GENERAL AUTHORITY OF CIVIL AVIATION BUILDING

Detailed Program TASK filter: Critical Activities

Activity ID Activity Name Original Start Finish BL1 Start BL1 Finish Activity % Total Float 2021 2022
Duration Complete
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
139 08-Jul-21 16-Dec-21 30-Dec-20 13-Jun-21 -159 16-Dec-21, Construction
Construction
139 08-Jul-21 16-Dec-21 30-Dec-20 13-Jun-21 -159 16-Dec-21, B06
B06
Fire Alarm 16 12-Oct-21 30-Oct-21 07-Apr-21 26-Apr-21 -159 30-Oct-21, Fire Alarm
CN-B06-SB-BF-S-3-3 Fire Alarm System Third Fix 16 12-Oct-21 30-Oct-21 07-Apr-21 26-Apr-21 0% -159 30-Oct-21

Furniture 35 02-Nov-21 12-Dec-21 28-Apr-21 08-Jun-21 -159 12-Dec-21, Furniture


CN-B06-SP-L1-FUR-1 Furniture 10 02-Nov-21 13-Nov-21 28-Apr-21 10-May-21 0% -159 13-Nov-21

CN-B06-SP-L2-FUR-1 Furniture 10 08-Nov-21 18-Nov-21 04-May-21 16-May-21 0% -159 18-Nov-21

CN-B06-SP-L3-FUR-1 Furniture 10 14-Nov-21 24-Nov-21 10-May-21 22-May-21 0% -159 24-Nov-21

CN-B06-SP-L4-FUR-1 Furniture 10 20-Nov-21 30-Nov-21 16-May-21 27-May-21 0% -159 30-Nov-21

CN-B06-SP-GF-FUR-1 Furniture 10 25-Nov-21 06-Dec-21 22-May-21 02-Jun-21 0% -159 06-Dec-21

CN-B06-SP-L5-FUR-1 Furniture 5 25-Nov-21 30-Nov-21 22-May-21 27-May-21 0% -159 30-Nov-21

CN-B06-SP-L6-FUR-1 Furniture 5 25-Nov-21 30-Nov-21 22-May-21 27-May-21 0% -159 30-Nov-21

CN-B06-SUB-BF-FUR-1 Furniture 10 01-Dec-21 12-Dec-21 27-May-21 08-Jun-21 0% -159 12-Dec-21

Painting 2 31-Oct-21 01-Nov-21 26-Apr-21 28-Apr-21 -159 01-Nov-21, Painting


CN-B06-SUB-BF-FS-W-5 Final Coat Paint 2 31-Oct-21 01-Nov-21 26-Apr-21 28-Apr-21 0% -159 01-Nov-21

Raised Floor & Carpet Tiles 20 08-Jul-21 31-Jul-21 30-Dec-20 21-Jan-21 -159 31-Jul-21, Raised Floor & Carpet Tiles
CN-B06-SP-L1-FS-F-6 Carpet Tiles on Raised Floor 10 08-Jul-21 19-Jul-21 30-Dec-20 10-Jan-21 0% -159 19-Jul-21

CN-B06-SP-L2-FS-F-6 Carpet Tiles on Raised Floor 10 20-Jul-21 31-Jul-21 11-Jan-21 21-Jan-21 0% -159 31-Jul-21

Snagging 4 13-Dec-21 16-Dec-21 08-Jun-21 13-Jun-21 -159 16-Dec-21, Snagging


CN-B6-SUB-BF-SNG-1 Snagging (By Consultant) - Basement 2 13-Dec-21 14-Dec-21 08-Jun-21 10-Jun-21 0% -159 14-Dec-21
Floor
CN-B6-SUB-BF-SNG-2 Incorporate Snagging comments & 4 13-Dec-21 16-Dec-21 08-Jun-21 13-Jun-21 0% -159 16-Dec-21
De-Snagging- Basement Floor
Wooden Doors 62 01-Aug-21 11-Oct-21 23-Jan-21 04-Apr-21 -159 11-Oct-21, Wooden Doors
CN-B06-SP-L2-DW-1 Wooden Doors 10 01-Aug-21 11-Aug-21 23-Jan-21 02-Feb-21 0% -159 11-Aug-21

CN-B06-SP-L3-DW-1 Wooden Doors 10 12-Aug-21 23-Aug-21 03-Feb-21 14-Feb-21 0% -159 23-Aug-21

CN-B06-SP-L4-DW-1 Wooden Doors 10 24-Aug-21 04-Sep-21 15-Feb-21 25-Feb-21 0% -159 04-Sep-21

CN-B06-SP-L5-DW-1 Wooden Doors 6 05-Sep-21 11-Sep-21 27-Feb-21 04-Mar-21 0% -159 11-Sep-21

CN-B06-SP-L6-DW-1 Wooden Doors 6 12-Sep-21 18-Sep-21 06-Mar-21 11-Mar-21 0% -159 18-Sep-21

CN-B06-SP-GF-DW-1 Wooden Doors 10 19-Sep-21 29-Sep-21 13-Mar-21 23-Mar-21 0% -159 29-Sep-21

CN-B06-SUB-BF-DW-1 Wooden Doors 10 30-Sep-21 11-Oct-21 24-Mar-21 04-Apr-21 0% -159 11-Oct-21

7 15-May-21 22-May-21 05-Nov-20 12-Nov-20 -159 22-May-21, Design


Design
7 15-May-21 22-May-21 05-Nov-20 12-Nov-20 -159 22-May-21, B03 & B04
B03 & B04
Details 7 15-May-21 22-May-21 05-Nov-20 12-Nov-20 -159 22-May-21, Details

Project Baseline Bar Remaining Work Baseline Milestone Date Revision Checked Approved
Page 1 of 3
01-May-21 Updated Project Schedule Critical Path
Actual Work Critical Remaining Work Milestone
GENERAL AUTHORITY OF CIVIL AVIATION BUILDING
Detailed Program TASK filter: Critical Activities

Activity ID Activity Name Original Start Finish BL1 Start BL1 Finish Activity % Total Float 2021 2022
Duration Complete
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
ENG-B3&4-DD-AR-1100 12000-General Details Submission & 7 15-May-21 22-May-21 05-Nov-20 12-Nov-20 0% -159 22-May-21
Approval
Flooring 7 15-May-21 22-May-21 05-Nov-20 12-Nov-20 -159 22-May-21, Flooring
ENG-B3&4-DD-AR-1030 4000-Flooring Submission & Approval 7 15-May-21 22-May-21 05-Nov-20 12-Nov-20 0% -159 22-May-21

Stairs 7 15-May-21 22-May-21 05-Nov-20 12-Nov-20 -159 22-May-21, Stairs


ENG-B3&4-DD-AR-1080 9000-Stairs Submission & Approval 7 15-May-21 22-May-21 05-Nov-20 12-Nov-20 0% -159 22-May-21

30 08-Jun-21 07-Jul-21 30-Nov-20 29-Dec-20 -185 07-Jul-21, Material Delivery


Material Delivery
30 08-Jun-21 07-Jul-21 30-Nov-20 29-Dec-20 -185 07-Jul-21, General
General
No Sub-Trade 30 08-Jun-21 07-Jul-21 30-Nov-20 29-Dec-20 -185 07-Jul-21, No Sub-Trade
ENG-MP-AR-NLL-1140 1st Cementitious raised floor Batch to Site 30 08-Jun-21 07-Jul-21 30-Nov-20 29-Dec-20 0% -185 07-Jul-21

14 23-May-21 07-Jun-21 14-Nov-20 29-Nov-20 -159 07-Jun-21, Shop Drawings


Shop Drawings
14 23-May-21 07-Jun-21 14-Nov-20 29-Nov-20 -159 07-Jun-21, B03 & B04
B03 & B04
Ceramic & Porcelain 7 23-May-21 30-May-21 14-Nov-20 21-Nov-20 -159 30-May-21, Ceramic & Porcelain
EN-SD-B3&4-AR-FS-01 Building No. 3 & 4 Basement Floor Plan 7 23-May-21 30-May-21 14-Nov-20 21-Nov-20 0% -159 30-May-21
Floor & Wall Tiling
EN-SD-B3&4-AR-FS-02 Building No. 3 & 4 Ground Floor Plan Floor 7 23-May-21 30-May-21 14-Nov-20 21-Nov-20 0% -159 30-May-21
& Wall Tiling
EN-SD-B3&4-AR-FS-03 Building No. 3 & 4 First Floor Plan Floor & 7 23-May-21 30-May-21 14-Nov-20 21-Nov-20 0% -159 30-May-21
Wall Tiling
EN-SD-B3&4-AR-FS-04 Building No. 3 & 4 Second Floor Plan Floor 7 23-May-21 30-May-21 14-Nov-20 21-Nov-20 0% -159 30-May-21
& Wall Tiling
EN-SD-B3&4-AR-FS-05 Building No. 3 & 4 Third Floor Plan Floor & 7 23-May-21 30-May-21 14-Nov-20 21-Nov-20 0% -159 30-May-21
Wall Tiling
EN-SD-B3&4-AR-FS-06 Building No. 3 & 4 Fourth Floor Plan Floor 7 23-May-21 30-May-21 14-Nov-20 21-Nov-20 0% -159 30-May-21
& Wall Tiling
EN-SD-B3&4-AR-FS-07 Building No. 3 & 4 Fifth Floor Plan Floor & 7 23-May-21 30-May-21 14-Nov-20 21-Nov-20 0% -159 30-May-21
Wall Tiling
EN-SD-B3&4-AR-FS-08 Building No. 3 & 4 Sixth Floor Plan Floor & 7 23-May-21 30-May-21 14-Nov-20 21-Nov-20 0% -159 30-May-21
Wall Tiling
EN-SD-B3&4-AR-FS-09 Building No. 3 & 4 General Details Floor & 7 23-May-21 30-May-21 14-Nov-20 21-Nov-20 0% -159 30-May-21
Wall Tiling
False Ceiling 7 31-May-21 07-Jun-21 22-Nov-20 29-Nov-20 -159 07-Jun-21, False Ceiling
EN-SD-B3&4-AR-FS-17 Building No. 3 & 4 Basement Floor Plan 7 31-May-21 07-Jun-21 22-Nov-20 29-Nov-20 0% -159 07-Jun-21
False Ceiling Works
EN-SD-B3&4-AR-FS-18 Building No. 3 & 4 Ground Floor Plan False 7 31-May-21 07-Jun-21 22-Nov-20 29-Nov-20 0% -159 07-Jun-21
Ceiling Works
EN-SD-B3&4-AR-FS-19 Building No. 3 & 4 First Floor Plan False 7 31-May-21 07-Jun-21 22-Nov-20 29-Nov-20 0% -159 07-Jun-21
Ceiling Works
EN-SD-B3&4-AR-FS-20 Building No. 3 & 4 Second Floor Plan False 7 31-May-21 07-Jun-21 22-Nov-20 29-Nov-20 0% -159 07-Jun-21
Ceiling Works
EN-SD-B3&4-AR-FS-21 Building No. 3 & 4 Third Floor Plan False 7 31-May-21 07-Jun-21 22-Nov-20 29-Nov-20 0% -159 07-Jun-21
Ceiling Works
EN-SD-B3&4-AR-FS-22 Building No. 3 & 4 Fourth Floor Plan False 7 31-May-21 07-Jun-21 22-Nov-20 29-Nov-20 0% -159 07-Jun-21
Ceiling Works
EN-SD-B3&4-AR-FS-23 Building No. 3 & 4 Fifth Floor Plan False 7 31-May-21 07-Jun-21 22-Nov-20 29-Nov-20 0% -159 07-Jun-21
Ceiling Works
EN-SD-B3&4-AR-FS-24 Building No. 3 & 4 Sixth Floor Plan False 7 31-May-21 07-Jun-21 22-Nov-20 29-Nov-20 0% -159 07-Jun-21
Ceiling Works
EN-SD-B3&4-AR-FS-25 Building No. 3 & 4 General Details False 7 31-May-21 07-Jun-21 22-Nov-20 29-Nov-20 0% -159 07-Jun-21
Ceiling Works
Raised Floor 7 31-May-21 07-Jun-21 22-Nov-20 29-Nov-20 -159 07-Jun-21, Raised Floor

Project Baseline Bar Remaining Work Baseline Milestone Date Revision Checked Approved
Page 2 of 3
01-May-21 Updated Project Schedule Critical Path
Actual Work Critical Remaining Work Milestone
GENERAL AUTHORITY OF CIVIL AVIATION BUILDING
Detailed Program TASK filter: Critical Activities

Activity ID Activity Name Original Start Finish BL1 Start BL1 Finish Activity % Total Float 2021 2022
Duration Complete
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
EN-SD-B3&4-AR-FS-10 Building No. 3 & 4 First Floor Plan Raised 7 31-May-21 07-Jun-21 22-Nov-20 29-Nov-20 0% -159 07-Jun-21
Floor System
EN-SD-B3&4-AR-FS-11 Building No. 3 & 4 Second Floor Plan 7 31-May-21 07-Jun-21 22-Nov-20 29-Nov-20 0% -159 07-Jun-21
Raised Floor System
EN-SD-B3&4-AR-FS-12 Building No. 3 & 4 Third Floor Plan Raised 7 31-May-21 07-Jun-21 22-Nov-20 29-Nov-20 0% -159 07-Jun-21
Floor System
EN-SD-B3&4-AR-FS-13 Building No. 3 & 4 Fourth Floor Plan 7 31-May-21 07-Jun-21 22-Nov-20 29-Nov-20 0% -159 07-Jun-21
Raised Floor System
EN-SD-B3&4-AR-FS-14 Building No. 3 & 4 Fifth Floor Plan Raised 7 31-May-21 07-Jun-21 22-Nov-20 29-Nov-20 0% -159 07-Jun-21
Floor System
EN-SD-B3&4-AR-FS-15 Building No. 3 & 4 Sixth Floor Plan Raised 7 31-May-21 07-Jun-21 22-Nov-20 29-Nov-20 0% -159 07-Jun-21
Floor System
EN-SD-B3&4-AR-FS-16 Building No. 3 & 4 General Details Raised 7 31-May-21 07-Jun-21 22-Nov-20 29-Nov-20 0% -159 07-Jun-21
Floor System
12 15-Mar-20 A 13-May-21 15-Mar-20 28-Mar-20 -159 13-May-21, Zoning
Zoning
12 15-Mar-20 A 13-May-21 15-Mar-20 28-Mar-20 -159 13-May-21, B03 & B04
B03 & B04
Zoning 12 15-Mar-20 A 13-May-21 15-Mar-20 28-Mar-20 -159 13-May-21, Zoning
ENG-B3&4-ZON-1010 B03 & B04 Zoning Approval 12 15-Mar-20 A 13-May-21 15-Mar-20 28-Mar-20 0% -159 13-May-21

0 16-Dec-21 16-Dec-21 14-Jun-21 14-Jun-21 -159 16-Dec-21, No WBS-Action


No WBS-Action
0 16-Dec-21 16-Dec-21 14-Jun-21 14-Jun-21 -159 16-Dec-21, No Location
No Location
No Sub-Trade 0 16-Dec-21 16-Dec-21 14-Jun-21 14-Jun-21 -159 16-Dec-21, No Sub-Trade
CNS-1010 Project Completion 0 16-Dec-21 14-Jun-21 0% -159 Project Completion

Project Baseline Bar Remaining Work Baseline Milestone Date Revision Checked Approved
Page 3 of 3
01-May-21 Updated Project Schedule Critical Path
Actual Work Critical Remaining Work Milestone