Professional Documents
Culture Documents
Internship Report
Internship Report
An Internship Report
on
1VJ18CV411
Internship Carried Out At
APTHA
VENTURE
Bengaluru
CERTIFICATE
Certified that the internship work entitled “Execution of Residential Project” carried out by
UJWAL CHAUHAN bearing USN 1VJ18CV411, a bonafide student of Vijaya Vittala
Institute of Technology, in partial fulfilment for the award of degree of Bachelor of
Engineering in Civil Engineering of the Visvesvaraya Technological University,
Belagavi during the year 2020-2021. It is certified that all corrections/suggestions indicated
for Internal Assessment have been incorporated in the report deposited in the departmental
library. The internship report has been approved as it satisfies the academic requirements in
respect of Internship work prescribed for the said degree.
External Viva
Name of the Examiners: Signature with Date
1.
2.
DECLARATION
i
ACKNOWLEDGEMENT
I would also like to thank my supervisor and guide Mr. Mani, Junior Engineer and all
the Technical and Non-Technical Staff of Landmark Nest Partner with Aaptha
venture, who extended their valuable guidance and cooperation in every step, thereby
ensuring successful completion of my internship work.
I would like to express my thanks to Dr. Rajendra S, Principal, for providing us the
required amenities and the opportunity for successful completion of Internship work
Last but not the least, I would here by acknowledge and thank my friends, family
members and all others who directly or indirectly helped me in completion of this
internship work.
UJWAL CHAUHAN
1VJ18CV411
LIST OF CONTENTS
CHAPTER
TITLE PAGE NO.
NO.
DECLARATION i
ACKNOWLEDGEMENT ii
LIST OF CONTENTS iii
LIST OF FIGURES vi
LIST OF TABLES vii
2.2.4 Surveyor 7
2.2.5 The Store Department 7
2.3 Site Details 7
2.4 Project Details 8
2.4.1 Location of the Project 8
2.4.2 Area Statement 9
iii
LIST OF CONTENTS
2.4.3 Access to Project 9
3 TASK PERFORMED 10
3.4 Materials 13
3.5 Excavation 14
3.6 Acoustic 14
3.7 Foundation 14
3.7.3 Waterproofing 14
3.7.4 Piles 15
3.13 Plumbing 21
3.14 Staircase 22
3.15 Putty 23
3.18 Plastering 27
iv
LIST OF CONTENTS
4 REFLECTION NOTES 29
4.1 Introduction 29
4.3.3 Concreting 30
4.4.1 Communication 31
v
LIST OF FIGURES
FIGURE PAGE
FIGURE DESCRIPTION
NO. NO.
1.1 Logo of Aaptha Landmark 2
1.2 Organizational Chart of Company 4
1.3 Location of Aaptha ventures 5
2.1 Organization Structure of Site Work 6
2.2 Map 8
3.1 Blockwork 15
3.2 Sill Concrete 15
3.3 Concrete Mixing 16
3.4 Boundary Wall Measurement and Marking 18
3.5 Plaster Mesh 19
3.6 Retaining Wall 20
3.7 Plumbing in Toilet 21
3.8 Concrete Mix Pouring in Staircase 22
3.9 Staircase 22
3.10 Putty Work in Wall 23
3.11 Centring 24
3.12 Stagging 24
3.13 Electrical Wiring 26
3.14 Plastering 27
vi
LIST OF TABLES
TABLE PAGE
TABLE DESCRIPTION
NO. NO.
2.1 Location of the project 8
2.2 Area Statement 9
2.3 Access to project 9
3.1 Work Schedule 10
vii
EXECUTION OF RESIDENTIAL PROJECT
CHAPTER 1
ABOUT THE COMPANY
1.1 INTRODUCTION
AAPTHA VENTURES has recently launched its new project AAPTHA LANDMARK,
located at Chikkagubbi, Hennur Main Road in Bengaluru. Hennur
main Road is well-connected through an integrated network of road and public transport.
Various shopping options, educational institutions, hotels and recreation centers are located
nearby. We indigenize the latest global technologies to local conditions and terrain to extract
maximum results and the tangible benefits are being experienced by our clients in all the project
executed by us. We have been part of prestigious projects across a multitude of verticals, where we are
proud to have introduced many new construction innovations. The expanding list of satisfied clients
reflects our ability to execute challenging projects despite all odds. Difficult working conditions,
weather or terrain has been no deterrent to our team which has delivered consistently and brought
accolades to the company.
2. The quality of final product and services will be improved through continuous
review and advancement of construction process.
3. The skill of our qualified and dedicated work force at all level will be enhanced
to serve our client better.
1.3 VISION
1. Endeavoring of total solution for Turn key project for all in house and for
customer.
2. Developing talent within by fostering knowledge through experience system
merchandising and maximum utilization of resources.
3. Complete project in time, safety and quality to satisfaction of customer
throughout pan India.
4. Ensuring growth beyond market and profit of all the skate holder of the company.
1.4. MISSION
1. Landmark Nest infrastructure walks towards customer satisfaction in the highest
level and continual improvement towards growth.
2. To improve customer experiences through constant innovation understanding,
with a focus on quality and transparency of process.
3. To offers Apartment with perfect combination of contemporary architecture and
features to provide comfortable living.
4. It also offers Car parking.
CHAPTER 2
ABOUT THE DEPARTMENT
2.1 CONSTRUCTION SITE WORKS DEPARTMENT
Construction site work department mainly deals with excavation, shuttering, bar
Kothanur Main Road and has good number of options for public transport. This project
holds a legal approval from BDA and BBMP.
Aaptha Landmark has 2 & 3 BHK apartments located at Hennur Road Bangalore. The
property is spread across 1090-1600sq.ft.(101.26-148.64 sq.m) of land with large
portion of land area allocated for greenery, landscaping and water bodies.
The Carpet area of 3 Bedroom apartments at Aaptha Landmark ranges between
101.26 sqm to 148.64sqm. The price of 2 BHK flat starts at Rs47.41 L to 52.20 L and
3BHK flat starts at Rs62.64 L to 69.60 L.
CHAPTER 3
TASKS PERFORMED
The basic objectives of “Internship”, planned as part of the curriculum for 8th semester
B.E are to understand the working flowchart of a design industry and to bridge the gap
between the academically knowledge and the Industrial procedures of the structural
design. In this regard, we had an opportunity to work with “LANDMARK NEST PVT.
LTD”, Hennur main road, Bengaluru. In a period of 4 weeks our objectives were to get
aquatint with the working nature of a construction of a residential building and to get
ourselves familiarized with the various processes involved in executing a typical
construction project work.
staircase. It is one staircase wing downstairs to the garage and one staircase wing up to
the apartment areas. In the entrance area there is common residential building
equipment such as cleaning room and staller room. Underground floor is used mainly
for parking, there is also storage areas and technical room. The building is not designed
specifically for use of disabled people. Disabled people will be in the building not
permanently, only occasionally. Underground level of the building is not fully and
whole under surrounding ground, but it is only half underground. Therefore, Execution
of residential building. There is no need of entering the object via ramp from the street
but the garage is in the same level as the pavement of the street.
expanding load bearing walls would be difficult. Wall system is also much stiffer than
skeleton system.
Fifth floor is smaller than the rest with slab above fourth level used as a terrace, this
time without slab break, which would create unwelcome appearance in the apartments
below. This recess of the fifth floor leads to thicker reinforced concrete slabs than in
the regular floor to thickness of 250 mm.
There is an elevator shaft with doubled wall in the face of apartment. Double wall starts
directly from foundation slab.
3.4 MATERIALS
CONCRETE:
Reinforced concrete columns underground level
C35/45 - XC2, XD1- dmax=22mm - Cl <2%-S4
Reinforced concrete perimeter walls underground level
C30/37 – XC2, XA1, XD1 - dmax=22mm-Cl <2%-S4
Reinforced concrete walls (communication areas) underground level
C30/37 - XC2, XD1 - dmax=22mm - Cl <2%-S4
Reinforced concrete walls (communication areas) upper levels
C30/37 – XC1 - dmax=22mm - Cl<2%-S4
Reinforced concrete slabs
C30/37 – XC1 - dmax=22mm – Cl<2%-S4
Reinforced concrete foundations
C25/30 - XC3, XA1, XD1 - dmax=22mm - Cl<2%-S4– Xypex
Reinforced concrete of precast staircase elements
C30/37 – XC1 - dmax=22mm - Cl<2%-S4
Reinforced concrete piles
C25/30 - XC3, XA1 - dmax=22mm - Cl<2%-S4
STEEL:
Reinforcing bars B500B
MASONRY: POROTHERM 25 AKU SYM P15, M10 250 mm
POROTHERM 19 AKU SYM P10, M10 250 mm
POROTHERM 17,5 P+D P8, M2,5 – PARTITIONS 175 mm
POROTHERM 11,5 P+D P10, M2,5 – PARTITIONS 115 mm
3.5 EXCAVATION
The excavation is made for underground construction. The excavation area is composed
of two drainage systems DN100 and backfill soil and gravel 60/32. Volume of
excavated soil = 743 m3. To the possible extent, most of the excavated soil will be used
as a backfill, the rest will be take-off the site and properly stored. The top 200 mm of
the ground will be carefully put out and used as agriculture soil elsewhere. Some of the
area of foundation is already above original ground, so the backfill and proper
compaction has to be realized. There will be several gravities and retaining
structures/wall realized in the area to organize the ground in the surroundings of the
building.
3.6 ACOUSTIC
Staircase is separated by acoustic foil elements the landing composition and on the joint
of precast flight and landings from load bearing structure of the building. Due to
acoustic reasons, every slab composition is equipped with acoustic insulation. The wall
composition also satisfies acoustic requirements. Façade of the building is also
estimated to acoustically isolate whole object.
3.7 FOUNDATION
3.7.1 CHARACTERISTIC OF SOIL
Clay F4 –angle of internal friction = 30 deg
Cohesion = 20 kPa
Gamma is = 20 KN/m3
Tabled load bearing capacity = 150 kPa
3.7.2 FOUNDATION SLAB
The building foundation slab is designed as 250 mm thick and it is from waterproofed
concrete with the additive XYPEX (used for closing the cracks in concrete after the
crack arising XYPEX reacts with water and very slowly close the crack).
3.7.3 WATERPROOFING
Waterproofing of the structure below ground is done by asphalt sheets in the places of
weak spots, recess in the walls, opening for pipeline, etc.
3.7.4 PILES
Piles are designed of two diameters, 900 mm and 600 mm. Diameter of 900 mm is used
under the places of big loads (columns in the underground level) Diameter of 600 mm
is used for example under perimeter wall of underground level or elevator shaft. Piles
are design of different length. Under the places of big load, the piles are designed of
length of 16 m to be able to carry all the load.
➢ In the past, lime based cement binders, such as lime putty, were often used but
sometimes with other hydraulic cements, such as a calcium aluminate cement or
with Portland cement to form Portland cement concrete (named for its visual
resemblance to Portland stone).
➢ The cement reacts with the water and other ingredients to form a hard matrix
that binds the materials together into a durable stone-like material that has many
uses. Often, additives (such as pozzolans or superplasticizers) are included in
the mixture to improve the physical properties of the wet mix or the finished
material.
➢ For the concrete mix, we have taken M20 grade whose ratio 1:1.5:3 concrete
mixture has always been a major concern; after all, it attaches each brick to
make a building.
➢ Well, the invention of the self-loading concrete mixer has made life bit
comfortable for the engineers.
➢ We offer the following types of plaster mesh: plastic mesh, fiberglass mesh
cloth, welded wire mesh, chain wire mesh, chicken wire, light type expanded
metal, and woven wire cloth.
➢ These metal mesh all has small square mesh and made from thin wire. Plastering
mesh in various kinds allows customers to find exactly the suitable one perfectly
meeting special requirements.
3.13 PLUMBING
population has been centralized in cities and towns has been the development of
adequate plumbing systems.
➢ The term plumbing fixture embraces not only showers, bathtubs, lavatory
basins, and toilets but also such devices as washing machines, garbage-disposal
units, hot-water heaters, dishwashers, and drinking fountains.
➢ The water-carrying pipes and other materials used in a plumbing system must
be strong, noncorrosive, and durable enough to equal or exceed the expected life
of the building in which they are installed.
➢ Toilets, urinals, and lavatories usually are made of stable porcelain or vitreous
china, although they sometimes are made of glazed cast iron, steel, or stainless
steel.
➢ Ordinary water pipes usually are made of steel, copper, brass, plastic, or other
nontoxic material; and the most common materials for sewage pipes are cast
iron, steel, copper, and asbestos cement.
3.14 STAIRCASE
➢ Stairs may be straight, round, or may consist of two or more straight pieces
connected at angles. Special types of stairs include escalators and ladders. Some
alternatives to stairs are elevators (also called lifts), stairlifts, inclined moving
walkways, and ramps.
3.15 PUTTY
➢ The structure would be built round a post acting as a datum, and each course of
stonework would be set at a distance from the datum.
➢ When the centring is removed (as in "striking the centring"), pointing and other
finishing continues.
➢ The portion which supports cantering & shuttering is called Staging. This can
be:
1. Wooden Ballies
2. Pipes/Props/Jacks
3. H frames
4. Space frames using Coupler / Cup-Lock system
3.18 PLASTERING
➢ They are lean mixes of Binding Materials (Lime or Cement) with fillers material
such as Sand or Crushed stones.
➢ And the process of covering surfaces with Plaster is called Plastering.
➢ Plastering is done after all the works like block work, wiring, plumbing.
➢ Plastering contains only cement and sand and their ratio 1:6.
➢ The thickness of the plastering is 12 to 15mm.
➢ They are specially prepared for two reasons.
• For Protection.
• For Decoration.
➢ In protective covering, the Plaster saves the Bricks or Stones from Direct
Destructive Attacks of Atmosphere such as Wind, Rain and Harmful Industrial
Gases.
➢ As a decorative finish, Plasters are used to give many appealing shades and
finish designs to the construction.
➢ There are two type of plastering, they are-
• Cement plaster
• Gypsum plaster
CHAPTER 4
REFLECTION NOTES
4.1 INTRODUUCTION
The four weeks Training at LANDMARKS NEST at Hennur main road, Bengaluru is
being one of the best things to take away from my bachelor of engineering program. As
a person without any prior site experience, it was a great chance to visualize the
execution of the works and to link them with the theoretical knowledge I had. It was a
great opportunity to gain practical knowledge about the various activities like marking,
levelling, mixing ratio, curing etc., that take place at the site. Also, it helped me in
improving my theoretical knowledge, communication skill, team working skill etc. An
internship is not just the first step on the ladder to a great career and comfortable salary
but it is also the perfect place to start learning skills and gain knowledge about different
fields.
• Internships are professionally experiencing that give students the opportunity to gain
practical experience in a professional environment. It is the opportunity for a student to
take what he has learned in the classroom and apply it in the real world.
• It is a chance to develop communication and interpersonal skills, to build a knowledge
base about a specific field, and to practice a higher level of responsibility and
confidence.
3. Personality development.
4. Responsibilities.
4.4.1 COMMUNICATION
The communication is more important in any of the industry in the world. And I have
learnt more about communicating with the staff, workers and engineers etc. I have learnt
the communication skills during the internship program and could able to understand
and communicate with the workers, engineers and staff.
4.4.2 TIME MANAGEMENT
During the internship program I have learnt about how to manage the time in the Work.
“Time management” refers to the way that you organize and plan how long you spend
on specific activities. It may seem counter-intuitive to dedicate precious time to learning
about time management.
Its benefits are:
• Greater productivity and efficiency.
• A better professional reputation.
• Less stress.
• Increased opportunities for advancement.
4.4.3 PERSONALITY DEVELOPMENT
During the internship I have gain more knowledge about the technical and non-technical
topics and could able to develop my personality and technical knowledge.
CHAPTER 5
CONCLUSION
The internship program was conducted for 4 weeks and on those 4 weeks I got to learn lot of
knowledge. During my internship program I have got a lot of knowledge in terms of improving my
practical skill. The various types of orientation programs, tasks and trainings that we have been
undertaking during the four weeks on the site enhanced my knowledge in building construction. I
am very glad to see that what I have learnt in the university can be a repeated in the working world.
I could able to apply my theoretical knowledge of designing and construction works in the real-life
situation. This program played an important role to break the conventional thought that field works
can be only implemented by students who hold a degree or people who have an experience in
building construction. I am able to acquire a high level of confidence to deal with problems that
arise in a building construction. During the four weeks of internship, I have been able to see the
different theoretical aspects, Methodologies. I have been fulfilling my curiosity in learning
practically building construction well in this internship program. Generally, the internship program
laid sound foundation for us to start our career. I will be definitely sensible to scale this practice up
and to replicate it in other disciplines as well.
REFERENCES