Shell Factory: Revamping of All Plant Hangar Project

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 1

Shell Factory

Revamping of all plant hangar project


DAILY PROGRESS REPORT
Day : Monday Date: 14 Oct 2019 Ref: STR/Shell/SRM/DPR/0024 No: 0024
Manpower/Equipment
Item # Staff No Item # Workforce No Item # Equipment No
1 Project manager 0 10 laborer 3 1 Truck 1
2 Construction Manager 1 11 Scaffolder 15 2 Forklift 1
3 Site Engineer 1 12 Scaffolder supervisor 1 3
4 Site supervisor 2 13 Steel workers 6 4
5 Safety supervisor 2 14 Steel supervisor 1 5
6 Safety Manager 1 15 Forklift driver 1 6
7 Rigger 0 16 Truck driver 1 7
8 Crane operator helper 0 17 Crane operator 0 8
9 18 9
Total 35 Total 2
Daily progress matrix
Original work scope
% the % of
Total Qty Number of Area of
Zone Activity Activity in Details unit Qty detail activity
of detail work force Zone
in zone
6 steel workers
Zone 1 Purlins repair Grinding piece 9 66 14 % - 10%
1 steel supervisor
Zone 2 - - - - - - - - -
Installing working deck at
M2 190 190 7 Scaffolders 100%
Installing scaffold Lvl 8:30 m in blending area
Zone 3 300* 100%
Installing handrail and
M2 190 190 6 scaffolders 100%
strengthen in scaffold base
Material Delivered to site
Qty received
# Activity unit Qty delivered Delivery note Ref Test required
cumulative
1407 Roof+800 for
1 scaffolding M2 800 HDT No 80/2019 Visual inspection
walls
Remarks and general comments

- 2 service scaffolders worked in barricading and organizing storage areas.


- Structo Team had to work late to unload material delivered until 2:00 AM :
Structo team that stayed late :
1- Safety manager = 1
2- Safety supervisor =1
3- Site supervisor = 1
4- Laborers = 3
5- Forklift river = 1
6- Truck driver = 1

Prepared by :Eyad Mohammed Refai


To: Ahmed Gamal , Ahmed Hekal

You might also like