Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 28

Abstract of costs

Pipeline Works

Dotekaraha Deurali lift Water Supply System Scheme no : 1

Sn Description Length Breadth Height Quantity Unit


A Transmission line
1 E/W in excavation in hard soil 132 0.45 0.90 53.46 m3
2 E/W in backfilling with hard soil 132 0.45 0.90 53.46 m3
3 Laying & Joining of Pipes
80mm(Heavy) GI Pipe with welded joints 523 523.00 m
20 mm HDPE 55 55.00 m
40 mm HDPE 44 44.00 m
50 mm HDPE 33 33.00 m
Sub-total 655 655
Value Added Tax @ 13.00 %
Total cost of transmission pipe line works
B Distribution line

1 E/W in excavation in hard soil 8920 0.45 0.90 3612.60 m3


2 E/W in backfilling with hard soil 8920 0.45 0.90 3612.60 m3
3 Laying & Jointing of Pipes
20 mmØGI with Socket Joints 468 468.00 m
20,25 mmØ HDPE 1073 1073.00 m
32 mmØ HDPE 2553 2553.00 m
40, 50 mmØ HDPE 2308 2308.00 m
63,75,90mmØ HDPE 2237 2237.00 m
110 mmØ HDPE 749 749.00 m
Sub-total 9388 9388
Value Added Tax @ 13.00 %
Total cost of distribution pipeline works

Transportation Cost of Pipes and fittings


S.No. Descriptionof items Quantity Unit
1 Transportation Cost of Pipes and fittings from store to site
In Scheme no # 1 14951.79 kg
Value Added Tax @ 13.00 %
Total transportation cost
Rate Amount

1,006.83 53825.13
507.44 27127.74

465.15 2 73 529.00
3.83 210.65
5.64 248.16
5.64 186.12
3 55 126.80
46 166.48
Rs. 4 01 293.28

1,006.83 36 37 274.06
507.44 18 33 177.74

70.63 33 054.84
3.83 4 109.59
4.63 11 820.39
5.64 13 017.12
77.22 1 72 741.14
113.41 84 944.09
Rs. 57 90 138.97
7 52 718.07
Rs. 65 42 857.04

ngs
Rate Amount

7.42 110942.2818
14 422.50
Rs 1 25 364.78
कामको विवरण.......
ठाउँको नाम.............
क्र.स कामदारको किसिम नाम,थर वतन बाबुको नाम दिन
१ २ ३ ४

स्थान.......
मिति......
स्वीकृ त भएको रकम रू......
भुक्तानी नभएको रकम....... अक्षेरुपी रकम रू................
भुक्तानी भएको रकम........
मिति......
भुक्तानी दिएको दस्तखत........
साक्षी(प्राबिधिक कर्मचारी)........
डोर हाजिर फारम
भाग १

फारम न.
मिति...........देखि मिति.......... सम्म
दिन जम्मा काम गरेको दिन दर जम्मा पाउने रकम १ % सामाजिक सुरक्षा कर रकम बुझिलिनेको सहिछाप
३० ३१ ३२

स्वीकृ त गर्ने दस्तखत............


दर्जा............
रकम रू................ मिति............
फारम न.
देखि मिति.......... सम्म
भुक्तानी दिनेको सहि र कै फियत
Project Evaluation report

S.N Project name Ward No MB no Amount


1 1 1
2 Okhreni Dotekaraha Road 4 2 200000
3 Golangdi lamdada Nisti Road 4 3 500000
4 Rumi adheri Doholi Mo.Ba 4 4 100000
5 Rukna Tari Kholakhet Road. 5 6 150000
Ferrocement Storage Tank
20 m³ Capacity
Diameter, d = 4.0 m Tank wall height, h = 1.8 m
Dome height, = 0.7 m
Length/Radi
S.N. Description No. Radius Breadth Height Qty. Unit Rate
us
1 Site Clearance(L= d+2*2.0m,B=d+1m) 8.00 6.00 48.00 m² 108.80
2 Earthwork in excavation for foundation in
Valve Chamber 1.70 1.50 1.30 3.32
Storage tank π 2.80 2.80 - 1.70 41.87
(Q = p x R² x h, R = d/2+0.05+0.75
Total 45.19 m³ 700.40
3 Earthwork in back filling with
in storage tank : total trench (p*R2*h') π 2.80 2.80 - 1.20 29.56 m³
Deduct tank portion (p*r *h'): r=d/2+.05
2
π 2.05 2.05 - 1.20 -15.84 m³
Net backfilling work 13.71 m³ 350.20
4 Stone soling work
Valve Chamber 1.70 1.50 0.15 0.38
Storage tank π 2.30 2.30 - 0.20 3.32
(Q = p x r² x h, r = d/2+0.05+0.25
erlapping with VC portion 1.70 0.40 0.20 -0.14
Total 3.57 m³ 3960.00
5 Stone masonry in 1:6 c-s mortar
Valve Chamber 5.00 0.35 1.15 2.01 m³ 11710.79
6 Plain cement concrete (1:2:4)
ver slab of valve chamber 1.70 1.50 0.10 0.255
tion for manhole opening π 0.30 0.30 - 0.05 -0.014
(Q = p x r² x h, r = 0.30)
Manhole Cover of tank π 0.30 0.30 - 0.05 0.014
Pipe embeddment block 2 1.00 0.35 0.20 0.140
Total 0.395 m³ 17925.53
7 Plain Cement Concrete (1:1.5:3)
for tank base(Q = pπ x r² x h, r = d/2+0.05+0.10
2.15 2.15 - 0.125 1.815 m³ 20763.70

8 Steel reinforcement
for VC slab cover 8 mmf bars @ 15 cm c/c both ways
Longer span 11 1.70 @ 0.395 kg/m 7.39
Shorter span 12 1.50 @ 0.395 kg/m 7.11
tion for manhole opening 8 0.60 @ 0.395 kg/m -1.90
Total 12.60 kg 124.99
9 Shuttering works for RCC
- Cover slab bottom 1.00 0.80 0.80
Side 6.40 - 0.10 0.64
tion for manhole opening π 0.30 0.30 -0.283
Total 1.16 m² 856.95
10 HDPE formwork for ferrocement
= 2 x p x r x h,2.03
- Wall portion (Q 2π r = d/2+.025) - 1.80 22.90
- Roof portio 2π 3.28 0.70 14.42
Q = 2 x p x R x h, R = ((d+.05)² +4h²)/8h,h=dome height
- Deduction for manhole
π opening 0.30
Q=pxr², r=0.30
0.30 -0.28
Total form work 37.04 m² 330.10

RT size: 20.00
S.N. Description No. Radius Length Breadth Height Quantity Unit Rate

11 Bar binding work including chicken wire mesh,


MS bar, GI wire, etc. as per HDPE form work 37.04 m² 1283.10

12 12.5 mm thick 1:2 cement-sand plaster


4 layers for ferrocement
= 4x2 p x r x h,2.03
- Wall portion (Q4×2π r = d/2+.025) 1.80 91.61
- Roof portio 4×2π 3.28 0.700 57.69
Q = 2 x p x R x h, R = ((d+.05)² +4h²)/8h,h=dome height
- Deduction 4×2π 0.30 0.30 -1.13
(Q = 4 x p x r², r = 0.60/2 = 0.30)
Total plaster 148.17 m² 463.74
13 12.5 mm thick 1:3 cement-sand plaster
sand mortar for
- Floor portio π 2.00 2.00 12.57 m² 408.07
(Q = p x r², r = d/2)

14 12.5 mm thick 1:4 cement-sand plaster


- Floor portion of valve chamber 1.00 0.80 0.80
- inner wall of valve chamber 3.60 1.15 4.14
Total plaster 4.94 m² 397.13

15 3 mm thick 1:1 cement sand punning


= p x r², r = d/2)
- Floor portion of πstorage tank(Q 2.00 2.00 12.57
- Wall portion of 2π = 2 x p x r x h)
storage tank (Q 2.00 1.80 22.62
Total punning 35.19 m² 243.60
16 Bitumen paint on the buried surface of storage tank
(Q = 2 x p x r x h, 2π
r = d/2+0.05) 2.05 1.40 18.03 m² 79.32

17 Snowcem paint on exposed surface of storage tank


- Wall porti 2π 2.05 0.40 5.15
(Q = 2 x p x r x h, r = d/2+0.05)
- Roof portio 2π 3.35 0.70 14.74
(Q = 2xpxRxh, R = (D²+4h²)/8h, D = d+0.10, h= dome height)
Total 19.89 m² 129.52

18 600 mmf circular metal manhole cover for ferrocement 2 set 3000.00

19 Installation of Pipes & fittings 1.00 job 700.00


20 Threading 1.00 Ls 5000.00
21 Barbed Wire 1 24.00 m 2226.33
22 Entrance Gat 1 1.00 no 18184.46

Total Amount

Total cost of reservoir tank Rs.

Ferrocement Storage Tank


14 m³ Capacity
Diameter, d = 3.5 m Tank wall height, h = 1.7 m
Dome height, = 0.6 m For Scheme # no: 1
Length/Radi
S.N. Description No. Radius Breadth Height Qty. Unit Rate
us
1 Site Clearance(L= d+2*2.0m,B=d+1m) 8.00 6.00 48.00 m² 108.80
2 Earthwork in excavation for foundation in
Valve Chamber 1.70 1.50 1.30 3.32
Storage tank π 2.55 2.55 - 1.60 32.69
(Q = p x R² x h, R = d/2+0.05+0.75
Total 36.00 m³ 700.40
3 Earthwork in back filling with
in storage tank : total trench (p*R2*h') π 2.55 2.55 - 1.10 22.47 m³
Deduct tank portion (p*r2*h'): r=d/2+.05 π 1.80 1.80 - 1.10 -11.20 m³
Net backfilling work 11.27 m³ 350.20
4 Stone soling work
Valve Chamber 1.70 1.50 0.15 0.38
Storage tank π 2.05 2.05 - 0.20 2.64
(Q = p x r² x h, r = d/2+0.05+0.25
erlapping with VC portion 1.70 0.40 0.20 -0.14
Total 2.89 m³ 3960.00
5 Stone masonry in 1:6 c-s mortar
Valve Chamber 5.00 0.35 1.15 2.01 m³ 11710.79
6 Plain cement concrete (1:2:4)
ver slab of valve chamber 1.70 1.50 0.10 0.255
tion for manhole opening π 0.30 0.30 - 0.05 -0.014
(Q = p x r² x h, r = 0.30)
Manhole Cover of tank π 0.30 0.30 - 0.05 0.014
Pipe embeddment block 2 1.00 0.35 0.20 0.140
Total 0.395 m³ 17925.53
7 Plain Cement Concrete (1:1.5:3)
for tank base(Q = pπ x r² x h, r = d/2+0.05+0.10
1.90 1.90 - 0.125 1.418 m³ 20763.70

8 Steel reinforcement
for VC slab cover 8 mmf bars @ 15 cm c/c both ways
Longer span 11 1.70 @ 0.395 kg/m 7.39
Shorter span 12 1.50 @ 0.395 kg/m 7.11
tion for manhole opening 8 0.60 @ 0.395 kg/m -1.90
Total 12.60 kg 124.99
9 Shuttering works for RCC
- Cover slab bottom 1.00 0.80 0.80
Side 6.40 - 0.10 0.64
tion for manhole opening π 0.30 0.30 -0.283
Total 1.16 m² 856.95
10 HDPE formwork for ferrocement
= 2 x p x r x h,1.78
- Wall portion (Q 2π r = d/2+.025) - 1.70 18.96
- Roof portio 2π 2.93 0.60 11.03
Q = 2 x p x R x h, R = ((d+.05)² +4h²)/8h,h=dome height
- Deduction for manhole
π opening 0.30
Q=pxr², r=0.30
0.30 -0.28
Total form work 29.71 m² 330.10

RT size: 14.00
S.N. Description No. Radius Length Breadth Height Quantity Unit Rate

11 Bar binding work including chicken wire mesh,


MS bar, GI wire, etc. as per HDPE form work 29.71 m² 1283.10

12 12.5 mm thick 1:2 cement-sand plaster


4 layers for ferrocement
= 4x2 p x r x h,1.78
- Wall portion (Q4×2π r = d/2+.025) 1.70 75.84
- Roof portio 4×2π 2.93 0.600 44.12
Q = 2 x p x R x h, R = ((d+.05)² +4h²)/8h,h=dome height
- Deduction 4×2π 0.30 0.30 -1.13
(Q = 4 x p x r², r = 0.60/2 = 0.30)
Total plaster 118.82 m² 463.74
13 12.5 mm thick 1:3 cement-sand plaster
sand mortar for
- Floor portio π 1.75 1.75 9.62 m² 408.07
(Q = p x r², r = d/2)
14 12.5 mm thick 1:4 cement-sand plaster
- Floor portion of valve chamber 1.00 0.80 0.80
- inner wall of valve chamber 3.60 1.15 4.14
Total plaster 4.94 m² 397.13

15 3 mm thick 1:1 cement sand punning


= p x r², r = d/2)
- Floor portion of πstorage tank(Q 1.75 1.75 9.62
- Wall portion of 2π = 2 x p x r x h)
storage tank (Q 1.75 1.70 18.69
Total punning 28.31 m² 243.60
16 Bitumen paint on the buried surface of storage tank
(Q = 2 x p x r x h, 2π
r = d/2+0.05) 1.80 1.30 14.70 m² 79.32

17 Snowcem paint on exposed surface of storage tank


- Wall porti 2π 1.80 0.40 4.52
(Q = 2 x p x r x h, r = d/2+0.05)
- Roof portio 2π 3.00 0.60 11.31
(Q = 2xpxRxh, R = (D²+4h²)/8h, D = d+0.10, h= dome height)
Total 15.83 m² 129.52

18 600 mmf circular metal manhole cover for ferrocement 2 set 3000.00

19 Installation of Pipes & fittings 1.00 job 700.00


20 Threading 1.00 Ls 5000.00
21 Barbed Wire 1 24.00 m 2226.33
22 Entrance Gat 1 1.00 no 18184.46

tal Amount without VAT


Add Value Added Tax @ 13.00%
Total cost of reservoir tank Rs.

Ferrocement Storage Tank


8 m³ Capacity
Diameter, d = 2.5 m Tank wall height, h = 1.85 m
Dome height, = 0.4 m For Scheme # no: 1
Length/Radi
S.N. Description No. Radius Breadth Height Qty. Unit Rate
us
1 Site Clearance(L= d+2*2.0m,B=d+1m) 7.00 5.00 35.00 m² 108.80
2 Earthwork in excavation for foundation in
Valve Chamber 1.70 1.50 1.30 3.32
Storage tank π 2.05 2.05 - 1.75 23.10
(Q = p x R² x h, R = d/2+0.05+0.75
Total 26.42 m³ 700.40
3 Earthwork in back filling with
in storage tank : total trench (p*R2*h') π 2.05 2.05 - 1.25 16.50 m³
Deduct tank portion (p*r *h'): r=d/2+.05
2
π 1.30 1.30 - 1.25 -6.64 m³
Net backfilling work 9.87 m³ 350.20
4 Stone soling work
Valve Chamber 1.70 1.50 0.15 0.38
Storage tank π 1.55 1.55 - 0.20 1.51
(Q = p x r² x h, r = d/2+0.05+0.25
erlapping with VC portion 1.70 0.40 0.20 -0.14
Total 1.76 m³ 3960.00
5 Stone masonry in 1:6 c-s mortar
Valve Chamber 5.00 0.35 1.15 2.01 m³ 11710.79
6 Plain cement concrete (1:2:4)
ver slab of valve chamber 1.70 1.50 0.10 0.255
tion for manhole opening π 0.30 0.30 - 0.05 -0.014
(Q = p x r² x h, r = 0.30)
Manhole Cover of tank π 0.30 0.30 - 0.05 0.014
Pipe embeddment block 2 1.00 0.35 0.20 0.140
Total 0.395 m³ 17925.53
7 Plain Cement Concrete (1:1.5:3)
for tank base(Q = pπ x r² x h, r = d/2+0.05+0.10
1.40 1.40 - 0.125 0.770 m³ 20763.70

8 Steel reinforcement
for VC slab cover 8 mmf bars @ 15 cm c/c both ways
Longer span 11 1.70 @ 0.395 kg/m 7.39
Shorter span 12 1.50 @ 0.395 kg/m 7.11
tion for manhole opening 8 0.60 @ 0.395 kg/m -1.90
Total 12.60 kg 124.99
9 Shuttering works for RCC
- Cover slab bottom 1.00 0.80 0.80
Side 6.40 - 0.10 0.64
tion for manhole opening π 0.30 0.30 -0.283
Total 1.16 m² 856.95
10 HDPE formwork for ferrocement
= 2 x p x r x h,1.28
- Wall portion (Q 2π r = d/2+.025) - 1.85 14.82
- Roof portio 2π 2.23 0.40 5.61
Q = 2 x p x R x h, R = ((d+.05)² +4h²)/8h,h=dome height
- Deduction for manhole
π opening 0.30
Q=pxr², r=0.30
0.30 -0.28
Total form work 20.15 m² 330.10

RT size: 8.00
S.N. Description No. Radius Length Breadth Height Quantity Unit Rate
11 Bar binding work including chicken wire mesh,
MS bar, GI wire, etc. as per HDPE form work 20.15 m² 1283.10

12 12.5 mm thick 1:2 cement-sand plaster


4 layers for ferrocement
= 4x2 p x r x h,1.28
- Wall portion (Q4×2π r = d/2+.025) 1.85 59.28
- Roof portio 4×2π 2.23 0.400 22.44
Q = 2 x p x R x h, R = ((d+.05)² +4h²)/8h,h=dome height
- Deduction 4×2π 0.30 0.30 -1.13
(Q = 4 x p x r², r = 0.60/2 = 0.30)
Total plaster 80.59 m² 463.74
13 12.5 mm thick 1:3 cement-sand plaster
sand mortar for
- Floor portio π 1.25 1.25 4.91 m² 408.07
(Q = p x r², r = d/2)

14 12.5 mm thick 1:4 cement-sand plaster


- Floor portion of valve chamber 1.00 0.80 0.80
- inner wall of valve chamber 3.60 1.15 4.14
Total plaster 4.94 m² 397.13

15 3 mm thick 1:1 cement sand punning


= p x r², r = d/2)
- Floor portion of πstorage tank(Q 1.25 1.25 4.91
- Wall portion of 2π = 2 x p x r x h)
storage tank (Q 1.25 1.85 14.53
Total punning 19.44 m² 243.60
16 Bitumen paint on the buried surface of storage tank
(Q = 2 x p x r x h, 2π
r = d/2+0.05) 1.30 1.45 11.84 m² 79.32

17 Snowcem paint on exposed surface of storage tank


- Wall porti 2π 1.30 0.40 3.27
(Q = 2 x p x r x h, r = d/2+0.05)
- Roof portio 2π 2.31 0.40 5.81
(Q = 2xpxRxh, R = (D²+4h²)/8h, D = d+0.10, h= dome height)
Total 9.08 m² 129.52

18 600 mmf circular metal manhole cover for ferrocement 2 set 3000.00

19 Installation of Pipes & fittings 1.00 job 700.00


20 Threading 1.00 Ls 5000.00
21 Barbed Wire 1 24.00 m 2226.33
22 Entrance Gat 1 1.00 no 18184.46

tal Amount without VAT


Add Value Added Tax @ 13.00%
Total cost of reservoir tank Rs.
Ferrocement Storage Tank
5 m³ Capacity
Diameter, d = 2.5 m Tank wall height, h = 1.3 m
Dome height, = 0.4 m For Scheme # no: 1
Length/Radi
S.N. Description No. Radius Breadth Height Qty. Unit Rate
us
1 Site Clearance(L= d+2*2.0m,B=d+1m) 7.00 5.00 35.00 m² 108.80
2 Earthwork in excavation for foundation in
Valve Chamber 1.70 1.50 1.30 3.32
Storage tank π 2.05 2.05 - 1.20 15.84
(Q = p x R² x h, R = d/2+0.05+0.75
Total 19.16 m³ 700.40
3 Earthwork in back filling with
in storage tank : total trench (p*R2*h') π 2.05 2.05 - 0.70 9.24 m³
Deduct tank portion (p*r *h'): r=d/2+.05
2
π 1.30 1.30 - 0.70 -3.72 m³
Net backfilling work 5.53 m³ 350.20
4 Stone soling work
Valve Chamber 1.70 1.50 0.15 0.38
Storage tank π 1.55 1.55 - 0.20 1.51
(Q = p x r² x h, r = d/2+0.05+0.25
erlapping with VC portion 1.70 0.40 0.20 -0.14
Total 1.76 m³ 3960.00
5 Stone masonry in 1:6 c-s mortar
Valve Chamber 5.00 0.35 1.15 2.01 m³ 11710.79
6 Plain cement concrete (1:2:4)
ver slab of valve chamber 1.70 1.50 0.10 0.255
tion for manhole opening π 0.30 0.30 - 0.05 -0.014
(Q = p x r² x h, r = 0.30)
Manhole Cover of tank π 0.30 0.30 - 0.05 0.014
Pipe embeddment block 2 1.00 0.35 0.20 0.140
Total 0.395 m³ 17925.53
7 Plain Cement Concrete (1:1.5:3)
for tank base(Q = pπ x r² x h, r = d/2+0.05+0.10
1.40 1.40 - 0.125 0.770 m³ 20763.70

8 Steel reinforcement
for VC slab cover 8 mmf bars @ 15 cm c/c both ways
Longer span 11 1.70 @ 0.395 kg/m 7.39
Shorter span 12 1.50 @ 0.395 kg/m 7.11
tion for manhole opening 8 0.60 @ 0.395 kg/m -1.90
Total 12.60 kg 124.99
9 Shuttering works for RCC
- Cover slab bottom 1.00 0.80 0.80
Side 6.40 - 0.10 0.64
tion for manhole opening π 0.30 0.30 -0.283
Total 1.16 m² 856.95
10 HDPE formwork for ferrocement
= 2 x p x r x h,1.28
- Wall portion (Q 2π r = d/2+.025) - 1.30 10.41
- Roof portio 2π 2.23 0.40 5.61
Q = 2 x p x R x h, R = ((d+.05)² +4h²)/8h,h=dome height
- Deduction for manhole
π opening 0.30
Q=pxr², r=0.30
0.30 -0.28
Total form work 15.74 m² 330.10

RT size: 5.00
S.N. Description No. Radius Length Breadth Height Quantity Unit Rate

11 Bar binding work including chicken wire mesh,


MS bar, GI wire, etc. as per HDPE form work 15.74 m² 1283.10

12 12.5 mm thick 1:2 cement-sand plaster


4 layers for ferrocement
= 4x2 p x r x h,1.28
- Wall portion (Q4×2π r = d/2+.025) 1.30 41.66
- Roof portio 4×2π 2.23 0.400 22.44
Q = 2 x p x R x h, R = ((d+.05)² +4h²)/8h,h=dome height
- Deduction 4×2π 0.30 0.30 -1.13
(Q = 4 x p x r², r = 0.60/2 = 0.30)
Total plaster 62.97 m² 463.74
13 12.5 mm thick 1:3 cement-sand plaster
sand mortar for
- Floor portio π 1.25 1.25 4.91 m² 408.07
(Q = p x r², r = d/2)

14 12.5 mm thick 1:4 cement-sand plaster


- Floor portion of valve chamber 1.00 0.80 0.80
- inner wall of valve chamber 3.60 1.15 4.14
Total plaster 4.94 m² 397.13

15 3 mm thick 1:1 cement sand punning


= p x r², r = d/2)
- Floor portion of πstorage tank(Q 1.25 1.25 4.91
- Wall portion of 2π = 2 x p x r x h)
storage tank (Q 1.25 1.30 10.21
Total punning 15.12 m² 243.60
16 Bitumen paint on the buried surface of storage tank
(Q = 2 x p x r x h, 2π
r = d/2+0.05) 1.30 0.90 7.35 m² 79.32

17 Snowcem paint on exposed surface of storage tank


- Wall porti 2π 1.30 0.40 3.27
(Q = 2 x p x r x h, r = d/2+0.05)
- Roof portio 2π 2.31 0.40 5.81
(Q = 2xpxRxh, R = (D²+4h²)/8h, D = d+0.10, h= dome height)
Total 9.08 m² 129.52

18 600 mmf circular metal manhole cover for ferrocement 2 set 3000.00

19 Installation of Pipes & fittings 1.00 job 700.00


20 Threading 1.00 Ls 5000.00
21 Barbed Wire 1 24.00 m 2226.33
22 Entrance Gat 1 1.00 no 18184.46

tal Amount without VAT


Add Value Added Tax @ 13.00%
Total cost of reservoir tank Rs.
3 58 167.74
Amount

5 222.40

31 648.38

4 802.31

14 138.41

23 567.96

7 080.58

37 691.34

1 574.87
991.71

12 227.35


Amount

47 527.74

68 710.21

5 127.96

1 961.82

8 571.27

1 430.36
2 576.69

6 000.00

700.00
5 000.00
53 431.92
18 184.46

3 58 167.74

3 58 167.74

3 51 216.51
Amount

5 222.40

25 214.49

3 948.29

11 432.55

23 567.96
7 080.58

29 435.53

1 574.87

991.71

9 805.86


Amount

38 115.41

55 102.93

3 926.09
1 961.82

6 897.19

1 166.21

2 050.77

6 000.00

700.00
5 000.00
53 431.92
18 184.46

3 10 811.07
40 405.44
3 51 216.51

2 77 894.74
Amount

3 808.00

18 504.18
3 455.27

6 953.90

23 567.96

7 080.58

15 981.62

1 574.87

991.71

6 650.67


Amount
25 851.16

37 372.67

2 003.11

1 961.82

4 735.24

939.45

1 175.94

6 000.00

700.00
5 000.00
53 431.92
18 184.46

2 45 924.55
31 970.19
2 77 894.74
2 51 570.45
Amount

3 808.00

13 418.30

1 934.95

6 953.90

23 567.96

7 080.58

15 981.62

1 574.87
991.71

5 196.22


Amount

20 197.72

29 199.56

2 003.11

1 961.82

3 682.97

583.11
1 175.94

6 000.00

700.00
5 000.00
53 431.92
18 184.46

2 22 628.72
28 941.73
2 51 570.45
Rate Anlysis 2074/075

Gabion Work Norms No.


1 Gabion Box S
Mesh Wire: 10# Selvedge Wire: 7# Binding Wire: 12#
Fabrication Uskilled
of gabion 0.23 MD 665.00 152.95 Mesh Wire
Labour
a box Per Box
including Skilled Selvedge
0.46 MD 935.00 430.10
rolling, Labour Wire
Packing and Uskilled
filling of 1.50 MD 665.00 997.50
Labour
b gabion Per Box
crates with Skilled Rubble
0.60 MD 780.00 468.00
rubble stone Labour Stone
Assembling Uskilled
of gabion 0.09 MD 665.00 59.85 Binding Wire
c Per Box Labour
box and
placing in Total Rate o
position

2 Gabion Box S
Mesh Wire: 10# Selvedge Wire: 7# Binding Wire: 12#
Fabrication Uskilled
of gabion 0.28 MD 665.00 186.20 Mesh Wire
Labour
a box Per Box
including Skilled Selvedge
0.57 MD 935.00 532.95
rolling, Labour Wire
Packing and Uskilled
filling of 2.25 MD 665.00 1,496.25
Labour
b gabion Per Box
crates with Skilled Rubble
0.90 MD 935.00 841.50
rubble stone Labour Stone
Assembling Uskilled
of gabion 0.13 MD 665.00 86.45 Binding Wire
c Per Box Labour
box and
placing in Total Rate o
position Total
Dolidar norms no. 17-1.4,17-5 & 17-6 Page 48, 49 & 50
Binding Wire: 12#

27.50 kg 106.22 2,921.05 3,074.00

2.88 kg 106.22 305.91 736.01

997.50

2.20 cum 1,600.00 3,520.00 3,988.00

0.95 kg 125.43 119.16 179.01

Total Rate of Gabion Box Size: 2m x 1m x 1m. Per Box 8,974.52

Binding Wire: 12#

34.08 kg 106.22 3,619.98 3,806.18

4.03 kg 106.22 428.07 961.02

1,496.25

3.30 cum 1,600.00 5,280.00 6,121.50

1.30 kg 125.43 163.06 249.51

Total Rate of Gabion Box Size: 3m x 1m x 1m. Per Box 12,634.45


Total Rate of Gabion Box all complete per cum 4,349.37

You might also like