1. Daily progress report from an ongoing plant hangar revamp project. 35 workers were on site from various roles like laborers, scaffolders, steel workers, and safety personnel.
2. Work focused on purlin repairs, installing working decks and scaffolding at level 8 (30m) in the blending area, and strengthening scaffold bases.
3. Materials delivered included 800 sqm of scaffolding bringing the cumulative total to over 2200 sqm. Late night unloading of deliveries required extra hours from 6 Structo team members.
1. Daily progress report from an ongoing plant hangar revamp project. 35 workers were on site from various roles like laborers, scaffolders, steel workers, and safety personnel.
2. Work focused on purlin repairs, installing working decks and scaffolding at level 8 (30m) in the blending area, and strengthening scaffold bases.
3. Materials delivered included 800 sqm of scaffolding bringing the cumulative total to over 2200 sqm. Late night unloading of deliveries required extra hours from 6 Structo team members.
1. Daily progress report from an ongoing plant hangar revamp project. 35 workers were on site from various roles like laborers, scaffolders, steel workers, and safety personnel.
2. Work focused on purlin repairs, installing working decks and scaffolding at level 8 (30m) in the blending area, and strengthening scaffold bases.
3. Materials delivered included 800 sqm of scaffolding bringing the cumulative total to over 2200 sqm. Late night unloading of deliveries required extra hours from 6 Structo team members.
1. Daily progress report from an ongoing plant hangar revamp project. 35 workers were on site from various roles like laborers, scaffolders, steel workers, and safety personnel.
2. Work focused on purlin repairs, installing working decks and scaffolding at level 8 (30m) in the blending area, and strengthening scaffold bases.
3. Materials delivered included 800 sqm of scaffolding bringing the cumulative total to over 2200 sqm. Late night unloading of deliveries required extra hours from 6 Structo team members.
DAILY PROGRESS REPORT Day : Monday Date: 14 Oct 2019 Ref: STR/Shell/SRM/DPR/0024 No: 0024 Manpower/Equipment Item # Staff No Item # Workforce No Item # Equipment No 1 Project manager 0 10 laborer 3 1 Truck 1 2 Construction Manager 1 11 Scaffolder 15 2 Forklift 1 3 Site Engineer 1 12 Scaffolder supervisor 1 3 4 Site supervisor 2 13 Steel workers 6 4 5 Safety supervisor 2 14 Steel supervisor 1 5 6 Safety Manager 1 15 Forklift driver 1 6 7 Rigger 0 16 Truck driver 1 7 8 Crane operator helper 0 17 Crane operator 0 8 9 18 9 Total 35 Total 2 Daily progress matrix Original work scope % the % of Total Qty Number of Area of Zone Activity Activity in Details unit Qty detail activity of detail work force Zone in zone 6 steel workers Zone 1 Purlins repair Grinding piece 9 66 14 % - 10% 1 steel supervisor Zone 2 - - - - - - - - - Installing working deck at M2 190 190 7 Scaffolders 100% Installing scaffold Lvl 8:30 m in blending area Zone 3 300* 100% Installing handrail and M2 190 190 6 scaffolders 100% strengthen in scaffold base Material Delivered to site Qty received # Activity unit Qty delivered Delivery note Ref Test required cumulative 1407 Roof+800 for 1 scaffolding M2 800 HDT No 80/2019 Visual inspection walls Remarks and general comments
- 2 service scaffolders worked in barricading and organizing storage areas.
- Structo Team had to work late to unload material delivered until 2:00 AM : Structo team that stayed late : 1- Safety manager = 1 2- Safety supervisor =1 3- Site supervisor = 1 4- Laborers = 3 5- Forklift river = 1 6- Truck driver = 1