Professional Documents
Culture Documents
DT 5A Theodolite Repair Manual PDF
DT 5A Theodolite Repair Manual PDF
(1)
(13)
(10)
(8) (14)
(4)
(11) (16)
(2)
(3)
(7)
(6) (5)
(9)
(15)
(12)
(Figure 1-1)
1
1. carrying handle
2. handle screw
3. sighting collimator
4. vertical tangent screw and motion clamp
5. operating key
6. RS-232C communication interface
7. objective lens
8. plate level
9. display window
10. eyepiece
11. base plate
12. foot screw
13. focusing knob
14. battery
15. horizontal tangent screw and motion clamp
16. base locking lever
2
1.2 Basic operation
(Figure 1-2)
3
Levo-incremental reading
R/L /dextro-incremental reading Setting mode
of horizontal angle
Output of
V/% Vertical angle/percent slope measurement
data
Power
4
II. Display and display label
Start, then the display will display all the symbols firstly (see
Figure 1-3) and then display the symbol which requires the vertical
angle to be set to zero.
5
Levo-incremental
Unit for distance
HAL reading of m
measurement:m
horizontal angle
Dextro-incremental
HAR reading of gon Angle unit
horizontal angle
The second
SFT 06-03-20 Date
function selection
Repetition of
REP measurements for 14:38 Time
horizontal angle
Function of
CRN inclination Auto off function
compensation
6
(ON).
7. Option for collimation error correction: ON, OFF
8. Option for “Angle” and “Gon”: Angle< OFF>, Gon< ON>.
(II) Functional allocation of the keys under the setup modes are
as follows:
[OSET]:Circularly select the setup item
[HOLD]:Circularly select Clock setup item (M/D/Y, H/M/S).
[L / R ]: Switch option value of setup item by circulating upward
or plus 1 to the option of clock setup item.
[V / % ]:Switch option value of setup item by circulating upward
or minus 1 from the option value of clock setup item.
[SFT]:Confirm the setup, exit setup mode and return to angle
measurement mode.
(III) Operation method for function setup
1. Press [SFT] key first and then press [L / R ] key, the
instrument will enter into setup mode (see Figure 1-4).
2. Press [0SET] key to select the setup options 1-7. If you want
to select the minimum angle reading of the forth option, press
[0SET] key for three times, shown as Figure 1-5.
1. OFF 4. 1″
7
3. Press [L/R] key or [V / % ] key to change the setup of
selected option. If you want to select 5″as the minimum angle
reading, press [L/R] key once, shown as Figure 1-6.
07–06–07 9:16 07–06–07 9:16
VA 90°14′32″
4. 5″ HAR 168°25′01″
4. Press [SFT] key to save the setting and return to the angle
measurement mode (see Figure 1-7).
1. OFF . . . . . .
8
option. If you want to change the 07–06–07 in the Figure into
07–08–07, press [HOLD] key for once to change option into the
“Month” from “Year”, and the “Month” (06) will blink. Press [L/R]
key for twice to change “06”into “08”, shown as Figure 1-10.
VA 90°14′32″
. . . . . . HAR 168°25′01″
4. Press [SFT] key to save all time settings and return to the
angle measurement mode (see Figure 1-11).
10
1.3 Inspection of complete equipment
1. To check the functions of the functional keys are normal or
not.
2. To check the measured angle is hopped
(1) Level the instrument and start it to carry out zero crossing,
and observe one far point A, and then record the vertical and
horizontal angle values. Rotate the vertical axis and horizontal axis
several times and observe point A repeatedly and also read the
vertical and horizontal angle values, and the variation shall not
exceed 5″.
(2) Carry out fine adjustment for the vertical and horizontal
handwheels, and observe whether the horizontal and vertical
indicated angle values are in ordered change. In case of abnormal
condition, it shows that the horizontal or vertical angle has hop
problem.
3. To check whether the left and right rotation increments are
correct
4. To check the zero crossing conditions in different directions
Level the instrument and start it, and rotate the telescope at a place
near to 90° of the direct position of telescope (left of plate), and
angle value shall be displayed vertically. (In case that “SET 0” is
always displayed, it shows that the problem of no zero crossing
exists for this instrument.)
(1) Stop the instrument and the telescope heads downwards,
and start the instrument and carry out zero crossing upwards, and
the vertical angle value shall be recorded by aiming at one target.
(2) Stop the equipment and the telescope heads upwards, and
11
start the equipment and carry out zero crossing downwards, and the
vertical angle value shall be recorded by aiming at the same target
as above.
(3) The difference between two values shall be less than 10″.
If the difference is excessively big, it shows that the problem of
excessively high zero-passage level exists.
5. To check the index error:
(1) Exactly level the instrument and start it to carry out zero
crossing.
(2) Rotate the telescope to make it in the level position of
direct position of telescope. Aim at target A and record the reading
value A1 of vertical angle.
(3) Rotate the alidade at 180º to make the telescope (reversed
telescope) aim at target A again, and then record the reading value
A2 of vertical angle. Half of │A1+A2–360│ will be the index error
and this value shall not exceed 10″. If it exceeds 10″, it shows that
the instrument has the problem of oversize index error.
6. To check the compensation precision of vertical angle
(1) The instrument is arranged on the calibration stand
(Wherein, one foot screw shall be aligned to the collimator), and
then exactly level the instrument and start it to carry out zero
crossing, and guarantee that the compensator is in the state of “on”.
If the vertical angle value in the vertical angle value column of the
second line is not displayed, but “TILT” is shown, it shows that the
zero position of electronic compensator is oversize, and repair is
needed for it firstly.
(2) The telescope aims at the origin 0 of reticule of collimator
12
(Some collimators are provided with near point reticules used to
inspect the minimum distance of visibility and optical axis of the
telescope. The origin 0 here refers to the origin 0 on the reticule at
the objective lens focus of the collimator equal to the target in
infinitive distance, similarly herein after), and record the vertical
angle value A.
(3) Rotate the foot screw to make the instrument be inclined
by 3′ backwards. (If the reticule scale unit of the collimator is 18″,
it is necessary to make the telescope aim at the vertical thread +10
of reticule of collimator namely, moving by 10 lattices.) Rotate the
focusing sleeve to make the telescope aim at the origin 0 of reticule
of collimator, and then record the vertical angle value A1.
(4) Rotate the foot screw to make the telescope aim at the
vertical thread -20 of reticule of the collimator (namely, the
instrument is inclined by 3′ forwards), and rotate the focusing
sleeve to make the telescope aim at the origin 0 of reticule of
collimator , and then record the vertical angle value A2.
(5) The absolute values of A1–A and A2–A shall be less than 6″
respectively, if it is oversize, it means that the compensation
precision is oversize.
13
Chapter II Maintenance of Common
Mechanical Faults
2.1 Over-tightness of the vertical axis during rotation
I. Shedding of horizontal grating circle
Strong vibration of the instrument may cause the horizontal
grating circle to shed with glue failure; in this case, the rotation of
the vertical axis may become over-tight. By dismantling the display
on one side of the telescope, you can find that the horizontal grating
circle (the grating circle on the top) will not follow the rotation of
the alidade when the alidade is rotating. Check four directions of
the whole circumference, at an interval of 90° with a 0.02mm
feeler gauge. The feeler gauge shall be able to insert between any
two grating circle . In case the feeler gauge can not be inserted
between a specified pair of grating circles, we can determine that
the horizontal grating circle has fallen off due to glue failure. When
maintaining such kind of failure, it is necessary to calibrate the
circle or return the grid circle to the factory for reparation.
II. Blocking of the vertical axis
If the alidade can not rotate or is hard to rotate, it is mainly
because that the vertical axis is blocked. At this time, the alidade
shall not be rotated forceably; otherwise, the vertical axis will be
scrapped due to the seizure of it. As the vertical axis requires very
high fitting accuracy, it is necessary to return it to the factory for
maintenance, because that repairing it with non-professional tools
can hardly ensure the fitting accuracy.
14
2.2 Over-tightness of the horizontal axis during rotation
For this kind of horizontal axis structure, no over-tightness
during rotation will occur under normal operation. Over-tightness
of this kind of horizontal axis is generally caused by long term
usage, strong vibration, collision, or scraping between the two
vertical grating disks. Check four directions of the whole
circumference, at an interval of 90° with a 0.02mm feeler gauge.
The feeler gauge shall be able to be inserted between any two
grating circles; if the feeler gauge can not be inserted between a
specified pair of grating circles, it can be determined that scrapping
has occurred. For the maintenance methods, refer to section
II—failures in vertical angle measurement in 3.3—Maintenance
of the failures in vertical angle measurement.
16
3
2
1
5
7 8 4 10
12
13
14
15
16
6 17
9
11
(Figure 2-1)
17
1. Display 2. Set screw 3. Brake and 4. Holding
micro screw
hanwheel unit
5. Base of the 6. Micro 7. Allen screw 8. Set screw
terminal handwheel
spring
9. Brake 10. 11. Adjusting 12. Spacing
handwheel Countersunk screw ring
set screw
13. Horizontal 14. 15. Set screw 16. Brake
stationary Horizontal shift fork
bushing locking lever
17. Micro screw rod
18
2.4 Maintenance of vertical tangent screw
Figure 2-2 shows the disassembly and assembly of the vertical
giggle system of this series of electronic theodolite.
1. Take down the battery case 1 from the right baffle plate 2.
2. Back out the six set screws 3 of the fixed right baffle plate 2.
3. Take down the right baffle plate 2 and pay attention to the
positions of the inner connections.
4. Back out the base of the terminal spring 4 and make sure that
the spring and relevant accessories do not spring out.
5. Back out a holding screw 5 and take out the vertical micro
handwheel 6 with an inner hexagon spanner.
6. Back out two Allen screws 7 and take down the micro
handwheel 8.
7. Back out the set screw 9 and back out in an anti-clockwise
direction the brake handwheel 10.
8. Back out 2 sunk screws 11 and one adjusting screw 12 and
then take down the spacing ring 13.
9. Take down the stationary bushing 14 from the vertical brake
rod 15.
19
4
9 6 5
10
11
12
14
15
16
17
18
8 7 13
(Figure 2-2)
20
1. Battery 2. Right 3. Set screw 4. Base of he
case baffle plate terminal
spring
5. Holding 6. Vertical 7. Set screw 8. micro
screw micro handwheel
handwheel
9. Set screw 10. Brake 11. Sunk 12. Adjusting
handwheel screw screw
13. Spacing 14. 15. Vertical 16. Set screw
ring Stationary brake rod
bushing
17. Shift fork 18. Micro
screw rod
10. Screw out two set screws 16 and take down the shift fork 17.
11. Screw out the micro screw rod 18.
12. Brush carefully all the parts and elements and make sure that
the adjusting pad of white nylon on the vertical brake rod 15
does not get lost during the brushing.
13. Refer to Figure 2-2 and assemble the vertical brake and micro
handwheel in the sequence reverse to the disassembling sequence
specified in 6-11. Apply a proper amount of handwheel oil between
the micro screw rod 18 and the vertical brake rod 15 and between
the stationary bushing 14 and the vertical brake rod 15. After the
assembling process, check whether the screws are tight and the
rotation is smooth. No over-tightness or lost motion is allowed at
any position. If the over-tightness or lost motion does occur, it is
necessary to eliminate it through adjusting the adjusting screw 12.
After the above adjustment, it is required to apply some varnish to
21
the adjusting screw for sealing.
14. Refer to Figure 2-2 and arrange the vertical tangent screw on
the support in the sequence reverse to that specified in 1-5.
15. During the assembling process, the holding screw 5 shown in
Figure 2-2 shall be inserted into the V-shape slot of the horizontal
stationary bushing with moderate pushing force. The assembly shall
meet the standard that the horizontal brake and micro system can
rotate freely without the risk of being pulled out.
16. Rotate the handwheel 10 shown in Figure 2-2 to make the
brake system operate reliably with a braking region of 45°–90°;
then tight the holding screw 5.
2.5 Common faults of WILD tribrach
I. Sliding of the level press board
7 8
6
5
4
3
(Figure 2-3)
1.lock screw 2. base backing nut 3. elastic washer
4. foot screw 5. level bearing 6. bearing backing nut
7.φ3 steel ball 8. level base plate
22
Sliding up and down of the level press board may cause that the
plate level can not swing to level, which is resulted from
loosening of the backing nut of the level bearing. The
maintenance procedures are as follows:
1. Screw the lock screw 1 tight clockwise (see Figure 2-3) to
unlock the wrench handle. Rotate the wrench handle anticlockwise
and remove the alidade.
2. Use a plate to remove the base backing nut 2.
3. Remove 2 pieces of elastic washer 3 (some instrument has
only one piece).
4. Turn the pedestal for 180º(see Figure 2-3) and remove the
level pedestal board 8.
5. Remove threeφ3steel balls 7.
6. Grasp the foot screw 4 and use a plate to screw the bearing
backing nut 6.
7. Drip a little vacuum pump oil between the bearing backing
nut 6 and the level bearing 5.
8. Install threeφ3steel balls 7 and level base boards 8 one by
one.
9. Turn the pedestal for 180º and install the elastic washer 3.
10. Install the base backing nut 2 and use a plate to screw it
tight.
11. Rotate the screw 1 anticlockwise and lock the wrench
handle.
23
sleeve. The maintenance procedures are as follows:
1. According to the operations 1-5 in I. Sliding of the level
press board above, remove relevant parts(see Figure 2-3)
2. Grasp the level hand wheel 3 and use a plate to remove the
backing nut 7 of the level bearing (see Figure 2-4).
3. Remove three bearing washers 6 and three level bearings 5.
4. Remove the level press board 4.
5. Rotate the foot screw 3 clockwise and slide it down until
it is close the guide sleeve 2 as much as possible, then adjust the
foot screw 3, allowing twoφ3 holes on the foot screw to be aligned
with the groove of the guide sleeve 2.
6. Loose the cone-point set screw 1 and use a plate to screw
the guide sleeve 2.
7. Screw the cone-point set screw 1, fasten the guide sleeve 2
and seal it with varnish.
8. Install the level press board 4, three level bearings 5 and
three bearing backing nuts 6.
9. Repeat operations 6-11 in I. Sliding of the level press
board above.
24
7
(Figure 2–4)
1. cone-point set screw 2. guide sleeve 3. foot screw 4. level press
board 5. level bearing 6. bearing washer 7. bearing backing nut
1 2 3
(Figure 2-5)
1. level handwheel 2. guide sleeve 3.split washer
26
2.6 Common faults of the slide pedestal
I. Malfunction of the locking mechanism of the pedestal
Fasten the pedestal lock handwheel 1 (see Figure 2-6) and
parallel move the alidade 4 to make sure that the alidade 4 can still
slide relative to the slide pedestal 3. The fault is caused by
malfunction of the locking mechanism of the pedestal, which
causes the alidade can not be locked.
The maintenance procedures are as follows:
1. Loose the two M2 cone-point top threads 2 on the pedestal
lock handwheel 1 (see Figure 2-6).
2. Screw the pedestal lock handwheel 1 clockwise and fasten
the alidade 4. Push the alidade 4 for checking to make sure no
displacement relative to the slide pedestal 3 will occur.
3. Tighten up the two M2 cone-point top threads 2.
4. Loose the pedestal lock handwheel 1 and push the alidade 4;
the alidade should be parallel moved freely.
(Figure 2-6)
27
1. lock handwheel 2. M2 cone-point top thread
3. slide pedestal 4. alidade
3 4
28
(Figure 2-7)
1. pedestal 2. M3 sunk screw 3. lock handwheel 4. alidade
(II) Fault elimination of sliding up and down of the level press
board
1. Use a plate to remove the base backing nut 1.
7
5 6
4
2
3
1
(Figure 2-8)
1. base backing nut 2. elastic washer
3. level handwheel 4. level bearing
5. bearing backing nut 6. φ3 steel ball
7. level base board
29
the level bearing and the level bearing 4.
7. Install threeφ3 steel balls 6 and the level base board 7 in
turn.
8. Turn the pedestal at 180º and install the elastic washer 2.
9. Install the base backing nut 1 and use a plate to screw it
tight.
10. Turn the instrument and install the slide pedestal and three
M3 sunk screws (see Figure 2-8). Firmly connect the slide pedestal
and the middle-lower housing of the alidade 4.
III. Tightness of the foot screw
After long term usage of the instrument, the foot screw may
become tight or the frame may become flexible. The maintenance
procedures are as follows:
1. Rotate the foot screw 4 of the slide pedestal 5 to let the
φ2.5 hole 1 on the foot screw 4 be aligned with theφ2.5 hole 2 on
the pressing sleeve 3 (see Figure 2-9).
5 4 3 2 1
(Figure 2-9)
30
1. φ2.5 hole 1 on foot screw 2. φ1.5 hole 3. pressing sleeve
4. footscrew 5. slide pedestal
2. Use a special plate to rotate the pressing sleeve. If the foot
screw is tight, rotate the pressing sleeve anticlockwise; if the
frame of the foot screw is flexible, rotate the pressing sleeve
clockwise.
3. After it is properly adjusted, turn the three foot screws one
by one and make sure that the three foot screws can be easily and
gently rotated and the frame can not be moved.
31
Chapter III Fault Maintenance of Angle
Measurement
3.1 Introduction about electrical circuit signal of angle
measurement
The angle measurement part of electronic theodolite consists of
horizontal angle measurement which is of diameter reading (two
sensors) and vertical angle measurement which is of single-sized
reading (one sensor), and each sensor outputs two ways of sine
waves which are taken as the basic signal for angle measurement
through further adjustment and treatment on main board and such
basic signal is the original signal of electronic angle measurement
(six ways of sine waves) which directly influences the results of
angle measurement, so the requirements for the wave form is
relatively high and precise adjustment is needed. One way of
zero-crossing pulse will be added to vertical angle measurement
part and the zero-crossing voltage signal should be adjusted for the
angle measurement circuit accordingly.
3.2 Cause and maintenance of fault of not being able to
start-up
I. Insufficient battery power
Multimeter is switched to DC voltage position to check the
voltage of the battery case, whose voltage shall be greater than 6.5V.
If less than 6.5V, it shows that battery power is not adequate. In this
case, the battery case shall be connected with the dedicated charger
and then connected with the power supply of the charger. When the
indicator indicates red, charging starts. The indicator will indicate
32
green when battery is fully charged. Power supply shall be cut off
before disconnecting the battery case. Then the battery case is
installed to check whether instrument can start up.
This charger is a quick charger that is able to complete
charging in 4 hours quickly with power reaching 80%. If battery
needs to be fully charged, it needs 2 to 4 hours’ trickle charging.
Attention shall be paid to that charging time shall not exceed 24
hours.
33
1
2
- + -
(Figure 3-1)
1. Angle measuring mainboard 2. Plug of buzzer
34
welding position of negative and positive poles shall be correct.
The black wire shall be welded to contact 2 and the red one shall be
welded to contact 5, otherwise, the serious result that angle
measuring mainboard may be burned when instrument is turned on
may be caused.
3 4
2
5
6
1
(Figure 3-2)
1. cover 2. contact (negative) 3.power wire (black) 4. power wire (red) 5.
contact (positive) 6. right cover board
(2) Loose connection of electrode
After using for a long time, the instrument may not be able to
rebound due to dust and oil deposited at the electrode, thus
resulting in that good connection with contact of battery case can
not be ensured.
Figure 3-3 shows electrode structure diagram of this series of
electronic theodolite. When maintaining, power wire can be
removed by welding to remove four cross recessed self-tapping
screws 1. Then cover 2 and contact spring 3 and contact 4 can be
35
removed. These parts shall be cleaned by using gasoline and then
reassembled. Lubricant shall not be applied when assembling.
1 2 3 4
(Figure 3-3)
1. cross recessed self-tapping screw 2. cover 3. contact spring 4.
contact 5. right baffle plate
III. Fault of electronic compensator
When there is no problem with battery power and connection
of power wire, and the instrument still can not start up, power
supply shall be cut off. Remove four M2.5 screws on fixed angle
measuring mainboard to separate angle measuring mainboard from
bracket of instrument. Remove plug of electronic compensator from
angle measuring mainboard 7 (see Figure 3-4) and then check
whether the instrument is able to start up or not. If it is able to start
up, it shows that electronic compensator has fault. It is necessary to
replace electronic compensator and calibrate new electronic
compensator (for replacement and calibration methods, see3.4
36
Fault maintenance of electronic compensator).
4 5
2
3
1 6
(Figure 3-4)
1. socket of power wire 2. socket of display 3. socket of electronic
compensator 4. socket of vertical simulator 5. socket of level
simulator 6. US232 socket 7. angle measuring mainboard
IV. Fault of LCD
37
not, it can be determined that the angle measuring mainboard has a
fault. It is necessary to replace the angle measuring mainboard.
During the above examination, if instrument can start up when
display on one side is plugged, but can not start up when display on
another side is plugged, it can be determined that there is a fault
with display on this side or the data wire of the display. At this time,
four M2 screws on the fixed display can be removed after power
supply is cut off. Data wire of display on the side in which
instrument can start up is removed and reassembled on another side.
Check whether instrument can start up. If not, it can be determined
that display on this side has a fault. If instrument can start up, it
shows that data wire has a fault. Display or data wire can be
replaced according to the fault.
In addition, after using for a long time, LCD may not display
or display incomplete things, or its key fails. New display or data
wire can be replaced according to the fault.
When replacing, remove four M2 screws on the fixed display and
connector of display and angle measuring mainboard. New display
or data wire is connected with angle measuring mainboard.
Connection shall be reliable and in the correct position. When
instrument can start up, the display shall be installed on the bracket
of the instrument. Four M2 screws shall be secured firmly.
38
first and then every connector on the angle measuring mainboard
shall be removed one by one (see Figure 3-4).
Debug the angular measurement electrical signal of the two
horizontal simulators and the single vertical simulator (see also 3.4
Maintenance of the Malfunction in Angular Measurement) and
zero-crossing voltage (see also 3.3 Non Display of the Zero
Position of the Vertical Angular).
After the angular measurement electrical signal of the two
horizontal simulators and the single vertical simulator have been
debugged well, the new angle measuring mainboard shall be
replaced and installed. While installation, every connector shall be
plugged in and connected to the corresponding socket of the angle
measuring mainboard. The position of the connectors shall be
correct and the connection of which shall be reliable. After the
connectors are examined to be correctly installed, the angular
measurement board shall be mounted on the support, and then
fasten by four M2.5 screws.
39
3.3 Non Display of the Zero Position of the Vertical
Angular
Leveling the instruments, and start the instrument. When the
screen displays the information of setting the zero position of the
vertical angular, you shall rotate the telescope in circles to pass zero
at the vicinity of the 90° of the vertical angular circle-left (direct
position of telescope). The angular value of the vertical angular on
the screen shall be displayed. If the screen continuously displays:
“SET 0” (see Figure 3-5), it means that the instruments have the
problem of not crossing zero. If such circumstance happens, the
zero-crossing electrical signal and zero-crossing voltage of the
angle measuring mainboard shall be measured and be debugged
again.
Adjustable electric resistance WR9 (see Figure 3-6) was
installed on the angle measuring mainboard of the instruments
produced in the early stage, so the adjustment of the zero-passing
voltage shall be carried out on the angle measuring mainboard. The
adjusting of the zero-passing voltage of the instruments currently
produced has already been adjusted by software. You shall
following the methods introduced below, to adopt corresponding
methods to adjust the zero-crossing voltage of different
instruments.
40
06–03–20 14:38
VA SET 0
HA
R
180°10′30″
(Figure 3-5)
I. The method of using adjustable electric resistance to adjust
the zero-crossing voltage: P11
WR9
P1
P2
P6
P5
1
P8
P3
P4
Lattice
(Figure 3-6)
1. Angle measuring mainboard
1. Shut down the instrument, remove the six M2.5 screw on
the left cover board of the fixed instrument, then open the left cover
board, pluck off the buzzer plug on the angle measuring mainboard
and remove the left cover board.
2. Switch on the instrument, use the oscillograph (select mode
A, a sensitivity of 500mV and a scanning speed of 1mS for the
41
oscillograph) to detect the waveform of the P8 point of the angular
measurement board (see Figure 3-6), and at the same time rotate the
telescope at the vicinity of the 90° of the vertical angular circle-left,
by doing so, the oscillograph shall display zero-crossing pulse
showing in Figure 3-7. The minimum voltages (Vs) of the
zero-crossing pulse shall pass 0.8V, and the amplitude of the
zero-crossing pulse shall be Vn – Vs ≥ 0.5V.
3. Use the oscilloprobe to detect the waveform of the P11
point (see Figure 3-6) of the mainboard, and the Figure displayed in
the oscillograph shall be a direct current level Va (see the Va in
Figure 3-8). The corresponding relationship with the zero-crossing
pulse in Figure 3-7 shall be that showing in Figure 3-8. When rotate
the telescope to not passing zero, the direct current level Va shall be
lower than the valley point Vs (see Figure 3-8) of that of
zero-crossing pulse).
A >1mS A >1mS
Vn Vn
Va
Vs Vs
42
1. Zero-crossing pulse
43
plug of the buzzer on the angle measuring mainboard, and then
remove the left cover board.
2. Press and hold both [OSET] and [ ] keys simultaneously
(see Figure 3-9), and then press [ ] key to start up; Display screen
displays “FAC” and then enter the instrument accuracy setting
mode after about 2 seconds. And then press the SFT key to enter the
factory pattern, as shown in Figure 3-9.
DIST S/H/V
OSET R/L
REP REC
HOLD V/%
SFT
(Figure 3-9)
06–03–20 14:38
82
1.58
(Figure 3-10)
P11
P1
P2
1
P6
P5
P8
P3
P4
L att ic e
(Figure 3-11)
1. The angle measuring mainboard
45
4. Press [V / % ] , inspect the wave shape of P11 (see Figure
3-11) on the the angle measuring mainboard by the oscillograph
probe, DC voltage level Va (see Figure 3-11) shall be displayed by
the oscillograph, relative relationship between which and the
zero-pulse as shown in Figure 3-7 is shown in 3-8. When rotation
of the telescope is not zero, the DC voltage level Va is less than the
valley point Vs of the zero-pulse wave (see Figure 3-8).
5. in case that the zero-crossing voltage Va is too low or too
high (although the too high zero-crossing voltage Va is able to be
zero, it may cause a overproof phenomenon of the vertical index
error.), it is able to modify the software parameter by press keys
on the panel as shown in Figure 3-9 to change the zero-crossing
voltage Va in order to meet the requirement. [L / R ] and [V / % ]
keys on the panel are for crude regulation, wherein [L/R] is the rise
key and [V/%] is the lower key. Upon press [L/R] or [V/%] a time,
the zero-crossing voltage Va will increase or rise or lower about
100mV. Observe the oscillograph at the same time until the position
DC voltage level Va moves upward and downward.
[OSET] and [HOLD] keys on the panel are for accurate
adjustment, wherein [OSET] is the rise key and [HOLD] is the
lower key. Upon press [OSET] or [HOLD] a time, the zero-crossing
voltage Va will increase or rise or lower about 20mV. DC voltage
level V shall be adjusted until it reaches to 1/2 (Vn–Vs)+Vs (see
Figure 3-8).
6. Press [ ] to verify, the display screen will return to the
interface shown in Figure 3-9.
7. shutdown and restart up, telescope shall be rotated at such
46
near 90º of the telescope direct (left side of the disc), to check the
instrument to be bale to be zero normally or not. If so, re-regulate
the index error of the vertical circle, in case of an unqualified index
error, it is good to lower DC voltage level Va. But it shall be
ensured that such DC voltage level Va is 0.3V more than the valley
point Vs of the zero-pulse. Method to regulate the index error of the
vertical circle is shown in 3.6 index error and collimation error
compensator zero point error setting.
8. Shutdown, insert the plug of the buzzer on the left cover
board in the twin core socket on the angle measuring mainboard.
Mount the left cover board, tight the six M2.5 screws and fix the
left cover board.
47
display is as shown in Figure 3-9, zero-crossing voltage of such
instrument is able to be adjusted with the software.
2. Press and hold both [ ] and [L / R ] keys simultaneously
(see Figure 3-9), if the display on the display screen is as shown in
Figure 3-12, number in the third line in the Figure is value of the
zero-crossing voltage Va, that is 1.10V.
06–03–20 14:38
56
1.10
(Figure 3-12)
48
not. If so, “0SET”will appear before the number in the second line,
as shown in Figure 3-13. (If not, check the instrument to be able to
be zero normally or not after higher the zero-crossing voltage.)
06–03–20 14:38
OSET 66
1.30
(Figure 3-13)
49
Recheck until telescope can be rotated to zero under the telescope
direct condition and can not be rotated to zero under the telescope
reverse condition.
10. Being the telescope direct condition, and object lens of the
telescope located over 90 º, start up , telescope shall be rotated
top-down to be zero. Cross wire of the telescope collimates the
collimator tubes and divides point A on the board, read the latitude
value, and shutdown. Object lens of the telescope located under 90
º, start up, telescope shall be rotated down -top to be zero. Cross
wire of the telescope still collimates the collimator tubes and
divides point A on the board, read the latitude value. Compare the
two values; difference between the two values shall not exceed 3″.
If so, indicating that the zero-crossing voltage Va is too high, so
zero-crossing voltage Va shall be lowered 100 mV as per the
above-mentioned method. Recheck until meet the requirement.
11. shutdown and restart up, telescope shall be rotated at such
near 90º of the telescope direct (left side of the disc), to check the
instrument to be bale to be zero normally or not. If so, re-regulate
the index error of the vertical circle, in case of an unqualified index
error, it is good to lower DC voltage level Va. Method to regulate
the the index error of the vertical circle is shown in 3.6 index error
and collimation error compensator zero point error setting.
50
3.4 Fault Maintenance of the Angle Measurement
Level the instrument, turn it on, and rotate the telescope
passing zero. After rotating the vertical shaft and the cross shaft
respectively 3 circles, observe point A on the parallel plain tube
reticule, record the values of the vertical angle and the horizontal
angle; after rotating the vertical shaft and the cross shaft
respectively 2 to 3 circles, still observe the object point A, read the
value variation between the vertical angle and the horizontal angle,
which shall not surpass 5″. If the value variation surpasses 5″, the
repetitiveness of the angle measurement is proved to be poor.
Slightly move the horizontal or vertical handwheel, and
observe the indicating value of the horizontal or vertical angle,
which shall be steadily increased or decreased according to the
minimum indicating value united 1″ (the angle measurement shown
shall be set of 1″). If there incurs any abnormal conditions, it is
proved that there are hop problems on the horizontal or vertical
angles.
WR9
P5 P11
P1
P2
P6
1
P8
P3
P4
Lattice
(Figure 3-14)
1. Angle measuring mainboard
52
P1 Horizontal angle measurement signal test point
P2 Horizontal angle measurement signal test point
P3 Horizontal angle measurement signal test point
P4 Horizontal angle measurement signal test point
P5 Vertical angle measurement signal test point
P6 Vertical angle measurement signal test point
P8 Zero-crossing pulse test point
P11 Zero-crossing voltage test point
53
A >1mS
1: >500mV 2: >500mV
(Figure 3-15)
1. Sine wave
CP 1
CP 2
V0
1 3
(Figure 3-16)
1. Test box 2. Power plug 3. Six-core socket
55
1
(Figure 3-17)
1. Horizontal simulator
56
waves. Potentiometer WR1 and WR4 (see Figure 3-21) respectively
change the central voltage of the two way sine waves.
When debugging, pay attention that the potentiometer can not
be adjusted at the limit position, otherwise, the amplitude voltage
and the central voltage will uneasily to change.
Moreover, when rotating the alidade and observing the variation of
the amplitude voltage, there are two abnormal conditions, one is the
variation of the amplitude voltage surpasses 500mV. In this way, it
may cause horizontal hop. The reason is that there is tackless
between the horizontal comb rack and the grid disk (the above
grating disk) or between the horizontal comb rack and the
positioning disk, thereby causing clearance variation of the grating
disk. It can be tested with a feeler of 0.02mm, from 4 directions of
the all-around, which shall be tested once per 90°, and the feeler
shall be plugged in between the two grid disks. If there is one place
can not be plugged, the clearance between the two grid disks can be
tested to be smaller. As it required to be dismantled with a tool, it
shall be returned to the factory for repair.
Another condition is: when observing the variation of the
amplitude voltage, there is up and down or left and right hop on the
sine wave. This is because there is oil stain, fingerprint or foreign
matter on the grating disk. In the two horizontal gating disks, the
lower one the main grating disk, if disk surface is dirty, the sine
wave will hop, and when the hop surpasses 200mV, it will cause
horizontal hop. Dip some mixed liquor (aether 70%, ethanol 30%)
with the absorbent cotton to clean the surface of the grating disk.
4. Probe CH1 shall be changed to be plugged on socket CP2 of
57
the special debugging box. Rotate the alidade, and the oscillograph
will display the sine wave of another way of electrical signal of the
horizontal simulator, as shown in Figure 3-15. The amplitude
voltage and central voltage of this sine wave shall conform to the
above technical requirements.
5. If the electrical signal amplitude voltage and central voltage
output by a horizontal simulator can not achieve the technical
requirements, the voltage can be adjusted in accordance with the
above methods.
6. After the horizontal simulator is adjusted, turn off the
instrument and disconnect the power. Put the six-core plug of the
long and short horizontal simulator into the respective position on
the angle measuring mainboard (see Figure 3-4). Then, test the
horizontal angle measurement electrical signal of the angle
measuring mainboard.
7. Put on the angle measuring mainboard, and fix it with 4
M2.5 screws; put the buzzer plug into the angle measuring
mainboard, install the left cover board, and fix it on the support
with 6 M2.5 screws.
58
A: DC level is 2.5V±0.02V
B: Partial amplitude value of AC is 1.2V±0.2V
C: The amplitude difference of electric signal of vertical angle
measurement between P5 circuit and P6 circuit is less than 0.1 V
WR9
P11
P1
P2
P6
P5
P8
1
P3
P4
Lat ti ce
(Figure 3-18)
1. Angle measuring mainboard
It can adjust according to the following procedures if the
waveform can not meet the above requirements:
1. Tear down four M2.5 of cross recess head screws on the
fixed angle measuring mainboard and remove the angle measuring
mainboard.
2. Unplug the plug of vertical stimulator from angle measuring
mainboard (see Figure 3-4) and insert into six-core socket of
dedicated debugging box.
3. DC power supply from dedicated debugging box is 5V±
0.02V. Oscillograph is selected as X-Y mode with sensitive degree
59
of 500mV. The two attenuating probes are selected as X1 gear,
respectively inserting into CP1and CP2 sockets of dedicated
debugging box (see Figure 3-16). The earth wire of oscillograph
connects with dedicated debugging box.
4. Inspect with a feeler ruler about 0.02 mm at one time for
four directions every 90°, the feeler ruler shall insert into the
clearance of two grating disks, with roughly same clearance at each
place. If one place can not be inserted, then it can be judged that the
clearance between two grating disks at this place has become
smaller.
1
2
(Figure 3-19)
1. Left bearing φ6 bore 2. M3X5 internal hexagonal top thread
3. Adjusting screw
5. Turn the lateral axis, aim the left bearing φ6 bore 1 (see
Figure 3-19) at internal hexagonal top thread 2 one by one,
counterclockwise spin a round for each M3X5 internal hexagonal
60
top thread 2 (totally 4) (as Figure 3-19, two more on the opposite of
mirror).
6. Turn the lateral axis to make the left bearing φ6 bore 1 (see
Figure 3-23) aim at the adjusting screw 3. Turn the telescope back
and forth with slow and constant speed at small angle, and observe
the Lissajous Figures on oscillograph at the same time. Slightly
adjust the adjusting screw 3 with a screwdriver (see Figure 3-19).
There are four adjusting screws with oriented angle of 90°to each
other, the amplitude voltage can be changed by respectively
adjusting the clearance between two grating disks at four directions
of up, down, left and right. Clockwise turning the adjusting screw
close to this place can increase the clearance between two grating
disks of this place to decrease the amplitude voltage. The
counterclockwise turning can reduce the clearance between two
grating disks to increase the amplitude voltage.
Turn the lateral axis for a round to observe the Lissajous Figures on
oscillograph, with the amplitude value shall be 500-1500mV (see
Figure 3-20).
61
A >1mS A >1mS
Vs
Vn
1 1
62
In addition, turn the lateral axis a round, and when observing
the Lissajous Figures on oscillograph, the Lissajous Figures will
has change in respect of size. The change of amplitude value shall
be less than 500mV. If it exceeds 500mV, it may cause the hop of
vertical angle measurement, which is due to the greater axial hop
amount of lateral axis after long time use of instrument. Because it
needs special tools to remove, it shall be returned to factory for
repair.
(Figure 3-22)
1. Vertical simulator
7. Oscillograph is selected as A mode, the probe CH1 is
changed to insert zero crossing socket (V0)of dedicated debugging
box (see Figure 3-16), turn the telescope near the right angle of face
mirror ( left of disk), oscillograph shall show zero crossing pulse as
Figure 3-21. The amplitude of this zero crossing pulse of Vs-Vn
shall be not less than 0.5V.
63
8. Oscillograph is selected as “A” mode with sensitive degree
of 500mV. The attenuating probe is selected as X1 gear, inserting
into CP1 socket of dedicated debugging box (see Figure 3-16). The
earth wire of oscillograph connects with dedicated debugging box.
A >1mS
1: >500mV 2: >500mV
(Figure 3-23)
1. Sine wave
Turn the lateral axis back and forth and observe the sine wave
signal on oscillograph. Adjust the potentiometer of vertical
stimulator with noninductive screwdriver (see Figure 3-22) to make
the amplitude voltage and center voltage of sine wave signal ( see
Figure 3-23) outputted by the first circuit meet the following
technical requirements:
A: DC level is 2.5V±0.02V
B: partial amplitude value of AC is 1.2V±0.2V
In Figure 3-22: potentiometers of WR6 and WR7 can respectively
change the amplitude voltage of sine wave on two circuits.
64
Potentiometers of WR5 and WR8 can respectively change the
center voltage of sine wave on two circuits.
Take care not to adjust the potentiometer to the limit position when
adjusting, thus the amplitude voltage or center voltage is not easy to
change.
9. Probe CH1 is changed to insert into CP2 socket of dedicated
debugging box. Turn the lateral axis, oscillograph shows the sine
wave of electric signal on another circuit of vertical stimulator, as
described in Figure 3-23. According to the above adjusting method,
make the amplitude voltage and center voltage of sine wave on this
circuit achieve the above technical requirements.
Apart from satisfying the above technical requirements, the
amplitude difference of electric signal of vertical angle
measurement on two circuits shall be less than 0.1 V.
10. After the completion of debugging, insert the six-core plug
of stimulator into the corresponding position of angle measuring
mainboard (see Figure 3-4).
11. Recheck the electric signal of vertical angle measurement
of angle measuring mainboard (test points of P5 and P6 in Figure
3-18), if there is no mistake, debug the zero crossing electric signal,
for the debugging method to which, see3.2 no display of vertical
angle of zero position.
12. Insert the buzzer plug into the angle measuring
mainboard and amount left cover board and fix on the support with
six M2.5 screws.
65
3.5 Fault maintenance of electronic compensator
Ⅰ. Change of electronic compensator
1. Dismantling six M2.5-screws fixing the left cover and
disconnecting buzzer plugs from the angle measuring mainboard is
for taking down the left cover.
2. Dismantling four M2.5-cross recessed pan head screws is for
taking down the angle measuring mainboard. The compensator
plugs are disconnected from the angle measuring mainboard (see
Figure 3-4).
1
2
(Figure 3-24)
1. M3-screw hole on the bracket, 2. Compensator,
3. Φ3 washer, 4. M3-screw
3. Dismantling six M2.5-screws fixing the left cover on the
instrument is for taking down the left cover.
4. Dismantling two M3-screws 4 and twoΦ3 washers 3 for
66
fixing the compensator 2 (see Figure 3-24) is for taking down the
compensator 2.
5. The new electronic compensator will be assembled on the
brackets by firmly fixing two M3-screws 4 and twoΦ3 washers 3.
6. Passing from one side of bracket without fitting plate level to
left side of bracket, the 6-way plug of compensator will be
connected to the compensator socket on the angle measuring
mainboard (see Figure 3-4).
7. The angle measuring mainboard will be fixed firmly on the
bracket by 4 M2.5- cross recessed pan head screws.
8. The buzzer plug will be connected to the angle measuring
mainboard, and the left cover will be fixed firmly by 6
M2.5-screws.
After changing the new electronic compensator, it is
necessary to correct the zero position, compensate precision and
index error of compensator.
67
4
3
1
2
(Figure 3-25)
1. Foot screw I, 2. Foot screw II, 3. Foot screw III
Judgment whether zero position or compensate precision
of electronic compensator is out of tolerance:
68
After starting-up, it is understood that the compensator is in
the closure if the opening mark “CRN” is not shown in the forth
row. It is available for starting-up the compensator as following
steps:
1. press (SFT) button (see Figure 3-26), and press (L/R) button
to show as Figure 3-27.
(Figure 3-26)
69
07–06–07 9:16 07–06–07 9:16
1. OFF 1. ON
06–03–20 14:38
VA TILT
HA 右 180°10′30″
(Figure 3-29)
70
showing “FAC” for 1 second on the display screen, the interface
shown as Figure 3-30 is shown. The 2″ in the third row means that
the precision of instrument leveling angle is 2″.
2. Press ( ) button to show as Figure 3-31.
Since settled as 2″ for the instrument at factory, if there is found
that it is changed as 5″, 10″ or 20″ due to incorrect operation during
maintenance, it is available to press (OSET) button to set it as 2″
again, then press ( ) button for confirmation and storage shown
as Figure 3-31.
07–06–07 9:16 07–06–07 9:16
VA 125°10′30″ VA 125°10′30″
–110 10
A
1
(Figure 3-34)
1. Compensator, 2. M3-screw
8. Striking cover of compensator by screwdriver with wooden
handle (see Figure 3-34) is to correct the zero error of compensator
to being less than ±15. when directing position of telescope, if the
72
zero error of compensator is negative (–110 shown as Figure 3-32),
strike downwards the A position of the compensator 1 as Figure
3-34. And if it is positive, strike downwards the B position of the
compensator 1 as Figure 3-34. So under the precondition of precise
leveling of instrument, revolving alidade to any position, absolute
value of zero error of compensator shall be less than 15 (as shown
in Figure 3-33).
If it is a newly changed compensator, the zero position of it may be
large due to incorrect mounting position. At this time, two
M3-screws shall be loosed for adjusting the compensator so as to
perform above correction by slightly fastening two M3-screws after
correcting absolute value of zero error of compensator to being less
than 100.
9. After fastening two M3 (2) screws fixing electronic
compensator, it is available to re-check the zero error of
compensator whose absolute value shall be still less than 15. Two
M3-screws shall be sealed by varnish.
Precision of compensator shall be corrected after zero
correction of compensator.
VA 90°11′32″ VA 90°08′32″
8 461
74
07–06–07 9:16 07–06–07 9:16
VA 90°14′32″ VA 90°14′32″
-449 HAR 168°25′01″
TILT
75
IV. Test on the Compensation Precision of Compensator
1. Place the compensator on the calibration stand, with the
direction of the triangular pedestal put as shown in Figure 3-25,
with elongated bubble pointing toward the operator, and with the
foot screw Ⅲ opposite the collimator tube. Conduct precise
leveling so that the deviation of all the four directions of the plate
level should be less than 1/2 grid. Start the compensator, wait for
zero passage, and confirm the compensator is turned on.
2. Move the telescope to aim at the point “A” on the reticule
of the collimator tube, and read the value of the vertical angle after
it is stable.
3. Clockwise rotate the pedestal foot screw Ⅲ to back-tilt the
compensator by 3′(If the value of the grids on the collimator tube
is 18″, up to 10 grids can be tilted). Rotate the vertical handwheel
slightly to let the telescope aim at the point “A” on the reticule of
the collimator tube again. Read the value of the vertical angel, the
error should be less than 6″.
4. Anticlockwise rotate the pedestal foot screw Ⅲ to front-tilt
the compensator by 3′. Rotate the vertical handwheel slightly to
let the telescope aim at the point “A” on the reticule of the
collimator tube again. Read the value of the vertical angel, the error
should be less than 6″too.
76
vertical angle of the same object “A”, if the total of the two reading
values measured is not equal to 360°, then the half of the
difference between the total and 360° is the zero error of the
vertical angle. For the 2″class compensator, if the zero error is
more than 10″, the calibration is necessary (Note: please confirm
the compensator is turned on before calibration).
If the index error is very bad, you can conduct setting as
follows. Measure the angles of the left limb and the right limb, and
set the index of the vertical limb again to let the index error meet
technical requirements. At the same time, measure the collimation
error of the compensator so that the compensator can correct the
collimation error for the measured value (Due to the correction
range of the collimation error is less than 30″, if 2C>30″,
you must correct and keep the error of the vertical axis of the
collimation axis within 30″). Besides, the zero error of the tilt
sensor also can be measured and set.
Note: After the modes of “the display unit of the smallest reading
value” and “tilt compensation function” are changed, above
calibrations should be carried out once more.
77
07–06–07 9:16 07–06–07 9:16
VA SET 0 SET F1
HAR 8°25′01″
SET F2 SET
HAR 8°25′01″ HAR 168°34′59″
4. For the inverted telescope (on the right of the limb), rotate
78
the alidade by 180°, and still move the telescope to aim at the
point “A”, and press the key【OSET】for confirmation. After the
“SET F2” on the second line flashes several times, the prompt of
“SET” is displayed, as shown in Figure 3-41.
5. Press the key 【 OSET 】 for confirmation, and the
compensator accepts the newly set index error, collimation error,
and zero error, and goes back to the mode of angel measurement.
79
Chapter IV Examination and Correction of
Geometric Relationship
Conduct the examination and correction of geometric
relationship according to the following order. This is because that
the relationship and interacting between various verification items
should be considered. For example, for such item will affect the
subsequent verification of various items, it is ought to firstly verify
the perpendicularity between plate level axis and vertical axis.
80
4
3
1
2
(Figure 4-1)
1. Foot screw I 2. Foot screw II 3. Plate level 4.Foot screw III
II 、Correction
1. Rotate alidade to so as to the axes of plate level3 is parallel
to the connecting line between foot screw I and foot screw II (see
Figure 4-1).
2. Rotate pedestal foot screw II or foot screwier of base to
center the bubble of plate level 3.
3. rotate alidade for 180°(or 200g), if the bubble deviates
center and exceeds the deviation, adjust the foot screw I shown in
Figure4-1 to move the bubble towards center by the half deviation.
4. Rotate the adjustment screw 1 shown in Figure 4-2 with
alignment to move the bubble 2 towards center until to be in center.
81
1 2
(Figure 4-2)
1. Adjustment screw 2. Plate level
82
1
(Figure 4-3)
1. Adjustment screw
84
II. Correction
To carry out the inspection according to the above methods, if
there has obvious deviation, it can correct in light of the following
steps:
1. Screw off the protecting cover 1(sees Figure 4-4).
2. Loose the four bolts 3 fastening the ocular head set 2 (see
Figure 4-4).
3. Rotate the ocular head set 2 to remove the deviation, and
tighten the four bolts 3. After inspected and accepted according to
the above-mentioned methods, install the protecting cover 1.
III. Cautions
When use the first method to inspect, if the target moves along
a curved line or it accompanies with jumping in the movement, at
the moment of slightly moving the vertical handwheel, it is mostly
caused by the uneven loads on the fine-motion screw, it should be
excluded previously. It also can refer to the above methods, slightly
move the horizontal handwheel to check wether the horizontal wire
is horizontal or not. Because the vertical wire will be plumb
likewise after leveling the horizontal wire (in the processing, it has
ensured the verticality between the horizontal wire and the vertical
wire on the stadia plate, the error of nonperpendicularity can not
more than 5´).
85
3
(Figure 4-4)
1. Protecting cover 2. ocular head set 3. bolt
86
reverse the telescope to collimate B staff, a reading M1 will be
gained from B staff (1.650m as shown in Figure 4-4). Then loose
the horizontal brake handwheel, turn the alidade to make the
telescope aim at N on A staff for the second time. Then tighten the
alidade, and reverse the telescope, if the cross wire of the telescope
still aims at M1 on B staff, it is illustrated the two axis is
perpendicular to each other. If the cross wire deviates to M2
(1.630m as shown on Figure 4-4), it is presented that there is a
collimation error.
Calculated according to the following formula:
1/4 M1 M2 ≥ allowable
C″= •ρ″
S value
This series of electronic theodolite belongs to Class 2" instrument.
When the allowable value is not less than 8", it is needed to correct.
A B
M 1 (1.650)
仪器
N Instrument
M (1.635)
M 2 (1.630)
S
(Figure 4-5)
II. Correction
When making the correction, take down the protecting cover 1
87
in Figure 4-6, switch the two regulating screw 2 on the left side and
the right side to make the vertical wire moves horizontally from M2
(sees Figure 4-5), and to reduce 1/4 of the offset M1M2, that is
from 1.630m in the Figure to 1.635m, at this moment, the
collimation axis is perpendicular to the horizontal axis. Repeat the
above-mentioned operation, and after inspected and accepted,
install the protecting cover 1.
2 1
(Figure 4-6)
1. Protecting cover 2. regulating screw
88
Figure 4-7 to see the division spanner clearly. Then turn the
focusing handwheel 3 to see the target A on the ground clearly.
Move the instrument or the target to make the aimed target A (sees
Figure 4-8) on the center of the division spanner. Then turn the
alidade 180° (or 200g), if the target deviates from the center (for
example deviates to B as shown in Figure 4-8), it is presented the
collimation axis of the optical plummet is not coincident to the
central line of the vertical axis. In the height of 0.8~1.5m, the offset
shall be less than 1mm. If it exceeds the offset, it is needed to
correct.
4
3 2
(Figure 4-7)
1. Protecting cap 2. ocular cap 3. focusing handwheel 4. correction screw
II. Correction
1. Screw off the protecting cap 1 of the optical plummet in
Figure 4-7.
2. Trough regulating the correction screw 4, adjust the half
offset of the target, that is correct the target on B in Figure 4-8 to C.
89
3. Adjust the pedestal foot screw to make the centre of the
division spanner aim at the target on the ground (refers to Figure
4-8).
B
C
A
(Figure 4-8)
4. Turn the alidade 180° (or 200g), if the target still deviates
from the center and exceeds the offset, it is necessary to repeat the
above-mentioned correction steps, until turn the alidade to any
place to observe, the target is on the center of the division spanner.
5. Install the protecting cap 1 of the optical plummet.
90
Appendix I: Error Information
Error
Error description
prompt
Index error of vertical limb is set incorrectly or
E01
exceeds the offset
91