Professional Documents
Culture Documents
Paper 4: Operations Management: Co-Principal Investigator
Paper 4: Operations Management: Co-Principal Investigator
Prof YoginderVerma
Co-Principal Investigator Pro–Vice Chancellor
Central University of Himachal Pradesh. Kangra. H.P.
Paper Coordinator
Dr. Vikas Singla
Assistant Professor,
School of Management Studies, Punjabi University, Patiala.
1
Paper 4
Paper Title: Operations Management
Module 35: Inventory Control Systems: Continuous Review System
35.0 Objectives
35.1 Introduction
35.2 Continuous Review (Q) System
35.2.1 The Assumptions of the Model
35.2.2 Two scenarios in Q system
35.2.3 Continuous Review System with uncertain demand before reorder point
35.2.4 Continuous Review System with uncertain demand after reorder point
35.2.5 Service Level: Determination of safety stock
35.2.6 Alternative Measures of Service Level
35.3 Summary
35.4 Glossary
35.5 References/ suggested readings
35.6 Short Answer Questions
35.7 Model Questions
35.0 OBJECTIVES
This chapter would help students to understand:
Difference between dependent and independent demand items
Continuous review (Q) inventory control system
Concept of service level and determination of reorder point when demand is uncertain
35.1 INTRODUCTION
Previous chapters on Inventory management have discussed various inventory models such as
Economic Order Quantity, Economic Production Quantity and Quantity discounts. The main purpose of these
models was to identify quantity that needs to be ordered per batch so that total cost of inventory should be
kept as low as possible. Total cost in these models was function of holding and ordering cost. Thus answer to
question of ‘How much to order’ was determined by these models under an assumption that demand of
quantity ordered would be constant. But in practice such an assumption is rarely fulfilled. Also these models
does not answer the question of ‘When to place an order’ under the conditions of uncertain demand. An
inventory control system helps in identifying answer to both the questions of how much and when to place an
order. The correctness of such an answer primarily depends on understanding of nature of demand.
Categorization of demand of an item into dependent or independent demand is crucial in selection of an
inventory control system. Independent demand is defined as demand for items which is influenced only by
2
market conditions and not by demand of any other item kept in stock. For instance, number of flowers a
flower shop should keep would be influenced by demand for those flowers, number of books of a bestselling
author a book store should keep in stock is influenced by market demand and not by any other book in the
store. Thus independent demand is primarily for final products or products stored at retailer level. Dependent
demand is for those items which are influenced by production of other items. Demand for such products is
influenced by number of units stored of associated items. For instance, number of units of emblems to be used
for cars produced is dependent on number of cars being manufactured. Number of tires produced is again a
function of number of cars produced. For each unit of car four units of tires has to be manufactured. Thus,
demand of tires is dependent on number of cars ordered. It is interesting to know that number of cars ordered
is influenced by market forces and thus it falls into independent demand category whereas every other item
goes into producing a car falls into dependent demand category.
This chapter discusses inventory control models for independent demand items. Two such models
have been discussed: continuous review system called as Q system and periodic review system called as P
system.
3
For a manufacturer managing its finished products inventory, the order will be for a production run of
size Q. For a wholesaler or retailer (or a manufacturer replenishing its raw materials inventory from a supplier),
the order will be a purchase order for Q units of the product. An inventory policy based on these two critical
numbers is a simple one.
Inventory policy: Whenever the inventory level of the product drops to R units, place an order for Q
more units to replenish the inventory.
4
varying demand. At reorder point an order of fixed and certain quantity of units is placed with the supplier.
Now this scenario provides us with two cases:
(i) If demand is uncertain before reorder point: as the continuous review system recommends checking
of stock level after every withdrawal so consequences of varying demand before reorder point is
easily managed. If demand is high then reorder point will be achieved earlier and next order
would be placed earlier whereas if demand is weak then reorder point would be achieved at a
later date and next order could be placed accordingly. This is easily and effectively tracked
because stock is continuously checked.
(ii) If demand is uncertain after reorder point: after placing an order stock is not checked continuously till
next order is made available. So question is what should happen if demand increases or
decreases at abnormal rate during the period which is after reorder level.
These two cases have been discussed in following sections with illustrations
35.2.3 Continuous review system with uncertain demand before reorder point:
Case 1: Suppose batch size i.e. Q = 100 units, daily demand d = 10 units and lead time L = 5 days. Lead time is
the time taken by the supplier to replenish stock by Q after order has been placed. If daily demand would have
been fixed and certain of 10 units then 100 units would be consumed in 10 days (Table 1) making Time
Between Order (TBO) to be of 10 days as shown by Fig.1(a). This TBO would remain same in case of certain
daily demand.
Case 2: But if demand before reorder point varies in a manner that on day 1 10 units, on day 2 20 units and on
day 3 20 units are consumed (Table 1). This means 50 units are consumed in 3 days instead of 5 days when
demand was certain. This could be tracked because of application of continuous review system as it checks
remaining stock after every withdrawal. Thus, next order of 100 units (Q) is placed i.e. reorder point is
achieved after 3 days. As in this illustration demand is certain after reorder point so remaining 50 units would
be consumed at rate of 10 units per day making TBO as 8 days as shown by Fig.1(b).
Case 3: In another instance if daily demand before reorder point is weak and varies in following fashion: 5 units
on day 1, 10 units on day 2, 5 units on day 3 and 10 units on day 4,5and 6 each then first 50 units would be
consumed in 6 days (Table 1). Thus reorder point is reached after 6 days and it is tracked from continuous
review system. Next 50 units because of constant daily demand would be consumed in 5 days making TBO as
11 days as shown in Fig.1(c).
Table 1
Day Case 1 Case 2 Case 3
d Remaining units d Remaining units d Remaining units
1. 10 10 5
2. 10 90 20 90 10 95
3. 10 80 20 70 5 85
5
4. 10 70 10 50 10 80
5. 10 60 10 40 10 70
6. 10 50 10 30 10 60
7. 10 40 10 20 10 50
8. 10 30 10 10 10 40
9. 10 20 10 30
10. 10 10 10 20
11. 10 10
35.2.4 Continuous review system with uncertain demand after reorder point:
As shown in previous section estimation of reorder point in Q system does not depend on variation in
demand before lead point. But what happens if demand is varying after lead time? This has been discussed by
illustrating following cases.
6
Suppose a batch size of 100 units is in the stock and for first five days 10 units daily are consumed.
Thus after 5 days a stock of 50 units is left. Now as lead time i.e. time between placing and receiving an order
is of 5 days so order is placed after 5 days assuming that by the time next batch of 100 units is obtained
remaining stock of 50 units would be consumed. This makes reorder point after 5th day when 50 units are left
in the stock.
Case 1: Now suppose demand varies in a manner such as: during 6th day 10 units, during 7th and 8th day 5 units
each and during 9th and 10th day 10 units each making a total of consumption of 40 units in next five days
(Table 2). Thus in first five days daily 10 units have been consumed at constant rate and in next five days a
total of 40 units are consumed as shown in Fig. 2(a). As order has been placed after 5th day so it would be
received after 10th day operation when in stock 10 units were still there making total inventory of 110 units.
These extra 10 units are called as safety stock. Thus,
Stock at ROP level (R = 50) – demand during Lead time (L = 40) = Safety stocky (SS = 10)
So, ROP = L + SS
Table 2
Day Case 1 Case 2
d Remaining units d Remaining units
During 6th day 10 40 10 40
During 7th day 5 35 20 20
th
During 8 day 5 30 10 10
During 9th day 10 20 10 0
During 10th day 10 10
Case 2: After 5 days when ROP is reached and stock is of 50 units suppose demand during lead time varies in a
manner such as: during 6th day 10 units, during 7th day 20 units and during 8th and 9th day 10 units each making
consumption of last 50 units in next 4 days (Table 2). Thus in first five days daily 10 units have been consumed
at constant rate and rest all 50 units are consumed in next four days as shown in Fig. 2(b). It implies that if
demand during lead time is strong then stock can get finished before replenishment. This situation is termed
as out of stock.
7
These two cases clearly indicate that:
As it is fixed order system so every time when ROP is reached an order of fixed batch size of Q is
placed with the supplier. So if demand is weak during lead time it would result in creation of safety
stock.
If demand is strong during lead time it would result in out of stock situation and might result in loss of
customers.
This result in uncertainty in estimation of reorder point. In section 35.2.1 it was shown that such
uncertainty in estimation of ROP was independent of variation in demand if it happens before lead
time. But this uncertainty in estimation of reorder point does happen if demand varies after lead
time. Resolution of this uncertainty requires understanding the concept of service level.
8
ordering cycle to other then higher safety stock can be kept. This is gauged by recording past demand data
during lead time. This data is plotted by calculating average and deviation values. This variation tends to follow
normal distribution implying that central value represents average demand. As these variations follow normal
distribution so safety stock is calculated by using following formula:
Safety stock = z (number of deviations deduced from z tables) * (standard deviation in demand during lead
time)
Higher service level would imply requirement of creating a higher buffer (safety stock) for higher variation in
demand. This variation is represented by higher z value. If z=0, there is no safety stock meaning stock outs will
occur during 50% of the order cycles.
Example: Records show that demand data for a product during lead time is normally distributed with an
average of 250 units and deviation of 22 units. Estimate safety stock if company intends to maintain a service
level of 99%. Also find reorder point.
Solution: At a service level of 99% value of number of deviations from z tables is 2.33
So Safety stock = z*standard deviation
= 2.33*22 = 51 units
ROP = average demand during lead time + safety stock
= 250 + 51 = 301 units
9
measures on which to focus primary attention, it is useful to explore the implications of several alternative
values of this measure on some of the other measures before choosing the best alternative.
35.3 SUMMARY
Inventory control systems help in determining when to reorder and how much to order of products
whose demand is independent from other products. Primarily two inventory control systems are discussed
namely Continuous review system (Q) and Periodic review system (P). This chapter has focussed on Q system
which tracks the level of stock after every withdrawal making it convenient to judge the reorder point when
demand variation is not constant. In this system number of units ordered per batch remains constant whereas
time between orders varies with variation in demand patterns. This concept has been illustrated in detail by
taking various cases under two sections. In one section variation in time between orders was evaluated when
variation in demand is before lead time and in other section it was emphasized when demand variation is after
lead time. Variation in demand during lead time can either result in safety stock or stock outs. To resolve these
issues concept of service level has been explained.
35.4 GLOSSARY
Dependent demand: is the demand for those items which are inter-related with each other and need
for one item is direct result of need for some other item.
Independent demand: is the demand for those items which are not related with each other.
Continuous review system: is an inventory control system wherein stock level is checked after every
withdrawal.
Safety stock: is the excess products that are available during one ordering cycle
Service level: is identified in terms of probability indicating level of customer service that a company
intends to provide.
10
Answer: c
3. In Q system estimation of ROP is effected by variation in demand during lead time only.
(a) True (b) False
Answer: a
4. 80% of service level implies that:
(a) chances of stock out is 20%
(b) company intends to provide customer service 80% of the time.
(c) desired probability of serving the customer at designed service level
(d) all of the above
Answer: d
5. Which of the following is given more consideration in deciding service level?
(a) safety stock (b) customer service
(c) both should be given equal importance
Answer: c
11
12