General Authority of Civil Aviation Building: Construction Construction
General Authority of Civil Aviation Building: Construction Construction
Activity ID Activity Name Original Start Finish BL1 Start BL1 Finish Activity % Total Float 2021 2022
Duration Complete
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
139 08-Jul-21 16-Dec-21 30-Dec-20 13-Jun-21 -159 16-Dec-21, Construction
Construction
139 08-Jul-21 16-Dec-21 30-Dec-20 13-Jun-21 -159 16-Dec-21, B06
B06
Fire Alarm 16 12-Oct-21 30-Oct-21 07-Apr-21 26-Apr-21 -159 30-Oct-21, Fire Alarm
CN-B06-SB-BF-S-3-3 Fire Alarm System Third Fix 16 12-Oct-21 30-Oct-21 07-Apr-21 26-Apr-21 0% -159 30-Oct-21
Raised Floor & Carpet Tiles 20 08-Jul-21 31-Jul-21 30-Dec-20 21-Jan-21 -159 31-Jul-21, Raised Floor & Carpet Tiles
CN-B06-SP-L1-FS-F-6 Carpet Tiles on Raised Floor 10 08-Jul-21 19-Jul-21 30-Dec-20 10-Jan-21 0% -159 19-Jul-21
CN-B06-SP-L2-FS-F-6 Carpet Tiles on Raised Floor 10 20-Jul-21 31-Jul-21 11-Jan-21 21-Jan-21 0% -159 31-Jul-21
Project Baseline Bar Remaining Work Baseline Milestone Date Revision Checked Approved
Page 1 of 3
01-May-21 Updated Project Schedule Critical Path
Actual Work Critical Remaining Work Milestone
GENERAL AUTHORITY OF CIVIL AVIATION BUILDING
Detailed Program TASK filter: Critical Activities
Activity ID Activity Name Original Start Finish BL1 Start BL1 Finish Activity % Total Float 2021 2022
Duration Complete
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
ENG-B3&4-DD-AR-1100 12000-General Details Submission & 7 15-May-21 22-May-21 05-Nov-20 12-Nov-20 0% -159 22-May-21
Approval
Flooring 7 15-May-21 22-May-21 05-Nov-20 12-Nov-20 -159 22-May-21, Flooring
ENG-B3&4-DD-AR-1030 4000-Flooring Submission & Approval 7 15-May-21 22-May-21 05-Nov-20 12-Nov-20 0% -159 22-May-21
Project Baseline Bar Remaining Work Baseline Milestone Date Revision Checked Approved
Page 2 of 3
01-May-21 Updated Project Schedule Critical Path
Actual Work Critical Remaining Work Milestone
GENERAL AUTHORITY OF CIVIL AVIATION BUILDING
Detailed Program TASK filter: Critical Activities
Activity ID Activity Name Original Start Finish BL1 Start BL1 Finish Activity % Total Float 2021 2022
Duration Complete
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
EN-SD-B3&4-AR-FS-10 Building No. 3 & 4 First Floor Plan Raised 7 31-May-21 07-Jun-21 22-Nov-20 29-Nov-20 0% -159 07-Jun-21
Floor System
EN-SD-B3&4-AR-FS-11 Building No. 3 & 4 Second Floor Plan 7 31-May-21 07-Jun-21 22-Nov-20 29-Nov-20 0% -159 07-Jun-21
Raised Floor System
EN-SD-B3&4-AR-FS-12 Building No. 3 & 4 Third Floor Plan Raised 7 31-May-21 07-Jun-21 22-Nov-20 29-Nov-20 0% -159 07-Jun-21
Floor System
EN-SD-B3&4-AR-FS-13 Building No. 3 & 4 Fourth Floor Plan 7 31-May-21 07-Jun-21 22-Nov-20 29-Nov-20 0% -159 07-Jun-21
Raised Floor System
EN-SD-B3&4-AR-FS-14 Building No. 3 & 4 Fifth Floor Plan Raised 7 31-May-21 07-Jun-21 22-Nov-20 29-Nov-20 0% -159 07-Jun-21
Floor System
EN-SD-B3&4-AR-FS-15 Building No. 3 & 4 Sixth Floor Plan Raised 7 31-May-21 07-Jun-21 22-Nov-20 29-Nov-20 0% -159 07-Jun-21
Floor System
EN-SD-B3&4-AR-FS-16 Building No. 3 & 4 General Details Raised 7 31-May-21 07-Jun-21 22-Nov-20 29-Nov-20 0% -159 07-Jun-21
Floor System
12 15-Mar-20 A 13-May-21 15-Mar-20 28-Mar-20 -159 13-May-21, Zoning
Zoning
12 15-Mar-20 A 13-May-21 15-Mar-20 28-Mar-20 -159 13-May-21, B03 & B04
B03 & B04
Zoning 12 15-Mar-20 A 13-May-21 15-Mar-20 28-Mar-20 -159 13-May-21, Zoning
ENG-B3&4-ZON-1010 B03 & B04 Zoning Approval 12 15-Mar-20 A 13-May-21 15-Mar-20 28-Mar-20 0% -159 13-May-21
Project Baseline Bar Remaining Work Baseline Milestone Date Revision Checked Approved
Page 3 of 3
01-May-21 Updated Project Schedule Critical Path
Actual Work Critical Remaining Work Milestone