Reliability Problems Synthesis Compressor-Drive Turbine

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 10

Standby 4

Major Problems Experienced by


Indo Gulf Fertilisers with the
Synthesis Compressor and Drive
Turbine
The Synthesis Compressor Train including the 26 MW drive steam turbine at Indo Gulf
Fertilisers, Jagdishpur was supplied by Nuovo Pignone (now GE Oil & Gas). The recycle
barrel of this compressor was revamped by modifying the recycle wheel by OEM and the
revamped unit was put into operation in April - May 2007. The performance of the compressor
after the revamp has not been satisfactory and finally resulted in failure of the thrust bearing
of the recycle barrel.

This paper highlights the problem of failure of the thrust bearing of the recycle barrel due to
its overloading caused by shortcomings during assembly despite deployment of possibly best
available resources including “Expert Supervision” from Nuovo Pignone. The paper also
explains design changes in the balance drum sizing. This was recommended by Nuovo
Pignone. After a detailed failure analysis. This replacement has been incorporated in April,
2009 Turn Around and the machine is running satisfactorily thereafter.

The paper also highlights other issues experienced by Indo Gulf Fertilsers during operation of
the synthesis gas compressor like two incidents of fire on synthesis compressor turbine due to
rupture of a flexible hose provided in the control oil line and wide cyclic variation of the thrust
bearing temperature with change in ambient conditions. Precautions taken by Indo Gulf
Fertilisers during fire fighting which helped in minimizing the negative effects of the fire and
the quick re-start of the turbine have also been included in the paper.

C.K. Datta and Ajit Kumar Srivastava


Indo Gulf Fertilisers

Introduction India. IGF produces prilled urea and converts


the entire ammonia produced in to urea. The

T he company Indo Gulf Fertilisers (IGF) plant where the compressor revamp project took
is a unit of Aditya Birla Nuvo Ltd, a place is situated in the eastern part of India in
flagship company of the Aditya Birla the state of Uttar Pradesh, at Jagdishpur.
Group – a global Fortune 500 company from

2009 311 AMMONIA TECHNICAL MANUAL


Facilities
The plant facilities comprises of

™ 1520 MTPD ammonia plant


™ 2620 MTPD prilled urea plant
™ Power Plant & Utilities having 2X100
TPH Boilers, 2X18 MW gas turbines
™ Bulk urea storage of 45,000 MT
™ Ammonia storage of 15,000 MT.

The basic raw material is natural gas. The


process licensors are:

™ Ammonia - Haldor Topsøe A/S,


Denmark A View of Synthesis Compressor Train
™ Urea - Snamprogetti SPA, Italy
The last compressor barrel incorporates one
Process Description recycle stage. The compressor train operates at
around 9000 RPM, to compress synthesis gas
Ammonia Plant from 25 Kg/cm2g (355.5 psi) to about 200
The natural gas is desulphurised via hydro Kg/cm2g (2844 psi) to facilitate synthesis of
desulphurization and is mixed with steam before
ammonia from synthesis gas - a mixture of
it is fed into the steam reforming unit. The re-
formed gas is cooled and fed to the shift reactors nitrogen and hydrogen. The synthesis gas
in order to convert CO to CO2. Subsequent to compressor is driven by a steam turbine with
this, converted gas is fed to a CO2 absorption inlet steam at 105 Kg/cm2g (1493 psi) pressure
system, where the CO2 is removed and used as and 515 0C (9590 F) temperature. Steam is
feedstock for the urea plant. After CO2 removal extracted at 38 Kg/cmgg (540.4 psi) and
the gas is fed to the methanator to remove final condenser operates at 0.13 ata (1.9 psi abs). The
traces of unconverted CO and CO2. The gas is
then compressed and sent to the ammonia complete synthesis compressor train including
synthesis unit. NH3 produced in the ammonia the steam turbine of 26 MW was supplied by
converter is cooled and condensed by water- M/s Nuovo Pignone (now GE Oil & Gas), Italy.
cooling and refrigeration and sent to urea plant.
Excess ammonia, as per requirement, is The compressor employs an “oil film sealing”
refrigerated further and sent to storage. system for end gas sealing.

Synthesis Gas Compressor


The synthesis gas compressor is a high speed
centrifugal compressor and consists of vertically
split compressor barrels
™ 2 BCL 508
™ BCL 408 a
™ 2 BCL 408 b and
™ Steam Turbine EHNK 40/45

AMMONIA TECHNICAL MANUAL 312 2009


as envisaged by machining of impeller vanes in
Nuovo Pignone works in Florence shop.

Fig 1 – Schematic Diagram of Synthesis


Compressor Train Fig 2 – Details of Impeller Wheel Modification
for Recycle Rotor

Revamp of Synthesis Compressor Installation of Modified Rotor


In the year 2005, IGF undertook a study for IGF took shut down the plants in April/May
revamp of the plant for capacity enhancement as 2007 to carry out the modifications for the
well as reduction in energy consumption for revamp of the plant. The modified rotor was put
ammonia production. Revamp study was carried in the machine during above shut down under
out by M/s Haldor Topsoe, the technology supervision of expert engineers from Nuovo
supplier and based on overall margins in various Pignone. During above period, overhauling of
equipment, targets were finalized. This study complete train was also performed. During the
also laid down process conditions to be met by overhauling, all clearances for seals, bearings
Synthesis Compressor. etc were maintained as per original protocol

These conditions were studied by Nuovo Performance of Compressor Post Revamp


Pignone and based on performance test of the After completion of all activities, the plant was
compressor train, design calculations and restarted in the last week of May 2007 and the
simulations, it was recommended by Nuovo synthesis compressor train was also re-
Pignone to carry out a minor modification in the commissioned. After start up of the synthesis
recycle impeller to reduce its vane diameter. No compressor, it performed well from process
change was advised in disc and counter disc of point of view and met process conditions as
recycle impeller as well as other parts of the envisaged in the revamp study. However, thrust
compressor. With above change, it was bearing temperature for the recycle barrel was
envisaged that the compressor would be able to observed to be very high after commissioning of
meet revised process requirements. the compressor post revamp. It was found to be
varying between 107 °C (224.60F) to 140 °C
Modification of Recycle Impeller (2840F) with change in ambient conditions in
Based on recommendations provided by Nuovo day and night. Surprisingly the temperature
Pignone, the order was placed in June 2006 and peaks for the thrust bearing was occurring
the recycle impeller of spare rotor was modified

2009 313 AMMONIA TECHNICAL MANUAL


during coolest period i.e. late in the night. Oil
consumption in the compressor was also
abnormally high ie approx 300 liters per day (80
gallons per day) against normal expected
consumption of 20 – 25 liters per day (5 – 7
gallons per day). The problem was referred to
OEM for analyzing it and to provide corrective
measures to be taken.

After investigation, it was observed that balance


drum leak off pressure and hence differential
pressure between balancing drum leak off
pressure and suction pressure of final make up Fig 3 - Damaged Active Side Thrust Bearing
stage was operating in the range of 15 – 16 Trial Run of Compressor after Bearing
Kg/cm2g (210 to 230 psi) against normal value Replacement
of 2 – 3 Kg/cm2g (30 – 40 psi) before revamp.
The rotor was found to be freely rotating and
While the matter was still being investigated hence it was decided to take a trial of the
and analysed with Nuovo Pignone, the thrust compressor after replacement of the thrust
bearing of recycle barrel rotor failed on 2nd July bearing, thrust collar, axial probe etc. During
2007, after operation of compressor for 40 days start up, the compressor was very stable with
in abnormal conditions. Subsequently, repair of axial displacement and radial vibration within
compressor was taken up. normal limits and Minimum Governor Speed -
MGS could be reached without any
abnormality. However, the compressor tripped
1st Repair on high axial shift when it was being loaded. It
On dismantling the free end bearing of the was then decided to carry out an internal
compressor, it was observed that inspection of the compressor barrel and
accordingly, the compressor barrel was
™ Both Axial probes were damaged. dismantled. On dismantling, the following were
™ Lot of metal debris was found in the observed –
bearing housing
™ The thrust collar has rubbed against the
™ Active side pads of thrust bearing were
in badly damaged shape - Babbitt metal thrust bearing active side pads.
has flown. ™ The rotor has rubbed against gas seal on
™ The active side face of the thrust collar TB side thrust flange creating a deep
has rubbed and was in badly damaged groove in the gas seal.
condition. ™ Rotor also rubbed against the labyrinth
™ Total axial float was found to be 5.85 seals for impeller suction eye.
mm (0.23 inch) against original set value ™ Rotor has also rubbed against the
of 5.35 mm (0.21 inch): diaphragms - radially as well as axially.

AMMONIA TECHNICAL MANUAL 314 2009


™ Impellers also show impressions of Subsequent to this repair, the compressor is
rubbing resulting in flowing out of performing satisfactorily for the last 20 months
material. with a thrust bearing temperature varying
™ Many inter-stage seals were also found between 90 – 115 °C (194 to 2390F) and a
damaged because of rubbing with rotor. differential pressure between balancing drum
leak off and final make-up stage suction in the
range of 2 to 3 Kg/cm2g (30 – 40 psi).
Final Repair
The modified rotor installed in the machine was The damaged rotor removed from the
not found to be usable and hence it was decided compressor was sent to the Nuovo Pignone
to replace the rotor with the original un- works in Florence for inspection and repair.
modified spare rotor available at site. During detailed inspection, three out of eight
Accordingly, the compressor was assembled impellers were found to have developed
with the old spare rotor. All damaged multiple cracks and were replaced with new
components like seals; bearings, thrust collar impellers.
etc. were replaced with spare sets. Orifice
Root Cause Analysis (RCA)
diameter in oil inlet line to the thrust bearing
As the temperature of the thrust bearing of the
was increased from 13 to 15 mm (0.51 to 0.59
recycle barrel was found to be running
inch) to ensure adequate quantity of oil to the
abnormally high beyond acceptable limits, it
thrust bearing after discussion with Nuovo
was concluded that the thrust bearing is
Pignone.
experiencing a thrust load much higher than its
The compressor was started and taken in line on capacity. This overloading would have been a
9th July 2007. All the parameters of the result of excessively high differential pressure
compressor parts were found to be within between balancing drum leak off and final make
acceptable limits. The thrust bearing up stage suction. Based on the root cause
temperature was varying from 90 to 115 0C (194 analysis done by Nuovo Pignone, some
to 2390F). Differential pressure between blockage was suspected in the leakage path of
balancing drum leak off and final make-up stage the gas leaking across balance drum. However,
suction was observed to be in the range of 2 - 3 during inspection of the compressor barrel, no
Kg/cm2g (30 – 40 psi). blockage was found. Further, after start up of
the compressor after replacement of rotor in
IGF had an opportunity of inspection of thrust July 07, the differential pressure as well as
bearing of the recycle barrel after operation of thrust bearing temperature was observed to be
the compressor for about a week and the thrust within acceptable limits indicating some other
bearing was found to be in good condition factors responsible for the high differential
during inspection. However, as a preventive pressure and the high thrust bearing
measure diameter of Oil Control Ring was also temperature.
increased from 14 mm to 14.8 mm (0.55 to 0.58
inch) based on recommendation of Nuovo Nuovo Pignone, although they confirmed that
Pignone. there were no issues with rotor design including
thrust balancing, advised for increase in balance

2009 315 AMMONIA TECHNICAL MANUAL


drum diameter from 274 mm to 285 mm (10.79 A simple inference of above is “The seal
to 11.22 inch), as a preventive measure. As the clearance of the modified rotor must have
RCA carried out by Nuovo Pignone was not been much higher than the protocol values –
conclusive, the IGF Team continued their effort of the order of > 1.5 mm (0.059 inch)”. To
to ascertain root cause to eliminate the chance of understand the phenomenon better, the question
recurrence of a similar failure. Scanning through was raised to understand the exact effect of this
history records revealed that during one repair, clearance on differential pressure, which was
the balance drum of one of the rotors was considered as main factor responsible for failure
replaced at BHEL, India because of scoring on of thrust bearing. Based on an empirical relation
the original balance drum. History records also provided by Nuovo Pignone, the effect of
revealed that during this repair final balance increased clearance was found to be matching
drum diameter was made as 275.10 mm. This with the observation of the higher differential
rotor with balance drum diameter of 275.10 mm pressure. Based on above it was concluded that
(10.83 inch) was in service before installation of the reason for failure of the thrust bearing was
rotor modified as part of revamp. The balance because of higher differential pressure caused
drum diameter of Modified Rotor was measured by the higher clearance between balance drum
as 273.80 mm (10.78 inch), which means that and its seal. Reduction in differential pressure
the diameter of balance drum, which was in across balance drum after replacement of rotor
service before installation of Modified Rotor, is maintaining seal clearance as per protocol,
higher, by 1.3 mm (0.05 inch). reinforced our thinking.

After failure of recycle barrel rotor on 2nd July Lessons Learnt


2007, IGF had to use old unmodified rotor with The overhauling and replacement of the rotor
balance drum diameter higher by 1.3 mm (0.05 was carried out under expert guidance of Nuovo
inch). During clearance checking exercise for Pignone engineer. With availability of Nuovo
installation of unmodified rotor with 1.3 mm Pignone expert for taking care of overhauling
higher balance drum diameter, the clearance the IGF team developed very high level of
between balance drum and its seal was found to confidence, which allowed them to relax their
(0.05 inch) be 0.50 – 0.55 mm (0.20 – 0.22 attention from the critical job. However, the
inch) which is within protocol values. IGF team major miss experienced during the process of
was surprised with this observation as same seal overhauling indicates that the end user must get
was in service with the modified rotor and fully involved during critical activities so as to
clearance reported in the assembly report at site ensure that proper checks balances are in place.
during installation of modified rotor with IGF learnt this lesson the hard way.
modified rotor and same seal was same as 0.50
– 0.55 mm (0.20 – 0.22 inch). This was Fire on Synthesis Compressor Drive Turbine
surprising for the IGF team as with balance At around 10:00 p.m. on 3rd June 2008,
drum seal remaining common, clearance can’t Ammonia Plant at Indo Gulf Fertilisers
remain the same with two rotors having including Synthesis Compressor, tripped due to
different diameter of balance drum. problem in CO2 Recovery Section. After
attending to the problem, the plant was

AMMONIA TECHNICAL MANUAL 316 2009


normalized. Synthesis Compressor was taken on
load at around midnight on the same day.
During start up, Synthesis Compressor once
tripped on high vibrations. On 4th June 2008 at
2.41 a.m., i.e. shortly after stabilization of
Synthesis Compressor, a fire was observed on
the Synthesis Compressor Turbine. Subsequent
to observing fire, machine tripped due to
burning of axial probe cable. It was observed
that the flames were emanating from Steam inlet
line, probably because of impingement of oil
stream on hot surface of inlet steam line. Fig 4 – Damaged HP Control Oil Hose – A
Therefore, lube oil supply to the machine was closer View
cut off by stopping lube oil pumps. Fire could
be extinguished with the help of steam, dry As plant and machinery are subject to a
chemical powder (DCP) and CO2 fire comprehensive insurance cover, dismantling
extinguishers. The lube oil console, seal oil/lube activity could be started only after completing
oil skids etc for the compressor train are located survey of the damaged areas by insurance
directly beneath compressor train. To avoid any company. After insurance clearance the steam
chances of fire reaching and affecting these turbine was dismantled. A major concern was
areas, a water curtain was created to cordon off the status of rotor as we were compelled to stop
these areas and cool/extinguish sparks that may oil supply with the turbine still very hot.
reach close to these areas. Care was taken to However, on dismantling all bearings were
ensure that water is not used in the areas close to found to be in good condition and no sagging
the extremely hot steam turbine to avoid was observed in the rotor. The steam turbine
quenching. The fire was concentrated at the was assembled replacing the damaged
front end of the turbine and it severely damaged components. While most of the components
components of the turbine at the front end like were available in stock, alternate arrangements
entire instrumentation including probes & were made for some of the parts like instrument
cables, hydraulic governor, components of pilot cabling which was rerouted to shorten lead
piston & servo motor, amplifier, gauge glasses between control room and field instruments,
etc. Figure 4 provide an idea about damage vibration/temperature probes, gauge glasses etc.
After completing assembly work, the oil
circulation was done with wire mesh in the
return line, which was continued for almost 36
hours, and a lot of debris was removed. Entire
maintenance activities could be completed in
about 7 days time from starting dismantling
activities to the machine was put back in to
operation. Looking at the damage caused by the
fire, it was an appreciable effort to come back

2009 317 AMMONIA TECHNICAL MANUAL


into operation so quickly. This became possible control oil line. As rupture of a flexible hose
because of quick identification of the fire, care was responsible for the fire, we implemented a
taken during fire extinguishing and excellent practice of replacing flexible hoses in every
teamwork. turnaround with new hoses duly hydro-tested.

Reason for Fire Corrective Actions to Mitigate the Risk


The steam turbine uses steam at 105 ata (1493 During interaction with similar Ammonia –
psi) and 515 °C (9590F) and has double inlet for Urea Manufacturers, the Indo Gulf team was
steam. The inlet connections for the steam line surprised to know that at most of the plants,
are flanged. only fixed stainless steel piping has been used in
Control Oil Circuit. It was also understood that
Analysis of the Problem size of control oil piping in these cases is up to a
In the control oil line as well as other similar maximum of 1” Nb as compared to 1 ½” Nb at
lines at the turbine front end, single braided Indo Gulf. This was also confirmed by Bharat
flexible hoses are provided to take care of Heavy Electricals Limited BHEL, Hyderabad,
thermal expansion. During inspection of the India – a reputed designer & supplier of
turbine after its stoppage, the hose provided in centrifugal compressors and turbines. As Indo
the HP Control oil line was found ruptured at Gulf experienced two serious failures on
the bottom end. Rupture in hose was found in Synthesis Compressor Drive Turbine, GE Oil &
the area of hose facing steam turbine. Further Gas was requested to provide their
review of data revealed that shortly before fire recommendation for replacement of flexible
was reported, a small dip in lube oil pump hose with stainless steel piping for which GE
discharge pressure was visible in the history Oil & Gas didn’t agree and Indo Gulf has to live
trend. Based on these findings and other with this situation.
observations at site and facts, it was concluded
that “because of rupture of the HP Control oil As usage of a flexible hose is inevitable, Indo
hose carrying control oil at around 8 kg/cm2 Gulf tried to work different options to relocate
(114 psi) a stream of oil emerged from the the flexible hose so as to achieve a “fail safe”
hose. This oil after striking hot surface of condition to eliminate chances of recurrence of
steam pipes and getting absorbed in such disasters. However, proposed solutions did
insulation caught fire. A small dip in oil not meet detailed scrutiny mainly because of the
pressure was probably the time when the risk involved with the Aluminum body of the
hose might have ruptured resulting in sudden cylinder for the pilot piston. This necessitated
increase in discharge flow and hence sudden installation of a fool proof design flexible hose.
reduction in oil pressure.” And based on study of relevant standards for
flexible hoses, following facts came up:
Past Failures
Indo Gulf had an experience of occurrence of 1. Flexible hose comes in three categories –
similar fire in the same machine on 16th July “A”, “B” and “C”.
1992. The reason of fire in that case also was
traced to a rupture of the hose provided in HP

AMMONIA TECHNICAL MANUAL 318 2009


2. While category “B” specifies for “Cycle
Test” up to 5000 Cycles, “C” category
“C” hoses are tested up to 50000 cycles.
3. All the vendors have supplied hose of
category “B” only
4. As the hoses are connected to the
turbine, some vibrations are inevitable –
in-fact a U-bolt which was used to fix
the HP Control Oil Hose with its support
was found sheared during the inspection
after failure. This suggested that the hose
must have vibrated substantially before
its eventual rupture.
5. As indicated in the earlier sections of
this paper – shortly before failure the
turbine tripped on high vibrations during
its start up. Though tripping of the
turbine is because of high vibrations at
the bearing locations, which is
independent of HP Control Oil hose, it
gives an indication that there might have
been vibrations in the hose as well.

Based on above it was thought that the hose


needs to be upgraded to make them resistant to
fatigue failure.

Accordingly, we have procured hoses of


category “C” which have been designed and
tested to withstand high fatigue stresses.

These hoses have been installed in the


turnaround in the month of April 2009 and
performance of hose is under observation.

2009 319 AMMONIA TECHNICAL MANUAL


AMMONIA TECHNICAL MANUAL 320 2009

You might also like