GENERAL AUTHORITY OF CIVIL AVIATION BUILDING

Detailed Program TASK filter: Critical Activities

Activity ID Activity Name Original Start Finish BL1 Start BL1 Finish Activity % Total Float 2020 2021 2022
Duration Complete
A S Oct N D J F M A M J Jul A S O N D J F M Apr M J Jul A S Oct N D J F M
139 24-Jun-21 02-Dec-21 30-Dec-20 13-Jun-21 -147 02-Dec-21, Con
Construction
139 24-Jun-21 02-Dec-21 30-Dec-20 13-Jun-21 -147 02-Dec-21, B06
B06
Fire Alarm 16 28-Sep-21 16-Oct-21 07-Apr-21 26-Apr-21 -147 16-Oct-21, Fire Alarm
CN-B06-SB-BF-S-3-3 Fire Alarm System Third Fix 16 28-Sep-21 16-Oct-21 07-Apr-21 26-Apr-21 0% -147 16-Oct-21

Furniture 35 19-Oct-21 28-Nov-21 28-Apr-21 08-Jun-21 -147 28-Nov-21, Furn


CN-B06-SP-L1-FUR-1 Furniture 10 19-Oct-21 30-Oct-21 28-Apr-21 10-May-21 0% -147 30-Oct-21

CN-B06-SP-L2-FUR-1 Furniture 10 25-Oct-21 04-Nov-21 04-May-21 16-May-21 0% -147 04-Nov-21

CN-B06-SP-L3-FUR-1 Furniture 10 31-Oct-21 10-Nov-21 10-May-21 22-May-21 0% -147 10-Nov-21

CN-B06-SP-L4-FUR-1 Furniture 10 06-Nov-21 16-Nov-21 16-May-21 27-May-21 0% -147 16-Nov-21

CN-B06-SP-GF-FUR-1 Furniture 10 11-Nov-21 22-Nov-21 22-May-21 02-Jun-21 0% -147 22-Nov-21

CN-B06-SP-L5-FUR-1 Furniture 5 11-Nov-21 16-Nov-21 22-May-21 27-May-21 0% -147 16-Nov-21

CN-B06-SP-L6-FUR-1 Furniture 5 11-Nov-21 16-Nov-21 22-May-21 27-May-21 0% -147 16-Nov-21

CN-B06-SUB-BF-FUR-1 Furniture 10 17-Nov-21 28-Nov-21 27-May-21 08-Jun-21 0% -147 28-Nov-21

Painting 2 17-Oct-21 18-Oct-21 26-Apr-21 28-Apr-21 -147 18-Oct-21, Painting


CN-B06-SUB-BF-FS-W-5 Final Coat Paint 2 17-Oct-21 18-Oct-21 26-Apr-21 28-Apr-21 0% -147 18-Oct-21

Raised Floor & Carpet Tiles 20 24-Jun-21 17-Jul-21 30-Dec-20 21-Jan-21 -147 17-Jul-21, Raised Floor & Carpet Til
CN-B06-SP-L1-FS-F-6 Carpet Tiles on Raised Floor 10 24-Jun-21 05-Jul-21 30-Dec-20 10-Jan-21 0% -147 05-Jul-21

CN-B06-SP-L2-FS-F-6 Carpet Tiles on Raised Floor 10 06-Jul-21 17-Jul-21 11-Jan-21 21-Jan-21 0% -147 17-Jul-21

Snagging 4 29-Nov-21 02-Dec-21 08-Jun-21 13-Jun-21 -147 02-Dec-21, Sna


CN-B6-SUB-BF-SNG-1 Snagging (By Consultant) - Basement 2 29-Nov-21 30-Nov-21 08-Jun-21 10-Jun-21 0% -147 30-Nov-21
Floor
CN-B6-SUB-BF-SNG-2 Incorporate Snagging comments & 4 29-Nov-21 02-Dec-21 08-Jun-21 13-Jun-21 0% -147 02-Dec-21
De-Snagging- Basement Floor
Wooden Doors 62 18-Jul-21 27-Sep-21 23-Jan-21 04-Apr-21 -147 27-Sep-21, Wooden Doo
CN-B06-SP-L2-DW-1 Wooden Doors 10 18-Jul-21 28-Jul-21 23-Jan-21 02-Feb-21 0% -147 28-Jul-21

CN-B06-SP-L3-DW-1 Wooden Doors 10 29-Jul-21 09-Aug-21 03-Feb-21 14-Feb-21 0% -147 09-Aug-21

CN-B06-SP-L4-DW-1 Wooden Doors 10 10-Aug-21 21-Aug-21 15-Feb-21 25-Feb-21 0% -147 21-Aug-21

CN-B06-SP-L5-DW-1 Wooden Doors 6 22-Aug-21 28-Aug-21 27-Feb-21 04-Mar-21 0% -147 28-Aug-21

CN-B06-SP-L6-DW-1 Wooden Doors 6 29-Aug-21 04-Sep-21 06-Mar-21 11-Mar-21 0% -147 04-Sep-21

CN-B06-SP-GF-DW-1 Wooden Doors 10 05-Sep-21 15-Sep-21 13-Mar-21 23-Mar-21 0% -147 15-Sep-21

CN-B06-SUB-BF-DW-1 Wooden Doors 10 16-Sep-21 27-Sep-21 24-Mar-21 04-Apr-21 0% -147 27-Sep-21

7 01-May-21 08-May-21 05-Nov-20 12-Nov-20 -147 08-May-21, Design


Design
7 01-May-21 08-May-21 05-Nov-20 12-Nov-20 -147 08-May-21, B03 & B04
B03 & B04
Details 7 01-May-21 08-May-21 05-Nov-20 12-Nov-20 -147 08-May-21, Details

Project Baseline Bar Remaining Work Baseline Milestone Date Revision Checked Approved
Page 1 of 3
17-Apr-21 Updated Project Schedule Critical Path
Actual Work Critical Remaining Work Milestone
GENERAL AUTHORITY OF CIVIL AVIATION BUILDING
Detailed Program TASK filter: Critical Activities

Activity ID Activity Name Original Start Finish BL1 Start BL1 Finish Activity % Total Float 2020 2021 2022
Duration Complete
A S Oct N D J F M A M J Jul A S O N D J F M Apr M J Jul A S Oct N D J F M
ENG-B3&4-DD-AR-1100 12000-General Details Submission & 7 01-May-21 08-May-21 05-Nov-20 12-Nov-20 0% -147 08-May-21
Approval
Flooring 7 01-May-21 08-May-21 05-Nov-20 12-Nov-20 -147 08-May-21, Flooring
ENG-B3&4-DD-AR-1030 4000-Flooring Submission & Approval 7 01-May-21 08-May-21 05-Nov-20 12-Nov-20 0% -147 08-May-21

Stairs 7 01-May-21 08-May-21 05-Nov-20 12-Nov-20 -147 08-May-21, Stairs


ENG-B3&4-DD-AR-1080 9000-Stairs Submission & Approval 7 01-May-21 08-May-21 05-Nov-20 12-Nov-20 0% -147 08-May-21

30 25-May-21 23-Jun-21 30-Nov-20 29-Dec-20 -171 23-Jun-21, Material Delivery


Material Delivery
30 25-May-21 23-Jun-21 30-Nov-20 29-Dec-20 -171 23-Jun-21, General
General
No Sub-Trade 30 25-May-21 23-Jun-21 30-Nov-20 29-Dec-20 -171 23-Jun-21, No Sub-Trade
ENG-MP-AR-NLL-1140 1st Cementitious raised floor Batch to Site 30 25-May-21 23-Jun-21 30-Nov-20 29-Dec-20 0% -171 23-Jun-21

14 09-May-21 24-May-21 14-Nov-20 29-Nov-20 -147 24-May-21, Shop Drawings


Shop Drawings
14 09-May-21 24-May-21 14-Nov-20 29-Nov-20 -147 24-May-21, B03 & B04
B03 & B04
Ceramic & Porcelain 7 09-May-21 16-May-21 14-Nov-20 21-Nov-20 -147 16-May-21, Ceramic & Porcelain
EN-SD-B3&4-AR-FS-01 Building No. 3 & 4 Basement Floor Plan 7 09-May-21 16-May-21 14-Nov-20 21-Nov-20 0% -147 16-May-21
Floor & Wall Tiling
EN-SD-B3&4-AR-FS-02 Building No. 3 & 4 Ground Floor Plan Floor 7 09-May-21 16-May-21 14-Nov-20 21-Nov-20 0% -147 16-May-21
& Wall Tiling
EN-SD-B3&4-AR-FS-03 Building No. 3 & 4 First Floor Plan Floor & 7 09-May-21 16-May-21 14-Nov-20 21-Nov-20 0% -147 16-May-21
Wall Tiling
EN-SD-B3&4-AR-FS-04 Building No. 3 & 4 Second Floor Plan Floor 7 09-May-21 16-May-21 14-Nov-20 21-Nov-20 0% -147 16-May-21
& Wall Tiling
EN-SD-B3&4-AR-FS-05 Building No. 3 & 4 Third Floor Plan Floor & 7 09-May-21 16-May-21 14-Nov-20 21-Nov-20 0% -147 16-May-21
Wall Tiling
EN-SD-B3&4-AR-FS-06 Building No. 3 & 4 Fourth Floor Plan Floor 7 09-May-21 16-May-21 14-Nov-20 21-Nov-20 0% -147 16-May-21
& Wall Tiling
EN-SD-B3&4-AR-FS-07 Building No. 3 & 4 Fifth Floor Plan Floor & 7 09-May-21 16-May-21 14-Nov-20 21-Nov-20 0% -147 16-May-21
Wall Tiling
EN-SD-B3&4-AR-FS-08 Building No. 3 & 4 Sixth Floor Plan Floor & 7 09-May-21 16-May-21 14-Nov-20 21-Nov-20 0% -147 16-May-21
Wall Tiling
EN-SD-B3&4-AR-FS-09 Building No. 3 & 4 General Details Floor & 7 09-May-21 16-May-21 14-Nov-20 21-Nov-20 0% -147 16-May-21
Wall Tiling
False Ceiling 7 17-May-21 24-May-21 22-Nov-20 29-Nov-20 -147 24-May-21, False Ceiling
EN-SD-B3&4-AR-FS-17 Building No. 3 & 4 Basement Floor Plan 7 17-May-21 24-May-21 22-Nov-20 29-Nov-20 0% -147 24-May-21
False Ceiling Works
EN-SD-B3&4-AR-FS-18 Building No. 3 & 4 Ground Floor Plan False 7 17-May-21 24-May-21 22-Nov-20 29-Nov-20 0% -147 24-May-21
Ceiling Works
EN-SD-B3&4-AR-FS-19 Building No. 3 & 4 First Floor Plan False 7 17-May-21 24-May-21 22-Nov-20 29-Nov-20 0% -147 24-May-21
Ceiling Works
EN-SD-B3&4-AR-FS-20 Building No. 3 & 4 Second Floor Plan False 7 17-May-21 24-May-21 22-Nov-20 29-Nov-20 0% -147 24-May-21
Ceiling Works
EN-SD-B3&4-AR-FS-21 Building No. 3 & 4 Third Floor Plan False 7 17-May-21 24-May-21 22-Nov-20 29-Nov-20 0% -147 24-May-21
Ceiling Works
EN-SD-B3&4-AR-FS-22 Building No. 3 & 4 Fourth Floor Plan False 7 17-May-21 24-May-21 22-Nov-20 29-Nov-20 0% -147 24-May-21
Ceiling Works
EN-SD-B3&4-AR-FS-23 Building No. 3 & 4 Fifth Floor Plan False 7 17-May-21 24-May-21 22-Nov-20 29-Nov-20 0% -147 24-May-21
Ceiling Works
EN-SD-B3&4-AR-FS-24 Building No. 3 & 4 Sixth Floor Plan False 7 17-May-21 24-May-21 22-Nov-20 29-Nov-20 0% -147 24-May-21
Ceiling Works
EN-SD-B3&4-AR-FS-25 Building No. 3 & 4 General Details False 7 17-May-21 24-May-21 22-Nov-20 29-Nov-20 0% -147 24-May-21
Ceiling Works
Raised Floor 7 17-May-21 24-May-21 22-Nov-20 29-Nov-20 -147 24-May-21, Raised Floor

Project Baseline Bar Remaining Work Baseline Milestone Date Revision Checked Approved
Page 2 of 3
17-Apr-21 Updated Project Schedule Critical Path
Actual Work Critical Remaining Work Milestone
GENERAL AUTHORITY OF CIVIL AVIATION BUILDING
Detailed Program TASK filter: Critical Activities

Activity ID Activity Name Original Start Finish BL1 Start BL1 Finish Activity % Total Float 2020 2021 2022
Duration Complete
A S Oct N D J F M A M J Jul A S O N D J F M Apr M J Jul A S Oct N D J F M
EN-SD-B3&4-AR-FS-10 Building No. 3 & 4 First Floor Plan Raised 7 17-May-21 24-May-21 22-Nov-20 29-Nov-20 0% -147 24-May-21
Floor System
EN-SD-B3&4-AR-FS-11 Building No. 3 & 4 Second Floor Plan 7 17-May-21 24-May-21 22-Nov-20 29-Nov-20 0% -147 24-May-21
Raised Floor System
EN-SD-B3&4-AR-FS-12 Building No. 3 & 4 Third Floor Plan Raised 7 17-May-21 24-May-21 22-Nov-20 29-Nov-20 0% -147 24-May-21
Floor System
EN-SD-B3&4-AR-FS-13 Building No. 3 & 4 Fourth Floor Plan 7 17-May-21 24-May-21 22-Nov-20 29-Nov-20 0% -147 24-May-21
Raised Floor System
EN-SD-B3&4-AR-FS-14 Building No. 3 & 4 Fifth Floor Plan Raised 7 17-May-21 24-May-21 22-Nov-20 29-Nov-20 0% -147 24-May-21
Floor System
EN-SD-B3&4-AR-FS-15 Building No. 3 & 4 Sixth Floor Plan Raised 7 17-May-21 24-May-21 22-Nov-20 29-Nov-20 0% -147 24-May-21
Floor System
EN-SD-B3&4-AR-FS-16 Building No. 3 & 4 General Details Raised 7 17-May-21 24-May-21 22-Nov-20 29-Nov-20 0% -147 24-May-21
Floor System
12 15-Mar-20 A 29-Apr-21 15-Mar-20 28-Mar-20 -147 29-Apr-21, Zoning
Zoning
12 15-Mar-20 A 29-Apr-21 15-Mar-20 28-Mar-20 -147 29-Apr-21, B03 & B04
B03 & B04
Zoning 12 15-Mar-20 A 29-Apr-21 15-Mar-20 28-Mar-20 -147 29-Apr-21, Zoning
ENG-B3&4-ZON-1010 B03 & B04 Zoning Approval 12 15-Mar-20 A 29-Apr-21 15-Mar-20 28-Mar-20 0% -147 29-Apr-21

0 02-Dec-21 02-Dec-21 14-Jun-21 14-Jun-21 -147 02-Dec-21, No


No WBS-Action
0 02-Dec-21 02-Dec-21 14-Jun-21 14-Jun-21 -147 02-Dec-21, No
No Location
No Sub-Trade 0 02-Dec-21 02-Dec-21 14-Jun-21 14-Jun-21 -147 02-Dec-21, No
CNS-1010 Project Completion 0 02-Dec-21 14-Jun-21 0% -147 Project Comple

Project Baseline Bar Remaining Work Baseline Milestone Date Revision Checked Approved
Page 3 of 3
17-Apr-21 Updated Project Schedule Critical Path
Actual Work Critical Remaining Work Milestone