General Authority of Civil Aviation Building: Construction Construction
General Authority of Civil Aviation Building: Construction Construction
Activity ID Activity Name Original Start Finish BL1 Start BL1 Finish Activity % Total Float 2020 2021 2022
Duration Complete
A S Oct N D J F M A M J Jul A S O N D J F M Apr M J Jul A S Oct N D J F M
139 24-Jun-21 02-Dec-21 30-Dec-20 13-Jun-21 -147 02-Dec-21, Con
Construction
139 24-Jun-21 02-Dec-21 30-Dec-20 13-Jun-21 -147 02-Dec-21, B06
B06
Fire Alarm 16 28-Sep-21 16-Oct-21 07-Apr-21 26-Apr-21 -147 16-Oct-21, Fire Alarm
CN-B06-SB-BF-S-3-3 Fire Alarm System Third Fix 16 28-Sep-21 16-Oct-21 07-Apr-21 26-Apr-21 0% -147 16-Oct-21
Raised Floor & Carpet Tiles 20 24-Jun-21 17-Jul-21 30-Dec-20 21-Jan-21 -147 17-Jul-21, Raised Floor & Carpet Til
CN-B06-SP-L1-FS-F-6 Carpet Tiles on Raised Floor 10 24-Jun-21 05-Jul-21 30-Dec-20 10-Jan-21 0% -147 05-Jul-21
CN-B06-SP-L2-FS-F-6 Carpet Tiles on Raised Floor 10 06-Jul-21 17-Jul-21 11-Jan-21 21-Jan-21 0% -147 17-Jul-21
Project Baseline Bar Remaining Work Baseline Milestone Date Revision Checked Approved
Page 1 of 3
17-Apr-21 Updated Project Schedule Critical Path
Actual Work Critical Remaining Work Milestone
GENERAL AUTHORITY OF CIVIL AVIATION BUILDING
Detailed Program TASK filter: Critical Activities
Activity ID Activity Name Original Start Finish BL1 Start BL1 Finish Activity % Total Float 2020 2021 2022
Duration Complete
A S Oct N D J F M A M J Jul A S O N D J F M Apr M J Jul A S Oct N D J F M
ENG-B3&4-DD-AR-1100 12000-General Details Submission & 7 01-May-21 08-May-21 05-Nov-20 12-Nov-20 0% -147 08-May-21
Approval
Flooring 7 01-May-21 08-May-21 05-Nov-20 12-Nov-20 -147 08-May-21, Flooring
ENG-B3&4-DD-AR-1030 4000-Flooring Submission & Approval 7 01-May-21 08-May-21 05-Nov-20 12-Nov-20 0% -147 08-May-21
Project Baseline Bar Remaining Work Baseline Milestone Date Revision Checked Approved
Page 2 of 3
17-Apr-21 Updated Project Schedule Critical Path
Actual Work Critical Remaining Work Milestone
GENERAL AUTHORITY OF CIVIL AVIATION BUILDING
Detailed Program TASK filter: Critical Activities
Activity ID Activity Name Original Start Finish BL1 Start BL1 Finish Activity % Total Float 2020 2021 2022
Duration Complete
A S Oct N D J F M A M J Jul A S O N D J F M Apr M J Jul A S Oct N D J F M
EN-SD-B3&4-AR-FS-10 Building No. 3 & 4 First Floor Plan Raised 7 17-May-21 24-May-21 22-Nov-20 29-Nov-20 0% -147 24-May-21
Floor System
EN-SD-B3&4-AR-FS-11 Building No. 3 & 4 Second Floor Plan 7 17-May-21 24-May-21 22-Nov-20 29-Nov-20 0% -147 24-May-21
Raised Floor System
EN-SD-B3&4-AR-FS-12 Building No. 3 & 4 Third Floor Plan Raised 7 17-May-21 24-May-21 22-Nov-20 29-Nov-20 0% -147 24-May-21
Floor System
EN-SD-B3&4-AR-FS-13 Building No. 3 & 4 Fourth Floor Plan 7 17-May-21 24-May-21 22-Nov-20 29-Nov-20 0% -147 24-May-21
Raised Floor System
EN-SD-B3&4-AR-FS-14 Building No. 3 & 4 Fifth Floor Plan Raised 7 17-May-21 24-May-21 22-Nov-20 29-Nov-20 0% -147 24-May-21
Floor System
EN-SD-B3&4-AR-FS-15 Building No. 3 & 4 Sixth Floor Plan Raised 7 17-May-21 24-May-21 22-Nov-20 29-Nov-20 0% -147 24-May-21
Floor System
EN-SD-B3&4-AR-FS-16 Building No. 3 & 4 General Details Raised 7 17-May-21 24-May-21 22-Nov-20 29-Nov-20 0% -147 24-May-21
Floor System
12 15-Mar-20 A 29-Apr-21 15-Mar-20 28-Mar-20 -147 29-Apr-21, Zoning
Zoning
12 15-Mar-20 A 29-Apr-21 15-Mar-20 28-Mar-20 -147 29-Apr-21, B03 & B04
B03 & B04
Zoning 12 15-Mar-20 A 29-Apr-21 15-Mar-20 28-Mar-20 -147 29-Apr-21, Zoning
ENG-B3&4-ZON-1010 B03 & B04 Zoning Approval 12 15-Mar-20 A 29-Apr-21 15-Mar-20 28-Mar-20 0% -147 29-Apr-21
Project Baseline Bar Remaining Work Baseline Milestone Date Revision Checked Approved
Page 3 of 3
17-Apr-21 Updated Project Schedule Critical Path
Actual Work Critical Remaining Work Milestone