120, the new truck is economical. At the break-even point both truck
have the same economical value.
2.6 Benefit-cost analysis (BCA) is a technique for evaluating a project or investment by
comparing the economic benefits with the economic costs of the activity. Benefit-cost analysis
has several objectives. First, BCA can be used to evaluate the economic merit of a project.
Second the results from a series of benefit-cost analysis can be used to compare competing
projects.
Discounting is a technique that converts all benefits and costs into their value in the present.
Discounting is based on the premise that a Birr received today is worth more than a Birr received
in the future. Another way of saying this is that a dollar received in the future is not worth as
much as that same dollar received in the present. That is, the future value of the dollar is
discounted. Discounting is the opposite of compounding. Not surprisingly, the rate at which a
future value is discounted is closely related to the rate at which present values are compounded,
namely the interest rate.
Whenever the benefits and costs used in a benefit-cost analysis occur in the future, it is important
to discount these future values to account for their present value. If the interest rate is r, then the
following formula can be used to find the present value (PV) of an amount (Pt) received at some
time t in the future:
𝑃𝑡
𝑃𝑉 =
(1 + 𝑟)𝑡
To apply the formula, remember:
PV is the present value of the amount invested; Pt is the value of the future amount in time t;
r is the discount rate; and t is the year in which Pt is realized.
Example
1. Suppose you are given the choice of two investments. The first pays you $210 today, but
nothing thereafter. The second investment pays $100 today and $115 next year (for a total of
$215). If the discount rate is 5%, which is the better investment? Find out by applying the
present value formula:
$210 $0
PV of investment 1 = (1+0.05)0 + (1+0.05)1 = $210
$100 $115
PV of investment 2 = (1+0.05)0 + (1+0.05)1 = $209.5
G5WSEEF- E 11
Engineering Economics & Management
Even though the second investment pays out a greater sum, after discounting the first deal looks
like a better choice.
Net present value (NPV): The net present value (NPV) is the current value of all project net
benefits. Net benefits are simply the sum of benefits minus costs. The sum is discounted at the
discount rate. Using this method, if the project has a NPV greater than zero then it appears to be
a good candidate for implementation. The formula used to calculate the NPV is:
𝑇
(𝐵𝑒𝑛𝑒𝑓𝑖𝑡𝑡 − 𝐶𝑜𝑠𝑡𝑡 )
𝑁𝑃𝑉 = ∑
(1 + 𝑟)𝑡
𝑡=1
[Or]
(𝐵1 − 𝐶1 ) (𝐵2 − 𝐶2 ) (𝐵3 − 𝐶3 ) (𝐵𝑁 − 𝐶𝑁 )
NPV =[(𝐵0 − 𝐶0 )] + [ ]+[ ]+[ ] + ……… + [ ]
(1+𝑟) (1+𝑟)2 (1+𝑟)3 (1+𝑟)𝑁
G5WSEEF- E 12
Engineering Economics & Management
Solution
Comparison of A and B
𝐵⁄ = (460,000−375,000) 85,000
𝐶 = 50,000 = 1.7 > 1. Discard A (the defender) and accept B
(200,000−150,000)
Therefore, B is the better alternative even though the benefit cost ratio is less than that of A. Alternative A
offers a greater benefit for the total expenditures.
2. Perform CBA with the application of NPV and ROI for a project with cost of 50,000 Birr.
Out of the total cost of the project of 50,000 Birr, 35,000 Birr is the initial investment. The
costs allotted for year 1, 2 and 3 are 5,000 Birr each. Assume the total benefits as 25,000
Birr/year and the Discounting factor as 2.5 %.
To find NPV
If ROI is calculated without considering Discount rate, ROI = (25,000/50,000) = 0.5 =50%
G5WSEEF- E 13
Engineering Economics & Management
By adding a discount factor and calculating NPV, ROI = (22,120/50,000) = 0.4424 =44.24%, but is still
positive, and more meaningful because it accounts for the time value of money. Since ROI is positive in
both the case, the investment is worthwhile.
Benefit-cost analysis: -
The benefit-cost analysis method is mainly used for economic evaluation of public projects
which are mostly funded by government organizations. In addition, this method can also used for
economic evaluation of alternatives for private projects. The main objective of this method is
used to find out desirability of public projects as far as the expected benefits on the capital
investment are concerned. As the name indicates, this method involves the calculation of ratio of
benefits to the costs involved in a project.
In benefit-cost analysis method, a project is considered to be desirable, when the net benefit
(total benefit less disbenefits) associated with it exceeds its cost.
Thus, the expression for conventional benefit-cost ratio (B/C ratio) is mentioned as follows;
𝐹𝑊 𝑜𝑓 𝐵𝑒𝑛𝑒𝑓𝑖𝑡𝑠 − 𝐹𝑊 𝑜𝑓 𝐷𝑖𝑠𝑏𝑒𝑛𝑒𝑓𝑖𝑡𝑠
𝐶𝑜𝑛𝑣𝑒𝑛𝑡𝑖𝑜𝑛𝑎𝑙 𝐵/𝐶 𝑟𝑎𝑡𝑖𝑜 =
𝐹𝑊 𝑜𝑓 𝑖𝑛𝑖𝑡𝑖𝑎𝑙 𝑐𝑜𝑠𝑡 + 𝐹𝑊 𝑜𝑓 𝑜𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 𝑎𝑛𝑑 𝑚𝑎𝑖𝑛𝑡𝑒𝑛𝑎𝑛𝑐𝑒 𝑐𝑜𝑠𝑡 − 𝑆𝑎𝑙𝑣𝑎𝑔𝑒 𝑣𝑎𝑙𝑢𝑒
In the above expressions, PW, AW, and FW refer to equivalent present worth, annual worth and
future worth respectively.
Modified B/C ratio
In the modified benefit-cost ratio method, the operating and maintenance cost is subtracted from
the benefits in the numerator of the ratio. In other words, operating and maintenance cost is
G5WSEEF- E 14
Engineering Economics & Management
considered similar to the disbenefits. The expression for modified benefit-cost ratio using PW,
AW or FW is given as follows;
𝑃𝑊 𝑜𝑓 𝐵𝑒𝑛𝑒𝑓𝑖𝑡𝑠 − 𝑃𝑊 𝑜𝑓 𝐷𝑖𝑠𝑏𝑒𝑛𝑒𝑓𝑖𝑡𝑠 − 𝑃𝑊 𝑜𝑓 𝑜𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 𝑎𝑛𝑑 𝑚𝑎𝑖𝑛𝑡𝑒𝑛𝑎𝑛𝑐𝑒 𝑐𝑜𝑠𝑡
𝑀𝑜𝑑𝑖𝑓𝑖𝑒𝑑 𝐵/𝐶 𝑟𝑎𝑡𝑖𝑜 =
𝐼𝑛𝑖𝑡𝑖𝑎𝑙 𝑐𝑜𝑠𝑡 − 𝑃𝑊 𝑜𝑓 𝑠𝑎𝑙𝑣𝑎𝑔𝑒 𝑣𝑎𝑙𝑢𝑒
5000000(𝑃/𝐴 , 𝑖, 𝑛) − 1100000(𝑃/𝐴 , 𝑖, 𝑛)
𝐶𝑜𝑛𝑣𝑒𝑛𝑡𝑖𝑜𝑛𝑎𝑙 𝐵/𝐶 𝑟𝑎𝑡𝑖𝑜 =
21000000 + 1600000(𝑃/𝐴 , 𝑖, 𝑛) − 4000000(𝑃/𝐹 , 𝑖, 𝑛)
G5WSEEF- E 15
Engineering Economics & Management
5000000𝑋11.2578 − 1100000𝑋11.2578
𝐶𝑜𝑛𝑣𝑒𝑛𝑡𝑖𝑜𝑛𝑎𝑙 𝐵/𝐶 𝑟𝑎𝑡𝑖𝑜 =
21000000 + 1600000𝑥11.2578 − 4000000𝑥0.0994
𝐴𝑊 𝑜𝑓 𝐵𝑒𝑛𝑒𝑓𝑖𝑡𝑠 − 𝐴𝑊 𝑜𝑓 𝐷𝑖𝑠𝑏𝑒𝑛𝑒𝑓𝑖𝑡𝑠
𝐶𝑜𝑛𝑣𝑒𝑛𝑡𝑖𝑜𝑛𝑎𝑙 𝐵/𝐶 𝑟𝑎𝑡𝑖𝑜 =
𝐴𝑊 𝑜𝑓 𝑖𝑛𝑖𝑡𝑖𝑎𝑙 𝑐𝑜𝑠𝑡 + 𝐴𝑊 𝑜𝑓 𝑜𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 𝑐𝑜𝑠𝑡 − 𝐴𝑊 𝑜𝑓 𝑠𝑎𝑙𝑣𝑎𝑔𝑒 𝑣𝑎𝑙𝑢𝑒
5000000 − 1100000
𝐶𝑜𝑛𝑣𝑒𝑛𝑡𝑖𝑜𝑛𝑎𝑙 𝐵/𝐶 𝑟𝑎𝑡𝑖𝑜 =
21000000(𝐴/𝑃, 𝑖, 𝑛) + 1600000 − 4000000(𝐴/𝐹, 𝑖, 𝑛)
5000000 − 1100000
𝐶𝑜𝑛𝑣𝑒𝑛𝑡𝑖𝑜𝑛𝑎𝑙 𝐵/𝐶 𝑟𝑎𝑡𝑖𝑜 =
21000000(𝐴/𝑃, 8%, 30) + 1600000 − 4000000(𝐴/𝐹, 8%, 30)
5000000 − 1100000
𝐶𝑜𝑛𝑣𝑒𝑛𝑡𝑖𝑜𝑛𝑎𝑙 𝐵/𝐶 𝑟𝑎𝑡𝑖𝑜 =
21000000𝑥0.0888 + 1600000 − 4000000𝑥0.0088
Conventional B/C ratio = 1.137
𝐹𝑊 𝑜𝑓 𝐵𝑒𝑛𝑒𝑓𝑖𝑡𝑠 − 𝐹𝑊 𝑜𝑓 𝐷𝑖𝑠𝑏𝑒𝑛𝑒𝑓𝑖𝑡𝑠
𝐶𝑜𝑛𝑣𝑒𝑛𝑡𝑖𝑜𝑛𝑎𝑙 𝐵/𝐶 𝑟𝑎𝑡𝑖𝑜 =
𝐹𝑊 𝑜𝑓 𝑖𝑛𝑖𝑡𝑖𝑎𝑙 𝑐𝑜𝑠𝑡 + 𝐹𝑊 𝑜𝑓 𝑜𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 𝑐𝑜𝑠𝑡 − 𝑆𝑎𝑙𝑣𝑎𝑔𝑒 𝑣𝑎𝑙𝑢𝑒
5000000(𝐹/𝐴, 𝑖, 𝑛) − 1100000(𝐹/𝐴, 𝑖, 𝑛)
𝐶𝑜𝑛𝑣𝑒𝑛𝑡𝑖𝑜𝑛𝑎𝑙 𝐵/𝐶 𝑟𝑎𝑡𝑖𝑜 =
21000000(𝐹/𝑃, 𝑖, 𝑛) + 1600000(𝐹/𝐴, 𝑖, 𝑛) − 4000000
5000000𝑥113.2832 − 1100000𝑥113.2832
𝐶𝑜𝑛𝑣𝑒𝑛𝑡𝑖𝑜𝑛𝑎𝑙 𝐵/𝐶 𝑟𝑎𝑡𝑖𝑜 =
21000000𝑥10.0627 + 1600000𝑥113.2832 − 4000000
Conventional B/C ratio = 1.137
As calculated above, the conventional benefit-cost ratio is found to be the same by using any of
the equivalent worth methods i.e. PW method, AW method or FW method. As the benefit-cost
ratio of the public project is 1.137 (i.e. greater than 1.0), the project is acceptable.
Now the modified benefit-cost ratio (B/C ratio) of the project is calculated.
Modified B/C ratio using Present worth:
The modified benefit-cost ratio of the public project is calculated as follows;
𝑃𝑊 𝑜𝑓 𝐵𝑒𝑛𝑒𝑓𝑖𝑡𝑠 − 𝑃𝑊 𝑜𝑓 𝐷𝑖𝑠𝑏𝑒𝑛𝑒𝑓𝑖𝑡𝑠 − 𝑃𝑊 𝑜𝑓 𝑜𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 𝑐𝑜𝑠𝑡
𝑀𝑜𝑑𝑖𝑓𝑖𝑒𝑑 𝐵/𝐶 𝑟𝑎𝑡𝑖𝑜 =
𝐼𝑛𝑖𝑡𝑖𝑎𝑙 𝑐𝑜𝑠𝑡 − 𝑃𝑊 𝑜𝑓 𝑠𝑎𝑙𝑣𝑎𝑔𝑒 𝑣𝑎𝑙𝑢𝑒
G5WSEEF- E 16
Engineering Economics & Management
G5WSEEF- E 17