Professional Documents
Culture Documents
Pressure Testing of Pressure Vessel
Pressure Testing of Pressure Vessel
The pressure testing article provides you with information about pressure vessel hydro-static
testing requirements and related item in pressure vessel inspection.
The requirements have been described based on ASME Code Section VIII. You need to do
this test after completion of the construction process, but before the internal parts assembly
and also before painting process.
This content covers all major requirements and provides you with guidelines for test
performance.
Please note that performing the pneumatic test instead of the Hydro-Static Test is not
allowed, and it can be replaced only when it is not possible due to the design and process.
1. Checking all welding already finished and fully accepted by the NDT examination per the
project Inspection and test plan.
2. Making sure the inner part of the vessel is clean and free of remaining slag or other
elements. Making sure the external surface is dry for the correct execution of the visual
inspection during the vessel pressure testing.
3. Checking the pressure gauges' calibration tag and certificate and the range of the lower
limit and upper limit of the gauges. It needs to be between 1.5 and 4 time of the pressure
test value.
4. Controlling testing equipment such as the test pump and housing for soundness and
tightness.
5. Making sure the test temperature will not violate the following values:
MDMT is the pressure vessel minimum design metal temperature, and it is stated in the
pressure vessel design document. This reduces the risk of a brittle fracture during the test.
6. Making sure which reinforcement pads are already
soap tested.
Activities during the pressure vessel hydro-static testing that need to be checked by
the manufacturer quality control team and a third party inspector:
1. Making sure the filling and pressurizing are done from the lowest point and venting from
the highest point.
2. Witnessing water overflow through the venting in order to assure that no air bubbles
remain in the vessel.
First Stage: Raise the pressure to 40% of the final pressure, stop pressurizing, keep it for 5
minutes, and then make a fast visual inspection of the external surface.
Second Stage: Restart pressurizing up to 70% of final pressure, stop the operation, keep for
5 minutes and make a fast visual inspection on external surface.
Third Stage: Restart pressurizing up to 100% of the final pressure, stop the operation, and
keep for 45 minutes.
4. When 45 minutes elapse, making sure the de-pressurizing is started and the pressure is
dropped to the “Inspection Pressure.”
Making sure a detail and a comprehensive inspection is carried out over the whole body of
the vessel and in the welding joints and attachments.
5. Making sure the pressure vessel hydro-static testing pressure calculated correctly as
following:
6. Making sure the vessel is immediately and carefully drained after the test and dried by air.
Activities after the pressure vessel hydro-static testing that need to be checked by the
manufacturer quality control team and a third party inspector:
1. The pressure vessel hydro-static testing report needs to be prepared by the manufacturer
quality control team and signed by the third party or authorized inspector.
2. If the test failed by leaking from weld joints or any other kind of defect, it is necessary that
the vessel is drained and dried and repaired based on approved repair procedure. Pressure
vessel hydro-static testing needs to be repeated.