Professional Documents
Culture Documents
Abstract of Costs: Pipeline Works Dotekaraha Deurali Lift Water Supply System Scheme No
Abstract of Costs: Pipeline Works Dotekaraha Deurali Lift Water Supply System Scheme No
Pipeline Works
1,006.83 53825.13
507.44 27127.74
465.15 2 73 529.00
3.83 210.65
5.64 248.16
5.64 186.12
3 55 126.80
46 166.48
Rs. 4 01 293.28
1,006.83 36 37 274.06
507.44 18 33 177.74
70.63 33 054.84
3.83 4 109.59
4.63 11 820.39
5.64 13 017.12
77.22 1 72 741.14
113.41 84 944.09
Rs. 57 90 138.97
7 52 718.07
Rs. 65 42 857.04
ngs
Rate Amount
7.42 110942.2818
14 422.50
Rs 1 25 364.78
कामको विवरण.......
ठाउँको नाम.............
क्र.स कामदारको किसिम नाम,थर वतन बाबुको नाम दिन
१ २ ३ ४
स्थान.......
मिति......
स्वीकृ त भएको रकम रू......
भुक्तानी नभएको रकम....... अक्षेरुपी रकम रू................
भुक्तानी भएको रकम........
मिति......
भुक्तानी दिएको दस्तखत........
साक्षी(प्राबिधिक कर्मचारी)........
डोर हाजिर फारम
भाग १
फारम न.
मिति...........देखि मिति.......... सम्म
दिन जम्मा काम गरेको दिन दर जम्मा पाउने रकम १ % सामाजिक सुरक्षा कर रकम बुझिलिनेको सहिछाप
३० ३१ ३२
8 Steel reinforcement
for VC slab cover 8 mmf bars @ 15 cm c/c both ways
Longer span 11 1.70 @ 0.395 kg/m 7.39
Shorter span 12 1.50 @ 0.395 kg/m 7.11
tion for manhole opening 8 0.60 @ 0.395 kg/m -1.90
Total 12.60 kg 124.99
9 Shuttering works for RCC
- Cover slab bottom 1.00 0.80 0.80
Side 6.40 - 0.10 0.64
tion for manhole opening π 0.30 0.30 -0.283
Total 1.16 m² 856.95
10 HDPE formwork for ferrocement
= 2 x p x r x h,2.03
- Wall portion (Q 2π r = d/2+.025) - 1.80 22.90
- Roof portio 2π 3.28 0.70 14.42
Q = 2 x p x R x h, R = ((d+.05)² +4h²)/8h,h=dome height
- Deduction for manhole
π opening 0.30
Q=pxr², r=0.30
0.30 -0.28
Total form work 37.04 m² 330.10
RT size: 20.00
S.N. Description No. Radius Length Breadth Height Quantity Unit Rate
18 600 mmf circular metal manhole cover for ferrocement 2 set 3000.00
Total Amount
8 Steel reinforcement
for VC slab cover 8 mmf bars @ 15 cm c/c both ways
Longer span 11 1.70 @ 0.395 kg/m 7.39
Shorter span 12 1.50 @ 0.395 kg/m 7.11
tion for manhole opening 8 0.60 @ 0.395 kg/m -1.90
Total 12.60 kg 124.99
9 Shuttering works for RCC
- Cover slab bottom 1.00 0.80 0.80
Side 6.40 - 0.10 0.64
tion for manhole opening π 0.30 0.30 -0.283
Total 1.16 m² 856.95
10 HDPE formwork for ferrocement
= 2 x p x r x h,1.78
- Wall portion (Q 2π r = d/2+.025) - 1.70 18.96
- Roof portio 2π 2.93 0.60 11.03
Q = 2 x p x R x h, R = ((d+.05)² +4h²)/8h,h=dome height
- Deduction for manhole
π opening 0.30
Q=pxr², r=0.30
0.30 -0.28
Total form work 29.71 m² 330.10
RT size: 14.00
S.N. Description No. Radius Length Breadth Height Quantity Unit Rate
18 600 mmf circular metal manhole cover for ferrocement 2 set 3000.00
8 Steel reinforcement
for VC slab cover 8 mmf bars @ 15 cm c/c both ways
Longer span 11 1.70 @ 0.395 kg/m 7.39
Shorter span 12 1.50 @ 0.395 kg/m 7.11
tion for manhole opening 8 0.60 @ 0.395 kg/m -1.90
Total 12.60 kg 124.99
9 Shuttering works for RCC
- Cover slab bottom 1.00 0.80 0.80
Side 6.40 - 0.10 0.64
tion for manhole opening π 0.30 0.30 -0.283
Total 1.16 m² 856.95
10 HDPE formwork for ferrocement
= 2 x p x r x h,1.28
- Wall portion (Q 2π r = d/2+.025) - 1.85 14.82
- Roof portio 2π 2.23 0.40 5.61
Q = 2 x p x R x h, R = ((d+.05)² +4h²)/8h,h=dome height
- Deduction for manhole
π opening 0.30
Q=pxr², r=0.30
0.30 -0.28
Total form work 20.15 m² 330.10
RT size: 8.00
S.N. Description No. Radius Length Breadth Height Quantity Unit Rate
11 Bar binding work including chicken wire mesh,
MS bar, GI wire, etc. as per HDPE form work 20.15 m² 1283.10
18 600 mmf circular metal manhole cover for ferrocement 2 set 3000.00
8 Steel reinforcement
for VC slab cover 8 mmf bars @ 15 cm c/c both ways
Longer span 11 1.70 @ 0.395 kg/m 7.39
Shorter span 12 1.50 @ 0.395 kg/m 7.11
tion for manhole opening 8 0.60 @ 0.395 kg/m -1.90
Total 12.60 kg 124.99
9 Shuttering works for RCC
- Cover slab bottom 1.00 0.80 0.80
Side 6.40 - 0.10 0.64
tion for manhole opening π 0.30 0.30 -0.283
Total 1.16 m² 856.95
10 HDPE formwork for ferrocement
= 2 x p x r x h,1.28
- Wall portion (Q 2π r = d/2+.025) - 1.30 10.41
- Roof portio 2π 2.23 0.40 5.61
Q = 2 x p x R x h, R = ((d+.05)² +4h²)/8h,h=dome height
- Deduction for manhole
π opening 0.30
Q=pxr², r=0.30
0.30 -0.28
Total form work 15.74 m² 330.10
RT size: 5.00
S.N. Description No. Radius Length Breadth Height Quantity Unit Rate
18 600 mmf circular metal manhole cover for ferrocement 2 set 3000.00
5 222.40
31 648.38
4 802.31
14 138.41
23 567.96
7 080.58
37 691.34
1 574.87
991.71
12 227.35
m³
Amount
47 527.74
68 710.21
5 127.96
1 961.82
8 571.27
1 430.36
2 576.69
6 000.00
700.00
5 000.00
53 431.92
18 184.46
3 58 167.74
3 58 167.74
3 51 216.51
Amount
5 222.40
25 214.49
3 948.29
11 432.55
23 567.96
7 080.58
29 435.53
1 574.87
991.71
9 805.86
m³
Amount
38 115.41
55 102.93
3 926.09
1 961.82
6 897.19
1 166.21
2 050.77
6 000.00
700.00
5 000.00
53 431.92
18 184.46
3 10 811.07
40 405.44
3 51 216.51
2 77 894.74
Amount
3 808.00
18 504.18
3 455.27
6 953.90
23 567.96
7 080.58
15 981.62
1 574.87
991.71
6 650.67
m³
Amount
25 851.16
37 372.67
2 003.11
1 961.82
4 735.24
939.45
1 175.94
6 000.00
700.00
5 000.00
53 431.92
18 184.46
2 45 924.55
31 970.19
2 77 894.74
2 51 570.45
Amount
3 808.00
13 418.30
1 934.95
6 953.90
23 567.96
7 080.58
15 981.62
1 574.87
991.71
5 196.22
m³
Amount
20 197.72
29 199.56
2 003.11
1 961.82
3 682.97
583.11
1 175.94
6 000.00
700.00
5 000.00
53 431.92
18 184.46
2 22 628.72
28 941.73
2 51 570.45
Rate Anlysis 2074/075
2 Gabion Box S
Mesh Wire: 10# Selvedge Wire: 7# Binding Wire: 12#
Fabrication Uskilled
of gabion 0.28 MD 665.00 186.20 Mesh Wire
Labour
a box Per Box
including Skilled Selvedge
0.57 MD 935.00 532.95
rolling, Labour Wire
Packing and Uskilled
filling of 2.25 MD 665.00 1,496.25
Labour
b gabion Per Box
crates with Skilled Rubble
0.90 MD 935.00 841.50
rubble stone Labour Stone
Assembling Uskilled
of gabion 0.13 MD 665.00 86.45 Binding Wire
c Per Box Labour
box and
placing in Total Rate o
position Total
Dolidar norms no. 17-1.4,17-5 & 17-6 Page 48, 49 & 50
Binding Wire: 12#
997.50
1,496.25